A double-arm parallel crane and working method

By adopting a double-arm parallel crane design in offshore crane, the rectangular base and circular transition structure and reinforced rib plate group are used to solve the problem of insufficient structural stability and load-bearing capacity of offshore cranes, and efficient and safe lifting performance is achieved .

CN109132897BActive Publication Date: 2024-12-03SOUTH CHINA MARINE MACHINERY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201811186229.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2018-10-12
Publication Date
2024-12-03
Estimated Expiration
2038-10-12

AI Technical Summary

Technical Problem

When used in harsh sea surface environments, the existing offshore cranes have poor structural stability and limited load-bearing capacity, and the operating capacity of fixed cranes is low. The base structure of the slewing cranes is unstable, making it difficult to meet the needs of large loads and high efficiency.

Method used

Design a double-arm parallel crane, adopting a base design of rectangular base and circular transition structure, strengthening the rib plate group and raised structure, combining the slewing support and the slewing platform to realize the parallel double-arm structure of the boom and 360-degree rotation, enhance the Stability and lifting capacity of the boom.

Benefits of technology

It improves the stability, load-bearing capacity and operating efficiency of the crane, can effectively withstand large loads, reduces the risk of distortion and bending of the base, and enhances safety performance and use efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109132897B_ABST
    Figure CN109132897B_ABST
Patent Text Reader

Abstract

The invention provides a double-arm parallel crane and a working method. The double-arm parallel crane comprises a base, a slewing bearing, a slewing platform, a slewing driving device, a tripod and a double-arm boom part. The base is connected to the outer ring of the slewing bearing, the slewing platform is connected to the inner ring screw of the slewing bearing, the tripod is fixedly installed on the slewing platform, and the double arms are hinged on the slewing platform. The base is a hollow base with a rectangular bottom surface and a circular top surface. A first upward cylinder is provided on the top of the base. The cross-sectional area of ​​the first cylinder is smaller than the area of ​​the bottom surface of the base. The central axis of the first cylinder is parallel to the central axis of the bottom surface of the base but does not overlap. The slewing platform comprises a quadrangular prism with a cavity, a second cylinder and a circular plate with a hollow structure. When retrieving goods, the slewing driving device is started to drive the slewing bearing and drive the slewing platform to rotate out of a suitable position for retrieving to a placement area. The crane can achieve large lifting capacity, strong pressure bearing capacity, small dead weight, high stability, energy saving and environmental protection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of cranes, and specifically discloses a double-arm parallel crane and a working method. Background Art

[0002] Offshore platform cranes are mainly used on offshore platforms. They are equipment for loading and unloading cargo and lifting personnel onto the platform. They are one of the most important production and safety equipment in offshore oil production. Due to the harsh sea environment, they have high requirements for safety, reliability, maintainability, wind resistance and corrosion resistance. At the same time, unlike general land cranes, offshore platform cranes are generally fixed on ship platforms, and the movement of the platform itself will have a strong impact on the movement of the load. During operation, offshore cranes will pitch, roll and heave with the waves. These movements will cause the load to swing, especially during the lifting process. Such movement of the platform can easily cause the hoisted load to collide with the deck again, thereby threatening the safety of the operation.

[0003] Offshore platform cranes include fixed cranes and slewing cranes. Fixed cranes have low construction costs and simple structures, so they are widely used in actual construction. However, due to structural reasons, their operating capacity is limited and their efficiency is relatively low. Slewing cranes can be rotated, and the rotatable base can overcome the shortcomings of fixed cranes. In addition, the boom can move forward and backward, so they are better than fixed cranes in terms of mobility.

[0004] With the rapid development of offshore wind power and oil extraction industries, newer and higher requirements have been put forward for offshore lifting equipment. Large lifting weight and large working range have become routine requirements. On this basis, higher requirements have been put forward for the effective operating area and carrying load of offshore platform cranes, that is, the deck area occupied by the lifting equipment should be as small as possible and the carrying load should be as large as possible, so as to improve the utilization efficiency of the offshore platform and reduce transportation costs. In order to achieve the above purpose, the advantages of pedestal cranes and rail column cranes can be effectively combined and realized by improving the structure of the crane itself.

[0005] A large-scale pile-wrapped offshore platform crane is disclosed in the patent document with application number CN201220444856.4, which includes pile legs inserted on the main deck, pile shoes on the pile legs, the pile shoes placed on the main deck, a base provided on the pile shoes, a slewing bearing device provided on the base, a slewing platform provided above the slewing bearing device, a driver's room and a machine room provided on one side of the slewing platform, a boom luffing winch, a main lifting winch, and an auxiliary lifting winch provided on the slewing platform in sequence, and the A herringbone frame is also provided on the slewing platform, a herringbone frame top pulley block is provided at the top of the herringbone frame, a boom is connected to the slewing platform, a boom head pulley block is provided at the top of the boom, a main hook, an auxiliary hook and a luffing hook are provided below the top of the boom. The offshore platform crane has a simple appearance, a compact structure, occupies little deck space, has strong adaptability and high utilization efficiency. However, the pile shoe of the offshore platform crane is a cylindrical structure, and the crane base is also a cylindrical structure. The load-bearing capacity of this structure is limited and the stability is poor.

[0006] A double-arm tower crane is disclosed in the patent document with application number CN201320664157.5, which includes a crane body and a boom part, the crane body and the boom part are hingedly connected, and a pull arm mechanism is also arranged therebetween, one end of the pull arm mechanism is connected to the boom part, and the other end is connected to the crane body through a steel rope; the boom part includes a first boom and a second boom, the first boom and the second boom are arranged side by side and fixed by a connecting piece; the pull arm mechanism includes a first connecting rod, a second connecting rod, a connecting frame and a pull arm pulley block, one end of the first connecting rod and the second connecting rod are connected to the pull arm pulley block through the connecting frame, and the other end is connected to the boom part The boom of the crane adopts a double-arm structure. When carrying the same load, the length of the single-arm boom required is more than twice that of the boom used when the double-arm boom is used. Therefore, the double-arm boom reduces its own weight, reduces the structural dimensions, and has good boom structure stability. However, the crane base is a long cylindrical structure, the fixed platform is directly connected to the hull and welded to the main deck of the ship, and the base is fixed on the fixed platform. The base is an long cylindrical structure with a small diameter, poor load-bearing capacity, a large height, a high center of gravity, and poor structural stability. The double-arm tower crane is a fixed crane with a limited scope of application and a low utilization rate. Summary of the invention

[0007] In order to solve the problems existing in the prior art, the present invention provides a double-arm parallel crane and a working method. By operating the double-arm parallel crane, large lifting capacity, strong pressure bearing capacity, high stability, improved safety performance, compact structure, strong adaptability and high utilization efficiency can be achieved.

