A circulation system for reducing energy and water discharge
By designing vehicle cleaning system and wastewater circulation system, using components such as grilles, water pipes and filter boxes, the problem of difficult silt cleaning during vehicle flushing at construction sites has been solved, and wastewater recycling and centralized treatment of silt are realized, and cleaning has been improved. Efficiency and resource utilization.
Patent Information
- Application Number
- CN201910605419.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-07-05
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2039-07-05
AI Technical Summary
In the existing construction site vehicle flushing device, the deposited sludge is difficult to clean up, making it difficult to effectively deal with pollutants.
A energy reduction and drainage circulation system is designed, including vehicle cleaning system and wastewater circulation system. Through components such as grilles, water pipes, filter boxes and sedimentation tanks, the filtration of wastewater and centralized collection and treatment of sludge are realized. The filter box is used to achieve the filtering of wastewater and the centralized collection and treatment of sludge. The body is welded from steel plates, and the partition components and filter plates are arranged to ensure filtration effect and resource utilization.
The recycling of wastewater and simple treatment of sludge is realized, pollutants are avoided from being taken out of the construction site, and the efficiency and resource utilization of the cleaning system are improved.
Smart Images

Figure CN110270159B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a drainage circulation system, in particular to an energy-reducing and drainage-reducing circulation system. Background Art
[0002] Since transport vehicles at construction sites drive out of the site without being washed, dirt and other debris will be scattered and pollute urban roads, construction sites must be equipped with vehicle washing equipment to reduce pollution in the construction industry. Currently, the practices of most construction sites are basically the same, that is, to build simple vehicle washing pools.
[0003] A Chinese patent with announcement number CN208134289U discloses an intelligent site flushing device, which includes a machine body, a side wall panel, a wastewater collection device, a first slope, a second slope, a water pipe, a water pump, a water spray pipeline, a control electrical box, a first water tank, a second water tank and a third water tank. The machine body and the side wall panel are fixed with bolts respectively, the control electrical box is installed on the outside of the side wall panel, the two ends of the water pipe are connected to the side wall panel and the water pump respectively, the wastewater collection device and the first water tank are connected through a square water pipe, the first water tank is connected to the second water tank, the second water tank is connected to the third water tank, the water pump is installed on the third water tank, the water spray pipeline is located on the inside of the side wall panel, and the machine body is located above the wastewater collection device.
[0004] However, in the above technical solution, the sludge deposited in the first water tank, the second water tank and the third water tank is not easy to clean, which needs to be improved. Summary of the invention
[0005] In view of the deficiencies in the prior art, the purpose of the present invention is to provide an energy-reducing and water-reducing circulation system, which can recycle the wastewater generated by vehicle washing and has the advantage of convenient sludge cleaning.
[0006] The above-mentioned object of the present invention is achieved through the following technical solutions:
[0007] An energy reduction and water reduction circulation system comprises a vehicle washing system and a wastewater circulation system, wherein the vehicle washing system comprises a wastewater collection tank, a grid with a hollow interior is arranged on the opening of the wastewater collection tank, a plurality of water spray holes with different water spray directions are penetrated at the upper end of the grid, the grid is connected to a water pipe for passing water inside, one end of the wastewater circulation system is connected to the wastewater collection tank, and the other end is connected to the water pipe;
[0008] The wastewater circulation system includes a filter box, which includes a primary sedimentation tank, a secondary sedimentation tank and a tertiary sedimentation tank through which the wastewater passes in sequence. The primary sedimentation tank and the secondary sedimentation tank are each provided with a plurality of adjacently arranged placement frames, each of which is provided with a filter bucket, and each of which is provided with a filter net for filtering the wastewater.
