Construction method for hoisting photovoltaic glass kiln steel structure beam based on BIM model

Through BIM model simulation and optimization, the installation complexity and safety of steel structure beams of photovoltaic glass kilns are solved, comprehensive prediction and real-time adjustment are achieved before construction, and construction safety and quality are improved.

CN118992822APending Publication Date: 2024-11-22CHINA MCC17 GRP CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411342849.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-24
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

In the construction of photovoltaic glass kilns, the ordinary installation mode cannot adapt to the demand for the narrow internal space of the glass kiln, resulting in complex and unsafe installation of steel structure beams. The existing large-span exterior hoisting construction has problems such as safety risks and high construction complexity. .

Method used

Using the construction method based on BIM model, the construction model of steel structure beams and glass kilns is established through BIM software, the lifting paths and installation positions are simulated, the collision detection and stress analysis are carried out, the lifting scheme is optimized, and the lifting equipment and beam positions are adjusted in real time. , ensure construction safety and quality.

Benefits of technology

The safety and quality of steel structure beam lifting construction has been improved, human errors have been reduced, the smooth progress of the construction process and reasonable stress have been ensured, comprehensive prediction and optimization have been achieved before construction, and the reliability of construction has been enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118992822A_ABST
    Figure CN118992822A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for hoisting a photovoltaic glass kiln steel structure beam based on a BIM model, and relates to the technical field of hoisting supporting. The construction method for hoisting the photovoltaic glass kiln steel structure beam based on the BIM model comprises the following specific operation steps: step 1, model establishment: establishing a steel structure beam and glass kiln construction model by using BIM software; 2, simulating a hoisting path, a hoisting point and a mounting position of the beam, and determining a placement position of hoisting equipment; according to the construction method for hoisting the photovoltaic glass kiln steel structure beam based on the BIM model, a steel structure beam and glass kiln construction model is established, collision detection is conducted, the collision problem possibly occurring in the hoisting process is found in time, the construction safety risk is avoided, the hoisting process is monitored in real time through the BIM model, the positions of hoisting equipment and the steel structure beam are adjusted in time, and the construction efficiency is improved. And the hoisting is implemented according to the guidance of the BIM model, so that the reduction of human errors is facilitated, and the construction quality is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of hoisting support, and in particular to a construction method for hoisting a steel structure beam of a photovoltaic glass furnace based on a BIM model. Background Art

[0002] As the country vigorously develops new energy, the construction of photovoltaic glass production lines is increasing. In the process of building glass kilns, due to the complexity of their production processes and the high precision of equipment installation, the relevant construction processes are relatively complicated. In particular, the internal space of the glass kiln is small, and the ordinary installation mode cannot be used when installing steel structure beams. Only large-span external hoisting construction can be used. External hoisting of steel structure beams refers to the operation of lifting the steel structure beams from one side through hoisting equipment during the construction process and installing them across the outside of the building.

[0003] In view of the deficiencies in the prior art, the present invention provides a construction method for hoisting steel structure beams with a large span outside the span, which has the advantages of being specially used for the hoisting construction of steel structure beams for glass kilns, performing comprehensive predictions before construction, and making construction safer, thereby solving the problems of the above-mentioned technologies. Summary of the invention

[0004] 1. Technical issues to be solved

[0005] In view of the deficiencies in the prior art, the present invention provides a construction method for hoisting steel structure beams of a photovoltaic glass kiln based on a BIM model, which solves the problems existing in the prior art.

[0006] (II) Technical solution

[0007] To achieve the above purpose, the present invention is implemented through the following technical scheme: a construction method for hoisting steel structure beams of photovoltaic glass furnace based on BIM model, the specific operation is as follows:

[0008] Step 1: Model establishment: Use BIM software to establish the construction model of steel structure beams and glass kiln;

[0009] Step 2: simulate the lifting path, lifting point and installation position of the beam to determine the placement of the lifting equipment;

[0010] Step 3: Collision detection: perform collision detection in the BIM model;

[0011] Step 4: Optimize the hoisting plan: Use BIM software to simulate different hoisting plans, analyze the stress conditions during the hoisting process, and find the optimal solution;

[0012] Step 5: Use BIM software to simulate the structural stability after installation. If the structural stability is lower than the national standard, return to step 2;

[0013] Step 6. Hoisting implementation: According to the hoisting path and plan of the BIM model, set up the hoisting equipment on site, guide the hoisting beams according to the hoisting points in the BIM model, monitor the hoisting process in real time through the BIM model, adjust the position of the hoisting equipment and steel structure beams, and install and fix the beams according to the guidance of the BIM model.

