Experimental system and method for mechanical properties of surrounding rock and supporting structure of tunnels constructed by step method
Through the step method, the mechanical characteristics experimental system of the surrounding rock and support structure of the tunnel are simulated and the impact of advance small conduits under high moisture content is studied, and the problem of insufficient safety and reliability of tunnel construction in the existing technology is solved, and the problem of insufficient tunnel construction is realized. The reliability evaluation of tunnel construction and the optimization of construction parameters were carried out.
Patent Information
- Application Number
- CN201711288024.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2017-12-07
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2037-12-07
AI Technical Summary
The existing technology lacks effective model tests to simulate tunnel construction and on-site environment, especially in the case of high moisture content, the impact of pre-grouting of advance small catheters is insufficient, which makes it difficult to ensure safety and reliability during tunnel construction. .
A step-by-step construction experiment system for mechanical properties of surrounding rock and support structure in tunnels was designed. The tunnel construction was simulated through similar indoor model experiments, and the mechanical characteristics of the excavated palm surface and its different sections in front were obtained, and when the moisture content was high The impact of burial and grouting of advance small conduits on rock mass was studied. Multiple sets of data were analyzed through the data processing center to quantitatively describe the impact of conduit angle and grouting pressure on tunnel excavation.
The reliability study of tunnel construction under different moisture content was achieved, which improved the operability and reliability of the experiment. By comparing laboratory and on-site data, the construction effect of advance small conduits under high moisture content was objectively evaluated, ensuring tunnel construction safety and stability.
Smart Images

Figure CN107991081B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a system and method for testing the mechanical properties of surrounding rock and supporting structure of a tunnel constructed by a step method. Background Art
[0002] With the development of social economy, the ground space is gradually unable to meet the requirements of transportation, and underground engineering is particularly important. As the most important part of underground transportation, the number of subways has increased in recent years. However, during the construction of subways, complex geological environments will be encountered, among which poor geological conditions will make the tunnel excavation process vulnerable to hazards including landslides and water inrush.
[0003] At present, there is still insufficient experimental research on the design of tunnel step construction under different water contents in China, and there is a lack of theoretical support for effective model tests simulating tunnel construction and field environment, especially the impact of advance small-duct pre-grouting under high water content.
[0004] In view of the above existing problems, it is necessary to propose an experimental model and test method to study the reliability of tunnel step method construction under different moisture contents. Summary of the invention
[0005] In order to solve the above problems, the present invention proposes an experimental system and method for the mechanical properties of surrounding rock and supporting structure of tunnels constructed by the step method. The present invention can use similar indoor model tests to simulate the tunnel step method construction, so as to obtain the mechanical characteristics of the excavation face and different sections in front of it, especially the influence of the burial and grouting of advance small guide tubes under high water content.
[0006] In order to achieve the above object, the present invention adopts the following technical solution:
[0007] An experimental system for mechanical properties of surrounding rock and supporting structure of a step-method tunnel construction, comprising a test soil structure unit, a soil containing device, a step-method excavation unit, a data acquisition unit and a data processing center, wherein:
[0008] The soil construction unit is configured to reshape the on-site soil according to different soil parameters to be tested, and during the reshaping process, monitoring elements are buried in the surrounding rock lining part and the excavation section part;
[0009] The soil body containing device is configured to have a certain containing space to contain and fix the test soil body used for monitoring the reshaped test soil body;
[0010] The step method tunnel excavation unit is configured to automatically simulate the on-site step method tunnel excavation process;
[0011] The data acquisition unit receives data obtained by the monitoring element in the soil structure unit and transmits it to the data processing center;
[0012] The data processing center receives monitoring data and determines the mechanical properties of the surrounding rock and supporting structure of the tunnel constructed by the step method under different surrounding rock parameters according to different detection data.
[0013] Furthermore, the soil structure unit is used to treat the soil c, Value (where c is cohesion, The value of internal friction angle) and water content are measured to obtain soil parameters and reshape the soil.
[0014] Furthermore, the reshaped soil model is in proportion to the on-site soil, meeting various mechanical indicators under stress analysis, and the ratio is controlled between 1:15 and 1:25. More preferably, the simulation ratio is adjusted to 1:20.
[0015] Furthermore, the monitoring elements include displacement meters, strain gauges or multi-point displacement meters, which are buried in the monitoring surrounding rock lining part and the excavation section part to measure the lining soil pressure, section soil pressure and stratum settlement.
