Cullet processing systems
By setting up a diversion device in the broken glass processing system to divert and disperse the blanking points of the broken glass, the stacking problem caused by the concentration of blanking points in the broken glass processing system is solved, shutdown accidents are avoided, and work efficiency is improved.
Patent Information
- Application Number
- CN201810015841.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2018-01-08
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2038-01-08
AI Technical Summary
In the existing broken glass processing system, due to the concentrated blanking points of broken glass, it is easy to accumulate at the discharge grille, resulting in shutdown accidents. It takes 30 minutes to manually clear the blockage, which affects work efficiency.
Design a broken glass processing system including a belt conveyor, a cutting grille and a splitting device. By setting a splitting device between the cut end of the belt conveyor and the cut grille, the broken glass is diverted during the falling process and changing the blanking Point position to avoid stacking, and optional belt machine scraper device and adjustment mechanism can be used to further disperse the blanking point.
It effectively avoids the shutdown of the broken glass processing system due to material blockage, improves production efficiency, reduces the need for manual clearance of material blockage, and improves work efficiency.
Smart Images

Figure CN108100668B_ABST
Abstract
Description
Technical Field
[0001] The present disclosure relates to the technical field of glass substrate production, and in particular, to a cullet processing system. Background Art
[0002] A large part of the raw materials used in LCD glass production lines come from cullet. Cullet is processed into finished glass of suitable size and uniform quality through a crushing and screening system, and then put into the furnace as raw material. Figure 1 As shown, in the existing broken glass processing system, the broken glass is transported by the belt conveyor 1. Since the falling points of the broken glass are concentrated and fixed, the broken glass is easily accumulated at the unloading grid 3, thereby causing a shutdown accident. Each shutdown requires manual unblocking of the unloading grid 3, which is labor-intensive and labor-intensive. Moreover, each shutdown takes at least 30 minutes to unblock, which seriously affects the work efficiency. Summary of the invention
[0003] The purpose of the present disclosure is to provide a cullet processing system, which can prevent cullet from piling up at a feed grid, thereby avoiding the cullet processing system from shutting down due to material blockage.
[0004] In order to achieve the above-mentioned purpose, the present disclosure provides a broken glass processing system, including a belt conveyor, a discharge grid and a diverter device, wherein the discharge grid is arranged below the discharge end of the belt conveyor, and the diverter device is arranged between the discharge end of the belt conveyor and the discharge grid, so that the broken glass falls onto the discharge grid after being diverted by the diverter device.
[0005] Optionally, the processing system further comprises a belt conveyor scraper device, and the belt conveyor scraper device is used to scrape off broken glass attached to the belt.
[0006] Optionally, the diverter device includes a first diverter device, which is arranged on the belt conveyor scraper device.
[0007] Optionally, the diverter device further comprises a second diverter device, which is arranged between the first diverter device and the lower material grid, so that the broken glass falls onto the lower material grid after being diverted by the first diverter device and the second diverter device in sequence.
[0008] Optionally, the first flow diverter device and the second flow diverter device are both circular tubes, and the central axes of the first flow diverter device and the second flow diverter device are parallel to the central axis of the pulley of the belt conveyor.
[0009] Optionally, the processing system further includes an outer cover and a mounting plate, the feed grid and the mounting plate are both mounted on the inner wall of the outer cover, a feed port is formed on the mounting plate, and the second diversion device is arranged on the mounting plate and located at the feed port.
[0010] Optionally, the processing system further comprises an adjusting mechanism for adjusting the position of the second diverter device.
[0011] Optionally, the adjustment mechanism includes a first bracket, a second bracket, a first adjusting screw, and a second adjusting screw. The first bracket and the second bracket are arranged on the mounting plate and are located on both sides of the second diverter device. The first adjusting screw passes through the first bracket to abut against the side of the second diverter device. The second adjusting screw passes through the second bracket to abut against the side of the second diverter device. The first adjusting screw and the second adjusting screw are both perpendicular to the second diverter device.
[0012] Optionally, two first fastening nuts are installed on each of the first adjusting screws, and the two first fastening nuts are respectively located on both sides of the first bracket, and two second fastening nuts are installed on each of the second adjusting screws, and the two second adjusting nuts are respectively located on both sides of the second bracket.
