High-speed railway earthquake monitoring, early warning and emergency response demonstration system

Through the high-speed railway earthquake monitoring and early warning and emergency response demonstration system, the wave output device and vibration device are used to simulate earthquake waveforms to vibrate the high-speed railway sand table platform, and the high-speed railway train is controlled through acceleration sensors and high-speed railway earthquake monitoring cabinets, which solves the safety of earthquakes during high-speed railway operation The threat of the company has achieved the effect of reducing accidents and losses in practice.

CN109545061BActive Publication Date: 2025-01-03WUHAN INST OF SEISMOLOGICAL INSTR CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201811624309.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2018-12-28
Publication Date
2025-01-03
Estimated Expiration
2038-12-28

AI Technical Summary

Technical Problem

In the operation of high-speed railways, earthquakes may lead to major safety accidents. It is difficult for existing technology to predict and effectively deal with the impact of earthquakes on high-speed trains in advance, resulting in the threat of the safety of passengers' lives and property.

Method used

A high-speed railway earthquake monitoring, early warning and emergency response demonstration system was designed, including wave output device, vibration device, high-speed railway sand table platform, acceleration sensor and high-speed railway earthquake monitoring cabinet. The high-speed railway sand table platform is vibrated by simulating historical earthquake waveforms and using acceleration signals Carry out early warning and control to achieve rapid braking and safe operation of high-speed trains.

Benefits of technology

The system can simulate the seismic environment when there is no earthquake, conduct simulation experiments, reduce or avoid safety accidents, reduce property losses and passenger life dangers, and improve the safe operation capabilities of high-speed rail in earthquake environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109545061B_ABST
    Figure CN109545061B_ABST
Patent Text Reader

Abstract

The present invention discloses a high-speed rail earthquake monitoring, early warning and emergency disposal demonstration system, including: a wave output device, a vibration device, a high-speed rail sand table platform, an acceleration sensor, and a high-speed rail earthquake monitoring cabinet. Wherein: the wave output device is connected to the vibration device, the vibration device is connected to the high-speed rail sand table platform, the high-speed rail sand table platform is connected to the acceleration sensor, and the acceleration sensor is connected to the high-speed rail earthquake monitoring cabinet. The present invention can simulate the operation of high-speed rail under earthquake conditions, and can perform simulation experiments that are not allowed to actually occur, thereby providing experience accumulation and technical support for the safe operation of high-speed rail under earthquake environments, reducing or avoiding safety accidents in practice, and reducing property losses and passenger life risks.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of high-speed rail earthquake monitoring, early warning and emergency response demonstration system, and is mainly used to simulate real-time earthquake monitoring and early warning of high-speed rail operation, and to control high-speed rail trains according to earthquake monitoring and early warning results. Background Art

[0002] Safety is the foundation of railway transportation. High-speed railways have higher requirements for the driving safety guarantee system due to the high-speed and high-density operation of trains. When countries around the world build high-speed railways, establishing a high-speed railway safety monitoring system is one of the key technologies that must be solved. Among the many natural disasters that endanger the safe operation of high-speed railways, earthquakes are a sudden disaster with a low probability of occurrence but the greatest harm. When the train is running at a low speed, the harm of earthquakes is not very prominent; but because the lateral force between the wheel and the rail is proportional to the square of the train's running speed, when the speed exceeds 200km / h, even a small earthquake may cause a major safety accident such as train derailment or even overturning. In the operation of high-speed railways, if the invasion of earthquake waves can be predicted tens of seconds in advance, an early warning can be issued, and the train can be braked quickly, the safety of passengers' lives and property can be guaranteed to the greatest extent.

[0003] At present, China has begun to carry out a series of explorations and research on earthquake monitoring and early warning for high-speed railways. The testing of high-speed railway earthquake monitoring cabinets organized by the China Academy of Railway Sciences has been carried out in Putian, Chengguan and other places, and corresponding results have been achieved. At present, the high-speed railway earthquake monitoring and early warning system is mainly used in outdoor applications. If there are safety hazards in the actual outdoor operation, it will cause significant losses. In view of this, it is necessary to propose a high-speed railway earthquake monitoring and early warning and emergency response device. This model can simulate the operation of high-speed railways under earthquake conditions, and can conduct simulation experiments that are not allowed to actually occur, thereby providing experience accumulation and technical support for the safe operation of high-speed railways in earthquake environments, reducing or avoiding safety accidents in practice, and reducing property losses and passenger life risks. Summary of the invention

[0004] In view of the above problems, the present invention is proposed to provide a method to overcome the above problems or at least partially solve the above problems.