[0016] Preferably, the monitoring elements comprise a plurality of groups, including those spaced apart at different distances in front of the excavation section, forming a monitoring surface system. Each group of monitoring surfaces comprises a plurality of monitoring lines located in the upper part of the tunnel, with a certain angle between two monitoring lines, and a plurality of monitoring elements are arranged on each monitoring line.
[0017] Furthermore, the soil holding device includes a steel shell, and the shell is provided with tempered glass to observe the construction progress. The shell is provided with a tunnel entrance on at least one side.
[0018] Preferably, a walking mechanism, such as a universal wheel, is provided at the lower end of the shell of the soil containing device to facilitate movement.
[0019] Furthermore, the step method tunnel excavation unit includes a guide rail, a sliding base, a lifting mechanism and a platform, wherein the guide rail is arranged on one side of the tunnel entrance of the soil holding device, the sliding base is movably arranged on the guide rail, the sliding base is provided with a lifting mechanism, and the upper end of the lifting mechanism is provided with a platform, so as to facilitate manual construction using the up and down step method.
[0020] The test method based on the above system includes the following steps:
[0021] 1) Before the test begins, indoor test calibration is carried out, including soil c, Value (where c is cohesion, Value is the internal friction angle) and water content;
[0022] 2) Reshape the soil on site and bury the monitoring components;
[0023] 3) The soil with installed monitoring elements is transported to the designated location. When the moisture content is less than the set value, the step method is simulated for construction and the initial lining is carried out. The mechanical parameters of different parts during excavation are collected and transmitted to the data processing center for comparison and analysis with the on-site experimental data.
[0024] 4) When the water content is higher than the set value, repeat the simulation experiment and collect the mechanical parameters of different parts during excavation;
[0025] 5) Compare the measured data with the field test to determine the reliability of the burial and grouting of the advance small guide tube for tunnel construction under different water content conditions.
[0026] Furthermore, when conducting simulation experiments with a water content higher than a set value, the required mechanical length is met, with the length of the small catheter being 13-17 cm ahead.
[0027] Carry out pre-grouting with small advance ducts, which are located within 120° of the tunnel top and 15° apart.
[0028] When the advance small pipe is sufficient to support the soil without causing large deformation or landslide, the test is repeated. At this time, the stability of the surrounding rock and soil without grouting can be obtained.
[0029] The number of advance small ducts corresponds to the number of lining frames, and a corresponding batch of advance small ducts with an angle of 120° is driven into every other frame.
[0030] If grouting is performed in a small conduit, the grouting reinforcement area is excavated by using a steel pipe with a guide device, and synthetic resin is poured for simulation.
[0031] Working principle of the present invention: The present invention simulates the mechanical properties of tunnel surrounding rock and supporting structure under step method construction with different surrounding rock parameters through indoor tests, artificially simulates tunnel step method construction under relatively low water content, so as to obtain the influence on the excavation face and the rock mass in front during the construction excavation process, and at the same time, based on this test, studies are conducted when the water content is high, after reinforcing the rock mass by burying and grouting the advance small guide tube, and then the experiment is repeated to obtain the relevant mechanical parameters of the excavation face and the rock mass in front under such field environment, and the obtained parameters are compared with the previous situation of no timely reinforcement, so as to study the reliability of pre-grouting of the advance small guide tube during tunnel step method construction.
[0032] Compared with the prior art, the present invention has the following beneficial effects:
[0033] (1) The present invention utilizes a similar indoor model test to simulate the tunnel step method construction, thereby obtaining the mechanical characteristics of the excavation face and different sections in front of it. The test is easy to operate and has high credibility.
[0034] (2) The test data are compared with each other, and the data measured in the laboratory are compared with the data under field conditions. At the same time, the two groups of model experiments under different moisture contents can also be compared with each other, making the test data more objective.
[0035] (3) When the water content is high, the experimental device can also be used to study the influence of the buried small pipe and grouting method on the mechanical properties of the surrounding rock mass under actual working conditions.
[0036] (4) Using the data processing center, we collect and analyze multiple sets of data in a diversified manner, and quantitatively describe the impact of factors such as the buried angle of the advance small guide tube, grouting pressure, and grouting concentration on the actual tunnel excavation. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] The drawings in the specification, which constitute a part of the present application, are used to provide further understanding of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute improper limitations on the present application.
[0038] Figure 1 Schematic diagram of the model test system.
[0039] Figure 2 Schematic diagram of the soil containment device.
[0040] Figure 3 Schematic diagram of soil excavation unit.
[0041] Figure 4 Schematic diagram of the monitoring surface.
