A kind of assembled bridge expansion device and construction method thereof
Through the design of the base and isolation plate of the prefabricated bridge expansion device, the problems of waste of materials and extended construction cycles in the construction of bridge expansion joints are solved, and more efficient construction processes and material utilization are achieved.
Patent Information
- Application Number
- CN201910025735.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-01-11
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2039-01-11
AI Technical Summary
In the prior art, the construction of bridge expansion joints has problems of waste of materials and prolonged construction cycles. Traditional methods require the reservation of notches, embedded anchor ribs and temporary laying of asphalt, resulting in complex construction and waste of materials, and waiting for the concrete to set a long time.
The base of the prefabricated bridge expansion device is adopted, including a symmetrically distributed base and isolation plate. The expansion device is installed between the isolation plates to control the asphalt paving range, avoid material waste and extend the construction cycle.
Through the design of the prefabricated telescopic device base and isolation plate, we can reduce material waste, shorten the construction cycle, avoid unnecessary processes and waiting time in traditional methods, and improve construction efficiency and efficiency.
Smart Images

Figure CN109505238B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of expansion joints, and in particular to an assembled bridge expansion device and a construction method thereof. Background Art
[0002] The expansion joints of bridges can ensure that the bridges can freely expand and contract longitudinally under the action of temperature changes, concrete shrinkage and creep, and live loads, and prevent excessive secondary internal forces. The expansion joints of bridges must have good flatness, be able to withstand various vehicle loads, and be firm, reliable, and durable. At the same time, they must be easy to install, maintain, repair, and replace. Since the expansion joints of bridges are subjected to repeated effects of wheel loads, the impact caused by the uneven position of the expansion joints will damage the expansion joints. Therefore, the expansion joint is one of the most easily damaged and difficult to repair parts of the bridge.
[0003] Under existing technical conditions, when constructing expansion joints, it is necessary to reserve expansion joint notches on the bridge to facilitate the installation of expansion joints later, and to embed anchor bars in the expansion joint notches. Then, temporary expansion joints are laid at the expansion joint notches, and then the lower layer and road surface asphalt are laid as a whole on the basis of the temporary expansion joints along with the bridge surface. When constructing expansion joints, it is necessary to saw and remove excess asphalt on both sides of the temporary expansion joints, and then chisel off the temporary expansion joints until the anchor bars are exposed, and then formally install the expansion joint components.
[0004] Traditional expansion joint construction methods will result in a lot of material waste and cause environmental pollution. In addition, when constructing the expansion joint, it is necessary to wait for the concrete base to solidify. When the other structures of the bridge are completed, it takes extra time to wait for the expansion joint concrete base, which prolongs the construction period. Summary of the invention
[0005] In order to overcome the deficiencies of the prior art, the present invention provides an assembled bridge expansion device and a construction method thereof, which are used to reduce material waste caused by the construction of expansion joints and shorten the construction period.
[0006] The technical solution adopted by the present invention to solve the above-mentioned problem is: a construction method of an assembled bridge expansion device, comprising a expansion device base installed on the end structure of the beam body, the expansion device base comprising two symmetrically distributed bases with a gap, two isolation plates respectively located on both sides of the beam seam for isolating asphalt and parallel to the length direction of the beam seam are arranged on the expansion device base, and the expansion device is installed between the two isolation plates
[0007] The beneficial effects achieved by this solution are: the prefabricated expansion joint base serves as the basis of the expansion joint, which can avoid the problem of long construction period caused by the expansion joint construction as the last process, and can avoid the problem of increasing construction waste and wasting construction materials due to damage to the completed project in the later stage.
[0008] Furthermore, in order to better implement the present invention, the following steps are included:
[0009] Step S1: prefabricate the beam end structure;
[0010] Step S2: With the isolation plate facing upward, the telescopic device base is installed on the end structure of the beam body, and a waterproof structure is installed in the gap along the length direction of the gap;
[0011] Step S3: installing a template between the two isolation boards to fill the space between the two isolation boards;
[0012] Step S4: pouring asphalt on the outer sides of the two isolation boards;
[0013] Step S5: taking out the template;
[0014] Step S6: Install an expansion device between two isolation panels to complete the construction of the expansion joint.