[0005] The present invention includes the following solutions:

[0006] The high-speed railway earthquake monitoring, early warning and emergency response demonstration system is characterized in that the system includes: a wave output device, a vibration device, a high-speed railway sand table platform, an acceleration sensor, and a high-speed railway earthquake monitoring cabinet; wherein:

[0007] The wave output device is connected to the vibration device, stores historical earthquake waveforms, and outputs at least one of the historical earthquake waveforms to the vibration device;

[0008] The vibration device is connected to the high-speed rail sand table platform, generates vibration according to the historical earthquake waveform, and drives the high-speed rail sand table platform to vibrate;

[0009] The high-speed rail sandbox platform includes a high-speed rail model and a high-speed train model to simulate the actual operation of the high-speed rail;

[0010] The acceleration sensor is installed on the high-speed rail sand table platform to detect the vibration of the high-speed rail sand table platform and generate an acceleration signal;

[0011] One end of the high-speed railway earthquake monitoring cabinet is connected to the acceleration sensor, and the other end is connected to the high-speed railway sand table platform. The high-speed railway earthquake monitoring cabinet outputs a control signal according to the acceleration signal to control the operation of the high-speed train model.

[0012] Further, the wave output device includes a signal generator and a power amplifier;

[0013] The signal generator will obtain at least one historical seismic waveform output;

[0014] The power amplifier amplifies the signal power of the historical earthquake waveform output by the signal generator and outputs it to the vibration device.

[0015] Furthermore, the vibration device is a vibration motor.

[0016] Furthermore, the high-speed rail sandbox platform also includes: a high-speed rail platform model and a map, and the high-speed railway model, high-speed train model, and high-speed platform model are installed on the map to simulate the actual geographical location of the high-speed rail operation.

[0017] Furthermore, the high-speed rail sand table platform also includes: alarm equipment;

[0018] The alarm device is connected to the high-speed railway earthquake monitoring cabinet, receives the control signal output by the high-speed railway earthquake monitoring cabinet, and realizes the alarm function.

[0019] Furthermore, the high-speed railway earthquake monitoring cabinet includes: a high-speed railway earthquake early warning unit, a server, a display, and a control unit.

[0020] in:

[0021] The input end of the high-speed railway earthquake early warning unit is connected to the acceleration sensor, and the output end is connected to the server. The acceleration signal of the acceleration sensor is received through the input end, the acceleration signal is compared with the preset threshold, and the early warning signal is output to the server;

[0022] One end of the server output is connected to a display to transmit the warning signal to the display, and the other end of the output is connected to a control unit. The control unit outputs a control signal according to the warning signal to control the operation of the high-speed train model.

[0023] Furthermore, the high-speed railway earthquake monitoring cabinet includes: a high-speed railway earthquake early warning unit, a server, a display, and a control unit, wherein:

[0024] The input end of the high-speed railway earthquake early warning unit is connected to the acceleration sensor, and the output end is connected to the server. The high-speed railway earthquake early warning unit receives the acceleration signal of the acceleration sensor through the input end, compares the acceleration signal with a preset threshold, and outputs a warning signal to the server;

[0025] One end of the server output is connected to a display to transmit the warning signal to the display, and the other end of the output is connected to a control unit. The control unit outputs a control signal according to the warning signal to control the alarm device and the operation of the high-speed train model.

[0026] Furthermore, the alarm device includes at least one of a sound alarm device and a light alarm device.

[0027] Furthermore, the control unit includes: an operation state control subunit and an acoustic and optical control subunit; wherein:

[0028] The operation control subunit is connected to the high-speed train model to control the operation of the high-speed train model;

[0029] The sound and light control subunit is connected to the alarm device to control the alarm device to sound an alarm.