[0009] By adopting the above technical solution, when vehicles on the construction site pass through the vehicle cleaning system, the water in the water pipe can be sprayed out from the grille to clean the tires, so as to prevent the mud on the construction site from being brought out and polluting the road surface. The wastewater generated by the cleaning flows into the wastewater collection pool through the grille, and then is filtered through the filter net in the wastewater circulation system. The sludge generated by the filtration will remain in the filter bucket. By taking out the filter bucket, the sludge can be directly collected and processed uniformly, and the sludge processing is relatively simple.
[0010] The present invention is further configured as follows: the bottom wall of the wastewater collection tank is arranged to be inclined, and a primary sedimentation tank is provided on one side of the lowest point of the bottom wall of the wastewater collection tank.
[0011] By adopting the above technical solution, the bottom wall of the wastewater collection pool is inclined, so that large mud blocks and gravel can be deposited in the primary sedimentation tank along the slope. When the gravel and large mud blocks in the primary sedimentation tank are deposited to a certain extent, the staff can directly use shovels and other tools to clean the primary sedimentation tank.
[0012] The present invention is further configured as follows: the wastewater collection pool and the filter box are connected by digging a water trough, the side wall of the filter box is penetrated by a water inlet hole connected to the water trough, the channel of the water trough is inclined, and the lower opening of the water trough is located above the primary sedimentation tank.
[0013] By adopting the above technical solution and arranging the channel of the water trough at an angle, it is possible to prevent gravel and large stones from flowing directly into the filter box with the water flow, so as to ensure step-by-step filtration.
[0014] The present invention is further configured as follows: the filter box body is welded from a plurality of steel plates, partitions are welded between the two opposite side walls of the primary sedimentation tank and the secondary sedimentation tank, the partitions are connected to the bottom wall of the filter box body, and a plurality of placement frames are arranged on the side of the corresponding partition away from the wastewater entering the corresponding primary sedimentation tank or the secondary sedimentation tank, and the height of the partition is not lower than the height of the plurality of placement frames.
[0015] By adopting the above technical solution, the waste water must flow into the filter bucket from above by setting the partition, thereby ensuring the filtering effect. In addition, the filter box is welded by a plurality of steel plates, so that the filter box can be reused, thereby improving resource utilization.
[0016] The present invention is further configured as follows: two parallel partition components are arranged between the two opposite side walls of the filter box, dividing the filter box into a primary sedimentation tank, a secondary sedimentation tank and a tertiary sedimentation tank, the partition component includes an upper baffle and a lower baffle, the upper baffle is arranged between the two opposite side walls of the filter box, the lower baffle is arranged between the two opposite side walls of the filter box and connected to the bottom wall, the height of the lower end surface of the upper baffle is lower than the height of the upper end surface of the lower baffle, and the side wall of the upper baffle is connected to one side of a plurality of placement frames.
[0017] By adopting the above technical solution and setting the partition assembly, the height of the lower end surface of the upper baffle is lower than the height of the upper end surface of the lower baffle, so that the silt does not need to rise to the next sedimentation tank under its own weight, thereby achieving a good separation effect and reducing the amount of silt entering the next sedimentation tank.
[0018] The present invention is further configured as follows: a fixing plate is arranged between two opposite side walls of the filter box, and the fixing plate is connected to the upper end surface of the upper baffle.
[0019] By adopting the above technical solution and providing the fixing plate, the staff can step on the fixing plate to facilitate the staff to replace the filter bucket.
[0020] The present invention is further configured as follows: a mounting plate is arranged between two opposite side walls of the filter box to separate the filter box into a three-stage sedimentation tank and a four-stage purification tank, and a plurality of vertically arranged filter plates are inserted on the side of the mounting plate away from the three-stage sedimentation tank.
[0021] By adopting the above technical solution, a filter plate is arranged on the mounting plate to perform the last stage of filtration, and the filter plate is installed in a plug-in manner, which is convenient for replacement and cleaning.
[0022] The present invention is further configured as follows: the four-stage purification tank is connected to a rainwater collection tank, the water pipe is located in a three-stage sedimentation tank, and a toilet flushing device is connected to the rainwater collection tank.