[0015] Furthermore, in order to better implement the present invention, after the beam end structure is prefabricated, the beam end structure is installed at the location of the construction expansion joint in step S1, step S2 or step S3.
[0016] The beneficial effect achieved by adopting the above further technical solution is that the expansion joint can be constructed simultaneously with other pavement structures, thereby saving time.
[0017] Furthermore, in order to better realize the present invention, the telescopic device is made of steel sections and waterproof rubber strips, so that the steel sections and the isolation plate are detachably connected.
[0018] Furthermore, in order to better realize the present invention, the telescopic device is made of a comb plate and a waterproof rubber strip, so that the comb plate and the isolation plate are detachably connected.
[0019] An assembled bridge expansion device comprises an expansion device base installed on a beam end structure and an expansion device arranged on the expansion device base, wherein the expansion device base comprises two symmetrically distributed bases with a gap and an isolation plate arranged on the upper surface of the base, wherein the length direction of the isolation plate is the same as the length direction of the gap, and the expansion device is detachably installed between the two isolation plates.
[0020] The beneficial effects achieved by this solution are: the use of isolation plates can control the paving range of asphalt, prevent asphalt from entering the space between the two isolation plates, and reduce the work of cleaning up excess asphalt in the later stage, which is conducive to reducing the construction period, improving construction efficiency and reducing material waste. The gap formed by the base can be used as a temporary expansion joint, and there is no need to chisel it out in the later stage, avoiding material waste and adding unnecessary processes. The expansion device and the isolation plate can be detachably connected, which facilitates the installation of the expansion device to form a formal expansion joint. The base can be built at the same time as the bridge, and does not need to be removed in the later stage, avoiding the time of waiting for the expansion joint concrete base to solidify in traditional technology, thereby saving time and shortening the construction period. This solution can also be used directly in the later construction process as prefabricated parts.
[0021] Furthermore, in order to better implement the present invention, the base includes a concrete base, an anchor plate arranged in the concrete base, and anchor bars arranged in the concrete base and installed on the anchor plate.
[0022] The beneficial effects achieved by adopting the above-mentioned further technical solution are: the base formed by the anchor bar concrete structure ensures that the base itself has sufficient compressive strength to meet actual use requirements, the anchor bars are connected as a whole to improve the strength and stability of the anchor bars, and when constructing the base, all anchor bars can be kept in a fixed position to facilitate the construction of the base.
[0023] Furthermore, in order to better realize the present invention, the telescopic device includes two side beams and a waterproof rubber strip installed between the two side beams, and the side beams are detachably connected to the isolation plate.
[0024] The beneficial effect achieved by adopting the above further technical solution is that the waterproof rubber strip can be easily installed between the isolation plates to achieve the effect of waterproofing and dustproofing.
[0025] Furthermore, in order to better realize the present invention, the telescopic device includes two comb plates and a waterproof rubber strip arranged between the two comb plates, and the comb plates correspond to the base one by one and are detachably connected.
[0026] The beneficial effect achieved by adopting the above further technical solution is that it is convenient to form a telescopic device by using the comb plate.
[0027] Furthermore, in order to better realize the present invention, a U-shaped waterproof structure is provided between the gaps, located below the telescopic device and opening upward; hooks opening downward are provided on both sides of the U-shaped waterproof structure, and a waterproof support structure for hook installation is provided on the base.
[0028] The beneficial effects achieved by adopting the above further technical solution are: further enhancing the waterproof function and utilizing the waterproof support structure to facilitate the fixing and installation of the U-shaped waterproof structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a structural schematic diagram of the telescopic device base;
[0030] Figure 2 is a schematic structural diagram of the base in Example 3;
[0031] Figure 3 It is a schematic diagram of the installation of the telescopic device and the telescopic device base;
[0032] Figure 4 for Figure 3 A magnified image of point A;
[0033] Figure 5 is the structural diagram of the side beam;
[0034] Figure 6 It is a structural schematic diagram of Example 6;
[0035] Figure 7 This is a schematic diagram of the structure of Example 9.