[0014] Preferably, the model building in step 1 further includes the following detailed steps:

[0015] S1.1. Select one of Revit, AutoCAD Civil 3D or Tekla Structures as the BIM software;

[0016] S1.2. Collect design drawings and information: Collect design drawings, CAD files and technical parameter information of steel structure beams and glass kilns for subsequent modeling;

[0017] S1.3. Create a new project in the selected BIM software, set the project units and coordinate system, import the CAD files, and import the collected design drawings and CAD files into the BIM software as the basis for modeling;

[0018] S1.4. Create architectural elements of steel structure beams and glass furnaces in BIM software, including walls, floors, roofs and glass furnace equipment, based on the imported CAD files, and add detailed attributes and parameters for each architectural element, including size, material and weight information;

[0019] S1.5. Build a three-dimensional model of the steel structure beam and glass kiln based on the design drawings and data.

[0020] Preferably, the step 2 further comprises the following detailed steps:

[0021] S2.1. Open the established steel structure beam and glass furnace construction model, and ensure that the model contains the accurate size, material and weight information of the beam;

[0022] S2.2. Determine the lifting starting point: According to the actual situation, determine the lifting starting point of the beam in the model and create the lifting point coordinates. According to the construction site conditions, determine the lifting path of the beam, including the horizontal movement path and the vertical lifting path. According to the structure and weight of the beam, determine the position of the lifting point.

[0023] S2.3. Add cranes and lifting ropes to the model, set lifting capacity and length parameters, and use the lifting simulation function provided by the BIM software to simulate the lifting process of the steel structure beam, including the lifting, moving and lowering steps;

[0024] S2.4. Analyze the stress conditions: During the simulation process, analyze the stress conditions of the lifting equipment. According to the simulation results and stress analysis, adjust the lifting path, lifting points and the placement of the lifting equipment as needed;

[0025] S2.5. Determine the installation position: According to the simulation results and the optimized lifting plan, determine that the final installation position of the steel structure beam is consistent with the building structure, and export the simulated lifting path, lifting point and installation position data.

[0026] Preferably, the step three also includes the following detailed steps:

[0027] S3.1. Open the established steel structure beam and glass furnace construction model in the selected BIM software;

[0028] S3.2. Find the collision detection tool or plug-in in the BIM software and set it up, including setting the collision detection range and accuracy parameters. According to project requirements, select the components, equipment and parts that need to be collided, or select the entire model and specific components for detection;

[0029] S3.3. Start the collision detection tool to perform collision detection between the selected components in the model. The software automatically analyzes the relationship between each component and detects whether there is a collision. After the collision detection is completed, the software lists all collision situations, including the specific location and type of the collision.

[0030] Preferably, in step three, collision is detected for tracing, and the tracing logic is: when a single component collides, the volume of its own part is magnified by 300%, and the nearby parts wrapped in this range form a traceability range. The traceability range is layered, and each 30% close to the collision component is a traceability sub-layer, for a total of ten layers. The traceability range increases by 10% for each layer, and a traceability query is performed on the source of the component itself for every 5% traceability range, and the query results are displayed in a list.

[0031] The traceability expression is:

[0032]

[0033] in:

[0034] 300%V means that when a single component collides, 300% of its own volume is used as the initial traceability range;

[0035] i ranges from 1 to 10, indicating that for each collision component, the parts around the collision component are layered in increments of 30%, for a total of ten layers, and the traceability range of each layer increases by 10%V;

[0036] j ranges from 1 to 20, indicating that within the traceability range of each layer, a traceability query is performed to the component's own source every 5% of the range, and the final results are displayed in a list.

