Method and system for calculating overall stability of slope filling body
By establishing the stability equation based on soil pressure, water and filling body load, combined with the anchor setting, the lack of stability calculation of new slope filling body is solved, and the safety of the filling body on the foundation pit of the nuclear power plant is achieved. Sex assessment and construction efficiency improvement.
Patent Information
- Application Number
- CN202411160064.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-11-22
AI Technical Summary
The existing technology lacks an overall stability calculation method for new slope filling bodies, and cannot effectively evaluate the stability of slope filling bodies in nuclear power plant foundation pits, resulting in difficult to ensure construction safety and compliance.
Based on soil pressure, water and top load of the filling body, horizontal anti-slip and anti-tilt stability equations are established, and stress analysis is carried out in combination with anchor setting to provide a unified and targeted stability calculation method.
The stability evaluation of the new slope filling body was achieved, ensuring the safety and efficiency of simultaneous construction in the foundation pit and the top of the foundation pit, filling the gaps in existing theories, and suitable for specific scenarios in deep foundation pit projects.
Smart Images

Figure CN119004625A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of engineering mechanics, and in particular to a method and system for calculating the overall stability of a slope filling body. Background Art
[0002] The construction of the nuclear island of a nuclear power plant requires a large excavation of the nuclear island foundation pit. According to the conventional construction process, the nuclear island plant building must first be built inside the foundation pit. After its main structure is completed and reaches the ground elevation, the foundation pit is backfilled, and then the auxiliary plant building is built at the edge of the foundation pit. At present, in order to improve construction efficiency and logic optimization, it is proposed to simultaneously promote the construction of the nuclear island plant building inside the foundation pit and the plant building on the top of the foundation pit slope.
[0003] This plan requires the use of concrete materials to fill the original slope surface in advance to form a new vertical concrete fill body, which will be close to the outside of the original slope, thereby providing a stable foundation platform for the construction of the factory building on the top of the slope before the foundation pit is backfilled.
[0004] Due to the uniqueness of this new type of slope fill design, the current national standards "Technical Specifications for Building Slope Engineering" (GB50330-2013) and "Technical Specifications for Identification and Reinforcement of Building Slope Engineering" (GB50843-2013) do not include specific calculation methods or design instructions for this type of specific slope fill. The pile-sheet retaining wall, cantilever retaining wall, buttress retaining wall, gravity retaining wall and anchor retaining wall structures covered by the current standards cannot be directly applied to the mechanical analysis and design calculation of this new type of fill.
[0005] In view of this, it is necessary to explore and formulate corresponding technical criteria and calculation models for the overall stability assessment of this new type of slope fill to ensure the safety, efficiency and compliance of the nuclear island construction of nuclear power plants. Summary of the invention
[0006] In order to solve the above problems, the present invention proposes a method and system for calculating the overall stability of slope fill. In order to meet the scenarios of the same construction inside and on the top of the foundation pit, the present invention considers the stress conditions of the fill under this special scenario, that is, based on the soil pressure, water, the load on the top of the fill and the setting of anchor rods, the stress analysis of the fill is carried out and the stability equation is established, thereby providing a unified and targeted stability analysis method for new fill, filling the gap in the existing theory.
[0007] In order to achieve the above object, the present invention adopts the following technical solution:
[0008] In a first aspect, the present invention provides a method for calculating the overall stability of a slope fill body, comprising:
[0009] According to the anchor setting, the force analysis of the fill body is carried out based on the earth pressure, water and the top load of the fill body, and the horizontal anti-sliding stability equation of the fill body and the anti-tilting stability equation around the front wall toe are established respectively;
[0010] The slope fill stability calculation parameters are determined based on the site investigation data, and the parameters are substituted into the equation for calculation.
[0011] Preferably, before performing stress analysis on the compacted body, a coordinate system is established with the horizontal direction of the lower corner point of the compacted body as the x-axis and the height direction of the lower corner point of the compacted body as the z-axis.