[0036] The symbols and corresponding parts names in the drawings are:
[0037] 1- beam end structure, 2- base, 21- concrete base, 22- anchor bars, 23- anchor plates, 24- fixed seats, 3- isolation plates, 4- side beams, 41- vertical beams, 42- through grooves, 5- waterproof rubber strips, 6- pressure plates, 7- U-shaped waterproof structure, 71- waterproof support structure, 8- middle beams, 9- comb plates. DETAILED DESCRIPTION
[0038] The present invention will be further described in detail below in conjunction with embodiments and drawings, but the embodiments of the present invention are not limited thereto.
[0039] Embodiment 1:
[0040] In this embodiment, an assembled bridge expansion device and a construction method thereof include an expansion device base installed on the beam end structure 1 and an expansion device arranged on the expansion device base. The expansion device base is prefabricated before the expansion joint is constructed. Figure 1 As shown, the telescopic device base includes two symmetrically distributed bases 2 with a gap and an isolation plate 3 arranged on the upper surface of the base 2. The length direction of the isolation plate 3 is the same as the length direction of the gap, wherein the gap is the beam gap reserved in the telescopic device base. The telescopic device can be detachably installed between the two isolation plates 3.
[0041] During construction, first determine the construction position of the expansion joint, complete the construction of the beam body, and use the beam end structure 1 at the end of the beam body as a reference to construct other positions of the bridge surface and the road surface asphalt. The beam end structure 1 mainly includes a beam body arranged horizontally and a bridge deck pavement arranged vertically on the beam body. At the same time, the expansion device base can be constructed, and the gap between the two bases 2 is used as the basis of the expansion joint. Then the expansion device is constructed to complete the project. This scheme adopts such a structure, which enables the pavement engineering and expansion joint engineering on both sides of the beam end structure 1 to be carried out simultaneously or at a short time interval, and does not need to construct temporary expansion joints in traditional processes, thereby saving time and materials for constructing temporary expansion joints. There is no need to chisel out temporary construction joints in the later stage, saving time for chiseling out temporary construction joints and avoiding construction waste and material waste generated by chiseling out temporary construction joints. After the construction of the expansion device base is completed, asphalt is laid, and the asphalt laying range can be controlled by using the isolation board 3 to prevent asphalt from entering the space between the two isolation boards 3 and filling the expansion joint. The material consumption when laying asphalt is saved, and the step of chiseling off excess asphalt in the traditional process is saved, thereby saving construction time, avoiding material waste and generating construction waste. The use of the isolation plate 3 also does not require manual measurement or calculation of the amount of asphalt. The top surface of the isolation plate 3 is made flush with the bridge deck paved with asphalt to avoid overall unevenness that affects vehicle driving or causes water accumulation. In order to ensure the performance of the isolation plate 3, the isolation plate 3 is made of corrosion-resistant metal material to ensure sufficient strength and service life.
[0042] The expansion device base can also be made as a prefabricated part in advance or at the beginning of construction, and multiple expansion device bases can be made at the same time according to the needs of the project. After the construction of the beam end structure 1 is completed, the prefabricated expansion device base can be directly installed on the beam end structure 1, thereby improving construction efficiency and saving time. This solution is also applicable to the construction of road expansion joints.
[0043] The beneficial effects achieved by this solution are: the prefabricated expansion joint base serves as the basis of the expansion joint, which can avoid the problem of long construction period caused by the expansion joint construction as the last process, and can avoid the problem of increasing construction waste and wasting construction materials due to damage to the completed project in the later stage.
[0044] Embodiment 2:
[0045] In this embodiment, a construction method of an assembled bridge expansion device includes the following steps:
[0046] Step S1: prefabricate the beam end structure 1. The beam end structure 1 mainly includes a beam arranged transversely and a bridge deck pavement arranged vertically on the beam, mainly used to form an L-shaped groove for installing the telescopic device base.
