A main plant column structure and installation construction method thereof

By designing a multi-section column structure and a column base cup method of pouring concrete in two times, the problem of insufficient stability and strength during the installation process of the steel structure factory building columns was solved, and high-quality installation and construction safety of the columns were achieved.

CN110130577BActive Publication Date: 2024-10-18CHINA THIRD METALLURGICAL GRP
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN201910498980.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-06-11
Publication Date
2024-10-18
Estimated Expiration
2039-06-11

AI Technical Summary

Technical Problem

The column structure of the existing steel structure factory building has problems of insufficient stability and strength during the installation process, and the installation quality is difficult to guarantee, especially the challenges caused by the differences in different factory building structures and foundation masonry methods.

Method used

By designing a main factory column structure, a structure composed of double column sections, box column sections and high-ceiling column sections is adopted, and a column base cup is poured with concrete in two times, combined with crane beam supports and cable wind ropes. The temporary fixing method ensures the verticality and strength of the column, adjusts the thickness of the pad to match the column length and foundation elevation, and performs precise positioning and marking to achieve stable installation.

Benefits of technology

It achieves the symmetry and overall strength of the column structure, reduces post-weld deformation, ensures a firm combination of the column and the foundation, improves the elevation and verticality after installation, facilitates subsequent installation of crane beams and roofs, and ensures the safety of the construction project. Safe for long term use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110130577B_ABST
    Figure CN110130577B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of steel structure building installation, and in particular to a main plant column structure and its installation and construction method, which is characterized in that a double column section, a box column section and a raised column section are sequentially arranged from bottom to top, and its specific structure is as follows: the double column section is composed of parallel steel columns and truss reinforcement bodies, the parallel steel columns are formed by two H-shaped steels arranged relatively parallel, and a footing sealing plate is provided at the bottom; the truss reinforcement body is two rows of multiple groups of cross trusses, and the two rows of cross trusses and two H-shaped steels are welded together by a tie plate to form a frame structure; the box column section is a box-shaped structure composed of two H-shaped steels and two side sealing plates; the raised column section is formed by two buckled channel steels welded together. Compared with the prior art, the beneficial effects of the present invention are: good overall strength, can well reduce post-welding deformation during the manufacturing process, the double column section is firmly combined with the column bottom foundation, and meets the overall stability and mechanical properties of the main plant steel structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of steel structure building installation, and in particular to a main plant column structure and an installation construction method thereof. Background Art

[0002] Steel structure workshop mainly refers to the main load-bearing components are made of steel, including steel columns, steel beams, steel structure foundation, steel roof truss and steel roof, etc. The walls of the steel structure can also be maintained by brick walls. Due to the increase in steel production in my country, steel structure workshops have been popularized and applied, which are specifically divided into light steel structure workshops and heavy steel structure workshops. Industrial and civil building facilities built with steel are collectively referred to as steel structures.

[0003] The characteristics of steel structure workshops are: light weight, high strength, good overall rigidity and strong deformation capacity. The building's self-weight is only one-fifth of that of a brick-concrete structure, and it can withstand a hurricane of 70 meters per second. The light steel structure residential structure is entirely composed of cold-bent thin-walled steel component systems, and the steel skeleton is made of super anti-corrosion high-strength cold-rolled galvanized sheet, which effectively avoids the influence of rust on the steel plate during construction and use, and increases the service life of light steel components. The thermal insulation material used is mainly glass fiber wool, which is used for the insulation board of the exterior wall. The thermal resistance value of R15 insulation wool with a thickness of about 100mm is equivalent to that of a 1m thick brick wall. Sound insulation effect is an important indicator for evaluating residential buildings. The windows installed in the light steel system are all hollow glass, and the wall composed of light steel keel and insulation material gypsum board has a sound insulation effect of up to 60 decibels. Dry operation construction effectively reduces the pollution caused by waste to the environment, and the steel structure materials of the house can be 100% recycled, which is in line with the current environmental awareness. The light steel wall adopts an efficient energy-saving system, which can adjust the indoor air dryness and humidity and achieve an energy-saving standard of 50%; the roof has a ventilation function, which can form a flowing air space above the inside of the house to ensure the ventilation and heat dissipation needs inside the roof. For a building of about 300 square meters, only 5 workers need 30 working days to complete the entire process from foundation to decoration.