[0008] To achieve the above-mentioned purpose, the first technical solution of the present invention is: a double-arm parallel crane, comprising a base, a slewing bearing, a slewing platform, a slewing drive device, a tripod and a double-arm boom portion, the top of the base is connected to the outer ring screw of the slewing bearing, the bottom of the slewing platform is connected to the inner ring screw of the slewing bearing, the tripod is fixedly installed on the top of the slewing platform, and the double-arm boom portion is hinged on the slewing platform, the base is a hollow base with a rectangular bottom cross-section and a circular top cross-section, a first cylinder extending upward is provided on the top of the base, and a hollow cylinder is provided from the bottom of the base to the top of the first cylinder. A base reinforcing rib plate group extending up and down and evenly arranged along the outer circumference direction of the base is provided on the inner wall of the base and the inner wall of the first cylinder, and all the base reinforcing rib plates in the base reinforcing rib plate group are arranged toward the central axis direction of the first cylinder; the base reinforcing rib plate at the transition part between the rectangular cross section and the circular cross section has an inward protrusion, and the lower end of the protrusion and the base reinforcing rib plate are in an arc transition; the cross-sectional area of ​​the first cylinder is smaller than the area of ​​the rectangle of the bottom surface of the base, the central axis of the first cylinder is parallel to the central axis of the bottom surface of the base, and the distance from the center of the bottom surface of the base to the central axis of the first cylinder is greater than 0;

[0009] The rotary platform includes a quadrangular prism with a cavity, a second cylinder and a circular plate with a hollow structure, wherein the quadrangular prism includes a rectangular top plate with a circular hollow structure and a rectangular bottom plate with a circular hollow structure, wherein the rectangular bottom plate includes a first rectangular bottom plate, a second rectangular bottom plate and a third rectangular bottom plate connected in sequence, wherein the first rectangular bottom plate is inclined with the second rectangular bottom plate, the third rectangular bottom plate is inclined with the second rectangular bottom plate, and the first rectangular bottom plate and the third rectangular bottom plate are arranged in parallel;

[0010] The top of the second cylinder is located in the quadrangular prism, and the top of the second cylinder is welded to the bottom surface of the rectangular top plate of the quadrangular prism, a circular plate with a circular hollow structure is welded to the bottom of the second cylinder, and two or more mounting holes of a slewing bearing are arranged on the inner circumference of the circular plate at the welding point of the second cylinder and the circular plate, the central axis of the circular hollow structure on the rectangular top plate of the quadrangular prism, the central axis of the circular hollow structure on the rectangular bottom plate of the quadrangular prism, the central axis of the second cylinder, the central axis of the circular hollow structure of the circular plate and the central axis of the first cylinder are in a straight line; the inner wall of the second cylinder is evenly distributed with a first reinforcing rib plate group along the radial direction of the second cylinder, the outer wall of the second cylinder in the quadrangular prism is distributed with a second reinforcing rib plate group along the radial direction of the second cylinder, a third reinforcing rib plate group installation area is arranged inside the quadrangular prism, the third reinforcing rib plate group installation area is located on the opposite side of the double-arm boom portion of the slewing platform, and a transverse reinforcing rib plate group and a longitudinal reinforcing rib plate group are arranged in the third reinforcing rib plate group installation area.

[0011] The piles are inserted into the base, the slewing bearing, the slewing platform in sequence from bottom to top, and then pass through the deck and are fixed on the seabed. They have high stability and strong impact resistance. Compared with a large pile-circling offshore platform crane in the prior art, the boom part adopts a parallel double boom, and the boom structure has good stability, large lifting capacity, greater lifting capacity, and stronger pressure-bearing capacity. Compared with a large pile-circling offshore platform crane and a double-arm tower crane in the prior art, a first cylinder structure extending upward is provided on the top of the base to facilitate connection with the outer ring screw of the slewing bearing. Since the central axis of the first cylinder is parallel to the central axis of the bottom surface of the base, and the distance from the center of the bottom surface of the base to the central axis of the first cylinder is greater than 0, that is, the central axis of the base deviates from the central axis of the first cylinder, the length of the reinforcing rib on the side of the connection position of the double-arm boom part on the base is increased.

[0012] The base is the main stress-bearing part of the entire device. The stress analysis of one end of the base equipped with a double-arm boom shows that when the cargo is retrieved and rotated to a suitable position and stops suddenly, due to the action of inertia, there is a torque stress in the tangent direction of the base along the cross-section circle. This stress can easily cause the base to twist and deform. At the same time, the cargo is hung on the head of the boom and pulls the boom downward, and there is a bending moment stress on the cross section of the base. The weight of the tripod, wire rope, winch, etc. placed on the slewing platform, the slewing support, the slewing platform, the double-arm boom, etc. and the weight of the base itself exert pressure on the deck. According to the principle of action and reaction force, the deck exerts a supporting force on the base. This force is dispersed on the base wall and is obliquely upward along the direction of the base wall. This supporting force can be decomposed into vertical upward stress and horizontal stress pointing to the central axis. This vertical upward stress and the bending moment stress constitute relative direction stress on the base, which causes extrusion to the base, and easily causes the base to bend and break in the axial direction. Compared with the existing large-scale pile-wrapped offshore platform crane and a double-arm tower crane, in the present invention, the first The central axis of the cylinder does not pass through the center of the bottom surface of the base, so that the bottom area of ​​the base near one end of the boom is larger, so that the base near one end of the boom is larger in volume, thicker in wall thickness, larger in inner wall area, longer and more reinforcing ribs, so that the strength and rigidity of the base at one end of the boom are increased, and the bending resistance is enhanced, preventing the base from twisting, deforming, bending or breaking; all the base reinforcing rib plates in the reinforcing rib plate group are arranged toward the central axis direction of the first cylinder, which is conducive to the weight of the rotating platform being evenly distributed downward on the base and reinforcing ribs; the bottom of the base is rectangular, so that the intersections of the four surfaces of the bottom of the base all form the most stable right angles, thereby increasing the stability of the crane; the cross-sectional area of ​​the extended first cylinder is smaller than the area of ​​the bottom rectangle, and the base adopts a structure with a small top and a large bottom, which increases the support surface formed by the contact between the bottom of the base and the deck, making the base more stable and more impact-resistant; compared with a double-arm tower crane in the prior art, the double-arm parallel crane has a rotary crane slewing bearing and a slewing platform, which can be rotatable, and the boom can achieve axial 90 o and radial 360o Rotation, so it has strong applicability, large operating range, strong adaptability and high efficiency; at the same time, when carrying a large load of 1200t, a larger slewing device is required. At this time, a slewing bearing is used as a slewing device, which has a compact and simple structure, can withstand axial force, radial force and tipping moment at the same time, and is highly practical.