[0047] Step S2: With the isolation plate 3 facing upward, the telescopic device base is installed in the L-shaped groove of the beam end structure 1. A waterproof structure is installed in the gap along the length direction of the gap.
[0048] Step S3: Install a template between two isolation boards 3 to fill the space between the two isolation boards 3. The template is used to limit the position of the isolation board 3 and balance the pressure of the asphalt on the isolation board 3 to prevent the position of the isolation board 3 from shifting or rotating after pouring the asphalt.
[0049] Step S4: pouring asphalt on the outer sides of the two isolation panels 3 .
[0050] Step S5: Take out the template.
[0051] Step S6: Install an expansion device between the two isolation panels 3 to complete the construction of the expansion joint.
[0052] Further, in order to better implement the present invention, after the beam end structure 1 is prefabricated, the beam end structure 1 is installed at the location where the expansion joint is to be constructed in step S1, step S2 or step S3. This ensures that the construction of the expansion joint can be carried out simultaneously with the asphalt, etc., thereby avoiding waiting for the expansion joint construction to be completed separately and saving time.
[0053] Embodiment 3:
[0054] like Figure 2 As shown, on the basis of the above embodiment, in this embodiment, the base 2 includes a concrete base 21, an anchor plate 23 arranged in the concrete base 21, and anchor bars 22 arranged in the concrete base 21 and installed on the anchor plate 23, and the two ends of the anchor bars 22 are respectively connected to the anchor plate 23 in a ring shape. The concrete base 21 and the anchor bars 22 form an anchor bar concrete structure to ensure that the base 2 has sufficient strength to meet the use requirements of the bridge. The anchor plates 23 can be used to connect the anchor bars 22 as a whole to improve the strength and stability of the anchor bars 22, and all the anchor bars 22 can be kept in a fixed position when constructing the base 2, so as to avoid the anchor bars 22 being impacted by concrete when pouring the base 2, resulting in structural instability, thereby facilitating the construction of the base 2.
[0055] The two ends of the anchor bar 22 are respectively connected to the anchor plate 23 in a ring shape. When the base 2 is subjected to the pressure of the car, there is a tendency to press downward. If there is a sharp structure inside the base 2, the concrete structure of the base 2 is easily damaged. The two ends of the anchor bar 22 are respectively connected to the anchor plate 23 in a ring shape to avoid the formation of a sharp structure inside the base 2, thereby avoiding the concrete structure of the base 2 from being damaged. In this embodiment, other contents not described are the same as those in the above embodiment, so they are not repeated.
[0056] Embodiment 4:
[0057] As Figure 2 shown, on the basis of the above embodiments, in this embodiment, the telescopic device includes two side beams 4 and a waterproof rubber strip 5 installed between the two side beams 4. The side beam 4 is detachably connected to the isolation board 3. The waterproof rubber strip 5 is installed between the two isolation boards 3 by using the side beam 4 to achieve the functions of waterproofing and dustproofing, and prevent rainwater, dust or other impurities from entering the expansion joint.
[0058] As Figure 5 shown, according to the national standard, the side beam 4 includes a vertical beam 41 and a through groove 42 arranged on one side of the vertical beam 41 and forming an F shape with the vertical beam 41. The through grooves 42 of the two side beams 4 are arranged opposite to each other, and the waterproof rubber strip 5 is installed in the through groove 42. The through groove 42 facilitates the installation and fixation of the waterproof rubber strip 5.
[0059] The side beam 4 is threadedly connected to the isolation board 3. This facilitates the installation of the side beam 4 and can ensure a certain installation strength to prevent the side beam 4 from loosening. In this embodiment, the other contents not described are the same as those in the above embodiments, so they will not be elaborated.