[0037] Preferably, the step 4 further includes the following detailed steps:

[0038] S4.1. Open the file containing the steel structure beam and glass furnace construction model in the selected BIM software; prepare different lifting plans according to the actual situation and needs, including lifting paths, lifting points and lifting equipment variables;

[0039] S4.2. Simulate the hoisting process: Use the hoisting simulation function in the BIM software to import different hoisting schemes one by one to simulate the hoisting process of the steel structure beam, including the lifting, moving and lowering steps;

[0040] S4.3. Analyze the stress conditions: During the simulation process, analyze the stress conditions of the lifting equipment and beam structure under each lifting scheme, including the stress points and the magnitude of the stress;

[0041] S4.4. Compare the lifting schemes: Compare and analyze the stress conditions of various lifting schemes to find the optimal scheme with the least impact on the construction of steel structure beams and glass kiln and the highest safety;

[0042] S4.5. Optimize the best solution: Based on the analysis results, further optimize and adjust the best solution, including adjusting the position of the lifting equipment and considering adding auxiliary supports.

[0043] Preferably, the expression of step 4 is:

[0044]

[0045] S represents the total force value;

[0046] e represents the number of lifting points;

[0047] P e Indicates the force value of the e-th lifting point;

[0048] D e Indicates the distance to the e-th lifting point.

[0049] Preferably, the step 5 is expressed using a conditional statement, and the expression is:

[0050] Return to step 2

[0051] S represents the stability index of the structure;

[0052] GB stands for the national standard index.

[0053] Preferably, in step six, the BIM model monitors the hoisting process in real time, uses on-site sensors, scanners or drones to capture data in real time, and adjusts the positions of the hoisting equipment and the steel structure beams.

[0054] (III) Beneficial effects

[0055] The invention provides a construction method for hoisting steel structure beams of a photovoltaic glass furnace based on a BIM model.

[0056] It has the following beneficial effects:

[0057] 1. The construction method of hoisting the steel structure beam of the photovoltaic glass kiln based on the BIM model established the construction model of the steel structure beam and the glass kiln, and carried out collision detection to timely discover the collision problems that may occur during the hoisting process and avoid construction safety risks. The BIM model is used to monitor the hoisting process in real time, and the hoisting equipment and the position of the steel structure beam are adjusted in time to ensure a smooth hoisting process. The hoisting is carried out according to the guidance of the BIM model, which helps to reduce human errors and improve construction quality. When the model is established, the three-dimensional model of the steel structure beam and the glass kiln is accurately established according to the design drawings and materials, and detailed attributes and parameter information are added to the architectural elements, achieving the beneficial effect of hoisting construction of steel structure beams dedicated to glass kilns.

[0058] 2. The present invention simulates the lifting path, lifting point and installation position of the beam in the BIM software, and analyzes different lifting schemes to conduct comprehensive prediction and optimization before construction, so as to ensure that the force in the lifting process is reasonable and improve the safety of construction. The lifting process is monitored in real time through the BIM model, and the lifting implementation is comprehensively predicted and planned before construction, and the lifting equipment and position are adjusted in real time to ensure that the construction is safer and more reliable, thus achieving the beneficial effect of comprehensive prediction before construction and safer construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0059] Figure 1 It is a schematic diagram of the process of the present invention;. DETAILED DESCRIPTION

[0060] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0061] See also Figure 1 The present invention provides a technical solution: a construction method for hoisting steel structure beams of photovoltaic glass furnace based on BIM model, and the specific operation is as follows:

[0062] Step 1: Model establishment: Use BIM software to establish the construction model of steel structure beams and glass kiln;

[0063] Step 2: simulate the lifting path, lifting point and installation position of the beam to determine the placement of the lifting equipment;

[0064] Step 3: Collision detection: perform collision detection in the BIM model;

[0065] Step 4: Optimize the hoisting plan: Use BIM software to simulate different hoisting plans, analyze the stress conditions during the hoisting process, and find the optimal solution;

[0066] Step 5: Use BIM software to simulate the structural stability after installation. If the structural stability is lower than the national standard, return to step 2;

[0067] Step 6. Hoisting implementation: According to the hoisting path and plan of the BIM model, set up the hoisting equipment on site, guide the hoisting beams according to the hoisting points in the BIM model, monitor the hoisting process in real time through the BIM model, adjust the position of the hoisting equipment and steel structure beams, and install and fix the beams according to the guidance of the BIM model.

[0068] The model building in step 1 also includes the following detailed steps:

[0069] S1.1. Select one of Revit, AutoCAD Civil 3D or Tekla Structures as the BIM software;

[0070] S1.2. Collect design drawings and information: Collect design drawings, CAD files and technical parameter information of steel structure beams and glass kilns for subsequent modeling;

[0071] S1.3. Create a new project in the selected BIM software, set the project units and coordinate system, import the CAD files, and import the collected design drawings and CAD files into the BIM software as the basis for modeling;

[0072] S1.4. Create architectural elements of steel structure beams and glass furnaces in BIM software, including walls, floors, roofs and glass furnace equipment, based on the imported CAD files, and add detailed attributes and parameters for each architectural element, including size, material and weight information;

[0073] S1.5. Build a three-dimensional model of the steel structure beam and glass kiln based on the design drawings and data.