[0013] Except for the transition between the rectangular section and the circular section, the rectangular section and the circular section of the base are neatly arranged molecules, while the transition between the rectangular section and the circular section forms a cross-sectional mutation. Therefore, the molecules in the structure of the transition between the rectangular section and the circular section change, which changes the overall force and also changes the force state and balance of the molecules at the mutation. Through analysis, the base is subjected to downward pressure, bending force and twisting force. Due to the drastic change in the molecular structure at the mutation, the molecules inside the rectangular section and the circular section are evenly distributed, and the force is also evenly distributed. The transition between the rectangular section and the circular section produces a greater force to resist the external force due to the molecular change, which makes the stress at the transition between the rectangular section and the circular section greater, forming stress concentration. When the stress at this point is greater than the extreme value of the material, the stress concentration is greater. If the limit stress is exceeded, it will damage the base and cause a major safety accident. In order to avoid the base being damaged due to stress concentration, in addition to adding a base reinforcement rib plate at the transition between the rectangular section and the circular section, a protrusion is also set. The base reinforcement rib plate provides a force roughly the same as the stress direction to increase the force to resist the base from pressure, bending force, and torsional force. The protrusion is located below the transition between the rectangular section and the circular section. When the transition between the rectangular section and the circular section of the base is subjected to bending force, the raised part is equivalent to giving an oblique upward force to increase the force to resist the base from receiving the bending force. Of course, the protrusion can also play a role in resisting pressure and torsional force, making the strength of the mutation point more reliable. An arc is set between the lower end of the protrusion and the base reinforcement rib plate to avoid the formation of stress concentration. In summary, the base reinforcement rib plate and the protrusion can greatly improve the strength of the base's mutation section and improve safety performance.

[0014] When the crane is operating with a large load of 1200t, in order to meet the requirements of the maximum lifting load, a large-sized tripod, winch and a large-diameter wire rope will also be selected, so that the structure and weight of the tripod, winch and wire are also large. Compared with the large-scale pile-wrapped offshore platform crane in the prior art, the inner wall of the second cylinder, the outer wall of the second cylinder in the quadrangular prism, and the inside of the quadrangular prism are all installed with a reinforcing rib plate group, which enhances the axial and radial strength, rigidity and bending resistance of the top of the rotating platform, and prevents the rotating platform from being broken due to excessive weight of the items carried on the rotating platform; the top of the second cylinder is welded to the bottom of the rectangular top plate of the quadrangular prism, and a circular plate with a circular hollow structure is welded to the bottom of the second cylinder, which is convenient for connection with the inner ring screw of the rotating support. The central axis of the rotating platform component is in a straight line and faces the end where the boom part is hinged, in order to balance the torque on both sides of the pile column with the base and improve stability.

[0015] Furthermore, four groups of upwardly extending tripod mounting panels are provided at diagonal positions of the rectangular top plate of the quadrangular prism, each group of tripod mounting panels includes two oppositely arranged first mounting panels, and each first mounting panel is provided with a tripod mounting hole, and two groups of upwardly extending double-arm boom part mounting panels are provided on one side of the rectangular top plate of the quadrangular prism close to the double-arm boom part, each group of double-arm boom part mounting panels includes two oppositely arranged second mounting panels, and the second mounting panels are provided with double-arm boom part mounting holes.

[0016] A group of slewing drive device mounting holes are respectively provided on both sides of the circular plate of the quadrangular prism at the outer circumference of the second cylinder. The slewing drive device mounting hole group is located between the tripod mounting panel and the double-arm boom mounting panel. Each slewing drive device mounting hole group includes two or more slewing drive mounting holes. One end of the slewing drive device passes through the slewing drive device mounting hole and engages with the outer ring of the slewing bearing. The other end of the slewing drive device is fixed to the circular plate of the quadrangular prism.

[0017] The tripod mounting holes are distributed at the diagonal positions of the quadrangular top plate, so that the weight of the tripod is evenly distributed on the slewing platform, thereby improving the stability of the crane; at the same time, when the crane is operating with a large load, the slewing platform is large in size and requires more slewing drive devices to drive the rotation. Since the slewing drive device mounting hole group is located between the tripod mounting panel and the double-arm boom mounting panel, the slewing drive device is symmetrically arranged on the circular plate, so that both sides are driven to rotate at the same time, which makes rotation easier and evenly shares the weight of the rotating platform, which is conducive to balance and preventing overturning.

[0018] Furthermore, the tripod includes two relatively arranged door frame assemblies and a first cross bar, the two door frame assemblies are respectively welded at both ends of the first cross bar, each of the door frame assemblies includes a vertical bar and a first diagonal bar, the bottom end of the vertical bar is fixedly installed on the rotating platform at a position opposite to the double-arm boom part and is perpendicular to the rotating platform, the bottom end of the first diagonal bar is fixedly installed on the rotating platform near the double-arm boom part, the top of the first diagonal bar is connected to the top of the vertical bar, and a second cross bar and a second diagonal bar are provided at a middle and lower position of the first diagonal bar, one end of the second diagonal bar is connected to the first diagonal bar, and the other end of the second diagonal bar is connected to the second cross bar, and the second cross bar, the second diagonal bar and the first diagonal bar of the door frame assembly form a triangular structure.

[0019] Since the gantry assemblies are symmetrically arranged relative to the revolving platform, the bottom ends of the vertical rods and diagonal rods of the gantry assemblies are fixedly mounted on the revolving platform and the fixed deck to form a stable triangular structure, thereby improving the structural stability of the gantry assembly and the convenience of maintenance; at the same time, the two gantry assemblies are connected by a first cross bar and two cross bar assemblies to further improve the stability of the gantry assembly.

[0020] A second horizontal bar and a second diagonal bar are arranged at a lower middle position of the diagonal bar, forming a triangular structure with the first diagonal bar. When the boom rises to a vertical position, they support the boom to prevent the boom from tipping over to the other side. The triangular structure has greater stability and impact resistance.

[0021] Furthermore, the double-arm boom portion includes a main boom and a secondary boom, the tail of the secondary boom is connected to the head of the main boom, and the main boom and the secondary boom are provided with hook assemblies; the main boom includes a first main boom and a second main boom, the first main boom and the second main boom are arranged side by side and fixed by a connecting piece, and the first main boom and the second main boom correspond to a gantry assembly respectively.

[0022] This double boom structure is symmetrically distributed, and the load force on the boom is dispersed, making the structure more stable and the strength increased. The lifting performance of the crane boom is improved, and the modularization of the crane boom structure can be realized.

[0023] Furthermore, the first main boom and the second main boom are both composed of a boom root section, a boom middle section and a boom tip section, and the boom root section, the boom middle section and the boom tip section are detachably connected.

[0024] The main boom adopts this connection method to realize the modularization of the boom structure and disperse the force. At the same time, it can be disassembled into sections for transportation, which is convenient for transportation.

[0025] Furthermore, the connecting member includes a first connecting member, a second connecting member and a third connecting member, the first connecting member is fixedly connected between the arm root sections, the second connecting member is fixedly connected between the arm middle sections, and the third connecting member is fixedly connected between the arm tip sections.

[0026] A connecting piece is provided between the two booms to improve the stability of the booms. Two or more second connecting pieces may be provided according to the length of the main boom of the boom part to ensure the structural strength of the boom part.

[0027] Furthermore, winches are respectively provided on the rotating platform near the two vertical rods, top pulley blocks are respectively provided on the tops of the two vertical rods, head pulley blocks are respectively provided on the heads of the main boom and the auxiliary boom, steel wire ropes are extended from the winches, and the steel wire ropes are respectively wound around the top pulley blocks of the vertical rods and wrapped around the corresponding head pulley blocks.