[0012] Preferably, the stress analysis of the compacted body is performed based on the earth pressure, water and the top load of the compacted body according to the setting of the anchor rods, and the horizontal anti-sliding stability equation and the anti-tilting stability equation around the front wall toe of the compacted body are established respectively, which specifically includes:
[0013] Without considering the anchor rod, the first level anti-sliding stability equation is:
[0014]
[0015] Among them, W n is the linear weight of the compacted structure, in kN / m; q1 is the uniformly distributed load on the top of the slope; L1 is the top width of the compacted structure; E a1n V is the vertical component of earth pressure acting on the fill; w is the vertical upward buoyancy generated by water on the new fill; μ is the friction coefficient at the bottom of the fill; E a1t H is the horizontal component of earth pressure acting on the fill; w is the horizontal lateral thrust generated by water on the fill body; γ0 is the structural importance coefficient.
[0016] Preferably, without considering the anchor rod, the anti-tilt stability equation of the first winding front wall toe is:
[0017]
[0018] Among them, W n is the linear weight of the compacted body, in kN / m; x0 is the x coordinate of the center of gravity of the compacted body; E aln is the vertical component of earth pressure acting on the fill; a1 is the height z coordinate of the point where the resultant earth pressure behind the fill body acts; E a1t is the horizontal component of earth pressure acting on the fill; a H is the horizontal x coordinate of the point where the resultant earth pressure behind the fill body acts; w is the horizontal lateral thrust exerted by water on the compacted structure; w V is the height z coordinate of the resultant water pressure behind the fill; wis the vertical upward buoyancy of water on the new fill; x w is the x-coordinate of the vertical upward buoyancy generated by the water behind the fill on the new fill; γ0 is the structural importance coefficient.
[0019] Preferably, considering the anchor rod, the second horizontal anti-sliding stability equation is:
[0020]
[0021] Among them, W n is the linear weight of the compacted structure, in kN / m; q1 is the uniformly distributed load on the top of the slope; L1 is the top width of the compacted structure; E a1n V is the vertical component of earth pressure acting on the fill; w is the vertical upward buoyancy generated by water on the new fill; μ is the friction coefficient at the bottom of the fill; Fsi is the pull-out force of a single anchor, ∑Fsi is the pull-out force of multiple anchors; E a1t H is the horizontal component of earth pressure acting on the fill; w is the horizontal lateral thrust generated by water on the fill body; γ0 is the structural importance coefficient.
[0022] Preferably, considering the anchor rod, the anti-tilt stability equation of the second winding front wall toe is:
[0023]
[0024] Among them, W n is the linear weight of the compacted body, in kN / m; x0 is the x-coordinate of the center of gravity of the compacted body; ∑Fsi is the resultant pull-out force of multiple anchors; D f is the force arm of the anchor rod around the origin of coordinates; E aln is the vertical component of earth pressure acting on the fill; a1 is the height z coordinate of the point where the resultant earth pressure behind the fill body acts; E a1t is the horizontal component of earth pressure acting on the fill; a H is the horizontal x coordinate of the point where the resultant earth pressure behind the fill body acts; w is the horizontal lateral thrust exerted by water on the compacted structure; w V is the height z coordinate of the resultant water pressure behind the fill; w is the vertical upward buoyancy of water on the new fill; x w is the x-coordinate of the vertical upward buoyancy generated by the water behind the fill on the new fill; γ0 is the structural importance coefficient.
[0025] Preferably, the slope fill stability calculation parameters are determined based on site investigation data, and the parameters are substituted into the equation for calculation. If the stability calculation result is less than a preset index, the anchor length is lengthened and the number of anchors is increased to meet the condition that no slip occurs in the potential slip area.