[0042] Figure 5 This is a schematic diagram of the monitoring element layout.
[0043] Figure 6 This is a schematic diagram of the distribution of advanced small catheters.
[0044] Among them, 1-1 is a soil holding device, 1-2 is a soil excavation unit, 1-3 is a data acquisition unit, 1-4 is a data processing center, 1-5 is a display, 1-6 is a data cable, 2-1 is a positioning nut, 2-2 is a steel trough, 2-3 is a notch, 2-4 is a universal wheel, 2-5 is a tempered glass, 2-6 is a tunnel entrance, 2-7 is a steel plate, 3-1 is a sliding guide rail, 3-2 is a sliding base, 3-3 is an operating platform, 3-4 is a hydraulic lifting device, 4-1 is a tunnel surface, 4-2 is a lining ring, 4-3 is a step method for excavating a tunnel entrance, 4-4 is the first monitoring surface, 4-5 is the second monitoring surface, 4-6 is the third monitoring surface, 5-1 is a monitoring element arrangement point, and 6-1 is an advance small guide tube. DETAILED DESCRIPTION
[0045] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0046] It should be noted that the following detailed descriptions are illustrative and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.
[0047] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0048] In the present invention, terms such as "upper", "lower", "left", "right", "front", "back", "vertical", "horizontal", "side", "bottom", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are relational words determined only for the convenience of describing the structural relationships of the various parts or elements of the present invention, and do not specifically refer to any part or element in the present invention and should not be understood as limitations on the present invention.
[0049] In the present invention, terms such as "fixed connection", "connected", "connection", etc. should be understood in a broad sense, indicating that it can be fixedly connected, integrally connected or detachably connected; it can be directly connected or indirectly connected through an intermediate medium. Relevant scientific research or technical personnel in this field can determine the specific meanings of the above terms in the present invention according to specific circumstances, and they should not be understood as limiting the present invention.
[0050] As introduced in the background technology, the existing technology is unable to establish an experimental model to simulate the field environment to study the reliability of the step method construction of tunnels under different water contents, especially the inability to study the impact of advance small-duct pre-grouting under high water content. In order to solve the above technical problems, the present application proposes a model test system and method for studying the mechanical properties of the surrounding rock and support structure of tunnels constructed by the step method under different surrounding rock parameters.
[0051] In a typical implementation of the present application, Figure 1 As shown, the experimental system includes a test soil construction unit, a soil holding device 1-1, a step excavation unit 1-2, a data acquisition unit 1-3 and a data processing center 1-4.
[0052] The soil structure unit is mainly used to reshape the on-site soil and simulate the moisture content. The monitoring system is mainly used to collect information about the impact of construction under current working conditions on the surrounding soil, including the burial of monitoring components. The step tunnel excavation unit mainly involves simulating on-site artificial step tunnel excavation. The data acquisition system transmits the data obtained from the monitoring components in the soil structure unit to the data processing center.
[0053] Before the test system and method begins, the indoor test is calibrated, including soil c, Value (where c is cohesion, The soil construction unit includes the remodeling of the soil on site, which is as close to the parameters obtained in the laboratory as possible. When studying the influence of the water content, the soil should be simulated according to the actual conditions. It also includes the burial of monitoring elements, including monitoring of the surrounding rock lining and the excavation section. When the water content is low, the influence of the excavation tunnel on the surrounding soil is studied.
[0054] The test includes field simulations at low and high water contents. Soils with different water contents need to be re-prepared and the test is conducted at least twice. The soil structural unit is reconstructed at least twice.
[0055] The soil containment device is mainly used for repeated tests. This test is mainly a field simulation under low water content conditions.
[0056] like Figure 2 As shown, the soil holding device holds the reshaped soil, specifically including a frame formed by a steel trough 2-2, a steel plate 2-7 is arranged on the bottom surface of the frame, a notch 2-3 is arranged on the inner side of the steel trough 2-2, a universal wheel 2-4 is arranged at the lower end of the frame, and tempered glass 2-5 is installed on the side of the frame, and a tunnel entrance 2-6 is arranged on at least one side of the tempered glass 2-5.
[0057] like Figure 3 As shown, the step method tunnel excavation unit mainly includes a sliding guide rail 3-1, a sliding base 3-2, a hydraulic lifting device 3-4 and an operating platform 3-3. The sliding guide rail 3-1 is arranged on one side of the tunnel entrance 2-6 of the soil holding device 1-1, the sliding base 3-2 is movably arranged on the sliding guide rail 3-1, the sliding base 3-2 is provided with a hydraulic lifting device 3-4, and the upper end of the hydraulic lifting device 3-4 is provided with an operating platform 3-3. It is convenient for manual construction using the up and down step method.