[0004] The invention patent with Chinese patent application number 201711219531.X discloses a beam-column structure of a steel structure factory building, including a device body, a steel column is arranged on the right side of the device body, and the steel column is fixedly connected to the device body, a crossbeam is arranged on the left side of the steel column, and the crossbeam is fixedly connected to the steel column, a bolt hole is arranged on the right side of the crossbeam, and the bolt hole is embedded in the crossbeam, a crossbeam assembly is arranged on the right side of the device body, and the crossbeam assembly is fixedly connected to the device body. The beam-column structure of the steel structure factory building has a simple connection method and is easy to build, which ensures that the supporting beam will not tilt or loosen, and effectively plays a role in protecting the stability of the device.

[0005] The main factory building columns play the role of skeleton foundation in the entire steel structure, requiring higher structural strength and higher installation quality. Different factory building structures have different structures and different masonry methods for column base structures. Summary of the invention

[0006] The purpose of the present invention is to provide a main plant column structure and an installation and construction method thereof, which overcomes the shortcomings of the prior art, designs the column structure according to the overall stress conditions of the plant, calculates the area of ​​the pad according to the weight of the column and the bearing strength of the foundation concrete, and based on the actual length of the column and the corresponding design elevation of the top surface of the column base cup, considers the installation requirements of the crane beam and the roof, clearly marks the column, and pours concrete in the column base cup in two times to ensure the installation and construction requirements of the main plant column structure.

[0007] To achieve the above object, the present invention is implemented through the following technical solutions:

[0008] One of the technical solutions: a main factory building column structure, characterized in that a double column section, a box column section and a raised column section are arranged in sequence from bottom to top, and its specific structure is: the double column section consists of parallel steel columns and truss reinforcements, the parallel steel columns are formed by two H-shaped steels arranged in parallel with each other, and a base plate is provided at the bottom; the truss reinforcement is two rows of multiple groups of cross trusses, and the two rows of cross trusses and the two H-shaped steels are welded together by tie plates to form a frame structure; the box column section is a box-shaped structure composed of two H-shaped steels and two side sealing plates, and a crane beam support formed by a horizontal support plate and a plurality of vertical rib plates is provided on the side of an H-shaped steel; the raised column section is formed by two interlocking channel steels welded together, and a channel steel section for connecting the roof truss is welded at the top.

[0009] A row of the cross-shaped trusses is sequentially arranged in 2 to 3 groups along the length direction of the H-shaped steel.

[0010] Two adjacent groups of cross-shaped trusses are separated by angle steel cross braces, and both ends of the angle steel cross braces are respectively connected to H-shaped steels.

[0011] The cross truss is made of 50×4 or 80×6 equilateral angle steels welded vertically, and reinforcement plates are provided at the intersections of the angle steels.

[0012] The 500-800mm range at the bottom of the double column section is the column base installation part.

[0013] A lifting hole is provided on the horizontal support plate on the crane beam support.

[0014] The vertical rib plates on the crane beam support are connected by pin shafts.

[0015] Technical Solution 2: A method for installing and constructing the main plant column structure, characterized in that the specific operation steps are as follows:

[0016] 1) Basic data collection and processing. Before installation, construction personnel should re-measure the main plant column foundation measurement data provided by the civil engineering department, and accept it after it is qualified. They should also calibrate the main plant column baseline to disperse the measurement error and eliminate the cumulative error;

[0017] 2) Align the column base to ensure that the elevation of the column base surface is at least 50mm lower than the design elevation of the footing cover plate. Check whether the shape of the column base cup is qualified. At the same time, mark the vertical and horizontal center lines on the column base to facilitate the subsequent alignment installation and alignment of the column.

[0018] 3) Design and install the pad. According to the weight of the column and the bearing strength of the column bottom foundation, calculate the area of ​​the pad and determine the geometric dimensions of the pad. The pad should be exposed 10 to 30 mm from the edge of the footing plate. Prepare the pad;

[0019] 4) Adjust the thickness of the pad. Before installing the column, measure the actual length of each column and the design elevation of the bottom and top surfaces of the corresponding column base cup in advance, and adjust the thickness of the pad according to the difference between the two. Each group of pads should not exceed 5 pieces. The pads should be padded before installation, and the contact between the pads and the base surface of the column should be flat and tight.