[0026] In a second aspect, the present invention provides a slope fill overall stability calculation system, comprising:
[0027] The equation building module is configured to perform a stress analysis on the compacted body based on the earth pressure, water and the top load of the compacted body according to the anchor setting conditions, and to respectively establish a horizontal anti-sliding stability equation of the compacted body and an anti-tilting stability equation around the front wall toe;
[0028] The stability calculation module is configured to determine the slope fill stability calculation parameters according to the site investigation data, and substitute the parameters into the equation for calculation.
[0029] In a third aspect, the present invention provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of the method for calculating the overall stability of a slope fill body described in the first aspect.
[0030] In a fourth aspect, the present invention provides a computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the steps in the method for calculating the overall stability of a slope fill body described in the first aspect are implemented.
[0031] Compared with the prior art, the present invention has the following beneficial effects:
[0032] In some projects with deep foundation pits, it is necessary to reinforce the fill on the slope to meet the requirements of early construction of the building on the top of the slope. The present invention provides a calculation method for the stability of the new fill on this special slope, taking into account the stress conditions of the fill in this special scenario, that is, based on the soil pressure, water, the load on the top of the fill and the setting of the anchor rods, the fill is subjected to stress analysis and a stability equation is established, and the stability of the fill is analyzed to meet the requirements of the construction of high-load buildings on the top of the slope. The new overall stability analysis and calculation model proposed by the present invention fills the gaps in existing theories. The overall stability calculation model and assumptions of the fill are simple, reasonable and reliable.
[0033] The method for calculating the overall stability of slope fill bodies described in the present invention can be applied to projects that require the construction of adjacent buildings both inside and on top of a foundation pit, such as in the construction of a nuclear power plant, so that the plant building inside the foundation pit and the building on top of the foundation pit meet the construction conditions at the same time, decoupling the construction of the two plant buildings, greatly saving construction time and improving on-site operation efficiency.
[0034] Advantages of additional aspects of the present invention will be given in part in the following description, and in part will become obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their description are used to explain the present invention but do not constitute a limitation of the present invention.
[0036] Figure 1 A schematic diagram of the same type of construction performed inside a foundation pit and on top of a foundation pit provided in the first embodiment of the present invention;
[0037] Figure 2 A main flow chart of a method for calculating the overall stability of a slope fill provided in the first embodiment of the present invention;
[0038] Figure 3 This is a schematic diagram of the stress analysis of the compacted material provided in the first embodiment of the present invention. DETAILED DESCRIPTION
[0039] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0040] In general engineering practice, for two buildings with different buried depths, the one with a deeper excavation depth is constructed first, and the one with a shallower buried depth is constructed later. For example, in a nuclear power plant, the nuclear island plant has 4 floors above ground and 2 floors underground; the adjacent plant has 4 floors above ground and no basement. The construction sequence is to excavate a deep foundation pit, first construct the two-story basement of the nuclear island plant, and after the nuclear island plant reaches the ground elevation, the surrounding slopes of the plant are backfilled to the ground elevation. The foundation of the adjacent building is completed, and then the adjacent plant without a basement can be started. This construction sequence can ensure the safe construction of the project.
[0041] In some deep foundation pit projects, due to special engineering requirements or time constraints, it is necessary to construct adjacent buildings both inside and on top of the foundation pit. First, on the construction surface, the existing slope needs to be backfilled with concrete to form the construction foundation surface for the slope top building. Figure 1 As shown. Secondly, after the concrete filling is completed, it forms a vertical surface, which together with the top surface of the slope supports the construction load of the building on the top of the slope. This makes the slope unstable and unsafe.
[0042] The safety of the fill needs to be evaluated by calculation. Commonly used structural forms, such as pile-board retaining walls, require piles to be driven at the bottom of the slope. The piles are buried to a certain depth to provide thrust resistance, and the main calculation is the mechanical balance of the soil on both sides of the piles; cantilever retaining walls, buttress retaining walls, and gravity retaining walls have requirements for the minimum burial depth of the retaining wall or restrictions on the slope height; anchor retaining walls use reinforced concrete components as the main body of the retaining wall, which is quite different from the fill used in the present invention.