[0028] The first main boom and the second main boom are both provided with head pulley blocks at the heads. The steel wires drawn out by the winch are respectively wound around the corresponding pulley blocks on the top of the vertical rods, and are respectively wound around the corresponding head pulley blocks of the main booms or the head pulley blocks of the auxiliary booms to avoid interference with the pile legs. At the same time, the pulling force is evenly distributed on the two booms, thereby achieving uniform force on the two booms and making the booms more stable.

[0029] The second technical solution of the present invention is: a working method of a double-arm parallel crane,

[0030] The following steps are involved:

[0031] 1) Preparation work, the rotary platform is in the initial position;

[0032] 2) starting the rotary drive device, which drives the rotary bearing and drives the rotary platform to rotate to the direction of the line connecting the center of the first cylinder on the base and the center of the rectangle on the bottom surface of the base and close to the central axis position of the rectangle on the bottom surface of the base;

[0033] 3) Start the double-arm crane to carry out the retrieval work;

[0034] 4) Control the rotary platform to rotate to the object placement area and place the object;

[0035] 5) Control the slewing platform to slew to the original position of the double-arm boom.

[0036] When it is necessary to retrieve the work, the slewing drive device drives the slewing bearing and drives the slewing platform to rotate to the direction of the line connecting the center of the first cylinder on the base and the center of the rectangle on the bottom surface of the base and close to the center axis position of the rectangle on the bottom surface of the base. When the rotation reaches the appropriate position and stops suddenly, due to the action of inertia, there is a torque stress in the tangent direction of the base along the cross-section circle. This stress can easily cause the base to twist and deform. At the same time, the cargo is hung on the head of the boom and pulls the boom downward. There is a bending moment stress on the cross section of the base. The weight of the items placed on the slewing platform such as the tripod, wire rope, winch, slewing bearing, slewing platform, double-arm boom, etc. and the weight of the base itself exert pressure on the deck. According to the principle of action and reaction force, the deck exerts a supporting force on the base. This force is dispersed on the base wall and is obliquely upward along the direction of the base wall. This supporting force can be decomposed into vertical upward stress and horizontal stress pointing to the central axis. This vertical upward stress and bending moment stress constitute relative direction stress on the base, which squeezes the base and easily causes the base to bend and break in the axial direction. Compared with the existing large-scale pile-wrapped offshore platform cranes and A double-arm tower crane, in the present invention, the central axis of the first cylinder does not pass through the center of the bottom surface of the base, so that the bottom area of ​​the base near one end of the boom is larger, so that the base near one end of the boom is larger in volume, thicker in wall thickness, larger in inner wall area, longer and more reinforcing ribs, so that the strength and rigidity of the base at one end of the boom are increased, the bending resistance is enhanced, and the base is prevented from twisting, deforming, bending or breaking; all the base reinforcing rib plates in the reinforcing rib plate group are arranged toward the central axis direction of the first cylinder, which is conducive to the weight of the rotating platform being evenly distributed downward on the base and the reinforcing ribs; the bottom of the base is rectangular, so that the intersections of the four surfaces of the bottom of the base all form the most stable right angles, thereby increasing the stability of the crane; the cross-sectional area of ​​the extended cylinder is smaller than the area of ​​the bottom rectangle, and the base adopts a structure with a small top and a large bottom, which increases the support surface formed by the contact between the bottom of the base and the deck, so that the base is more stable and more impact-resistant; compared with a double-arm tower crane in the prior art, the double-arm parallel crane has a rotary crane slewing support and a slewing platform, which can be rotatable, and the boom can achieve axial 90 o and radial 360 o Rotation, so it has strong applicability, large operating range, strong adaptability and high efficiency; at the same time, when carrying a large load of 1200t, a larger slewing device is required. At this time, a slewing bearing is used as a slewing device, which has a compact and simple structure, can withstand axial force, radial force and tipping moment at the same time, and is highly practical.

[0037] Except for the transition between the rectangular section and the circular section, the rectangular section and the circular section of the base are neatly arranged molecules, and the transition between the rectangular section and the circular section forms a cross-sectional mutation. Therefore, the molecules in the structure of the transition between the rectangular section and the circular section change, which changes the overall force and also changes the force state and balance of the molecules at the mutation. Through analysis, the base is subjected to downward pressure, bending force and twisting force, and due to the drastic change in the molecular structure at the mutation, the molecules inside the rectangular section and the circular section are evenly distributed, and the force is also evenly distributed. The transition between the rectangular section and the circular section produces a greater force to resist the external force due to the molecular change, which makes the stress at the transition between the rectangular section and the circular section greater, forming stress concentration. When the stress at this point is greater than the limit of the material Stress will damage the base and cause major safety accidents. In order to avoid the damage to the base due to stress concentration, in addition to adding a base reinforcement rib plate at the transition between the rectangular section and the circular section, a protrusion is also set. The base reinforcement rib plate provides a force roughly the same as the stress direction to increase the force to resist the base from pressure, bending force, and torsional force. The protrusion is located below the transition between the rectangular section and the circular section. When the transition between the rectangular section and the circular section of the base is subjected to bending force, the raised part is equivalent to giving an oblique upward force to increase the force to resist the base from receiving the bending force. Of course, the protrusion can also play a role in resisting pressure and torsional force, making the strength of the mutation point more reliable. An arc is set between the lower end of the protrusion and the base reinforcement rib plate to avoid the formation of stress concentration. In summary, the base reinforcement rib plate and the protrusion can greatly improve the strength of the base's mutation section and improve safety performance. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 The present invention is a front view of a double-arm parallel crane.

[0039] Figure 2 The present invention is a left side view of a double-arm parallel crane.

[0040] Figure 3 for Figure 1 Enlarged view of part A.

[0041] Figure 4 It is a front view of the base of the present invention.

[0042] Figure 5 It is a top view of the base of the present invention.

[0043] Figure 6 for Figure 5 Cross-section of the BB.

[0044] Figure 7 It is the front view of the rotary platform of the present invention.

[0045] Figure 8 It is a top view of the rotary platform of the present invention.

[0046] Fig. 9 It is a structural schematic diagram of the boom portion of the present invention. DETAILED DESCRIPTION

[0047] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0048] Figures 1 to 9 An embodiment of the present invention is shown.

[0049] A double-arm parallel crane comprises a base 1, a slewing bearing 2, a slewing platform 3, a slewing drive device 4, a tripod 5 and a double-arm boom part 6. The top of the base 1 is connected to the outer ring screw of the slewing bearing 2, the bottom of the slewing platform 3 is connected to the inner ring screw of the slewing bearing 2, the tripod 5 is fixedly installed on the top of the slewing platform 3, and the double-arm boom part 6 is hinged on the slewing platform 3. The base 1 is a hollow base with a rectangular bottom cross section and a circular top cross section. A first cylinder 7 extending upward is provided on the top of the base 1. From the bottom of the base 1 to the top of the first cylinder 7, there is a hollow base inner wall and the first cylinder 7. A base reinforcing rib plate group is provided on the inner wall thereof and is evenly arranged along the outer circumference direction of the base and extends up and down, and all base reinforcing rib plates 71 in the base reinforcing rib plate group are arranged toward the central axis direction of the first cylinder 7; the base reinforcing rib plate at the transition part between the rectangular cross section and the circular cross section has an inward protrusion 700, and a circular arc transition is formed between the lower end of the protrusion 700 and the base reinforcing rib plate; the cross-sectional area of ​​the first cylinder 7 is smaller than the area of ​​the rectangular bottom surface of the base 1, the central axis of the first cylinder 7 is parallel to the central axis of the bottom surface of the base 1, and the distance from the center of the bottom surface of the base 1 to the central axis of the first cylinder 7 is greater than 0.