[0020] 5) Column measurement and positioning marking: Measure the lateral bending and twisting values ​​of the column before installation. Consider the installation requirements of the crane beam and roof, and mark the positioning points, axis lines, and elevation control lines on the column for installation positioning and review;

[0021] 6) The column is in place, erected into the base cup at the bottom of the column, and temporarily fixed with a cable wind rope and chain crane. The elevation and verticality are adjusted using a level and theodolite. The axis position of the column is adjusted with a steel wedge to make it coincide with the positioning axis of the base at the bottom of the column. After all adjustments are completed and meet the quality standards, tighten the cable wind rope and drive in the bottom wedge for temporary fixation;

[0022] 7) Concrete pouring column base cup, pouring concrete in two times, the first pouring depth should be 200 ~ 300mm lower than the upper edge of the cup. After the concrete strength reaches 70% of the design strength, remove the steel wedge and pour the remaining concrete to complete the installation of the column.

[0023] In the step 6), the column is hoisted by a hoist, which is a steel wire rope. One end of the steel wire rope is connected to a hoisting hole or a pin on a crane beam support, and the other end is connected to the top of the elevated column section, so that the column is kept vertical under the traction of the crane.

[0024] Compared with the prior art, the beneficial effects of the present invention are: 1) The column structure is symmetrical and has good overall strength, which can well reduce the post-welding deformation during the manufacturing process. The double column section is firmly combined with the column base, which meets the overall stability and mechanical properties of the main plant steel structure. 2) During the installation and construction, the multiple degrees of freedom of the column are fully considered, and the deformation of the column itself and the deformation that occurs at any time during the installation are corrected, so that the installed column can achieve the ideal elevation and verticality, which is convenient for the subsequent installation of crane beams and roofs, and finally lays the foundation for the long-term safe use of the construction project. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a structural schematic diagram of an embodiment of a main plant column structure of the present invention.

[0026] Figure 2 yes Figure 1 Section view along line AA.

[0027] Figure 3 yes Figure 1 Sectional view along line BB.

[0028] Figure 4 yes Figure 1 Partial axle-side diagram of the center crane beam support.

[0029] Figure 5 It is a schematic diagram of column positioning of the present invention.

[0030] Figure 6 It is a schematic diagram of temporary fixing of the column of the present invention.

[0031] In the figure: 1-double column section, 2-box column section, 3-high column section, 4-cabling wind rope, 5-chain hoist, 6-column, 7-column bottom foundation surface, 8-column base cup, 9-shim, 10-steel wedge, 11-parallel steel column, 12-truss reinforcement body, 21-crane beam support, 101-H-shaped steel, 102-bottom foot cover plate, 103-column base installation part, 121-cross truss, 122-stitching plate, 123-angle steel cross brace, 124-reinforcement plate, 201-side cover plate, 202-horizontal support plate, 203-vertical rib plate, 204-hanging hole, 205-pin shaft, 301-channel steel, 302-channel steel section. DETAILED DESCRIPTION

[0032] The preparation method of the present invention is further described below in conjunction with embodiments:

[0033] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0034] See Figure 1-Figure 4 , is a schematic diagram of the structure of an embodiment of the main plant column structure of the present invention, wherein a double column section 1, a box column section 2 and a raised column section 3 are sequentially arranged from bottom to top, and its specific structure is as follows: the double column section 1 comprises parallel steel columns 11 and a truss reinforcement body 12, the parallel steel columns are formed by two H-shaped steels 101 arranged relatively parallel, a footing sealing plate 102 is provided at the bottom, and the bottom 500~800mm range of the double column section is the column base installation part 103.

[0035] The truss reinforcement body is composed of two rows of multiple groups of cross trusses. The two rows of cross trusses 121 and two H-shaped steels are welded together by a gusset plate 122 to form a frame structure. Three groups of cross trusses 121 are arranged in sequence along the length direction of the H-shaped steel. Two adjacent groups of cross trusses 121 are separated by angle steel cross braces 123, and the two ends of the angle steel cross braces 123 are respectively welded to the H-shaped steel 101. The cross trusses 121 are made of 80×6 equilateral angle steels welded vertically, and reinforcement plates 124 are provided at the intersection of the angle steels.

