Complex geological condition tunnel blasting design method based on explosive density partition
By using density adjustable explosives in tunnel blasting design, adjusting the single consumption of the gun hole and loading density, forming explosive density partitions, the shortcomings of tunnel blasting design under complex geological conditions are solved, the blasting effect and construction efficiency are improved, and the cost is reduced .
Patent Information
- Application Number
- CN202411208474.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-22
AI Technical Summary
Under complex geological conditions, traditional tunnel blasting design methods are difficult to meet the needs of high-quality blasting, and the blasting effect in mechanized drilling and blasting construction is far less than expected, and has a negative impact on construction efficiency and emotions.
Using explosives with adjustable density, the distribution of rock mass at all levels of the tunnel pallet surface is determined, and the single consumption of the gun hole and the charge density are adjusted to form explosive density partitions to realize tunnel blasting design under complex geological conditions, and maintain the traditional blasting design. Parameters and homework habits remain unchanged.
It realizes the differential distribution of explosive energy for rock mass at different levels under complex geological conditions, improves the blasting effect, reduces construction costs, is highly applicable, and avoids additional burdens on technicians and construction personnel.
Smart Images

Figure CN118999285A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel blasting, and more particularly to a tunnel blasting design method under complex geological conditions based on explosive density zoning. Background Art
[0002] With the continuous improvement of the manufacturing level of tunnel construction machinery in my country, various types of tunnel construction machinery have been domestically produced, the mechanization degree of tunnel blasting construction has been continuously improved, tunnel drilling has realized mechanized construction based on rock drilling trolleys, and tunnel charging has broken through the bottleneck of mechanized charging in two technical paths: on-site mixed explosive trolleys and bulk explosive charging trolleys. The mechanization of drilling and charging processes has played a positive role in improving the efficiency, reducing costs, and ensuring safety of tunnel blasting construction. However, the mechanized drilling and blasting construction of tunnels currently still uses the blasting design method formed under the conditions of traditional manual drilling and charging, which makes the blasting effect of mechanized drilling and blasting construction of tunnels far less than expected. In addition, for tunnels with complex geological conditions, the rock mass conditions of the face are complex and changeable, and the traditional blasting design method based on a single rock mass condition can no longer meet the requirements of high-quality tunnel blasting. Therefore, under the premise of mechanized drilling and blasting of tunnels, a tunnel blasting design method that adapts to complex geological conditions is urgently needed.
[0003] For tunnel blasting design under complex geological conditions, technicians adjust the blasting design based on engineering experience and face rock characteristics on the basis of traditional tunnel blasting design methods. However, the above method has some shortcomings. On the one hand, technicians have no time to adjust the blasting design in most cases. On the other hand, the adjusted blasting design has a negative impact on the construction efficiency and mood of construction workers. It can be seen that how to achieve tunnel blasting design that adapts to complex geological conditions without changing traditional blasting parameters to the greatest extent is still a problem to be solved.
[0004] Therefore, the use of density-adjustable explosives is considered to achieve differential distribution of explosive energy for different levels of rock mass at the face. Without changing the blasting hole network parameters and the working habits of construction workers, tunnel blasting design for complex geological conditions based on traditional blasting design is implemented to ensure the expected tunnel blasting excavation effect. Summary of the invention
[0005] In view of this, for mechanized tunnel drilling and blasting conditions, the present invention provides a tunnel blasting design method for complex geological conditions based on explosive density zoning. For different levels of rock mass on the face, density-adjustable explosives are used to achieve differential distribution of explosive energy. Under the premise of not changing the tunnel blasting hole network parameters and the working habits of construction workers, the tunnel blasting design for complex geological conditions is realized, which helps to ensure the expected tunnel blasting excavation effect and save construction costs.
[0006] To achieve the above object, the technical solution adopted by the present invention is:
[0007] An embodiment of the present invention provides a method for tunnel blasting design under complex geological conditions based on explosive density zoning, the method comprising:
[0008] (1) Determine the distribution of rock mass at the tunnel face: Conduct a survey of the rock mass conditions at the tunnel face, measure and determine the distribution range of rock mass at each level at the tunnel face, form a distribution map of rock mass at each level at the tunnel face, and mark the specific level of rock mass and the corresponding strength coefficient in each distribution area.