[0050] The piles are inserted into the base 1, the slewing bearing 2, and the slewing platform 3 from bottom to top, and then pass through the deck and are fixed on the seabed. They have high stability and strong impact resistance. Compared with a large pile-wrapped offshore platform crane in the prior art, the double-arm boom part 6 adopts a parallel double boom, and the boom structure has good stability, large lifting capacity, greater lifting capacity, and stronger pressure-bearing capacity. Compared with a large pile-wrapped offshore platform crane and a double-arm tower crane in the prior art, a first cylinder 7 extending upward is provided on the top of the base 1 to facilitate connection with the outer ring screw of the slewing bearing. Since the central axis of the first cylinder 7 is parallel to the central axis of the bottom surface of the base 1, and the distance from the center of the bottom surface of the base 1 to the central axis of the first cylinder 7 is greater than 0, that is, the central axis of the base 1 deviates from the central axis of the first cylinder 7, the length of the reinforcing rib on the side of the connection position of the double-arm boom part 6 on the base 1 is increased.

[0051] The base 1 is the main stress-bearing part of the whole device. The stress analysis of one end of the base 1 equipped with the double-arm boom 6 shows that when the goods are transferred and rotated to a suitable position and stopped suddenly, due to the effect of inertia, there is a torque stress in the tangent direction of the cross-section of the base 1. This stress can easily cause the base to twist and deform. At the same time, the goods are hung on the head of the boom and pull the boom downward, and there is a bending moment stress on the cross section of the base. The tripod 5, wire rope, winch 8, etc. are placed on the rotating platform 3. The weight of the goods, the slewing bearing, the rotating platform 3, the double-arm boom 6, and the base 1's own weight exerts pressure on the deck. According to the principle of action and reaction, the deck exerts a supporting force on the base. This force is dispersed on the base wall and is obliquely upward along the direction of the base wall. This supporting force can be decomposed into vertical upward stress and horizontal central axis stress. This vertical upward stress and bending moment stress constitute relative direction stress on the base, which squeezes the base 1 and easily causes the base 1 to bend and break in the axial direction. Compared with the existing large pile-wrapped offshore platform crane and a double-arm tower crane, in the present invention, The central axis of a cylinder 7 does not pass through the center of the bottom surface of the base 1, so that the bottom area of ​​the base near one end of the double-arm boom portion 6 is larger, so that the base near one end of the double-arm boom portion 6 is larger in volume, thicker in wall thickness, larger in inner wall area, longer and more reinforcing ribs, so that the strength and rigidity of the base at one end of the boom are increased, the bending resistance is enhanced, and the base is prevented from twisting, deforming, bending or breaking; all the base reinforcing rib plates in the reinforcing rib plate group are arranged toward the central axis direction of the first cylinder 7, which is conducive to the weight of the rotating platform being evenly distributed downward on the base and the reinforcing ribs; the bottom of the base 1 is rectangular, so that the intersections of the four surfaces at the bottom of the base 1 all form the most stable right angles, which increases the stability of the crane; the cross-sectional area of ​​the extended first cylinder 7 is smaller than the area of ​​the bottom rectangle, and the base adopts a structure with a small top and a large bottom, which increases the support surface formed by the contact between the bottom of the base and the deck, so that the base is more stable and more impact-resistant; compared with a double-arm tower crane in the prior art, the double-arm parallel crane has a rotary crane slewing bearing and a slewing platform, which can be rotatable, and the boom can achieve an axial 90 o and radial 360 o Rotation, so it has strong applicability, large operating range, strong adaptability and high efficiency; at the same time, when carrying a large load of 1200t, a larger slewing device is required. At this time, a slewing bearing is used as a slewing device, which has a compact and simple structure, can withstand axial force, radial force and tipping moment at the same time, and is highly practical.

[0052] Except for the transition between the rectangular section and the circular section, the rectangular section and the circular section of the base are neatly arranged molecules. Since the transition between the rectangular section and the circular section forms a cross-sectional mutation, the molecules in the structure of the transition between the rectangular section and the circular section change, changing the overall force and also changing the force state and balance of the molecules at the mutation. Through analysis, the base is subjected to downward pressure F1, bending force F2 and twisting force F3. Since the molecular structure at the mutation changes sharply, the molecules inside the rectangular section and the circular section are evenly distributed, and the force is also evenly distributed. The transition between the rectangular section and the circular section produces a greater force to resist the external force due to the molecular change, making the stress at the transition between the rectangular section and the circular section greater, forming stress concentration. When the stress at this point is greater than the limit of the material Stress will damage the base and cause major safety accidents. In order to avoid the damage to the base due to stress concentration, in addition to adding a base reinforcing rib plate at the transition between the rectangular section and the circular section, a raised portion 700 is also provided. The base reinforcing rib plate provides a force roughly the same as the stress direction to increase the force to resist the base 1 from receiving pressure, bending force, and twisting force. The protrusion 700 is located below the transition between the rectangular section and the circular section. When the transition between the rectangular section and the circular section of the base is subjected to bending force, the raised portion is equivalent to providing an oblique upward force to increase the force to resist the base 1 from receiving bending force. Of course, the protrusion can also play a role in resisting pressure and twisting force, making the strength of the mutation more reliable. An arc is provided between the lower end of the protrusion and the base reinforcing rib plate to avoid the formation of stress concentration. In summary, the base reinforcing rib plate and the protrusion 700 can greatly improve the strength of the base's mutation section and improve safety performance.

[0053] The rotating platform 3 includes a quadrangular prism 31 with a cavity, a second cylinder 32 and a circular plate 33 with a hollow structure. The quadrangular prism 31 includes a rectangular top plate 311 with a circular hollow structure and a rectangular bottom plate 312 with a circular hollow structure. The rectangular bottom plate includes a first rectangular bottom plate 3121, a second rectangular bottom plate 3122 and a third rectangular bottom plate 3123 which are connected in sequence. The first rectangular bottom plate 3121 is inclined with the second rectangular bottom plate 3122, the third rectangular bottom plate 3123 is inclined with the second rectangular bottom plate 3122, and the first rectangular bottom plate 3121 and the third rectangular bottom plate 3123 are parallel.