[0013] By arranging the diverter device between the unloading end of the belt conveyor and the unloading grid, the broken glass can first contact the diverter device during the falling process, so that the position of the broken glass landing point is changed and dispersed, that is, after being diverted by the diverter device, it falls evenly on the unloading grid, solving the problem of local accumulation at the unloading grid caused by the concentration of the broken glass landing points, thereby avoiding the abnormal shutdown of the broken glass processing system due to blockage and ensuring the production efficiency of the processing operation.
[0014] Other features and advantages of the present disclosure will be described in detail in the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] The accompanying drawings are used to provide a further understanding of the present disclosure and constitute a part of the specification. Together with the following specific embodiments, they are used to explain the present disclosure but do not constitute a limitation of the present disclosure. In the accompanying drawings:
[0016] Figure 1 It is a structural schematic diagram of a cullet processing system provided by the prior art;
[0017] Figure 2 is a schematic structural diagram of a cullet processing system provided by an exemplary embodiment of the present disclosure;
[0018] Figure 3is a top view of a cullet processing system provided by an exemplary embodiment of the present disclosure along direction A, wherein the adjusting screw abuts against the middle of the second diverter device;
[0019] Figure 4 3 is a top view of a cullet processing system provided by an exemplary embodiment of the present disclosure along direction A, wherein the adjusting screw abuts against the end of the second diverter device.
[0020] Description of Reference Numerals
[0021] 1 Belt conveyor 11 Pulley
[0022] 2 Belt conveyor scraper device 3 Unloading grid
[0023] 4 Outer cover 51 First flow distribution device
[0024] 52 Second diversion device 6 Mounting plate
[0025] 61 Dropping port 71 First bracket
[0026] 72 second bracket 73 first adjusting screw
[0027] 74 Second adjusting screw 75 First fastening nut
[0028] 76 Second fastening nut DETAILED DESCRIPTION
[0029] The specific implementation of the present disclosure is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described herein is only used to illustrate and explain the present disclosure, and is not used to limit the present disclosure.
[0030] like Figures 2 to 4 As shown, the present disclosure provides a broken glass processing system, including a belt conveyor 1, a discharge grid 3 and a diverter device, wherein the discharge grid 3 is arranged below the discharge end of the belt conveyor 1, where the discharge end refers to the end of the broken glass leaving the belt on the belt conveyor 1. The diverter device is arranged between the discharge end of the belt conveyor 1 and the discharge grid 3, so that the broken glass falls on the discharge grid 3 after being diverted by the diverter device. By arranging the diverter device just below the discharge end of the belt conveyor 1, the broken glass can first contact the diverter device during the falling process, so that the position of the broken glass falling point is changed and dispersed, that is, after being diverted by the diverter device, the broken glass falls evenly on the discharge grid 3, thereby solving the problem of local accumulation at the discharge grid 3 caused by the concentration of the broken glass falling points, thereby avoiding the abnormal shutdown of the broken glass processing system due to material blockage, and ensuring the production efficiency of the processing operation.
[0031] Furthermore, the broken glass processing system disclosed in the present invention also includes a belt conveyor scraper device 2, which is used to scrape off broken glass attached to the belt, and the above-mentioned diverter device includes a first diverter device 51, which is arranged on the belt conveyor scraper device 2 and corresponds to the position of the unloading end of the belt conveyor 1, so that the broken glass can be diverted through the first diverter device 51 during the falling process. The first diverter device 51 can be fixed on the belt conveyor scraper device 2 by welding, clamping, bolting, etc., or the first diverter device 51 can be wound around the belt conveyor scraper device 2 by a metal wire. During the working process of the belt conveyor scraper device 2, due to the contact between the scraper and the belt, the belt conveyor scraper device 2 will vibrate slightly, and the first diverter device 51 fixed on the belt conveyor scraper device 2 can move slightly with the belt conveyor scraper device 2, thereby automatically adjusting the position to further disperse the broken glass.