[0009] (2) Tunnel preliminary blasting design: The rock mass level of the tunnel face is uniformly regarded as the best level among all levels of rock mass of the tunnel face, and conventional blasting design is carried out to determine the tunnel blasting hole network parameters and the charge amount of blast holes such as slot holes, auxiliary holes and peripheral holes. A preliminary blasting design scheme based on single rock mass conditions is obtained.
[0010] (3) Adjusting the blasting unit consumption in the tunnel surrounding rock areas of different levels: Based on the distribution map of the various levels of rock mass on the tunnel face and the preliminary blasting design plan, the blasting unit consumption in the area with lower rock mass level is determined according to the actual rock mass level. The blasting unit consumption and charge amount in the blasting design in step (2) are corrected accordingly. The blasting hole network parameters in the blasting design in step (2) remain unchanged, and the blasting design plan after adjusting the blasting unit consumption in the local area is obtained.
[0011] (4) Adjust the density of explosives charged in the blastholes in the lower-level rock mass area: Based on the principle of consistent explosive energy, keep the charge length of the blastholes in the unit consumption adjustment area unchanged, and adjust the density of explosives charged in the blastholes in the corresponding area according to the unit consumption of the blastholes in the lower-level rock mass area determined in step (3). The charge structure of the blastholes in the unit consumption adjustment area can adopt a coupled charge structure or an uncoupled charge structure according to actual needs. The calculation method of the explosive adjustment density is the same under the two charge structure conditions.
[0012] (5) Determine the charge density zoning of the rock mass areas at each level of the tunnel face: According to the calculation result of the adjusted density of the explosives charged in the blastholes within the unit consumption adjustment area, density-adjustable bulk emulsion explosives or mixed explosives with corresponding densities are equipped, and the explosive density of the blasthole charge in the unit consumption adjustment area in the blasting design is corrected in step (3), so as to realize the charge density zoning (i.e., explosive density zoning) of the rock mass areas at each level of the tunnel face, and obtain the tunnel blasting design scheme based on the explosive density zoning.
[0013] (6) Refining the charge density zoning of the tunnel face: Based on the blasting design scheme obtained in step (5), the charge density zoning of the tunnel face is locally refined according to the control requirements of harmful effects such as blasting vibration or special blasting excavation requirements, so as to obtain the final tunnel blasting design scheme that adapts to complex geological conditions.
[0014] Compared with the prior art, the present invention, based on the traditional tunnel blasting design method based on single rock mass conditions, only uses density-adjustable explosives to correct the unit consumption of local areas of the tunnel face, realizes the charging density zoning of rock mass areas at all levels of the tunnel face, and forms a tunnel blasting design method for complex geological conditions based on explosive density zoning. The method has at least the following beneficial effects:
[0015] 1. The method of the present invention forms charging density zones for various levels of rock mass areas by charging density-adjustable explosives, realizes tunnel blasting design under complex geological conditions based on explosive density zones, can solve complex working conditions such as interlaced soft and hard surrounding rocks, is suitable for working conditions with different geological conditions and different blasthole arrangements, has strong applicability, and can be widely promoted.
[0016] 2. The method of the present invention does not change the traditional tunnel blasting design procedure, but only partially amends the formed traditional tunnel blasting design scheme, thereby avoiding adding complex work tasks to the technical personnel and ensuring the continuity of the blasting design work.
[0017] 3. The method of the present invention does not change the parameters such as the hole network parameters and blasthole length determined based on the traditional tunnel blasting design, and does not need to change the original working mode of blasting management, technology and construction personnel. It is easy to be widely accepted by on-site construction units and management, technology, construction personnel, etc., does not require additional operation training, and does not affect the construction mood and efficiency of construction workers.
[0018] 4. This method takes into account both the blasting effect and the control of harmful effects of blasting under complex geological conditions. On the premise of meeting the blasting effect, it avoids additional engineering measures and saves construction costs.
[0019] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the written description and the accompanying drawings.
[0020] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, a brief introduction will be given below to the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0022] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.
[0023] Figure 1 A schematic diagram of a simplified flow chart of a tunnel blasting design method for complex geological conditions based on explosive density zoning provided in an embodiment of the present invention.