[0074] Wherein, the step 2 also includes the following detailed steps:

[0075] S2.1. Open the established steel structure beam and glass furnace construction model, and ensure that the model contains the accurate size, material and weight information of the beam;

[0076] S2.2. Determine the lifting starting point: According to the actual situation, determine the lifting starting point of the beam in the model and create the lifting point coordinates. According to the construction site conditions, determine the lifting path of the beam, including the horizontal movement path and the vertical lifting path. According to the structure and weight of the beam, determine the position of the lifting point.

[0077] S2.3. Add cranes and lifting ropes to the model, set lifting capacity and length parameters, and use the lifting simulation function provided by the BIM software to simulate the lifting process of the steel structure beam, including the lifting, moving and lowering steps;

[0078] S2.4. Analyze the stress conditions: During the simulation process, analyze the stress conditions of the lifting equipment. According to the simulation results and stress analysis, adjust the lifting path, lifting points and the placement of the lifting equipment as needed;

[0079] S2.5. Determine the installation position: According to the simulation results and the optimized lifting plan, determine that the final installation position of the steel structure beam is consistent with the building structure, and export the simulated lifting path, lifting point and installation position data.

[0080] Wherein, the step three also includes the following detailed steps:

[0081] S3.1. Open the established steel structure beam and glass furnace construction model in the selected BIM software;

[0082] S3.2. Find the collision detection tool or plug-in in the BIM software and set it up, including setting the collision detection range and accuracy parameters. According to project requirements, select the components, equipment and parts that need to be collided, or select the entire model and specific components for detection;

[0083] S3.3. Start the collision detection tool to perform collision detection between the selected components in the model. The software automatically analyzes the relationship between each component and detects whether there is a collision. After the collision detection is completed, the software lists all collision situations, including the specific location and type of the collision.

[0084] Among them, in the step three, collision is detected and traced, and the traceability logic is: when a single component collides, the volume of its own parts is magnified by 300% proportionally, and the nearby parts wrapped in this range form a traceability range. The traceability range is layered, and each 30% close to the collision component is a traceability sub-layer, with a total of ten layers. The traceability range of each layer increases by 10%, and a traceability query is performed on the source of the component itself for every 5% traceability range, and the query results are displayed in a list.

[0085] The traceability expression is:

[0086]

[0087] in:

[0088] 300%V means that when a single component collides, 300% of its own volume is used as the initial traceability range;

[0089] i ranges from 1 to 10, indicating that for each collision component, the parts around the collision component are layered in increments of 30%, for a total of ten layers, and the traceability range of each layer increases by 10%V;

[0090] j ranges from 1 to 20, indicating that within the traceability range of each layer, a traceability query is performed to the component's own source every 5% of the range, and the final results are displayed in a list.

[0091] Wherein, the step 4 also includes the following detailed steps:

[0092] S4.1. Open the file containing the steel structure beam and glass furnace construction model in the selected BIM software; prepare different lifting plans according to the actual situation and needs, including lifting paths, lifting points and lifting equipment variables;

[0093] S4.2. Simulate the hoisting process: Use the hoisting simulation function in the BIM software to import different hoisting schemes one by one to simulate the hoisting process of the steel structure beam, including the lifting, moving and lowering steps;

[0094] S4.3. Analyze the stress conditions: During the simulation process, analyze the stress conditions of the lifting equipment and beam structure under each lifting scheme, including the stress points and the magnitude of the stress;

[0095] S4.4. Compare the lifting schemes: Compare and analyze the stress conditions of various lifting schemes to find the optimal scheme with the least impact on the construction of steel structure beams and glass kiln and the highest safety;

[0096] S4.5. Optimize the best solution: Based on the analysis results, further optimize and adjust the best solution, including adjusting the position of the lifting equipment and considering adding auxiliary supports.

[0097] Wherein, the expression of step 4 is:

[0098]

[0099] S represents the total force value;

[0100] e represents the number of lifting points;

[0101] P e Indicates the force value of the e-th lifting point;

[0102] D e Indicates the distance to the e-th lifting point.