[0030] The beneficial effects of the above-mentioned technical solution provided by the embodiment of the present invention include at least: the model can simulate the operation of high-speed railways under earthquake conditions, and can conduct simulation experiments that are not allowed to actually occur, and after receiving earthquake waves, it can control the high-speed railway trains, thereby providing experience accumulation and technical support for the safe operation of high-speed railways in earthquake environments, reducing or avoiding safety accidents in practice, and reducing property losses and passenger life risks. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0032] Figure 1 This is a schematic diagram of the structure of a high-speed railway earthquake monitoring, early warning and emergency response demonstration system in Embodiment 1 of the present invention;

[0033] Figure 2 This is a schematic diagram of the structure of the high-speed railway earthquake monitoring, early warning and emergency response demonstration system in the second embodiment of the present invention;

[0034] Figure 3 This is another structural diagram of the high-speed railway earthquake monitoring, early warning and emergency response demonstration system in the second embodiment of the present invention;

[0035] Figure 4This is a schematic diagram of the structure of the high-speed railway earthquake monitoring, early warning and emergency response demonstration system in Example 3 of the present invention. DETAILED DESCRIPTION

[0036] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0037] In order to solve the problems existing in the prior art, the embodiment of the present invention provides a high-speed railway earthquake monitoring, early warning and emergency response demonstration system

[0038] Embodiment 1

[0039] Figure 1 The schematic diagram of the high-speed rail earthquake monitoring, early warning and emergency response demonstration system is shown in FIG. The system includes: a wave output device 1, a vibration device 2, a high-speed rail sand table platform 3, an acceleration sensor 4, and a high-speed rail earthquake monitoring cabinet 5; wherein:

[0040] The wave output device 1 is connected to the vibration device 2. The wave output device 1 stores historical earthquake waveforms in advance and outputs at least one of the historical earthquake waveforms to the vibration device 2. The wave output device 1 stores a large number of historical real earthquake waveforms, and can simulate the situation of an earthquake when no earthquake occurs outdoors.

[0041] The vibration device 2 is connected to the high-speed rail sand table platform 3. The vibration device 2 generates vibration according to the historical earthquake waveform, driving the high-speed rail sand table platform 3 to vibrate. The structure of the vibration device 2 can be designed according to actual conditions, and in this embodiment, a vibration motor is preferably used.

[0042] The high-speed rail sandbox platform 3 includes a high-speed rail model 31 and a high-speed train model 32, which are used to simulate the actual high-speed rail operation; wherein, the high-speed rail train model is installed on the high-speed rail model 31, and a certain voltage is applied between the rails of the high-speed rail model 31 to drive the high-speed train model 32 to operate.

[0043] The acceleration sensor 4 is installed on the high-speed rail sand table platform 3. The acceleration sensor 4 vibrates with the vibration of the high-speed rail sand table platform 3 to generate an acceleration signal. In some embodiments, the acceleration sensor adopts the CT1500L type with a sensitivity of 5V / G. The sensor is suitable for ultra-low frequency vibration measurement, has high resolution, and is suitable for large structures, bridges, high-rise buildings, etc. Its output is a 4-20mA current signal, which is output as a signal after the I / V change.

[0044] One end of the high-speed rail earthquake monitoring cabinet 5 is connected to the acceleration sensor 4, and the other end is connected to the high-speed rail sand table platform 3. The high-speed rail earthquake monitoring cabinet 5 receives the acceleration signal, processes and analyzes it, and outputs a control signal to control the operation of the high-speed train model 32. Among them, the high-speed rail earthquake monitoring cabinet 5 determines the earthquake warning level according to the preset acceleration signal threshold and outputs a control signal. When the acceleration signal value is less than the threshold, the train runs normally. When the acceleration signal value exceeds the threshold, the train is controlled to slow down or stop.

[0045] The high-speed rail earthquake monitoring, early warning and emergency response demonstration system of the present invention has a simple structure, is easy to use, and can simulate the operation of high-speed rail under earthquake conditions without the actual occurrence of an earthquake. After receiving the earthquake wave, the acceleration signal generated by the acceleration sensor 4 can be used to judge the intensity of the earthquake, and the hazard of the earthquake to the high-speed rail can be judged based on the intensity. The operation of the high-speed rail is controlled according to the magnitude of the hazard, providing experience accumulation and technical support for the safe operation of the high-speed rail in an earthquake environment in actual situations, which can reduce or avoid safety accidents in actual applications, reduce property losses and passenger life risks. For example, as shown in Table 1, the acceleration signals corresponding to various earthquake waves and the control of the train are made into corresponding tables to provide technical references for future high-speed rail operations.