[0058] The step tunnel excavation unit is mainly used for tunnel excavation and initial lining. Tunnel excavation includes simulating on-site excavation methods and adopting the up and down step method. The initial lining also simulates the on-site initial lining. Annular plexiglass is used in the test. The size is determined according to the similarity ratio and the thickness is 1cm to simulate the on-site concrete lining ring.
[0059] The monitoring system includes three groups of monitoring elements. The planes where the monitoring elements are located are perpendicular to the tunnel axis. Since the soil around the tunnel excavation is long along the axis in actual engineering, the experimental model meets the plane stress-strain principle. The monitoring elements include displacement gauges, strain gauges, and micro multi-point displacement gauges, which measure the lining soil pressure, cross-section soil pressure, and stratum settlement.
[0060] like Figure 4 As shown in the figure, the size of the experimental system is proportional to the field test, meeting the mechanical indicators under the force analysis, and the simulation ratio is adjusted to 1:20. The three sides are 2m long, 2.1m wide, and 1.6m high. The monitoring elements include three groups, including 0.5m before the excavation section, 1.0m before the excavation section, and 1.5m before the excavation section, which are the first monitoring surface 4-4, the second monitoring surface 4-5, and the third monitoring surface 4-6, forming a monitoring surface system. Each group of monitoring surfaces has a total of 5 monitoring lines, located in the upper part of the tunnel, with a difference of 45° between two monitoring lines, and a total of 6 monitoring elements on each monitoring line.
[0061] In the experimental model, when the water content is high, the small advance pipes are buried and grouting is carried out. The small advance pipes are located within 120° of the top of the tunnel and are 15° apart. When the small advance pipes are sufficient to support the soil without large deformation or landslide, the test is repeated, and the stability of the surrounding rock and soil without grouting can be obtained. The number of small advance pipes corresponds to the number of lining frames, and a corresponding batch of small advance pipes with an angle of 120° are driven in every other frame.
[0062] When conducting simulation experiments under conditions of high moisture content, the length required for mechanics is met, and the length of the advance small duct is preferably 13-17 cm. More preferably, the length of the advance small duct is 15 cm, and the material is tempered plastic strip.
[0063] A model test system and method for studying the mechanical characteristics of surrounding rock and supporting structure of tunnels constructed by step method under different surrounding rock parameters. The experimental steps are as follows:
[0064] 1) Before the test begins, indoor test calibration is carried out, including soil c, Value (where c is cohesion, The value is the internal friction angle) and the water content.
[0065] 2) The construction soil system includes the reshaping of the on-site soil and the burial of monitoring components.
[0066] 3) The soil with installed monitoring elements is transported to the designated location. Under the condition of low water content, the step method is artificially simulated for construction and the initial lining is carried out. The mechanical parameters of different parts during excavation are collected and transmitted to the data processing center using the data acquisition system for comparison and analysis with the on-site experimental data.
[0067] 4) When the water content is high, the simulation experiment is repeated, and the measured data are compared with the field test to explore the reliability of the burial and grouting of the advance small guide tube for tunnel construction under the condition of high water content, and compare it with the field test.
[0068] Through indoor tests, the mechanical properties of the surrounding rock and supporting structure of the tunnel constructed by the step method under different surrounding rock parameters are simulated. When the water content is relatively low, the tunnel step method construction is artificially simulated to obtain the influence on the excavation face and the rock mass in front during the construction excavation process. At the same time, based on this test, the study is carried out when the water content is high. After reinforcing the rock mass by burying and grouting the advance small guide tube, the experiment is repeated to obtain the relevant mechanical parameters of the excavation face and the rock mass in front under this field environment. The obtained parameters are compared with the previous situation of no timely reinforcement, so as to study the reliability of pre-grouting of the advance small guide tube during the tunnel step method construction process.
[0069] The second implementation method:
[0070] Before the test system and method begins, the indoor test is calibrated, including soil c, The soil construction unit includes the remodeling of the on-site soil, which is as close to the parameters obtained in the laboratory as possible. When studying the influence of the water content, the soil should be simulated according to the actual conditions. It also includes the burial of monitoring elements, including monitoring of the surrounding rock lining part and the excavation section part. When the water content is high, the influence of tunnel excavation on the surrounding soil under the action of advance small pipes and grouting is carried out.