[0054] The top of the second cylinder 32 is located in the quadrangular prism 31, and the top of the second cylinder 32 is welded to the bottom surface of the rectangular top plate 311 of the quadrangular prism, and a circular plate 33 with a circular hollow structure is welded to the bottom of the second cylinder 32. Two or more mounting holes 3311 for slewing bearings are arranged on the circular plate 33 at the welding position between the second cylinder 32 and the circular plate 33. The central axis of the circular hollow structure on the rectangular top plate 311 of the quadrangular prism, the central axis of the circular hollow structure on the rectangular bottom plate 312 of the quadrangular prism, the central axis of the second cylinder 32, the central axis of the circular hollow structure of the circular plate 33 and The central axis of the first cylinder 7 is in a straight line; the inner wall of the second cylinder 32 is evenly distributed with a first reinforcing rib plate group 321 along the radial direction of the second cylinder, and the outer wall of the second cylinder 32 in the quadrangular prism 31 is evenly distributed with a second reinforcing rib plate group 322 along the radial direction of the second cylinder 32, and a third reinforcing rib plate group installation area is provided inside the quadrangular prism 31, and the third reinforcing rib plate group installation area is located on the opposite side of the double-arm boom portion 6 on the rotating platform 3, and a transverse reinforcing rib plate group 3231 and a longitudinal reinforcing rib plate group 3232 are provided in the third reinforcing rib plate group installation area.

[0055] When the crane is operating with a large load of 1200t, in order to meet the requirements of the maximum lifting load, a large-sized tripod, winch and a steel wire rope with a larger diameter will be selected, so that the structure and weight of the tripod, winch and steel wire are also larger. The inner wall of the second cylinder, the outer wall of the second cylinder in the quadrangular main body, and the inner side of the quadrangular prism located on the opposite side of the double-arm boom part on the slewing platform are all installed with a reinforcing rib plate group, which enhances the axial and radial strength, rigidity and bending resistance of the top of the slewing platform to prevent the weight of the objects carried on the slewing platform from being too heavy. Cause the rotating platform to break; a cylinder is welded at the bottom of the rectangular top plate of the hollow quadrangular prism, and a circular plate with a circular hollow structure is welded at the bottom of the cylinder. The circular plate is convenient for connection with the inner ring screw of the rotating support. The cylinder is used to prevent the rotating platform from contacting the top of the base during rotation, increasing friction and hindering rotation; the central axes of the hollow structure of the rectangular top plate of the rotating platform, the second cylinder, the hollow structure of the rectangular bottom plate, and the hollow structure of the circular plate are in a straight line and face the end where the boom is hinged, in order to balance the torque with the base on both sides of the pile.

[0056] Four groups of tripod mounting panels 3111 extending upward are arranged at the diagonal positions of the quadrangular top plate 311, each group of tripod mounting panels includes two first mounting panels 31111 arranged opposite to each other, and each first mounting panel is provided with a tripod mounting hole, the tripod 5 includes two door frame assemblies 52 and a first cross bar 51 arranged opposite to each other, the two door frame assemblies are welded to the two ends of the first cross bar 51, each door frame assembly includes a first oblique rod 521 and a vertical rod 522, the bottom end of the vertical rod 522 is fixedly mounted on the rotary platform 3 and connected to the double-arm boom part 6 relative to the rotating platform 3 and perpendicular to the rotating platform 3, the bottom end of the first inclined rod 521 is fixedly installed on the rotating platform 3 near the double-arm boom part 6, the top of the first inclined rod 521 is connected to the top of the vertical rod 522, and a second cross rod 523 and a second diagonal rod 524 are provided at a lower middle position of the first inclined rod 521, one end of the second diagonal rod 524 is connected to the first diagonal rod 521, and the other end of the second diagonal rod 524 is connected to the second cross rod 523, and the second cross rod 523, the second diagonal rod 524 and the first diagonal rod 521 of the gantry assembly form a triangular structure.

[0057] The gantry assemblies are arranged symmetrically relative to the piles, and the bottom ends of the vertical rods and diagonal rods of the gantry assemblies are fixedly mounted on the revolving platform and the fixed deck to form a stable triangular structure, thereby improving the structural stability of the gantry assemblies and the convenience of maintenance; at the same time, the two gantry assemblies are connected by a first cross bar and two cross rods 53 assemblies to further improve the stability of the gantry assemblies.

[0058] A second horizontal bar and a second diagonal bar are arranged at a lower middle position of the diagonal bar, forming a triangular structure with the first diagonal bar. When the boom rises to a vertical position, they support the boom to prevent the boom from tipping over to the other side. The triangular structure has greater stability and impact resistance.

[0059] Two groups of upwardly extending double-arm boom mounting panels 3112 are provided on one side of the quadrangular prism rectangular top plate 311 close to the double-arm boom part 6, and each group of double-arm boom part mounting panels 3112 includes two oppositely arranged second mounting panels 31121, and the second mounting panels are provided with mounting holes for the double-arm boom part 6.

[0060] The tripod mounting holes are distributed at diagonal positions of the quadrangular top plate, so that the weight of the tripod is evenly distributed on the slewing platform, thereby improving the stability of the crane.

[0061] The double-arm boom portion 6 includes a main boom and an auxiliary boom 63. The tail of the auxiliary boom is connected to the head of the main boom. The main boom and the auxiliary boom 63 are provided with hook assemblies. The main boom includes a first main boom 61 and a second main boom 62. The first main boom 61 and the second main boom 62 are arranged side by side and fixed by a connecting piece 64. The first main boom 61 and the second main boom 62 correspond to a gantry assembly respectively.

[0062] This double-arm structure disperses the force, making the structure more stable and increasing the strength. The lifting performance of the crane boom is improved, and the modularization of the crane boom structure can be achieved.

[0063] The first main boom 61 and the second main boom 62 are both composed of a boom root section, a boom middle section and a boom tip section, and the boom root section, the boom middle section and the boom tip section are detachably connected.

[0064] The main boom adopts this connection method to realize the modularization of the boom structure, disperse the force, and can be disassembled and assembled during transportation, which is convenient for transportation.

[0065] The connecting member 64 includes a first connecting member 641, a second connecting member 642 and a third connecting member 643. The first connecting member 641 is fixedly connected between the arm root sections, the second connecting member 642 is fixedly connected between the arm middle sections, and the third connecting member 643 is fixedly connected between the arm tip sections.

[0066] A connecting piece is provided between the two booms to improve the stability of the booms. Two or more second connecting pieces 642 may be provided according to the length of the main boom of the boom part to ensure the structural strength of the boom part.

[0067] Protruding panels 331 are respectively provided on both sides of the quadrangular prism circular plate 33 at the outer circumference of the second cylinder 32, and mounting hole groups 332 of the rotary drive device 4 are evenly distributed on the protruding panels 331. The rotary drive device mounting hole group 332 is located between the tripod mounting panel 3111 and the double-arm boom portion mounting panel 3112 (that is, between the two tripod mounting panels 3111 located on the same side), and each rotary drive device mounting hole group 332 includes two or more rotary drive mounting holes. In this embodiment, two rotary drive device mounting hole groups 332 are provided between the tripod mounting panel 3111 and the double-arm boom portion mounting panel 3112, and the rotary drive device mounting hole groups 332 are symmetrically arranged, and each rotary drive device mounting hole group 332 includes five rotary drive mounting holes. One end of the rotary drive device 4 passes through the rotary drive device mounting hole to engage with the outer ring of the rotary bearing 2, and the other end of the rotary drive device 4 is fixed on the quadrangular prism circular plate 33.