[0043] It can be seen that these structural forms are quite different from the scenarios in which the present invention is applied. The present invention is applied to deep foundations greater than 12m, and a factory building is to be built on the top of the slope, which has higher requirements on the bearing capacity and deformation of the slope. Therefore, due to the different force systems and established calculation models, the existing structural forms are not suitable for the scenarios of the present invention.
[0044] In addition, for the calculation method, the contact surface between the concrete fill and the existing slope is in a state of reverse tilt. According to the formula provided by the gravity retaining wall, the earth pressure is in a negative state, that is, there is no earth pressure. The calculation method of the gravity retaining wall is not applicable.
[0045] Since there is no retaining wall in the backfill of the built-up body in the scenario proposed in this embodiment, various retaining wall stability analyses based on existing specifications are not applicable. For new built-up bodies, the present invention proposes a new overall stability analysis and calculation model to fill the gaps in existing theories.
[0046] Embodiment 1
[0047] like Figure 2 As shown, this embodiment discloses a method for calculating the overall stability of a slope fill body, comprising the following steps:
[0048] S1: According to the setting of anchor rods, the stress analysis of the fill is carried out based on the earth pressure, water and the top load of the fill, and the horizontal anti-sliding stability equation of the fill and the anti-tilting stability equation around the toe of the front wall are established respectively;
[0049] S2: Determine the slope fill stability calculation parameters based on the site investigation data, and substitute the parameters into the equation for calculation.
[0050] Next, combine Figure 2 , a method for calculating the overall stability of a slope fill disclosed in this embodiment is described in detail.
[0051] In some deep foundation pit projects, due to special engineering requirements, adjacent buildings need to be constructed both inside and on top of the foundation pit. Therefore, the existing slope needs to be reinforced with concrete backfill, such as Figure 1 .
[0052] The concrete fill forms a vertical surface after completion, which is used to support the construction load of the building on the slope top. The safety of the fill needs to be evaluated by calculation.
[0053] (I) Assumptions
[0054] The following assumptions were used in the calculation of new fill:
[0055] 1. The new fill is a whole, rigid body, and the crack damage surface inside the fill caused by construction quality is not considered;
[0056] 2. The new fill and the original slope are densely filled, and the bearing capacity and modulus of the underlying bedrock are extremely high, so no slip failure will occur along the interface.
[0057] (II) Model calculation scheme
[0058] Because groundwater will produce vertical upward buoyancy on the fill, this will reduce the effective weight of the fill to a certain extent, thereby increasing the possibility of its sliding; in addition, the horizontal lateral thrust generated by groundwater on the fill is also a factor that cannot be ignored. This lateral thrust will increase the horizontal load on the fill and reduce its anti-overturning stability; at the same time, the presence of water will change the physical and mechanical properties of the soil, such as reducing the internal friction angle and cohesion of the soil, which will directly affect the anti-sliding stability of the fill.
[0059] Therefore, in this embodiment, when calculating the horizontal anti-sliding stability of the fill body and the anti-tilting stability around the front wall toe, the effect of the groundwater behind is taken into account. Figure 3 .
[0060] In engineering practice, in order to improve the structural safety, anchor rods are anchored inside the potential slip surface. This embodiment provides two cases, one without considering anchor rods and the other with considering anchor rods, just for calculation comparison. According to practice and judgment, it must be safer to add anchor rods. The calculation of the case where the fill body is not anchored is to consider whether the fill body itself is in a structural safety state.
[0061] 1. Without considering anchor rods
[0062] (1) Formula for horizontal anti-sliding stability of landfill:
[0063]
[0064] Among them, W n is the linear weight of the compacted structure, in kN / m; q1 is the uniformly distributed load on the top of the slope (the top part of the compacted structure); L1 is the top width of the compacted structure; E aln V is the vertical component of earth pressure acting on the fill (positive upward); w is the vertical upward buoyancy generated by water on the new fill; μ is the friction coefficient at the bottom of the fill; Ea1t H is the horizontal component of earth pressure acting on the fill; w is the horizontal lateral thrust generated by water on the fill body; γ0 is the structural importance coefficient.