[0046] seismic waveform Acceleration Control Operation A1 B1 Keep driving A2 B2 slow down A3 B3 stop …… …… ……

[0047] Table 1

[0048] In some cases, when an earthquake really occurs, if the real earthquake waveform can be detected in time and accurately, the waveform can be matched with the historical earthquake waveform pre-stored in the wave output device 1. If the match is successful, the situation in Table 1 can be directly used to judge the impact of the earthquake on the high-speed rail, so as to take appropriate control methods for the high-speed rail. Compared with the prior art, the early warning analysis time for the arrival of an earthquake is reduced. If an early warning can be given, the loss of property and the danger to the lives of passengers can be greatly reduced. It can be understood that the system of the present invention can also be applied to rail transportation such as subways and trains.

[0049] Embodiment 2

[0050] Figure 2 This is a system structure diagram of Example 2, the system includes: a wave output device 1, a vibration device 2, a high-speed rail sand table platform 3, an acceleration sensor 4, and a high-speed rail earthquake monitoring cabinet 5; wherein, the wave output device 1 includes: a signal generator 11 and a power amplifier 12.

[0051] The output end of the wave output device 1 is connected to the vibration device 2. The wave output device 1 generates a seismic waveform and transmits the seismic waveform to the vibration device 2. The wave output device 1 is used to simulate seismic waves in actual situations, which solves the problem that actual seismic waves are not allowed to occur during outdoor operation. In this embodiment, the wave output device 1 is composed of a signal generator and a power amplifier. The input end of the power amplifier is connected to the signal generator, and the output end is connected to the vibration device 2. The process of the wave output device 1 generating a seismic waveform and driving the vibration device 2 is as follows: the signal generator 11 downloads and stores the waveform of the required historical earthquake according to actual needs, and transmits it to the power amplifier 12. The power amplifier 12 amplifies the signal power of the seismic waveform and drives the vibration device 2 to vibrate.

[0052] The vibration device 2 is connected to the high-speed rail sand table platform 3. The vibration device 2 generates vibration according to the historical earthquake waveform, driving the high-speed rail sand table platform 3 to vibrate. In some embodiments, the vibration device 2 can be a vibration motor.

[0053] The high-speed rail sandbox platform 3 includes: a high-speed rail model 31 and a high-speed train model 32, which are used to simulate the actual high-speed rail operation; wherein, a certain voltage is applied between the rails of the high-speed rail model 31 to drive the high-speed train model 32 to operate.

[0054] In some embodiments, Figure 3 The high-speed rail sand table platform 3 also includes: a high-speed rail platform model 33, a map 34 and an alarm device 35. Among them, the high-speed rail platform model 33 is installed on both sides of the high-speed rail model 31, and the high-speed rail model 31, the high-speed train model 32, and the high-speed rail platform model 33 are installed on the map 34 to display the geographical location of the high-speed rail train model. The acceleration sensor 4 is installed at the bottom of the high-speed rail sand table platform 3. The acceleration sensor 4 generates an acceleration signal according to the vibration of the vibration device 2, and transmits the acceleration signal to the high-speed rail earthquake monitoring cabinet 5. The sound and light alarm is installed on the high-speed train model 32 to receive the control signal input by the high-speed rail earthquake monitoring cabinet 5.

[0055] The acceleration sensor 4 is installed on the high-speed rail sand table platform 3. The acceleration sensor 4 vibrates with the vibration of the high-speed rail sand table platform 3 to generate an acceleration signal. In some embodiments, the acceleration sensor adopts the CT1500L type with a sensitivity of 5V / G. The sensor is suitable for ultra-low frequency vibration measurement, has high resolution, and is suitable for large structures, bridges, high-rise buildings, etc. Its output is a 4-20mA current signal, which is output as a signal after the I / V change.