[0023] By adopting the above technical solution, rainwater in the rainwater collection pool can flow into the fourth-level purification pool after being collected to a certain extent, and then be removed from the mixed sediment through the filter plate and poured into the third-level sedimentation pool, and the water in the third-level sedimentation pool is refilled into the grille through the water pipe to clean the wheels. The connection to the toilet flushing device allows the water in the rainwater collection pool to be continuously consumed, avoiding overflow of the collected water, and when the cleaning device flushes the vehicle, the excess water can flow from the third-level sedimentation pool into the fourth-level purification pool and pour into the rainwater collection pool, achieving a balance of circulating water use.
[0024] The present invention is further configured as follows: the inner core of the filter plate is configured as a low-density water-permeable sponge.
[0025] By adopting the above technical solution, the low-density permeable sponge is not only easy to clean but also has low replacement cost.
[0026] The present invention is further configured such that: the filter housing is coated with a perfluoropolyether layer on the surface before installation.
[0027] By adopting the above technical solution, perfluoropolyether has good lubrication and is in an oily state, which has a good isolation effect on concrete. During the concrete solidification process, it can prevent the side wall of the filter box from being too firmly bonded to the concrete, so as to facilitate the subsequent recycling and reuse of the filter box. In addition, perfluoropolyether has good volatility, so that the concrete can form a certain degree of adhesion with the filter box in the later stage, so as to improve the stability of the filter box.
[0028] In summary, the beneficial technical effects of the present invention are:
[0029] 1. When vehicles on the construction site pass through the vehicle washing system, the water in the water pipe can be sprayed out from the grille to clean the tires to prevent mud on the construction site from being brought out and polluting the road surface. The wastewater generated by the washing flows into the collection pool through the grille, and then is filtered through the filter net in the wastewater circulation system. The sludge generated by the filtration will remain in the filter bucket. By taking out the filter bucket, the sludge can be directly collected and processed uniformly, and the sludge processing is relatively simple;
[0030] 2. The bottom wall of the collection tank is inclined so that large mud and gravel can be deposited in the primary sedimentation tank along the slope. When the gravel and large mud in the primary sedimentation tank are deposited to a certain extent, the staff can directly use shovels and other tools to clean the primary sedimentation tank;
[0031] 3. Through the setting of the partition assembly, the height of the lower end surface of the upper baffle is lower than the height of the upper end surface of the lower baffle, so that the sediment does not need to rise to the next sedimentation tank under its own weight, thereby achieving a good separation effect and reducing the amount of sediment entering the next sedimentation tank;
[0032] 4. After the rainwater in the rainwater collection pool is collected to a certain extent, it can flow into the fourth-level purification pool, and then the mud and sand mixed in it are removed through the filter plate and poured into the third-level sedimentation pool. The water in the third-level sedimentation pool is refilled into the grille through the water pipe to clean the wheels. The access to the toilet flushing device allows the water in the rainwater collection pool to be continuously consumed to avoid overflow of the collected water. When the cleaning device flushes the vehicle, the excess water can flow from the third-level sedimentation pool into the fourth-level purification pool and pour into the rainwater collection pool to achieve a balance in circulating water use. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1It is a schematic diagram of the system distribution structure of the present invention.
[0034] Figure 2 It is a structural schematic diagram of the vehicle cleaning system in the present invention.
[0035] Figure 3 It is a structural schematic diagram of the filter box in the present invention.
[0036] Explanation of the reference numerals: 1. Vehicle cleaning system; 11. Wastewater collection tank; 111. Primary sedimentation tank; 12. Vehicle washing station; 2. Wastewater circulation system; 21. Rainwater collection tank; 22. Filter box; 221. Primary sedimentation tank; 222. Secondary sedimentation tank; 223. Tertiary sedimentation tank; 224. Fourth-stage purification tank; 225. Placement frame; 226. Filter bucket; 227. Filter plate; 3. Partition assembly; 31. Upper baffle; 32. Lower baffle; 4. Partition plate; 5. Water trough. DETAILED DESCRIPTION
[0037] The present invention is further described in detail below in conjunction with the accompanying drawings.