[0068] When the crane is operating with a large load, the slewing platform is larger in size and requires more slewing drive devices to drive the rotation. At the same time, it is necessary to share part of the weight of the slewing platform. The symmetrical setting allows both sides to be driven to rotate at the same time, making rotation easier. At the same time, the weight of the slewing platform is evenly shared, which is conducive to balance and prevents overturning.

[0069] Winch 8 is respectively provided on the rotating platform 3 near the two vertical rods 522, top pulley blocks 5221 are respectively provided on the top of the two vertical rods 522, and head pulley blocks 65 are respectively provided at the head of the main boom. A steel wire rope 9 extends out of the winch 8, and the steel wire rope 9 is respectively wound around the top pulley block 5221 of the vertical rod 522, and is respectively wound around the head pulley block 65 of the main boom or the auxiliary boom.

[0070] The steel wires drawn out by the winch are respectively wound around the corresponding pulley blocks at the top of the vertical rods, and are respectively wound around the corresponding pulley blocks at the head of the main boom or the head pulley blocks of the auxiliary boom, to avoid interference with the pile legs or entanglement of the two sets of steel wires. At the same time, the pulling force is evenly distributed on the two booms, achieving uniform force on the two booms and making the booms more stable.

[0071] The double-arm parallel crane of the present invention comprises the following steps when working:

[0072] 1) Preparation work, the rotary platform 3 is located at the initial position;

[0073] 2) Start the rotary drive device 4, which drives the rotary bearing 2 and drives the rotary platform 3 to rotate to the direction of the line connecting the center of the first cylinder on the base 1 and the center of the rectangle on the bottom surface of the base 1 and close to the central axis position of the rectangle on the bottom surface of the base;

[0074] 3) Start the double-arm crane 6 to carry out the retrieval work;

[0075] 4) Control the rotary platform 3 to rotate to the object placement area and place the object;

[0076] 5) Control the rotary platform 3 to rotate to the original position of the double-arm boom part 6.

[0077] The piles are inserted into the base 1, the slewing bearing 2, and the slewing platform 3 from bottom to top, and then pass through the deck and are fixed on the seabed. They have high stability and strong impact resistance. Compared with a large pile-wrapped offshore platform crane in the prior art, the double-arm boom part 6 adopts a parallel double boom, and the boom structure has good stability, large lifting capacity, greater lifting capacity, and stronger pressure-bearing capacity. Compared with a large pile-wrapped offshore platform crane and a double-arm tower crane in the prior art, a first cylinder 7 extending upward is provided on the top of the base 1 to facilitate connection with the outer ring screw of the slewing bearing. Since the central axis of the first cylinder 7 is parallel to the central axis of the bottom surface of the base 1, and the distance from the center of the bottom surface of the base 1 to the central axis of the first cylinder 7 is greater than 0, that is, the central axis of the base 1 deviates from the central axis of the first cylinder 7, the length of the reinforcing rib on the side of the connection position of the double-arm boom part 6 on the base 1 is increased.

[0078] The base 1 is the main stress-bearing part of the whole device. The stress analysis of one end of the base 1 equipped with the double-arm boom 6 shows that when the goods are transferred and rotated to a suitable position and stopped suddenly, due to the effect of inertia, there is a torque stress in the tangent direction of the cross-section of the base 1. This stress can easily cause the base to twist and deform. At the same time, the goods are hung on the head of the boom and pull the boom downward, and there is a bending moment stress on the cross section of the base. The tripod 5, wire rope, winch 8, etc. are placed on the rotating platform 3. The weight of the goods, the slewing bearing, the rotating platform 3, the double-arm boom 6, and the base 1's own weight exerts pressure on the deck. According to the principle of action and reaction, the deck exerts a supporting force on the base. This force is dispersed on the base wall and is obliquely upward along the direction of the base wall. This supporting force can be decomposed into vertical upward stress and horizontal central axis stress. This vertical upward stress and bending moment stress constitute relative direction stress on the base, which squeezes the base 1 and easily causes the base 1 to bend and break in the axial direction. Compared with the existing large pile-wrapped offshore platform crane and a double-arm tower crane, in the present invention, The central axis of a cylinder 7 does not pass through the center of the bottom surface of the base 1, so that the bottom area of ​​the base near one end of the double-arm boom portion 6 is larger, so that the base near one end of the double-arm boom portion 6 is larger in volume, thicker in wall thickness, larger in inner wall area, longer and more reinforcing ribs, so that the strength and rigidity of the base at one end of the boom are increased, the bending resistance is enhanced, and the base is prevented from twisting, deforming, bending or breaking; all the base reinforcing rib plates in the reinforcing rib plate group are arranged toward the central axis direction of the first cylinder 7, which is conducive to the weight of the rotating platform being evenly distributed downward on the base and the reinforcing ribs; the bottom of the base 1 is rectangular, so that the intersections of the four surfaces at the bottom of the base 1 all form the most stable right angles, which increases the stability of the crane; the cross-sectional area of ​​the extended first cylinder 7 is smaller than the area of ​​the bottom rectangle, and the base adopts a structure with a small top and a large bottom, which increases the support surface formed by the contact between the bottom of the base and the deck, so that the base is more stable and more impact-resistant; compared with a double-arm tower crane in the prior art, the double-arm parallel crane has a rotary crane slewing bearing and a slewing platform, which can be rotatable, and the boom can achieve an axial 90 o and radial 360 o Rotation, so it has strong applicability, large operating range, strong adaptability and high efficiency; at the same time, when carrying a large load of 1200t, a larger slewing device is required. At this time, a slewing bearing is used as a slewing device, which has a compact and simple structure, can withstand axial force, radial force and tipping moment at the same time, and is highly practical.

[0079] Except for the transition between the rectangular section and the circular section, the rectangular section and the circular section of the base are neatly arranged molecules, and the transition between the rectangular section and the circular section forms a cross-sectional mutation. Therefore, the molecules in the structure of the transition between the rectangular section and the circular section change, which changes the overall force and also changes the force state and balance of the molecules at the mutation. Through analysis, the base is subjected to downward pressure F1, bending force F2 and twisting force F3. Due to the drastic change in the molecular structure at the mutation, the molecules inside the rectangular section and the circular section are evenly distributed, and the force is also evenly distributed. The transition between the rectangular section and the circular section produces a greater force to resist the external force due to the molecular change, which makes the stress at the transition between the rectangular section and the circular section greater, forming stress concentration. When the stress at this point is greater than the limiting stress of the material, the stress at this point is greater than the limiting stress of the material. If the base 1 is subjected to stress, it will damage the base and cause a major safety accident. In order to avoid the base being damaged due to stress concentration, in addition to adding a base reinforcing rib plate at the transition between the rectangular section and the circular section, a raised portion 700 is also provided. The base reinforcing rib plate provides a force roughly the same as the stress direction to increase the force to resist the base 1 from receiving pressure, bending force, and twisting force. The protrusion 700 is located slightly below the transition between the rectangular section and the circular section. When the transition between the rectangular section and the circular section of the base is subjected to bending force, the raised portion is equivalent to providing an oblique upward force to increase the force to resist the base 1 from receiving bending force. Of course, the protrusion can also play a role in resisting pressure and twisting force, making the strength of the mutation more reliable. An arc is provided between the lower end of the protrusion and the base reinforcing rib plate to avoid the formation of stress concentration. In summary, the base reinforcing rib plate and the protrusion 700 can greatly improve the strength of the base's mutation section and improve safety performance.