[0056] One end of the high-speed rail earthquake monitoring cabinet 5 is connected to the acceleration sensor 4, and the other end is connected to the high-speed rail sand table platform 3. The high-speed rail earthquake monitoring cabinet 5 receives the acceleration signal, processes and analyzes it, and outputs a control signal to control the operation of the high-speed train model 32. Among them, the high-speed rail earthquake monitoring cabinet 5 determines the earthquake warning level according to the preset acceleration signal threshold and outputs a control signal. When the acceleration signal value is less than the threshold, the train runs normally. When the acceleration signal value exceeds the threshold, the train is controlled to decelerate.

[0057] In this embodiment, not only the operation of high-speed rail in the case of simulated earthquake is guaranteed, but also simulation experiments that are not allowed to actually occur can be carried out, thereby providing experience accumulation and technical support for the safe operation of high-speed rail in earthquake environment, reducing or avoiding safety accidents in practice, reducing property losses and passenger life dangers. The wave output device 1 also downloads and outputs historical earthquake waveforms according to actual needs, and the high-speed rail sand table platform 3 can also better simulate the actual outdoor high-speed rail operation environment to ensure the accuracy of the device.

[0058] Embodiment 3

[0059] Figure 4 This is a system structure diagram of the third embodiment, the system includes: a wave output device 1, a vibration device 2, a high-speed rail sand table platform 3, an acceleration sensor 4, and a high-speed rail earthquake monitoring cabinet 5; wherein the wave output device 1 includes: a signal generator 11 and a power amplifier 12. The high-speed rail earthquake monitoring cabinet 5 includes: a power box 51, a high-speed rail earthquake early warning unit 52, a server 53, a display 54, and a control unit 55.

[0060] The output end of the wave output device 1 is connected to the vibration device 2, and the wave output device 1 generates a seismic waveform and transmits the seismic waveform to the vibration device 2; the wave output device 1 is used to simulate seismic waves in actual situations, which solves the problem that actual seismic waves are not allowed to occur during outdoor operation. In this embodiment, the wave output device 1 is composed of a signal generator 11 and a power amplifier 12, the input end of the power amplifier 12 is connected to the signal generator, and the output end is connected to the vibration device 2. The process of the wave output device 1 generating a seismic waveform and driving the vibration device 2 is as follows: the signal generator 11 downloads and stores the waveform of the required historical earthquake according to actual needs, and transmits it to the power amplifier 12, the power amplifier 12 amplifies the signal power of the seismic waveform, and drives the vibration device 2 to vibrate.

[0061] The vibration device 2 is connected to the high-speed rail sand table platform 3. The vibration device 2 generates vibration according to the historical earthquake waveform, driving the high-speed rail sand table platform 3 to vibrate. In some embodiments, the vibration device 2 can be a vibration motor.

[0062] The high-speed rail sandbox platform 3 includes: a high-speed rail model 31 and a high-speed train model 32, which are used to simulate the actual high-speed rail operation; wherein, a certain voltage is applied between the rails of the high-speed rail model 31 to drive the high-speed train model 32 to run on the rails of the high-speed rail model 31.

[0063] The acceleration sensor 4 is installed on the high-speed rail sand table platform 3. The acceleration sensor 4 vibrates with the vibration of the high-speed rail sand table platform 3 to generate an acceleration signal. In some embodiments, the acceleration sensor adopts the CT1500L type with a sensitivity of 5V / G. The sensor is suitable for ultra-low frequency vibration measurement, has high resolution, and is suitable for large structures, bridges, high-rise buildings, etc. Its output is a 4-20mA current signal, which is output as a signal after the I / V change.