[0038] Reference Figure 1 , Figure 2 , is an energy reduction and water discharge reduction circulation system disclosed in the present invention, comprising a vehicle washing system 1 and a wastewater circulation system 2. The vehicle washing system 1 comprises a wastewater collection pool 11 dug on the ground, and a grille with a hollow interior is fixedly connected to the opening of the wastewater collection pool 11, and a plurality of water spray holes with different water spray directions are penetrated at the upper end of the grille, and a water pipe for passing water through the interior of the grille is connected to form a vehicle washing station 12. Among them, the grille and the water pipe are both provided in two, and the vehicles leaving the construction site are washed in conjunction with an additional washing device, and the wastewater generated by the washing leaks into the wastewater collection pool 11 through the grille. One end of the wastewater circulation system 2 is connected to the wastewater collection pool 11, and the other end is connected to the water pipe. The silt and sand in the wastewater collection pool 11 are filtered out through the wastewater circulation system 2 to achieve the purpose of recycling.
[0039] The bottom wall of the wastewater collection tank 11 is inclined, and a primary sedimentation tank 111 is dug at the lowest side of the bottom wall of the wastewater collection tank 11. Large mud and gravel can follow the slope of the bottom wall of the wastewater collection tank 11 and thus be concentrated in the primary sedimentation tank 111. When the large mud and gravel accumulate to a certain extent, the staff can open the grille and clean the sediment in the primary sedimentation tank 111 with tools such as shovels.
[0040] Reference Figure 1 , Figure 3The wastewater circulation system 2 includes an installation pool and a rainwater collection pool 21 dug on the ground, a filter box 22 is buried in the installation pool, and the filter box 22 is fixed by pouring concrete in the gap between the installation pool and the filter box 22. The filter box 22 includes a primary sedimentation tank 221, a secondary sedimentation tank 222 and a tertiary sedimentation tank 223 for wastewater to flow through in sequence, and a quaternary purification tank 224 that balances the water volume with the rainwater collection system.
[0041] A water channel 5 is dug between the wastewater collection tank 11 and the installation tank (refer to Figure 2 ) is connected, and a mesh plate is installed at the upper opening of the water trough 5 for easy construction. The side wall of the filter box 22 is penetrated with a water inlet hole connected to the water trough 5, the bottom of the water trough 5 is inclined, and the side opening of the water trough 5 at the lower part is located above the primary sedimentation tank 111.
[0042] The filter box 22 is welded by a plurality of steel plates, and two mutually parallel partition components 3 are fixedly connected between two opposite side walls of the filter box 22, thereby dividing the filter box 22 into a primary sedimentation tank 221, a secondary sedimentation tank 222, and a tertiary sedimentation tank 223. Each partition component 3 includes an upper baffle 31 and a lower baffle 32. The upper baffle 31 is welded between two opposite side walls of the filter box 22 and is spaced apart from the bottom of the box. The lower end surface of the upper baffle 31 is located below the water surface, and the upper end surface is higher than the water surface. Both sides of the lower baffle 32 are welded between two opposite side walls of the filter box 22. At the same time, the bottom end of the lower baffle 32 and the bottom wall of the filter box 22 are welded and fixed to each other to form a closure. The upper end surface of the lower baffle 32 is located below the water surface, and the height of the lower end surface of the upper baffle 31 is lower than the height of the upper end surface of the lower baffle 32. During the flow, the wastewater must pass through the lower end surface of the upper baffle 31 and enter between the upper baffle 31 and the lower baffle 32, and then flow into the next-level sedimentation tank 221 through the upper end surface of the lower baffle 32. During this rising process, the silt is difficult to rise into the next-level sedimentation tank 221 due to its own weight, thereby effectively reducing the silt content.