[0103] Wherein, the step 5 is expressed using a conditional statement, and the expression is:

[0104] Return to step 2

[0105] S represents the stability index of the structure;

[0106] GB stands for the national standard index.

[0107] Among them, the BIM model in step six monitors the hoisting process in real time, uses on-site sensors, scanners or drones to capture data in real time, and adjusts the positions of the hoisting equipment and steel structure beams.

[0108] In summary, the construction method of hoisting steel structure beams of photovoltaic glass furnace based on BIM model established the construction models of steel structure beams and glass furnace, and carried out collision detection to timely discover the collision problems that may occur during the hoisting process and avoid construction safety risks. The BIM model is used to monitor the hoisting process in real time, and the hoisting equipment and the position of the steel structure beams are adjusted in time to ensure the smooth progress of the hoisting process. The hoisting is carried out according to the guidance of the BIM model, which helps to reduce human errors and improve the construction quality. When the model is established, the three-dimensional model of the steel structure beams and glass furnace is accurately established according to the design drawings and materials, and detailed attributes and parameter information are added to the architectural elements, achieving the beneficial effect of hoisting construction of steel structure beams dedicated to glass furnaces.

[0109] The present invention simulates the lifting path, lifting point and installation position of the beam in the BIM software, and analyzes different lifting schemes to perform comprehensive prediction and optimization before construction, so as to ensure reasonable force in the lifting process and improve the safety of construction. The lifting process is monitored in real time through the BIM model, and the lifting implementation is comprehensively predicted and planned before construction, and the lifting equipment and position are adjusted in real time to ensure safer and more reliable construction, thus achieving the beneficial effects of comprehensive prediction before construction and safer construction.

[0110] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0111] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A construction method for hoisting steel structure beams of photovoltaic glass furnace based on BIM model, characterized by: The specific operations are as follows: Step 1: Model establishment: Use BIM software to establish the construction model of steel structure beams and glass kiln; Step 2: simulate the lifting path, lifting point and installation position of the beam to determine the placement of the lifting equipment; Step 3: Collision detection: perform collision detection in the BIM model; Step 4: Optimize the hoisting plan: Use BIM software to simulate different hoisting plans, analyze the stress conditions during the hoisting process, and find the optimal solution; Step 5: Use BIM software to simulate the structural stability after installation. If the structural stability is lower than the national standard, return to step 2; Step 6. Hoisting implementation: According to the hoisting path and plan of the BIM model, set up the hoisting equipment on site, guide the hoisting beams according to the hoisting points in the BIM model, monitor the hoisting process in real time through the BIM model, adjust the position of the hoisting equipment and steel structure beams, and install and fix the beams according to the guidance of the BIM model.

2. According to claim 1, a construction method for hoisting steel structure beams of a photovoltaic glass furnace based on a BIM model, characterized in that: The model building in step 1 also includes the following detailed steps: S1.

1. Select one of Revit, AutoCAD Civil 3D or Tekla Structures as the BIM software; S1.

2. Collect design drawings and information: Collect design drawings, CAD files and technical parameter information of steel structure beams and glass kilns for subsequent modeling; S1.

3. Create a new project in the selected BIM software, set the project units and coordinate system, import the CAD files, and import the collected design drawings and CAD files into the BIM software as the basis for modeling; S1.

4. Create architectural elements of steel structure beams and glass furnaces in BIM software, including walls, floors, roofs and glass furnace equipment, based on the imported CAD files, and add detailed attributes and parameters for each architectural element, including size, material and weight information; S1.

5. Build a three-dimensional model of the steel structure beam and glass kiln based on the design drawings and data.

3. The construction method for hoisting the steel structure beam of a photovoltaic glass furnace based on a BIM model according to claim 1 is characterized in that: The step 2 also includes the following detailed steps: S2.

1. Open the established steel structure beam and glass furnace construction model, and ensure that the model contains the accurate size, material and weight information of the beam; S2.

2. Determine the lifting starting point: According to the actual situation, determine the lifting starting point of the beam in the model and create the lifting point coordinates. According to the construction site conditions, determine the lifting path of the beam, including the horizontal movement path and the vertical lifting path. According to the structure and weight of the beam, determine the position of the lifting point. S2.