[0036] The box column section 2 is a box structure composed of two H-shaped steels 101 and two side sealing plates 201. The crane beam installation side of one H-shaped steel is provided with a crane beam support 21 formed by a horizontal support plate 202 and a plurality of vertical rib plates 203. The horizontal support plate on the crane beam support is provided with a hanging hole 204. The vertical rib plates 203 on the crane beam support are connected by a pin shaft 205.

[0037] The elevated column section 3 is formed by welding two interlocking channel steels 301, and a channel steel section 302 for connecting the roof truss is welded on the top thereof. The specification and size of the channel steel section 302 are selected according to the weight of the roof.

[0038] The specific operation steps of the installation construction method of a main plant column structure according to an embodiment of the present invention are as follows:

[0039] 1) Basic data collection and processing. Before installation, the column foundation measurement data of each installation area should be handed over by the civil engineering company to the project management department of the structural installation company at one time. The management department will organize relevant personnel to re-measure the foundation, and accept it after it is qualified. It will also calibrate the column foundation row and column baseline of the main plant, average out the measurement errors, and eliminate the cumulative errors.

[0040] 2) Align the column base to ensure that the elevation of the column base surface 7 is at least 50mm lower than the design elevation of the base cover 102. Check whether the column base cup 8 is qualified and repair it if necessary. At the same time, mark the vertical and horizontal center lines on the column base to facilitate subsequent alignment and alignment of the column.

[0041] 3) Design and install pads. Calculate the area of ​​pads 9 according to the weight of column 6 and the bearing strength of the column base. Determine the geometric dimensions of the pads. The edge of pads 9 should be exposed 10 to 30 mm from the edge of the footing plate 102. Prepare 1 to 2 sets of pads.

[0042] 4) Adjustment of pad thickness: Before installing the column 6, measure the actual length of each column and the corresponding design elevation of the column bottom foundation surface and the top surface, and adjust the thickness of the pad 9 according to the difference between the two. Each group of pads should not be stacked more than 5 layers. To avoid slippage, a group of pads can be spot welded. Pad the pad 9 before installation. The pad 9 should be able to contact the column bottom foundation surface 7 smoothly and tightly.

[0043] 5) Column measurement and positioning marking: Measure the lateral bending and twisting values ​​of column 6 before installation. Consider the installation requirements of the crane beam and roof, mark the relevant installation positioning points, axis lines, and elevation control lines on the column, and correct deformation if necessary to prepare for positioning and review during the installation process.

[0044] 6) The column is in place, see Figure 5 , Figure 6 , use a crane to erect the column base installation part 103 into the column base cup 8, use the cable wind rope 4 and chain crane 5 for temporary fixation, use a level and theodolite to adjust the elevation and verticality, use the steel wedge 10 to adjust the axis position of the column 6 so that it coincides with the positioning axis of the column bottom foundation. After all adjustments are completed and meet the quality standards, tighten the cable wind rope 4 and drive the steel wedge 10 between the column and the column base cup 8 for temporary fixation; after the column 6 is aligned, install the inter-column support while ensuring the verticality of the column, and the support must not be bent.

[0045] If a crane is not used for lifting, protective shims or wooden blocks must be placed at the contact point between the column and the wire rope during the lifting process to avoid local deformation of the steel column or damage to the wire rope after the lifting force.

[0046] 7) Concrete pouring column base cup, pouring concrete in two times, the first pouring depth should be 200-300mm lower than the upper edge of the cup mouth, after the concrete strength reaches 70% of the design strength, take out the steel wedge 10 and pour the remaining concrete, and the installation of the column is completed. On this basis, the subsequent installation of the crane beam and the roof can be carried out.

[0047] The embodiments described above are only specific examples selected to illustrate the purpose, technical solutions and beneficial effects of the present invention in detail, but should not limit the scope of protection of the invention. All modifications, equivalent substitutions and improvements made without violating the spirit and principles of the present invention should fall within the scope of protection of the present invention.