[0043] The two upper baffles 31 are welded and fixed with a plurality of adjacent and evenly arranged placement frames 225 on one side away from the adjacent lower baffle 32, and the edges of the two placement frames 225 at the edge are respectively fixed and welded with the two opposite side walls of the filter box 22. The placement frames 225 in the secondary sedimentation tank 222 are welded and fixed with the lower baffle 32 in another partition assembly 3 on one side away from the corresponding partition assembly 3, and the placement frames 225 in the primary sedimentation tank 221 are welded and fixed with the partition 4 on one side away from the corresponding partition assembly 3, and the two opposite side walls of the partition 4 are fixed and welded with the filter box 22, and the lower end surface of the partition 4 is welded and fixed with the bottom wall of the filter box 22. Among them, the height of the partition 4 and the lower baffle 32 welded with the placement frames 225 is not lower than the height of the plurality of placement frames 225, so that the wastewater always flows in from the top of the plurality of placement frames 225. The lower baffle 32 in the secondary sedimentation tank 222 is equivalent to the partition 4 in the primary sedimentation tank 221, and both can be used to ensure the flow direction of the wastewater.
[0044] A filter hopper 226 is placed in each placement frame 225. The filter hopper 226 is made of stainless steel and has low-density permeable holes on its surface. A filter screen made of stainless steel is fixedly connected to the filter hopper 226. The filter screen in the primary sedimentation tank 221 is 100 mesh, and the filter screen in the secondary sedimentation tank 222 is 120 mesh. From the outside, the height of the filter hopper 226 in the primary sedimentation tank 221 is higher than that in the secondary sedimentation tank 222, thereby increasing the storage capacity of the filter hopper 226 in the primary sedimentation tank 221 for sediment.
[0045] Preferably, in order to facilitate the staff to place and remove the filter bucket 226, two fixing plates are welded between the two opposite side walls of the filter box 22, and the two fixing plates are respectively welded to the upper end surfaces of the two upper baffles 31, so that the staff can directly stand on the fixing plates for easy operation.
[0046] A mounting plate is fixedly welded between two opposite side walls of the filter box 22 to separate the tertiary sedimentation tank 223 and the quaternary purification tank 224. A plurality of "T"-shaped plug-ins are fixedly welded on the side of the mounting plate away from the tertiary sedimentation tank 223, and a vertically arranged filter plate 227 is inserted between adjacent plug-ins. The inner core of the filter plate 227 is set to be a 50mm thick low-density sponge. The water pipe is placed in the tertiary sedimentation tank 223, and the quaternary purification tank 224 is connected to the rainwater collection tank 21, and a toilet flushing device is connected to the rainwater collection tank 21.
[0047] After the rainwater in the rainwater collection tank 21 is collected to a certain extent, it can flow into the fourth-level purification tank 224, and then filter out the sediment through the low-density sponge and pour into the third-level sedimentation tank 223. The water in the third-level sedimentation tank 223 is filled into the grille through the water pipe to wash the wheels. When the toilet flushing device is connected, the water in the rainwater collection tank 21 can be continuously consumed to avoid overflow of the collected water. When the washing device flushes the vehicle, the excess water can flow from the third-level sedimentation tank 223 to the fourth-level purification tank 224 and pour into the rainwater collection tank 21, achieving a balance of circulating water.
[0048] In addition, before pouring concrete into the gap between the installation pool and the filter box 22, the surface of the filter box 22 is coated with a perfluoropolyether layer. Perfluoropolyether has good lubrication and is in an oily state, which has a good isolation effect on concrete. During the curing process of concrete, it can prevent the side wall of the filter box 22 from being too firmly bonded to the concrete. Perfluoropolyether has good volatility, so that the concrete can form a certain degree of bonding with the filter box 22 in the later stage, so as to improve the stability of the filter box 22. Finally, the filter box 22 can form a partial bond with the concrete, so that the filter box 22 has good stability and is easy to be dismantled and reused in the later stage.