[0024] Figure 2 A schematic diagram of the rock mass distribution at the tunnel face provided by an embodiment of the present invention.
[0025] Figure 3 A schematic diagram of a conventional blasting design provided in an embodiment of the present invention.
[0026] Figure 4 A schematic diagram of tunnel blasting design under complex geological conditions based on explosive density zoning provided in an embodiment of the present invention. DETAILED DESCRIPTION
[0027] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.
[0028] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0029] See also Figure 1 As shown, the present invention provides a tunnel blasting design method for complex geological conditions based on explosive density zoning, and the method mainly includes the following steps:
[0030] S1. Obtain the rock mass distribution data at all levels of the tunnel face;
[0031] S2. Take the highest performance level among all levels of rock mass at the tunnel face as the unified rock mass level of the tunnel face, carry out blasting design, determine tunnel blasting related parameters, and obtain a preliminary blasting design plan based on single rock mass conditions;
[0032] S3. Based on the preliminary blasting design, adjust the blasthole consumption of each level of rock mass area according to the rock mass performance level;
[0033] S4. Keep the charge length of the blasthole unchanged, and adjust the charge density of the blastholes in each level of rock mass area according to the adjusted blasthole unit consumption;
[0034] S5. According to the adjusted charge density of the blastholes, density-adjustable explosives are correspondingly provided in the blasthole unit consumption adjustment area, and the explosive density zoning of the rock mass areas at all levels of the tunnel face is determined to obtain a tunnel blasting design plan based on the explosive density zoning.
[0035] S6. Based on the need to control the harmful effects of blasting vibration or other relevant blasting requirements, the density of explosives at the tunnel face is locally refined to obtain the final tunnel blasting design plan that adapts to complex geological conditions.
[0036] Taking a railway tunnel under construction as an example, the specific implementation mode of the method of the present invention and the working principle involved are described in detail below:
[0037] This embodiment is a railway tunnel under construction, the rock mass conditions in the tunnel face are complex, and the soft and hard rocks are staggered on the tunnel face. The traditional tunnel blasting design method based on a single rock mass condition is used, and the tunnel blasting excavation effect is not as expected. In order to obtain the ideal tunnel excavation blasting effect under complex geological conditions, a tunnel blasting design method under complex geological conditions based on explosive density zoning proposed in the present invention is used to carry out blasting design for the tunnel under construction, and the specific implementation is as follows:
[0038] (1) Determine the rock mass distribution at the tunnel face:
[0039] In this embodiment, the rock mass condition of the tunnel face is first investigated. It is found that the rock mass condition of the tunnel face can be divided into four interlaced areas. The distribution range of the rock mass of each level of the tunnel face is determined by measuring with instruments such as a three-dimensional laser scanner, and a distribution map of the rock mass of each level of the tunnel face is formed. According to the tunnel geological survey data, the specific level (III, IV, V) of the rock mass in each distribution area and the corresponding strength coefficient f (6-12) are marked, and the distribution of the rock mass of the tunnel face is obtained as follows: Figure 2 shown.
[0040] (2) Carry out conventional tunnel blasting design:
[0041] The present invention uniformly regards the rock mass level of the tunnel face as the level with the best performance among the various rock masses of the tunnel face, that is, level III surrounding rock (A zone); conventional blasting design (preliminary blasting design) is carried out according to level III surrounding rock, and the tunnel blasting hole network parameters and the charge amount of blast holes such as slot holes, auxiliary holes and peripheral holes are determined to obtain a preliminary blasting design scheme based on a single rock mass condition, as shown in the following example. Figure 3 As shown, the circular holes in the figure represent blast holes, and the connecting lines between the blast holes represent that the blast holes involved in the connecting lines are detonated simultaneously.
[0042] (3) Adjust the blasting unit consumption in the tunnel surrounding rock areas of different levels:
[0043] according to Figure 2The distribution of various levels of rock mass at the tunnel face is shown in Figure 3 On the basis of the preliminary blasting design shown in FIG1 , the blasthole consumption in the area with lower rock mass grade (B-D area) is determined according to the actual rock mass grade, and the blasthole consumption and charge amount in the blasting design in step (2) are corrected accordingly. The blasting hole network parameters in the blasting design in step (2) remain unchanged, and the blasting design scheme after the blasthole consumption in the local area is obtained. The consumption of the B-D area before and after the adjustment is shown in Table 1.