Claims

1. A main plant column structure, characterized in that: From bottom to top, there are double column sections, box column sections and elevated column sections, and their specific structures are as follows: The double column section includes parallel steel columns and truss reinforcement bodies. The parallel steel columns are formed by two H-shaped steels arranged in parallel with each other, and a foot sealing plate is provided at the bottom. The truss reinforcement body is composed of two rows of multiple groups of cross trusses. The two rows of cross trusses and the two H-shaped steels are welded together by a tie plate to form a frame structure. Two to three groups of cross trusses are arranged in sequence along the length direction of the H-shaped steel in one row. Two adjacent groups of cross trusses are separated by angle steel cross braces. The two ends of the angle steel cross braces are respectively connected to the H-shaped steel. The cross trusses are made of 50×4 or 80×6 equilateral angle steels vertically welded, and reinforcement plates are provided at the intersections of the angle steels. The box-shaped column section is a box-shaped structure composed of two H-shaped steels and two side sealing plates, and the side of one H-shaped steel is provided with a crane beam support formed by a horizontal support plate and a plurality of vertical rib plates; The elevated column section is formed by welding two interlocking channel steels, and a channel steel section for connecting the roof truss is welded on the top of the column section.

2. A main plant column structure according to claim 1, characterized in that: The 500-800mm range at the bottom of the double column section is the column base installation part.

3. A main plant column structure according to claim 1, characterized in that: A lifting hole is provided on the horizontal support plate on the crane beam support.

4. A main plant column structure according to claim 1, characterized in that: The vertical rib plates on the crane beam support are connected by pin shafts.

5. The installation construction method of the structure according to claim 1, characterized in that: The specific steps are as follows: 1) Basic data collection and processing. Before installation, construction personnel should re-measure the main plant column foundation measurement data provided by the civil engineering department, and accept it after it is qualified. They should also calibrate the main plant column baseline to disperse the measurement error and eliminate the cumulative error; 2) Align the column base to ensure that the elevation of the column base surface is at least 50mm lower than the design elevation of the footing cover plate. Check whether the shape of the column base cup is qualified. At the same time, mark the vertical and horizontal center lines on the column base to facilitate the subsequent alignment installation and alignment of the column. 3) Design and install the pad. According to the weight of the column and the bearing strength of the column bottom foundation, calculate the area of ​​the pad and determine the geometric dimensions of the pad. The pad should be exposed 10 to 30 mm from the edge of the footing plate. Prepare the pad; 4) Adjust the thickness of the pad. Before installing the column, measure the actual length of each column and the design elevation of the bottom and top surfaces of the corresponding column base cup in advance, and adjust the thickness of the pad according to the difference between the two. Each group of pads should not exceed 5 pieces. The pads should be padded before installation, and the contact between the pads and the base surface of the column should be flat and tight. 5) Column measurement and positioning marking: Measure the lateral bending and twisting values ​​of the column before installation. Consider the installation requirements of the crane beam and roof, and mark the positioning points, axis lines, and elevation control lines on the column for installation positioning and review; 6) Put the column in place, erect it into the column base cup, temporarily fix it with cable wind rope and chain crane, use level and theodolite to adjust the elevation and verticality, use steel wedge to adjust the axis position of the column to make it coincide with the positioning axis of the column bottom foundation, and after all adjustments are completed and meet the quality standards, tighten the cable wind rope and drive the bottom wedge to temporarily fix it; 7) Concrete pouring column base cup, pouring concrete in two times, the first pouring depth should be 200 ~ 300mm lower than the upper edge of the cup. After the concrete strength reaches 70% of the design strength, remove the steel wedge and pour the remaining concrete to complete the installation of the column.

6. The installation and construction method of the main plant column structure according to claim 5 is characterized in that: In the step 6), the column is hoisted by a hoist, which is a steel wire rope. One end of the steel wire rope is connected to a hoisting hole or a pin on a crane beam support, and the other end is connected to the top of the elevated column section, so that the column is kept vertical under the traction of the crane.

Citation Information

Patent Citations

  • Beam column structure of steel structure factory building

    CN107724531A

  • Heavy battened steel column construction process

    CN102434003A

  • Heavy lattice type support system and using method thereof

    CN104675143A

  • High-stability combined latticed column and processing technology thereof

    CN106337531A

  • Reinforced connecting joint of steel structure beam and steel column and construction method of reinforced connecting joint

    CN106836485A