[0065] (2) Anti-overturning calculation of fill:
[0066]
[0067] Among them, W n is the linear weight of the compacted body, in kN / m; x0 is the x coordinate of the center of gravity of the compacted body; E aln is the vertical component of earth pressure acting on the fill; a1 is the height z coordinate of the point where the resultant earth pressure behind the fill body acts; E a1t is the horizontal component of earth pressure acting on the fill; a H is the horizontal x coordinate of the point where the resultant earth pressure behind the fill body acts; w is the horizontal lateral thrust exerted by water on the compacted structure; w V is the height z coordinate of the resultant water pressure behind the fill; w is the vertical upward buoyancy of water on the new fill; x w is the x-coordinate of the vertical upward buoyancy generated by the water behind the fill on the new fill; γ0 is the structural importance coefficient.
[0068] This embodiment takes into account the effects of water buoyancy and horizontal lateral thrust, and can evaluate the impact of water on the stability of the landfill, thereby preventing landslides or collapses caused by the effects of water. At the same time, the introduction of the structural importance coefficient can adjust the safety factor according to the importance and safety level of the project, ensuring the safety of the project under different conditions. In addition, the line weight is a direct reflection of the gravity of the landfill itself, and is the basis for calculating the anti-sliding stability. Considering the line weight can ensure that the downward trend of the landfill due to gravity is included in the calculation, thereby more accurately evaluating its stability.
[0069] 2. Considering anchor bolts
[0070] (1) Formula for horizontal anti-sliding stability of landfill:
[0071]
[0072] Among them, W n is the linear weight of the compacted structure, in kN / m; q1 is the uniformly distributed load on the top of the slope (the top part of the compacted structure); L1 is the top width of the compacted structure; E aln V is the vertical component of earth pressure acting on the fill (positive upward); wis the vertical upward buoyancy generated by water on the new fill; μ is the friction coefficient at the bottom of the fill; Fsi is the pull-out force of a single anchor, ∑Fsi is the pull-out force of multiple anchors; E a1t H is the horizontal component of earth pressure acting on the fill; w is the horizontal lateral thrust generated by water on the fill body; γ0 is the structural importance coefficient.
[0073] (2) Anti-overturning calculation of fill:
[0074]
[0075] Among them, W n is the linear weight of the compacted body, in kN / m; x0 is the x-coordinate of the center of gravity of the compacted body; ∑Fsi is the resultant pull-out force of multiple anchors; D f is the force arm of the anchor rod around the origin of coordinates; E aln is the vertical component of earth pressure acting on the fill; a1 is the height z coordinate of the point where the resultant earth pressure behind the fill body acts; E a1t is the horizontal component of earth pressure acting on the fill; a H is the horizontal x coordinate of the point where the resultant earth pressure behind the fill body acts; w is the horizontal lateral thrust exerted by water on the compacted structure; w V is the height z coordinate of the resultant water pressure behind the fill; w is the vertical upward buoyancy of water on the new fill; x w is the x-coordinate of the vertical upward buoyancy generated by the water behind the fill on the new fill; γ0 is the structural importance coefficient.
[0076] As a specific implementation method, the friction force generated by the combined force of the anchor rods is ignored, and only the horizontal component is considered, which is safer.
[0077] In this embodiment, the Z coordinate is the height coordinate from the lower corner point of the fill body; the X coordinate is the horizontal coordinate from the lower corner point of the fill body; γ0 is the structural importance coefficient, which is obtained according to the technical specifications of building slope engineering.
[0078] It should be understood that the parameters in the equations described in this embodiment can be obtained by those skilled in the art based on engineering manuals and actual measurements.
[0079] The stability calculation parameters of the slope fill body are determined according to the site investigation data, and the parameters are substituted into the equation for calculation to perform stability analysis on the fill body.