[0044] Table 1 Unit consumption adjustment table for each level of rock mass area
[0045] area <![CDATA[Traditional design unit consumption (kg / m 3 )]]> <![CDATA[Adjusted specific consumption (kg / m 3 )]]> Zone B 1.8 1.7 Zone C 1.8 1.6 Area D 1.8 1.5
[0046] The unit consumption in Table 1 is based on a density of 1200kg / m 3 emulsion explosives shall prevail.
[0047] (4) Adjust the density of explosives in blastholes in rock mass areas with lower grade:
[0048] Based on the principle of consistent explosive energy, the length of the charge in the blastholes in the unit consumption adjustment area is kept unchanged. According to the unit consumption of the blastholes in the lower-grade rock mass area determined in step (3), the density of the explosives in the blastholes in the corresponding area is adjusted. The adjusted density of the explosives in the blastholes in the B-D area is shown in Table 2.
[0049] Table 2 Adjustment table of explosive density for blasthole filling in various rock mass areas
[0050] area <![CDATA[Density of traditional design filled explosives (kg / m 3 )]]> <![CDATA[Adjusted density of the loaded explosive (kg / m 3 )]]> Zone B 1200 1100 Zone C 1200 1000 Area D 1200 800
[0051] (5) Determine the charge density zones at each level of rock mass in the tunnel face:
[0052] According to the calculation result of the density adjustment of the explosives charged in the blastholes in the unit consumption adjustment area, the density-adjustable bulk emulsion explosives or mixed explosives with corresponding density are equipped, and the explosive density of the blasthole charge in the unit consumption adjustment area in the blasting design is corrected in step (3), so as to realize the charge density zoning of the rock mass areas at all levels of the tunnel face. The tunnel blasting design scheme under complex geological conditions based on the explosive density zoning is as follows: Figure 4 shown.
[0053] (6) Refine the charging density zoning of the tunnel face:
[0054] Furthermore, based on the blasting design scheme obtained in step (5), the tunnel face charge density zoning is locally refined according to the control requirements of harmful effects such as blasting vibration or special blasting excavation requirements, so as to obtain the final tunnel blasting design scheme that adapts to complex geological conditions.
[0055] From the description of the above embodiments, those skilled in the art can know that the present invention provides a method for tunnel blasting design under complex geological conditions based on explosive density zoning, which uses density-adjustable explosives to achieve differential distribution of explosive energy for different levels of rock mass at the face, and implements tunnel blasting design under complex geological conditions based on traditional blasting design without changing the blasting hole network parameters and the working habits of construction workers, which is conducive to ensuring the expected tunnel blasting excavation effect. The method of the present invention takes into account both the blasting effect and the control of harmful effects of blasting under complex geological conditions, avoids additional engineering measures, and can save construction costs. The method of the present invention can solve complex working conditions such as the interlacing of soft and hard surrounding rocks, is suitable for different geological conditions and different blast hole conditions, has strong applicability, and can be widely promoted.
[0056] Furthermore, the present invention also provides a complex geological condition tunnel blasting design system based on explosive density zoning, which is applied to a complex geological condition tunnel blasting design method based on explosive density zoning in the above embodiment to perform tunnel blasting design, and the system comprises:
[0057] Data acquisition module, used to obtain rock mass distribution data at all levels of the tunnel face;
[0058] The blasting parameter module is used to take the highest performance level among all levels of rock mass at the tunnel face as the unified rock mass level of the tunnel face, carry out blasting design, determine tunnel blasting related parameters, and obtain a preliminary blasting design plan based on a single rock mass condition;
[0059] Unit consumption adjustment module, used to adjust the unit consumption of blastholes in various rock mass areas according to the rock mass performance level based on the preliminary blasting design plan;
[0060] The density adjustment module is used to keep the charge length of the blasthole unchanged and adjust the charge density of the blastholes in each level of rock mass area according to the adjusted blasthole unit consumption;
[0061] The density zoning module is used to equip density-adjustable explosives in the blasthole unit consumption adjustment area according to the adjusted blasthole charging density, determine the explosive density zoning of the rock mass areas at all levels of the tunnel face, and obtain the tunnel blasting design plan based on the explosive density zoning.