[0064] One end of the high-speed rail earthquake monitoring cabinet 5 is connected to the acceleration sensor 4, and the other end is connected to the high-speed rail sand table platform 3. The high-speed rail earthquake monitoring cabinet 5 receives the acceleration signal, processes and analyzes it, and outputs a control signal to control the operation of the high-speed train model 32. In this embodiment, the high-speed railway earthquake monitoring cabinet 5 includes: a power box 51, a high-speed railway earthquake early warning unit 52, a server 53, a display 54, and a control unit 55. The power box 51 supplies power to the high-speed railway earthquake monitoring cabinet 5. The input end of the high-speed railway earthquake early warning unit 52 is connected to the acceleration sensor 4, and the output end is connected to the server. The output signal of the acceleration sensor 4 is received through the input end, compared with the preset threshold value, and different early warning signals are output, and the early warning signal is transmitted to the server through the output end; the specific process can be to pre-set the output threshold values ​​A and B of the acceleration sensor 4, wherein A is less than B, and when the output signal of the acceleration sensor 4 is less than the preset threshold value A, the early warning signal is in normal mode; when the output signal of the acceleration sensor 4 is greater than the preset threshold value A and less than the threshold value B, the early warning signal is in weak earthquake mode; when the output signal of the acceleration sensor 4 is greater than the preset threshold value B, the early warning signal is in strong earthquake mode;

[0065] One end of the output end of the server 53 is connected to the display 54, and the warning signal is transmitted to the display 54 to display the earthquake warning information. The other end of the output end is connected to the control unit 55, and the high-speed railway model 31 is controlled to run by the control unit 55. In some embodiments, the high-speed railway sand table platform 3 also includes an alarm device 35, and the alarm device 35 can be a sound alarm device and a light alarm device. The control unit 55 includes: an operation state control subunit, a sound and light control subunit; wherein: the operation control subunit is connected to the high-speed train model 32 to control the operation of the high-speed train model 32; the sound and light control subunit is connected to the alarm device 35 to control the alarm device 35 to alarm.

[0066] The specific process may be: when the server receives the warning signal normally, the operation status control subunit outputs the operation status unchanged control signal to the high-speed train model 32, the high-speed train model 32 operates normally, the sound and light control subunit controls the light alarm device to light up the green light, and the sound and light control subunit controls the sound alarm device to be in the off state.

[0067] When the server receives a warning signal indicating a weak earthquake, the operation state control subunit outputs a control signal to the high-speed train model 32, the high-speed train model 32 decelerates, the sound and light control subunit controls the light alarm device to light up the yellow light, and the sound and light control subunit controls the sound alarm device to start. When the earthquake alarm is lifted, the sound and light alarm is lifted through manual operation, and the entire system returns to normal operation.

[0068] When the server receives the early warning signal of a strong earthquake, the operation state control subunit outputs a control signal to the high-speed train model 32, the high-speed train model 32 stops running, the sound and light control subunit controls the light alarm device to light up the red light, and the sound and light control subunit controls the sound alarm device to start. When the earthquake alarm is lifted, the sound and light alarm is lifted through manual operation, and the entire system returns to normal operation.

[0069] In this embodiment, not only the operation of high-speed rail in the case of simulated earthquake is guaranteed, but also simulation experiments that are not allowed to actually occur can be carried out, thereby providing experience accumulation and technical support for the safe operation of high-speed rail in earthquake environment, reducing or avoiding safety accidents in practice, reducing property losses and passenger life risks. The high-speed rail earthquake control cabinet can also make a variety of control instructions to the high-speed rail EMU model according to the different levels of simulated seismic waves, and realize a variety of control methods for the EMU high-speed rail model.

[0070] It should be understood that the specific order or hierarchy of steps in the disclosed process is an example of an exemplary method. Based on design preferences, it should be understood that the specific order or hierarchy of steps in the process can be rearranged without departing from the scope of protection of the present disclosure. The attached method claims present the elements of the various steps in an exemplary order and are not intended to be limited to the specific order or hierarchy described.

[0071] In the above detailed description, various features are grouped together in a single embodiment to simplify the disclosure. This method of disclosure should not be interpreted as reflecting an intention that the embodiments of the claimed subject matter require more features than are clearly stated in each claim. On the contrary, as reflected in the appended claims, the invention is in a state of having less than all the features of the disclosed individual embodiments. Therefore, the appended claims are hereby expressly incorporated into the detailed description, with each claim standing on its own as a separate preferred embodiment of the invention.