[0080] Since the construction load on the top of the slope is large, it is also necessary to verify or take effective measures for the potential slip surface. The effective measure is to lengthen the length of the anchor rod and anchor it inside the potential slip surface. The number of anchor rods must meet the requirement of no slip. New fill bodies generally need to be equipped with multiple rock anchors to meet stability requirements. It should be understood that the length and number of anchor rods can be determined by those skilled in the art according to actual needs.
[0081] As a specific implementation method, the new fill and the soil outside the potential slip surface need to be anchored to the soil or rock inside the potential slip surface by anchor rods. According to the weight of the anchored soil and the force angle of the anchor rod, the total required anchoring force can be calculated, and the standard value of the tension of each anchor rod can be obtained according to the design of the standard anchor rod. If the anchor rod force is greater than the required anchoring force, no slip will occur. It should be understood that the calculation process can be implemented by those skilled in the art.
[0082] In order to meet the scenario of the same construction being carried out inside and on top of a foundation pit, this specific embodiment takes into account the stress condition of the compact under this special scenario, namely, based on the soil pressure, water, the load on the top of the compact and the setting of anchor rods, a stress analysis of the compact is performed and a stability equation is established, thereby providing a unified and targeted stability analysis method for new compacts, filling the gaps in existing theories.
[0083] Embodiment 2
[0084] This embodiment provides a slope fill body overall stability calculation system, including:
[0085] The equation building module is configured to perform a stress analysis on the compacted body based on the earth pressure, water and the top load of the compacted body according to the anchor setting conditions, and to respectively establish a horizontal anti-sliding stability equation of the compacted body and an anti-tilting stability equation around the front wall toe;
[0086] The stability calculation module is configured to determine the slope fill stability calculation parameters according to the site investigation data, and substitute the parameters into the equation for calculation.
[0087] Embodiment 3
[0088] This embodiment provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the steps in the method for calculating the overall stability of a slope fill body as described in the first embodiment above are implemented.
[0089] Embodiment 4
[0090] This embodiment provides a computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the program, the steps in the method for calculating the overall stability of a slope fill body as described in the first embodiment above are implemented.
[0091] The steps or modules involved in the above embodiments 2 to 4 correspond to those in embodiment 1. For the specific implementation, please refer to the relevant description of embodiment 1. The term "computer-readable storage medium" should be understood as a single medium or multiple media including one or more instruction sets; it should also be understood to include any medium that can store, encode or carry an instruction set for execution by a processor and enable the processor to execute any method in the present invention.
[0092] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for calculating the overall stability of a slope fill, characterized in that: include: According to the anchor setting, the force analysis of the fill body is carried out based on the earth pressure, water and the top load of the fill body, and the horizontal anti-sliding stability equation of the fill body and the anti-tilting stability equation around the front wall toe are established respectively; The slope fill stability calculation parameters are determined based on the site investigation data, and the parameters are substituted into the equation for calculation.
2. A method for calculating the overall stability of a slope fill as claimed in claim 1, characterized in that: Before carrying out stress analysis on the compacted body, a coordinate system is established with the horizontal direction of the lower corner point of the compacted body as the x-axis and the height direction of the lower corner point of the compacted body as the z-axis.
3. A method for calculating the overall stability of a slope fill as claimed in claim 1, characterized in that: According to the anchor setting, the force analysis of the fill body is carried out based on the soil pressure, water and the top load of the fill body, and the horizontal anti-sliding stability equation of the fill body and the anti-tilting stability equation around the front wall toe are established respectively, which specifically includes: Without considering the anchor rod, the first level anti-sliding stability equation is: Among them, W n is the linear weight of the compacted structure, in kN / m; q1 is the uniformly distributed load on the top of the slope; L1 is the top width of the compacted structure; E a1n V is the vertical component of earth pressure acting on the fill; w is the vertical upward buoyancy generated by water on the new fill; μ is the friction coefficient at the bottom of the fill; E a1t H is the horizontal component of earth pressure acting on the fill; w is the horizontal lateral thrust generated by water on the fill body; γ0 is the structural importance coefficient.