[0071] The soil holding device is mainly used for repeated tests. This test is a field simulation under higher conditions. The step method tunnel excavation unit mainly includes tunnel excavation and initial lining. Tunnel excavation includes simulating the on-site excavation method and adopts the up and down step method for construction. The initial lining also simulates the on-site initial lining. Organic glass is used in the test. The size is determined according to the similarity ratio and the thickness is 1 cm to simulate the on-site concrete lining ring.
[0072] The monitoring system includes three groups of monitoring elements. The planes where the monitoring elements are located are perpendicular to the tunnel axis. Since the soil around the tunnel excavation is long along the axis in actual engineering, the experimental model meets the plane stress-strain principle. The monitoring elements include displacement gauges, strain gauges, and micro multi-point displacement gauges, which measure the lining soil pressure, cross-section soil pressure, and stratum settlement.
[0073] In the experimental model, when the water content is high, the advance small pipes are pre-grouted. The advance small pipes are located within 120° of the top of the tunnel and are 15° apart. When the advance small pipes are sufficient to support the soil without large deformation or landslides, the test is repeated, and the stability of the surrounding rock and soil without grouting can be obtained. The advance small pipes correspond to the number of lining frames, and a corresponding batch of advance small pipes with an angle of 120° are driven in every other frame.
[0074] The simulation ratio was adjusted to 1:20. In this model test, the soil ratio was set to 2.5 when the ratio was 1:20. The specimen simulated a tunnel with a diameter of 6m. The width of the two sides of the model was 3 times the diameter of the tunnel. Therefore, the three sides of the specimen were 2m long, 2.1m wide, and 1.6m high. The monitoring elements included three groups, including 0.5m in front of the excavation section, 1.0m in front of the excavation section, and 1.5m in front of the excavation section, forming a monitoring surface system. Each group of monitoring surfaces had a total of 6 monitoring lines, located in the upper part of the tunnel, with a difference of 45° between the two monitoring lines. There were a total of 6 monitoring elements on each monitoring line.
[0075] When conducting simulation experiments under high water content conditions, the length of the leading small conduit that meets the mechanical requirements is selected to be 15 cm, and the material is selected to be a tempered plastic strip. If grouting is performed on the small conduit, the grouting reinforcement area is excavated by jumping a Φ3 stainless steel pipe with a guide device, and synthetic resin is poured for simulation.
[0076] A model test system and method for studying the mechanical characteristics of surrounding rock and supporting structure of tunnels constructed by step method under different surrounding rock parameters. The experimental steps are as follows:
[0077] 1) Before the test begins, indoor test calibration is carried out, including soil c, Value (where c is cohesion, The value is the internal friction angle) and the water content.
[0078] 2) The construction soil system includes the reshaping of the on-site soil and the burial of monitoring components.
[0079] 3) The soil with installed monitoring elements is transported to the designated location. Under the condition of low water content, the step method is artificially simulated for construction and the initial lining is carried out. The mechanical parameters of different parts during excavation are collected and transmitted to the data processing center using the data acquisition system for comparison and analysis with the on-site experimental data.
[0080] 4) When the water content is high, the simulation experiment is repeated and the measured data are compared with the field test to explore the reliability of advance small-duct pre-grouting for tunnel construction under high water content conditions and compare it with the field test.
[0081] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
[0082] Although the above describes the specific implementation mode of the present invention in conjunction with the accompanying drawings, it is not intended to limit the scope of protection of the present invention. Those skilled in the art should understand that various modifications or variations that can be made by those skilled in the art on the basis of the technical solution of the present invention without creative work are still within the scope of protection of the present invention.