[0049] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. An energy reduction and wastewater reduction circulation system, comprising a vehicle washing system (1) and a wastewater circulation system (2), characterized in that: The vehicle washing system (1) comprises a wastewater collection tank (11), a grille with a hollow interior is arranged at the opening of the wastewater collection tank (11), a plurality of water spray holes with different water spray directions are penetrated at the upper end of the grille, the grille is connected to a water pipe for passing water inside, one end of the wastewater circulation system (2) is connected to the wastewater collection tank (11), and the other end is connected to the water pipe; The bottom wall of the wastewater collection tank (11) is arranged in an inclined manner, and a primary sedimentation tank (111) is provided on one side of the bottom wall of the wastewater collection tank (11) at the lowest point; The wastewater circulation system (2) comprises a filter housing (22), the filter housing (22) comprising a primary sedimentation tank (221), a secondary sedimentation tank (222) and a tertiary sedimentation tank (223) through which wastewater passes in sequence, the primary sedimentation tank (221) and the secondary sedimentation tank (222) are each provided with a plurality of adjacently arranged placement frames (225), a filter hopper (226) is placed in each of the placement frames (225), and a filter net for filtering wastewater is provided in each of the filter hoppers (226); The filter box (22) is welded from a plurality of steel plates. A partition (4) is welded between the two opposite side walls of the primary sedimentation tank (221) and the secondary sedimentation tank (222). The partition (4) is connected to the bottom wall of the filter box (22). The plurality of placement frames (225) are arranged on the side of the corresponding partition (4) away from the wastewater entering the corresponding primary sedimentation tank (221) or the secondary sedimentation tank (222). The height of the partition (4) is not less than the height of the plurality of placement frames (225). Two mutually parallel partition components (3) are arranged between the two opposite side walls of the filter box (22) to divide the filter box (22) into the primary sedimentation tank (221). , a secondary sedimentation tank (222) and a tertiary sedimentation tank (223), the partition assembly (3) comprising an upper baffle (31) and a lower baffle (32), the upper baffle (31) being arranged between two opposite side walls of the filter box (22), the lower baffle (32) being arranged between two opposite side walls of the filter box (22) and connected to the bottom wall, the lower end surface of the upper baffle (31) being located at a lower height than the upper end surface of the lower baffle (32), the side wall of the upper baffle (31) being connected to one side of a plurality of placement frames (225), a fixing plate being arranged between two opposite side walls of the filter box (22), the fixing plate being connected to the upper end surface of the upper baffle (31).
2. The energy reduction and drainage reduction circulation system according to claim 1, characterized in that: The wastewater collection pool (11) and the filter housing (22) are connected by digging a water trough (5); a water inlet hole connected to the water trough (5) is penetrated through the side wall of the filter housing (22); the channel of the water trough (5) is arranged obliquely; the lower opening of the water trough (5) is located above the primary sedimentation tank (111).
3. The energy reduction and drainage reduction circulation system according to claim 1, characterized in that: A mounting plate is arranged between two opposite side walls of the filter box (22) to separate the filter box (22) into a third-stage sedimentation tank (223) and a fourth-stage purification tank (224); a plurality of vertically arranged filter plates (227) are inserted on a side of the mounting plate away from the third-stage sedimentation tank (223).
4. The energy reduction and drainage reduction circulation system according to claim 3 is characterized in that: The four-stage purification tank (224) is connected to a rainwater collection tank (21), the water pipe is located in the three-stage sedimentation tank (223), and a toilet flushing device is connected to the rainwater collection tank (21).
5. The energy reduction and drainage reduction circulation system according to claim 3, characterized in that: The inner core of the filter plate (227) is configured as a low-density water-permeable sponge.
6. The energy reduction and drainage reduction circulation system according to claim 1, characterized in that: The filter housing (22) is coated with a perfluoropolyether layer on its surface before installation.