[0060] Embodiment 5:
[0061] As Figure 2 shown, on the basis of the above embodiments, in this embodiment, a pressing plate 6 is arranged below the through groove 42, and the screw passes through the pressing plate 6, the vertical beam 41 in sequence and then is connected to the isolation board 3. The pressing plate 6 can play a role in pressing the side beam 4 and provide an operating space for the rotation of the screw, avoiding the nut entering the space directly below the through groove 42 during the screwing process and making it difficult to operate. In this embodiment, the other contents not described are the same as those in the above embodiments, so they will not be elaborated.
[0062] Embodiment 6:
[0063] As Figure 6 shown, on the basis of the above embodiments, in this embodiment, several intermediate beams 8 are arranged between the side beams 4. The intermediate beam includes an intermediate vertical beam and through grooves 42 arranged on both sides of the intermediate vertical beam. In this embodiment, the intermediate vertical beam is an inverted T shape, and the intermediate vertical beam and the through grooves 42 on both sides form a "king" character shape. The intermediate beam can be used to realize the construction of the modular expansion joint. A support structure for supporting the intermediate beam is arranged between the bases 2. The support structure can improve the stability of the intermediate beam. In this embodiment, the other contents not described are the same as those in the above embodiments, so they will not be elaborated.
[0064] Embodiment 7:
[0065] As Figure 4As shown, on the basis of the above embodiment, in this embodiment, a U-shaped waterproof structure 7 located below the telescopic device and opening upward is provided between the gaps. The U-shaped waterproof structure 7 can further enhance the waterproof function. Hooks opening downward are provided on both sides of the U-shaped waterproof structure 7, and a waterproof support structure 71 for hook installation is provided on the base 2. The waterproof support structure 71 facilitates the fixation and installation of the U-shaped waterproof structure. The U-shaped waterproof structure 7 is made of waterproof and corrosion-resistant materials to meet actual use needs, such as waterproof and corrosion-resistant rubber, waterproof and corrosion-resistant metal or waterproof and corrosion-resistant alloy. The specific materials are common knowledge of those skilled in the art, and the specific materials of the U-shaped waterproof structure 7 are not limited here. In this embodiment, other undescribed contents are the same as those in the above embodiment, so they are not repeated.
[0066] Embodiment 8:
[0067] like Figure 2 , Figure 6 As shown, based on the above embodiment, in this embodiment, the base 2 further includes a fixing seat 24, the isolation plate 3 is mounted on the upper surface of the fixing seat 24, and the anchor plate 23 is mounted on the lower surface of the fixing seat 24. The fixing seat 24 can be provided with multiple layers, and the height of the isolation plate 3 can be adjusted by increasing or decreasing the number of layers of the fixing seat 24 or increasing or decreasing gaskets between two layers of the fixing seat 24, and accordingly the thickness of the asphalt paving or the top surface height of the asphalt can be controlled.
[0068] Embodiment 9:
[0069] like Figure 7 As shown, on the basis of the above embodiment, in this embodiment, when the comb plate 9 is used to construct the expansion joint, two comb plates 9 are directly detachably installed on the anchor plate 23, and the waterproof rubber strip 5 is installed between the two comb plates 9. In this embodiment, the detachable connection between the comb plate 9 and the anchor plate 23 is achieved by threaded connection. In this embodiment, the comb plate 9 is a useful technical means for those skilled in the art, and the specific structure and working principle of the comb plate 9 are not described in detail here.
[0070] What has been described above is only a preferred embodiment of the present invention and does not constitute any form of limitation to the present invention. According to the technical essence of the present invention, within the spirit and principles of the present invention, any simple modification, equivalent replacement and improvement made to the above embodiments shall still fall within the protection scope of the technical solution of the present invention.