[0032] In addition, the above-mentioned diverter device also includes a second diverter device 52, which is arranged between the first diverter device 51 and the lower material grid 3, so that the broken glass is divided by the first diverter device 51 and the second diverter device 52 in sequence and then falls on the lower material grid 3. The second diverter device 52 can cooperate with the first diverter device 51 to further disperse the position of the falling point of the broken glass, so that the broken glass falls on the lower material grid 3 evenly.
[0033] The first flow diverter 51 and the second flow diverter 52 may be of any appropriate structure. In the cullet processing system provided by the present disclosure, as an exemplary embodiment, the first flow diverter 51 and the second flow diverter 52 are both round tubes, and the central axes of the first flow diverter 51 and the second flow diverter 52 are parallel to the central axis of the pulley 11. Optionally, the diameter of the first flow diverter 51 is in the range of 20 mm to 30 mm, the diameter of the second flow diverter 52 is in the range of 30 mm to 60 mm, and both the first flow diverter 51 and the second flow diverter 52 are made of SUS304.
[0034] Furthermore, the second flow dividing device 52 can be installed between the first flow dividing device 51 and the lower material grid 3 in various embodiments. As an optional embodiment, Figures 2 to 4 As shown, the processing system of the present invention also includes an outer cover 4 and a mounting plate 6. The feed grid 3 and the mounting plate 6 are both mounted on the inner wall of the outer cover 4. The feed grid 3 and the mounting plate 6 are arranged in parallel. A drop opening 61 is formed on the mounting plate 6. The second diverter device 52 is arranged on the mounting plate 6 and is located at the drop opening 61. The broken glass can fall onto the feed grid 3 through the drop opening 61 after being diverted by the second diverter device 52.
[0035] In addition, the cullet processing system of the present disclosure further includes an adjustment mechanism for adjusting the position of the second diverter 52. Thus, by using the adjustment mechanism, the position of the second diverter 52 can be adjusted according to the diverting effect of the first diverter 51. If the diverting of the first diverter 51 is uneven, the second diverter 52 can be adjusted toward the side where more cullet falls, and a second diversion is performed to ensure that the cullet can fall evenly on the discharge grid 3.
[0036] Specifically, the adjustment mechanism includes a first bracket 71, a second bracket 72, a first adjustment screw 73, and a second adjustment screw 74. The first bracket 71 and the second bracket 72 are arranged on the mounting plate 6 and are located on both sides of the second diverter 52. The first adjustment screw 73 passes through the first bracket 71 to abut against the side of the second diverter 52. The second adjustment screw 74 passes through the second bracket 72 to abut against the side of the second diverter 52. The first adjustment screw 73 and the second adjustment screw 74 are both perpendicular to the second diverter 52. The position of the second diverter 52 can be adjusted by rotating the adjustment screw.
[0037] According to an embodiment provided by the present disclosure, Figure 3 As shown, the first adjusting screw 73 and the second adjusting screw 74 abut against both sides of the middle of the second diverter 52, and a force is applied to the middle of the second diverter 52 by rotating the adjusting screw, thereby pushing the entire second diverter 52 to move. The number of the first adjusting screw 73 and the second adjusting screw 74 can be multiple.
[0038] In another embodiment provided by the present disclosure, Figure 4 As shown, two groups of first adjusting screws 73 and second adjusting screws 74 are provided, one group of first adjusting screws 73 and second adjusting screws 74 abuts against both sides of the head end of the second diverter device 52, and the other group of first adjusting screws 73 and second adjusting screws 74 abuts against both sides of the tail end of the second diverter device 52. By adjusting the adjusting screws located at the head end and the tail end of the second diverter device 52 at the same time, the position of the second diverter device 52 can be adjusted.
[0039] Further, two first fastening nuts 75 are installed on each first adjusting screw 73, and the two first fastening nuts 75 are respectively located on both sides of the first bracket 71, and two second fastening nuts 76 are installed on each second adjusting screw 74, and the two second adjusting nuts 76 are respectively located on both sides of the second bracket 72. When adjusting the position of the second diverter 52, the first fastening nut 75 and the second fastening nut 76 can be loosened first, and then the first adjusting screw 73 and the second adjusting screw 74 can be rotated so that the first adjusting screw 73 and the second adjusting screw 74 can move along their length direction, thereby pushing the second diverter 52 to move. When the second diverter 52 is adjusted to the ideal position, the first fastening nut 75 and the second fastening nut 76 are tightened to fix the position of the second diverter 52. The adjustable range of the position of the second diverter 52 is related to the length of the first adjusting screw 73 and the second adjusting screw 74. In the exemplary embodiment provided by the present disclosure, the horizontal adjustment range of the second diverter 52 is -75mm-75mm.