4. A method for calculating the overall stability of a slope fill as claimed in claim 3, characterized in that: Also includes: Without considering the anchor rods, the anti-tilt stability equation of the first winding front wall toe is: Among them, W n is the linear weight of the compacted body, in kN / m; x0 is the x coordinate of the center of gravity of the compacted body; E aln is the vertical component of earth pressure acting on the fill; a1 is the height z coordinate of the point where the resultant earth pressure behind the fill body acts; E a1t is the horizontal component of earth pressure acting on the fill; a H is the horizontal x coordinate of the point where the resultant earth pressure behind the fill body acts; w is the horizontal lateral thrust exerted by water on the compacted structure; w V is the height z coordinate of the resultant water pressure behind the fill; w is the vertical upward buoyancy of water on the new fill; x w is the x-coordinate of the vertical upward buoyancy generated by the water behind the fill on the new fill; γ0 is the structural importance coefficient.
5. A method for calculating the overall stability of a slope fill as claimed in claim 3, characterized in that: Also includes: Considering the anchor rod, the second level anti-sliding stability equation is: Among them, W n is the linear weight of the compacted structure, in kN / m; q1 is the uniformly distributed load on the top of the slope; L1 is the top width of the compacted structure; E a1n V is the vertical component of earth pressure acting on the fill; w is the vertical upward buoyancy generated by water on the new fill; μ is the friction coefficient at the bottom of the fill; Fsi is the pull-out force of a single anchor, ∑Fsi is the pull-out force of multiple anchors; E a1t H is the horizontal component of earth pressure acting on the fill; w is the horizontal lateral thrust generated by water on the fill body; γ0 is the structural importance coefficient.
6. A method for calculating the overall stability of a slope fill as claimed in claim 3, characterized in that: Also includes: Considering the anchor rod, the anti-tilt stability equation of the second winding front wall toe is: Among them, W n is the linear weight of the compacted body, in kN / m; x0 is the x-coordinate of the center of gravity of the compacted body; ∑Fsi is the resultant pull-out force of multiple anchors; D f is the force arm of the anchor rod around the origin of coordinates; E aln is the vertical component of earth pressure acting on the fill; a1 is the height z coordinate of the point where the resultant earth pressure behind the fill body acts; E a1t is the horizontal component of earth pressure acting on the fill; a H is the horizontal x coordinate of the point where the resultant earth pressure behind the fill body acts; w is the horizontal lateral thrust exerted by water on the compacted structure; w V is the height z coordinate of the resultant water pressure behind the fill; w is the vertical upward buoyancy of water on the new fill; x w is the x-coordinate of the vertical upward buoyancy generated by the water behind the fill on the new fill; γ0 is the structural importance coefficient.
7. A method for calculating the overall stability of a slope fill as claimed in claim 1, characterized in that: Determine the slope fill stability calculation parameters based on the site investigation data, substitute the parameters into the equation for calculation, and if the stability calculation result is less than the preset index, lengthen the anchor rod length and increase the number of anchor rods to meet the condition that no slip occurs in the potential slip area.
8. A slope fill overall stability calculation system, characterized in that: include: The equation building module is configured to perform a stress analysis on the compacted body based on the earth pressure, water and the top load of the compacted body according to the anchor setting conditions, and to respectively establish a horizontal anti-sliding stability equation of the compacted body and an anti-tilting stability equation around the front wall toe; The stability calculation module is configured to determine the slope fill stability calculation parameters according to the site investigation data, and substitute the parameters into the equation for calculation.
9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the steps of a method for calculating the overall stability of a slope fill body as described in any one of claims 1 to 7 are implemented.
10. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, the The steps in a method for calculating the overall stability of a slope fill as described in any one of claims 1-7.