Claims
1. An experimental method for mechanical properties of surrounding rock and supporting structure of a step-construction tunnel, characterized by: The following steps are involved: 1) Before the test begins, indoor test calibration is carried out, including the determination of soil cohesion, internal friction angle and moisture content; 2) Reshape the soil on site and bury the monitoring components; 3) The soil with installed monitoring elements is transported to the designated location. When the moisture content is less than the set value, the step method is simulated for construction and the initial lining is carried out. The mechanical parameters of different parts during excavation are collected and transmitted to the data processing center for comparison and analysis with the on-site experimental data. 4) When the water content is higher than the set value, repeat the simulation experiment and collect the mechanical parameters of different parts during excavation; 5) Compare the measured data with the field test to determine the reliability of the advance small-duct pre-grouting for tunnel construction under different water content conditions; The experimental method is implemented based on an experimental system for mechanical properties of surrounding rock and supporting structure of a step-method tunnel; the experimental system includes a test soil structure unit, a soil containing device, a step-method excavation unit, a data acquisition unit and a data processing center, wherein: The soil construction unit is configured to reshape the on-site soil according to different soil parameters to be tested, and to bury monitoring elements in the surrounding rock lining part and the excavation section part during the reshaping process; and is also configured to simulate the moisture content of the soil; The soil body containing device is configured to have a certain containing space to contain and fix the test soil body used for monitoring the reshaped test soil body; The step method tunnel excavation unit is configured to automatically simulate the on-site step method tunnel excavation process; and is also configured to bury and grout the advance small conduit when simulating soil with a high water content; specifically: when the water content is low, artificially simulate the tunnel step method construction and perform the initial lining; when the water content is high, bury and grout the advance small conduit; wherein, when the advance small conduit is sufficient to support the soil without deformation and landslide, repeat the test; and obtain the stability of the soil without grouting; The data acquisition unit receives data obtained by the monitoring element in the soil structure unit and transmits it to the data processing center; The data processing center receives monitoring data, determines the mechanical properties of the surrounding rock and supporting structure of the tunnel under different surrounding rock parameters under the step method construction according to different detection data; and quantitatively describes the influence of the buried angle of the advance small guide tube, the grouting pressure, and the grouting concentration on the actual tunnel excavation; Among them, when the water content is high, the rock mass is reinforced by burying and grouting small advance pipes, and then the experiment is carried out again to obtain the relevant mechanical parameters of the excavation face and the rock mass in front under this field environment. The obtained parameters are compared with the previous situation without timely reinforcement, so as to study the reliability of pre-grouting of small advance pipes during the tunnel step method construction process.
2. The method for testing the mechanical properties of surrounding rock and supporting structure of a tunnel constructed by a step method as claimed in claim 1, characterized in that: The soil construction unit measures the cohesion, internal friction angle and water content of the soil to be simulated, obtains soil parameters, and reshapes the soil.
3. The method for testing the mechanical properties of surrounding rock and supporting structure of a step-method tunnel as claimed in claim 1, characterized in that: The reshaped soil model is in proportion to the on-site soil, meeting various mechanical indicators under stress analysis, and the ratio is controlled between 1:15 and 1:
25.
4. The method for testing the mechanical properties of surrounding rock and supporting structure of a step-method tunnel as claimed in claim 1, characterized in that: The monitoring elements include displacement meters, strain gauges or multi-point displacement meters, which are buried in the monitoring surrounding rock lining part and the excavation section part to measure the lining soil pressure, section soil pressure and stratum settlement.
5. The method for testing the mechanical properties of surrounding rock and supporting structure of a step-method tunnel as claimed in claim 1, characterized in that: The monitoring elements comprise a plurality of groups, which are arranged at different distances before the excavation section to form a monitoring surface system. Each group of monitoring surfaces comprises a plurality of monitoring lines located at the upper part of the tunnel. Two monitoring lines are spaced at a certain angle, and a plurality of monitoring elements are arranged on each monitoring line.
6. The method for testing the mechanical properties of surrounding rock and supporting structure of a step-method tunnel as claimed in claim 1, characterized in that: The soil holding device comprises a steel shell, on which tempered glass is provided for observing the construction progress, and a tunnel entrance is provided on at least one side of the shell.
7. The method for testing the mechanical properties of surrounding rock and supporting structure of a tunnel constructed by a step method as claimed in claim 1, characterized in that: The step method tunnel excavation unit comprises a guide rail, a sliding base, a lifting mechanism and a platform. The guide rail is arranged on one side of the tunnel entrance of the soil holding device, the sliding base is movably arranged on the guide rail, the sliding base is provided with a lifting mechanism, and the upper end of the lifting mechanism is provided with a platform, so that it is convenient for manual construction using the up and down step method.
8. The experimental method according to claim 1, characterized in that: When conducting simulation experiments with a water content higher than the set value, the length required for mechanics is met, with the length of the small catheter ahead by 13-17cm.
9. The experimental method according to claim 1, characterized in that: Carry out pre-grouting with advance small conduits, which are located within 120° of the tunnel top and are 15° apart. The number of advance small conduits corresponds to the number of lining frames, and a corresponding batch of advance small conduits with an angle of 120° is driven in every other frame.
Citation Information
Patent Citations
PROCEDURE FOR CONTROLLING A TEST BENCH
AT6235U2
Tunnel micro-step method technology teaching simulation body
CN103680288A
Similarity model test method for simulating tunnel construction