[0040] The preferred embodiments of the present disclosure are described in detail above in conjunction with the accompanying drawings; however, the present disclosure is not limited to the specific details in the above embodiments. Within the technical concept of the present disclosure, a variety of simple modifications can be made to the technical solution of the present disclosure, and these simple modifications all fall within the protection scope of the present disclosure.
[0041] It should also be noted that the various specific technical features described in the above specific embodiments can be combined in any suitable manner without contradiction. In order to avoid unnecessary repetition, the present disclosure will not further describe various possible combinations.
[0042] In addition, various embodiments of the present disclosure may be arbitrarily combined, and as long as they do not violate the concept of the present disclosure, they should also be regarded as the contents disclosed by the present disclosure.
Claims
1. A cullet processing system, It is characterized in that It comprises a belt conveyor (1), a material discharge grid (3) and a diverter device, wherein the material discharge grid (3) is arranged below the material discharge end of the belt conveyor (1), and the diverter device is arranged between the material discharge end of the belt conveyor (1) and the material discharge grid (3), so that the broken glass falls onto the material discharge grid (3) after being diverted by the diverter device; The flow dividing device comprises a first flow dividing device (51) and a second flow dividing device (52), wherein the second flow dividing device (52) is arranged between the first flow dividing device (51) and the lower material grid (3), so that the broken glass is divided by the first flow dividing device (51) and the second flow dividing device (52) in sequence and then falls onto the lower material grid (3); The processing system further comprises an adjusting mechanism, which is used to adjust the position of the second flow dividing device (52) according to the flow dividing effect of the first flow dividing device (51); The processing system further comprises a belt conveyor scraper device (2), the belt conveyor scraper device (2) being used to contact the belt to scrape off broken glass attached to the belt, and the first diverter device (51) being arranged on the belt conveyor scraper device (2), so that the first diverter device (51) fixed on the belt conveyor scraper device (2) can move with the vibration of the belt conveyor scraper device (2), thereby automatically adjusting the position of the first diverter device (51); The first flow dividing device (51) and the second flow dividing device (52) are both circular tubes, and the central axes of the first flow dividing device (51) and the second flow dividing device (52) are parallel to the central axis of the pulley (11) of the belt conveyor (1); The diameter of the first flow dividing device (51) is in the range of 20 mm to 30 mm.
2. The cullet processing system according to claim 1, It is characterized in that The processing system further comprises an outer cover (4) and a mounting plate (6); the material discharge grid (3) and the mounting plate (6) are both mounted on the inner wall of the outer cover (4); a material discharge opening (61) is formed on the mounting plate (6); and the second flow dividing device (52) is arranged on the mounting plate (6) and is located at the material discharge opening (61).
3. The cullet processing system according to claim 2, It is characterized in that The adjustment mechanism comprises a first bracket (71), a second bracket (72), a first adjustment screw (73), and a second adjustment screw (74); the first bracket (71) and the second bracket (72) are arranged on the mounting plate (6) and are located on both sides of the second flow diverter (52); the first adjustment screw (73) passes through the first bracket (71) to abut against a side of the second flow diverter (52); the second adjustment screw (74) passes through the second bracket (72) to abut against a side of the second flow diverter (52); and the first adjustment screw (73) and the second adjustment screw (74) are both perpendicular to the second flow diverter (52).
4. The cullet processing system according to claim 3, It is characterized in that Each of the first adjusting screws (73) is mounted with two first fastening nuts (75), and the two first fastening nuts (75) are respectively located on both sides of the first bracket (71); each of the second adjusting screws (74) is mounted with two second fastening nuts (76), and the two second fastening nuts (76) are respectively located on both sides of the second bracket (72).