Claims
1. A construction method for an assembled bridge expansion device, characterized in that: The invention comprises a telescopic device base installed on a beam end structure (1), the telescopic device base is a prefabricated part, the telescopic device base comprises two symmetrically distributed bases (2) with a gap, two isolation plates (3) are arranged on the telescopic device base and are respectively located on both sides of the beam joint and are used to isolate asphalt and are parallel to the length direction of the beam joint, the telescopic device is installed between the two isolation plates (3), the telescopic device comprises two side beams (4) and a waterproof rubber strip (5) installed between the two side beams (4), the side beams (4) The side beam (4) is detachably connected to the isolation plate (3), the side beam (4) comprises a vertical beam (41) and a through groove (42) arranged on one side of the vertical beam (41) and forming an F-shaped through groove (42) with the vertical beam (41), the through grooves (42) of the two side beams (4) are arranged opposite to each other, the waterproof rubber strip (5) is installed in the through groove (42), the side beam (4) is threadedly connected to the isolation plate (3), and a pressure plate (6) is arranged below the through groove (42), so that the screw passes through the pressure plate (6), the vertical beam (41) and then connected to the isolation plate (3) in sequence.
2. The construction method of a prefabricated bridge expansion device according to claim 1, characterized in that: It includes the following steps: Step S1: prefabricate the beam end structure (1); Step S2: With the isolation plate (3) facing upward, the telescopic device base is installed on the beam end structure (1), and a waterproof structure is installed in the gap along the length direction of the gap; Step S3: installing a template between the two isolation boards (3) to fill the space between the two isolation boards (3); Step S4: pouring asphalt on the outer sides of the two isolation plates (3); Step S5: taking out the template; Step S6: Install an expansion device between the two isolation panels (3) to complete the construction of the expansion joint.
3. The construction method of a prefabricated bridge expansion device according to claim 2, characterized in that: After the beam end structure (1) is prefabricated, the beam end structure (1) is installed at the location where the expansion joint is to be constructed in step S1, step S2 or step S3.
4. A construction method for an assembled bridge expansion device according to any one of claims 1, 2 and 3, characterized in that: The telescopic device is made of profiled steel and waterproof rubber strips, so that the profiled steel and the isolation plate (3) are detachably connected.
5. A construction method for an assembled bridge expansion device according to any one of claims 1, 2 and 3, characterized in that: The telescopic device is made of a comb plate (9) and a waterproof rubber strip, so that the comb plate (9) and the isolation plate (3) are detachably connected.
6. An assembled bridge expansion device, characterized in that: The invention comprises a telescopic device base installed on a beam end structure (1) and a telescopic device arranged on the telescopic device base, wherein the telescopic device base is a prefabricated component, the telescopic device base comprises two symmetrically distributed bases (2) with a gap and an isolation plate (3) arranged on the upper surface of the base (2), the length direction of the isolation plate (3) is the same as the length direction of the gap, and the telescopic device is detachably installed between the two isolation plates (3).
7. The assembled bridge expansion device according to claim 6, characterized in that: The base (2) comprises a concrete base (21), an anchor plate (23) arranged in the concrete base (21), and anchor bars (22) arranged in the concrete base (21) and mounted on the anchor plate (23).
8. The assembled bridge expansion device according to claim 6 or 7, characterized in that: The telescopic device comprises two side beams (4) and a waterproof rubber strip (5) installed between the two side beams (4); the side beams (4) are detachably connected to the isolation plate (3).
9. The assembled bridge expansion device according to claim 6 or 7, characterized in that: The telescopic device comprises two comb plates (9) and a waterproof rubber strip (5) arranged between the two comb plates (9); the comb plates (9) correspond to the base (2) one by one and are detachably connected.
10. The assembled bridge expansion device according to claim 9, characterized in that: A U-shaped waterproof structure (7) located below the telescopic device and opening upward is provided between the gaps; hooks opening downward are provided on both sides of the U-shaped waterproof structure (7), and a waterproof support structure (71) for installing the hooks is provided on the base (2).
Citation Information
Patent Citations
Bridge expansion joint device without transition section concrete and mounting method of bridge expansion joint device
CN103741597A
Quickly replaceable bridge expansion joint device and mounting method thereof
CN104018425A
Drainage pavement lining type expansion equipment for bridge, and construction method therefor
JP2004316187A
Precast expansion joints and method of construction for easy maintenance
KR101785624B1
Expansion joint with and construction method
KR1020100011819A