[0062] The implementation principle and technical effects of the system provided in the embodiment of the present invention are the same as those of the aforementioned method embodiment. For the sake of brief description, for matters not mentioned in the system embodiment, reference can be made to the corresponding contents in the aforementioned method embodiment, which will not be repeated here.
[0063] In the description of the present invention, it should be noted that: in some processes described in the specification and drawings of this application, multiple operations appearing in a specific order are included, but it should be clearly understood that these operations may not be performed in the order in which they appear in this document or may be performed in parallel. In addition, various serial numbers are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0064] It should be noted that the word "comprising" does not exclude the presence of components or steps not listed in the claims. The word "a" or "an" preceding a component does not exclude the presence of a plurality of such components. The invention can be implemented by means of hardware comprising several distinct components, and by means of a suitably programmed computer.
[0065] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0066] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A tunnel blasting design method for complex geological conditions based on explosive density zoning, characterized in that: The method comprises the following steps: S1. Obtain the rock mass distribution data at all levels of the tunnel face; S2. Take the highest performance level among all levels of rock mass at the tunnel face as the unified level of rock mass at the tunnel face, carry out blasting design, determine tunnel blasting related parameters, and obtain a preliminary blasting design plan based on single rock mass conditions; S3. Based on the preliminary blasting design, the unit consumption of blastholes in each level of rock mass is adjusted according to the rock mass performance level; S4. Keep the charge length of the blasthole unchanged, and adjust the charge density of the blastholes in each level of rock mass area according to the adjusted blasthole unit consumption; S5. According to the adjusted charge density of the blastholes, density-adjustable explosives are correspondingly provided in the blasthole unit consumption adjustment area, and the explosive density zoning of the rock mass areas at all levels of the tunnel face is determined to obtain a tunnel blasting design plan based on the explosive density zoning.
2. The method for designing tunnel blasting under complex geological conditions based on explosive density zoning according to claim 1, characterized in that: The method further includes: S6. Based on the need to control the harmful effects of blasting vibration or other relevant blasting requirements, the density of explosives at the tunnel face is locally refined to obtain the final tunnel blasting design plan that adapts to complex geological conditions.
3. The method for designing tunnel blasting under complex geological conditions based on explosive density zoning according to claim 1, characterized in that: In step S1, a three-dimensional laser scanner is used to measure and determine the distribution range of rock masses at various levels on the tunnel face, to form a distribution map of rock masses at various levels on the tunnel face, and to mark the specific level and strength coefficient of rock mass performance in each distribution area.
4. The method for designing tunnel blasting under complex geological conditions based on explosive density zoning according to claim 1, characterized in that: In step S2, the tunnel blasting related parameters include: tunnel blasting hole network parameters and blast hole charges of the slot holes, auxiliary holes and peripheral holes.
5. The method for designing tunnel blasting under complex geological conditions based on explosive density zoning according to claim 3, characterized in that: In step S3, according to the distribution map of rock masses at various levels on the tunnel face, on the basis of the preliminary blasting design plan, the blasthole consumption in each level of rock mass area is determined according to the actual rock mass level, the blasthole consumption and charge amount in the preliminary blasting design plan are corrected accordingly, and the blasting hole network parameters in the preliminary blasting design plan are kept unchanged, so as to obtain a blasting design plan after the blasthole consumption in the local area of the rock mass is adjusted.
6. The method for designing tunnel blasting under complex geological conditions based on explosive density zoning according to claim 1, characterized in that: In step S4, the charge structure of the blastholes in the blasthole unit consumption adjustment area adopts a coupled charge structure or a non-coupled charge structure.
7. The method for designing tunnel blasting under complex geological conditions based on explosive density zoning according to claim 1, characterized in that: In the step S5, the density-adjustable explosive is: bulk emulsion explosive or mixed explosive with adjustable density.
Citation Information
Patent Citations
Extra-long lower step blasting construction method based on blasting refined analysis
CN114719698A
Tunnel wedge cut blasting design method based on multi-element geological information
CN117592317A
Tunnel excavation partition combination smooth blasting method
CN117824447A
Cited By
Tunnel blasting parameter optimization method and system based on data driving
CN122174516A
Data-driven tunnel blasting parameter optimization method and system
CN122174516B