Claims

1. A double-arm parallel crane, comprising a base, a slewing bearing, a slewing platform, a slewing drive device, a tripod and a double-arm boom portion, wherein the top of the base is connected to the outer ring screw of the slewing bearing, the bottom of the slewing platform is connected to the inner ring screw of the slewing bearing, the tripod is fixedly mounted on the top of the slewing platform, and the double-arm boom portion is hinged on the slewing platform, characterized in that: The base is a hollow base with a rectangular bottom cross-section and a circular top cross-section. A first cylinder extending upward is provided on the top of the base. A base reinforcing rib plate group extending up and down and evenly arranged along the outer circumference of the base is provided on the inner wall of the hollow base and the inner wall of the first cylinder from the bottom of the base to the top of the first cylinder. All base reinforcing rib plates in the base reinforcing rib plate group are arranged toward the central axis of the first cylinder. The base reinforcing rib plate at the transition part between the rectangular cross-section and the circular cross-section has an inward protrusion, and a circular arc transition is formed between the lower end of the protrusion and the base reinforcing rib plate. The cross-sectional area of ​​the first cylinder is smaller than the rectangular area of ​​the bottom surface of the base, the central axis of the first cylinder is parallel to the central axis of the bottom surface of the base, and the distance from the center of the bottom surface of the base to the central axis of the first cylinder is greater than 0. The rotary platform includes a quadrangular prism with a cavity, a second cylinder and a circular plate with a hollow structure, wherein the quadrangular prism includes a rectangular top plate with a circular hollow structure and a rectangular bottom plate with a circular hollow structure, wherein the rectangular bottom plate includes a first rectangular bottom plate, a second rectangular bottom plate and a third rectangular bottom plate connected in sequence, wherein the first rectangular bottom plate is inclined with the second rectangular bottom plate, the third rectangular bottom plate is inclined with the second rectangular bottom plate, and the first rectangular bottom plate and the third rectangular bottom plate are arranged in parallel; The top of the second cylinder is located in the quadrangular prism, and the top of the second cylinder is welded to the bottom surface of the rectangular top plate of the quadrangular prism, a circular plate with a circular hollow structure is welded to the bottom of the second cylinder, and two or more mounting holes for slewing bearings are arranged on the inner circumference of the circular plate at the welding point between the second cylinder and the circular plate, the central axis of the circular hollow structure on the rectangular top plate of the quadrangular prism, the central axis of the circular hollow structure on the rectangular bottom plate of the quadrangular prism, the central axis of the second cylinder, the central axis of the circular hollow structure of the circular plate and the central axis of the first cylinder are in a straight line; the inner wall of the second cylinder is evenly distributed with a first reinforcing rib plate group along the radial direction of the second cylinder, the outer wall of the second cylinder in the quadrangular prism is evenly distributed with a second reinforcing rib plate group along the radial direction of the second cylinder, a third reinforcing rib plate group installation area is arranged inside the quadrangular prism, the third reinforcing rib plate group installation area is located on the opposite side of the double-arm boom portion on the slewing platform, and a transverse reinforcing rib plate group and a longitudinal reinforcing rib plate group are arranged in the third reinforcing rib plate group installation area; Four groups of tripod mounting panels extending upward are arranged at diagonal positions of the rectangular top plate of the quadrangular prism, each group of tripod mounting panels includes two first mounting panels arranged oppositely, and each first mounting panel is provided with a tripod mounting hole, and two groups of double-arm boom mounting panels extending upward are arranged on one side of the rectangular top plate of the quadrangular prism close to the double-arm boom portion, each group of double-arm boom mounting panels includes two second mounting panels arranged oppositely, and the second mounting panels are provided with double-arm boom mounting holes; The circular plate of the quadrangular prism is provided with a group of slewing drive device mounting holes on both sides at the outer circumference of the second cylinder, and the slewing drive device mounting hole group is located between the tripod mounting panel and the double-arm boom mounting panel, and each slewing drive device mounting hole group includes two or more slewing drive mounting holes, one end of the slewing drive device passes through the slewing drive device mounting hole and meshes with the outer ring of the slewing bearing, and the other end of the slewing drive device is fixed to the circular plate of the quadrangular prism; The tripod includes two relatively arranged door frame assemblies and a first cross bar, the two door frame assemblies are respectively welded at both ends of the first cross bar, each of the door frame assemblies includes a vertical bar and a first diagonal bar, the bottom end of the vertical bar is fixedly installed on the rotating platform at a position opposite to the double-arm boom part and is perpendicular to the rotating platform, the bottom end of the first diagonal bar is fixedly installed on the rotating platform near the double-arm boom part, the top of the first diagonal bar is connected to the top of the vertical bar, a second cross bar and a second diagonal bar are provided at a middle and lower position of the first diagonal bar, one end of the second diagonal bar is connected to the first diagonal bar, and the other end of the second diagonal bar is connected to the second cross bar, the second cross bar, the second diagonal bar and the first diagonal bar of the door frame assembly form a triangular structure.

2. The double-arm parallel crane according to claim 1, characterized in that: The double-arm boom portion includes a main boom and an auxiliary boom, the tail of the auxiliary boom is connected to the head of the main boom, and hook assemblies are provided on the main boom and the auxiliary boom; the main boom includes a first main boom and a second main boom, the first main boom and the second main boom are arranged side by side and fixed by a connecting piece, and the first main boom and the second main boom correspond to a gantry assembly respectively.

3. The double-arm parallel crane according to claim 2, characterized in that: The first main boom and the second main boom are both composed of a boom root section, a boom middle section and a boom tip section, and the boom root section, the boom middle section and the boom tip section are detachably connected.

4. The double-arm parallel crane according to claim 2, characterized in that: The connecting member comprises a first connecting member, a second connecting member and a third connecting member, wherein the first connecting member is fixedly connected between the arm root sections, the second connecting member is fixedly connected between the arm middle sections, and the third connecting member is fixedly connected between the arm tip sections.

5. The double-arm parallel crane according to claim 2, characterized in that: Winches are respectively provided on the rotating platform near the two vertical rods, top pulley blocks are respectively provided on the tops of the two vertical rods, head pulley blocks are respectively provided at the heads of the main boom and the auxiliary boom, steel wire ropes are extended from the winches, and the steel wire ropes are respectively wound around the top pulley blocks of the vertical rods and wrapped around the corresponding head pulley blocks.

6. A working method of a double-arm parallel crane according to any one of claims 1 to 5, Features: The following steps are involved: 1) Preparation work, the rotary platform is in the initial position; 2) starting the rotary drive device, which drives the rotary bearing and drives the rotary platform to rotate to the direction of the line connecting the center of the first cylinder on the base and the center of the rectangle on the bottom surface of the base and close to the central axis position of the rectangle on the bottom surface of the base; 3) Start the double-arm crane to carry out the retrieval work; 4) Control the rotary platform to rotate to the object placement area and place the object; 5) Control the slewing platform to slew to the original position of the double-arm boom.