[0072] The above description includes examples of one or more embodiments. Of course, it is impossible to describe all possible combinations of components or methods for the purpose of describing the above embodiments, but it should be recognized by those skilled in the art that the various embodiments may be further combined and arranged. Therefore, the embodiments described herein are intended to cover all such changes, modifications and variations that fall within the scope of protection of the appended claims. In addition, with respect to the term "comprising" used in the specification or claims, the word is covered in a manner similar to the term "including", just as "including," is explained as a transitional word in the claims. In addition, any term "or" used in the specification of the claims is intended to mean "non-exclusive or".

Claims

1. High-speed railway earthquake monitoring, early warning and emergency response demonstration system, characterized by: The system includes: a wave output device, a vibration device, a high-speed rail sand table platform, an acceleration sensor, and a high-speed rail earthquake monitoring cabinet; wherein: The wave output device is connected to the vibration device, stores historical earthquake waveforms, and outputs at least one of the historical earthquake waveforms to the vibration device; The vibration device is connected to the high-speed rail sand table platform, generates vibration according to the historical earthquake waveform, and drives the high-speed rail sand table platform to vibrate; The high-speed rail sandbox platform includes a high-speed rail model and a high-speed train model to simulate the actual operation of the high-speed rail; The acceleration sensor is installed on the high-speed rail sand table platform to detect the vibration of the high-speed rail sand table platform and generate an acceleration signal; One end of the high-speed railway earthquake monitoring cabinet is connected to the acceleration sensor, and the other end is connected to the high-speed railway sand table platform. The high-speed railway earthquake monitoring cabinet outputs a control signal according to the acceleration signal to control the operation of the high-speed train model. When an earthquake really occurs, the real earthquake waveform is matched with the historical earthquake waveform pre-stored in the wave output device. If the match is successful, the corresponding control method is determined by using the acceleration signals corresponding to various earthquake waves and the control signal of the high-speed train model.

2. The system according to claim 1, characterized in that: The wave output device includes a signal generator and a power amplifier; The signal generator outputs at least one acquired historical seismic waveform; The power amplifier amplifies the signal power of the historical earthquake waveform output by the signal generator and outputs it to the vibration device.

3. The system according to claim 1, characterized in that: The vibration device is a vibration motor.

4. The system according to claim 1, characterized in that: The high-speed rail sandbox platform also includes: a high-speed rail platform model and a map. The high-speed railway model, high-speed train model, and high-speed platform model are installed on the map to simulate the actual geographical location of the high-speed rail operation.

5. The system according to claim 1, characterized in that: The high-speed rail sand table platform also includes: an alarm device; the alarm device is connected to the high-speed rail earthquake monitoring cabinet, receives a control signal output by the high-speed rail earthquake monitoring cabinet, and realizes an alarm function.

6. The system according to claim 1, characterized in that: The high-speed rail earthquake monitoring cabinet includes: a high-speed rail earthquake early warning unit, a server, a display, and a control unit, among which: The input end of the high-speed railway earthquake early warning unit is connected to the acceleration sensor, and the output end is connected to the server. The acceleration signal of the acceleration sensor is received through the input end, the acceleration signal is compared with the preset threshold, and the early warning signal is output to the server; One end of the server output is connected to a display to transmit the warning signal to the display, and the other end of the output is connected to a control unit. The control unit outputs a control signal according to the warning signal to control the operation of the high-speed train model.

7. The system according to claim 5, characterized in that: The high-speed rail earthquake monitoring cabinet includes: a high-speed rail earthquake early warning unit, a server, a display, and a control unit, among which: The input end of the high-speed railway earthquake early warning unit is connected to the acceleration sensor, and the output end is connected to the server. The high-speed railway earthquake early warning unit receives the acceleration signal of the acceleration sensor through the input end, compares the acceleration signal with a preset threshold, and outputs a warning signal to the server; One end of the server output is connected to a display to transmit the warning signal to the display, and the other end of the output is connected to a control unit. The control unit outputs a control signal according to the warning signal to control the alarm device and the operation of the high-speed train model.

8. The system according to claim 1, characterized in that: The alarm device includes at least one of a sound alarm device and a light alarm device.

9. The system according to claim 6, characterized in that: The control unit includes: an operation state control subunit and an acoustic and optical control subunit; wherein: The operation control subunit is connected to the high-speed train model to control the operation of the high-speed train model; The sound and light control subunit is connected to the alarm device to control the alarm device to sound an alarm.