3. Add cranes and lifting ropes to the model, set lifting capacity and length parameters, and use the lifting simulation function provided by the BIM software to simulate the lifting process of the steel structure beam, including the lifting, moving and lowering steps; S2.

4. Analyze the stress conditions: During the simulation process, analyze the stress conditions of the lifting equipment. According to the simulation results and stress analysis, adjust the lifting path, lifting points and the placement of the lifting equipment as needed; S2.

5. Determine the installation position: According to the simulation results and the optimized lifting plan, determine that the final installation position of the steel structure beam is consistent with the building structure, and export the simulated lifting path, lifting point and installation position data.

4. The construction method for hoisting the steel structure beam of a photovoltaic glass furnace based on a BIM model according to claim 1 is characterized in that: The step three also includes the following detailed steps: S3.

1. Open the established steel structure beam and glass furnace construction model in the selected BIM software; S3.

2. Find the collision detection tool or plug-in in the BIM software and set it up, including setting the collision detection range and accuracy parameters. According to project requirements, select the components, equipment and parts that need to be collided, or select the entire model and specific components for detection; S3.

3. Start the collision detection tool to perform collision detection between the selected components in the model. The software automatically analyzes the relationship between each component and detects whether there is a collision. After the collision detection is completed, the software lists all collision situations, including the specific location and type of the collision.

5. The construction method for hoisting the steel structure beam of a photovoltaic glass furnace based on a BIM model according to claim 1 is characterized in that: In the step three, collision is detected and traced, and the traceability logic is: when a single component collides, the volume of its own part is magnified by 300% proportionally, and the nearby parts wrapped in this range form a traceability range. The traceability range is layered, and each 30% close to the collision component is a traceability sub-layer, totaling ten layers. The traceability range of each layer increases by 10%, and a traceability query is performed on the source of the component itself for every 5% traceability range, and the query results are displayed in a list. The traceability expression is: in: 300%V means that when a single component collides, 300% of its own volume is used as the initial traceability range; i ranges from 1 to 10, indicating that for each collision component, the parts around the collision component are layered in increments of 30%, for a total of ten layers, and the traceability range of each layer increases by 10%V; j ranges from 1 to 20, indicating that within the traceability range of each layer, a traceability query is performed to the component's own source every 5% of the range, and the final results are displayed in a list.

6. The construction method for hoisting the steel structure beam of a photovoltaic glass furnace based on a BIM model according to claim 1 is characterized in that: The step 4 also includes the following detailed steps: S4.

1. Open the file containing the steel structure beam and glass furnace construction model in the selected BIM software; prepare different lifting plans according to the actual situation and needs, including lifting paths, lifting points and lifting equipment variables; S4.

2. Simulate the hoisting process: Use the hoisting simulation function in the BIM software to import different hoisting schemes one by one to simulate the hoisting process of the steel structure beam, including the lifting, moving and lowering steps; S4.

3. Analyze the stress conditions: During the simulation process, analyze the stress conditions of the lifting equipment and beam structure under each lifting scheme, including the stress points and the magnitude of the stress; S4.

4. Compare the lifting schemes: Compare and analyze the stress conditions of various lifting schemes to find the optimal scheme with the least impact on the construction of steel structure beams and glass kiln and the highest safety; S4.

5. Optimize the best solution: Based on the analysis results, further optimize and adjust the best solution, including adjusting the position of the lifting equipment and considering adding auxiliary supports. Preferably, the expression of step 4 is: S represents the total force value; e represents the number of lifting points; P e Indicates the force value of the e-th lifting point; D e Indicates the distance to the e-th lifting point.

7. The construction method for hoisting the steel structure beam of a photovoltaic glass furnace based on a BIM model according to claim 1 is characterized in that: The step 5 is expressed using a conditional statement, and the expression is: Return to step 2 S represents the stability index of the structure; GB stands for the national standard index.

8. The construction method for hoisting steel structure beams of photovoltaic glass furnace based on BIM model according to claim 1 is characterized by: In step six, the BIM model monitors the hoisting process in real time, uses on-site sensors, scanners or drones to capture data in real time, and adjusts the positions of the hoisting equipment and steel structure beams.

Citation Information

Cited By

  • Thermal power engineering construction hoisting path optimization method and device combined with BIM (Building Information Modeling)

    CN119783196A

  • Method and system for hoisting and unloading old beam body by double cranes based on BIM (Building Information Modeling) technology

    CN121719176A