A horizontal rapid cooling and settling device for primary flue gas of an electric furnace and its process flow

Through the heating, decomposition, quenching and settling processes of the electric furnace primary flue gas horizontal quenching and settling device, the problem of dioxin and dust control in the electric furnace flue gas is solved, and efficient settlement and system safety are improved.

CN110332816BActive Publication Date: 2024-10-11CISDI RES & DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910718410.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-08-05
Publication Date
2024-10-11
Estimated Expiration
2039-08-05

AI Technical Summary

Technical Problem

Existing electric furnace flue gas treatment technology is difficult to achieve complete decomposition of dioxin and efficient sedimentation of dust, leading to safety hazards such as increased load on the dust removal system and dust accumulation and hardening of pipelines.

Method used

Design a horizontal quenching and settling device for the primary flue gas of an electric furnace, including a combustion chamber, a quenching chamber and a settling chamber. Through the four-step process of heating, decomposition, quenching and settling, it ensures the decomposition of dioxin and the settling of dust. The horizontal setting is used to reduce System height improves settling efficiency.

Benefits of technology

It achieves complete decomposition of dioxin and efficient sedimentation of dust, reduces the load on the dust removal system, prevents dust accumulation and hardening of the dust removal pipeline, and extends the operating life of the bag dust collector.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 1
    Figure 1
Patent Text Reader

Abstract

The present invention belongs to the field of quenching and dust removal of flue gas in the metallurgical industry, and relates to a horizontal quenching and settling device for primary flue gas of an electric furnace and its process flow, including a quenching chamber, a combustion chamber and a settling chamber; the combustion chamber includes a combustion chamber flue gas inlet arranged on the combustion chamber, and a combustion chamber flue gas outlet is also provided on the side of the combustion chamber; the settling chamber includes a settling chamber flue gas inlet arranged on the side of the settling chamber, and a settling chamber flue gas outlet is also provided on the settling chamber; one end of the quenching chamber is connected to the combustion chamber through the combustion chamber flue gas outlet, and the other end is connected to the settling chamber through the settling chamber flue gas inlet; an atomizing spray gun for spraying is also provided inside the quenching chamber. The present invention adopts a horizontal setting different from the prior art, improves the settling efficiency of dust in the flue gas after quenching, and the droplets that are not evaporated by spraying can also be settled and captured in the settling chamber, which can effectively prevent the accumulation of dust and hardening inside the subsequent dust removal pipeline, reduce the operating load of the bag filter, and improve the operating life.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of rapid cooling and dust removal of flue gas in the metallurgical industry, and relates to a horizontal rapid cooling and settling device for primary flue gas of an electric furnace and a process flow thereof. Background Art

[0002] The electric furnace smelting process will produce a large amount of high-temperature primary flue gas, which contains a large amount of dust (10-20g / m 3 ), the primary flue gas is first cooled and then sent to the bag filter for fine dust removal before being discharged. If the scrap steel used in the electric furnace smelting is of poor quality, such as containing a large amount of paint, grease, plastic, copper, etc., a large amount of dioxin-like highly toxic substances may be produced in the primary flue gas of the electric furnace.

[0003] Dioxin is a general term for 210 chlorine-containing organic compounds, including polychlorinated dibenzo-p-dioxins (PCDDs) and polychlorinated dibenzofurans (PCDFs). This type of substance has the characteristics of high-temperature decomposition and low-temperature de novo synthesis. Specifically, when the flue gas stays at 850℃ for more than 2s, the dioxins in it can be completely decomposed into simple substances; and during the cooling process of the flue gas, especially in the range of 300-500℃, dioxin-like substances will be synthesized again through elementary reactions. This range is the temperature window for dioxin synthesis.

[0004] At present, the treatment of electric furnace dust and dioxins mainly involves cooling the primary flue gas first, including spray cooling tower, mechanical air cooler, mixed air, waste heat boiler, etc., and then purifying the flue gas with bag filter before discharge. With the increasingly stringent environmental protection standards, it will be difficult for systems using mechanical air cooling, mixed air or waste heat boiler cooling methods to achieve standard emission of flue gas dioxins. Spray cooling towers have also become the mainstream solution for treating dioxins in flue gas from electric furnaces. Spray cooling is used to quickly (within 2 seconds) cool high-temperature flue gas (850°C) to below 300°C. However, in order to ensure sufficient mixing of the spray water and the flue gas, the height of the spray quenching tower is generally designed to be relatively high (10 to 25 meters), which makes it difficult for the site of some renovation projects to meet the height requirements. In addition, in actual operation, water wetting the walls and dust compaction often occur in the spray tower. At the same time, the flue gas flow rate at the spray tower inlet and in the spray tower is relatively high, making it difficult for dust to settle. Droplets that have not evaporated from the spray will also enter the rear-end dust removal system with the airflow, resulting in a large amount of dust accumulation and compaction in the rear-end dust removal pipeline, which in turn causes pipeline collapse, bag sticking and other accidents. Summary of the invention

[0005] In view of this, the purpose of the present invention is to provide a horizontal rapid cooling and settling device for primary flue gas of an electric furnace and its process flow, so as to achieve the thorough decomposition and reliable inhibition of dioxins in the primary flue gas of the electric furnace, and at the same time efficiently settle the large particles of dust in the flue gas to reduce the load of the dust removal system and prevent dust accumulation and hardening in the dust removal pipeline.

[0006] To achieve the above object, the present invention provides the following technical solutions: a horizontal rapid cooling and settling device for primary flue gas of an electric furnace, comprising a rapid cooling chamber, wherein both ends of the rapid cooling chamber are respectively connected to a combustion chamber and a settling chamber;

[0007] The combustion chamber comprises a combustion chamber smoke inlet arranged on the combustion chamber, a supplementary burner and an inlet temperature sensor are arranged inside the combustion chamber smoke inlet, and a combustion chamber smoke outlet is also opened on the side of the combustion chamber;

[0008] The settling chamber comprises a settling chamber smoke inlet arranged on the side of the settling chamber, and a settling chamber smoke outlet is also opened on the settling chamber, and an outlet temperature sensor is arranged inside the settling chamber smoke outlet;

[0009] One end of the quenching chamber is connected to the combustion chamber through the smoke outlet of the combustion chamber, and the other end is connected to the settling chamber through the smoke inlet of the settling chamber; an atomizing spray gun for spraying is also arranged inside the quenching chamber.

[0010] Optionally, the flow direction of the flue gas in the quenching chamber is a first direction, the plane perpendicular to the first direction is the first plane, the projection area of ​​the quenching chamber on the first plane is smaller than the projection area of ​​the combustion chamber on the first plane, and the projection area of ​​the quenching chamber on the first plane is smaller than the projection area of ​​the sedimentation chamber on the first plane.

[0011] Optionally, the smoke outlet of the combustion chamber is a contraction structure, and the projection area of ​​the smoke outlet at one end close to the quenching chamber on the first plane gradually increases along the direction where the combustion chamber is located.

[0012] Optionally, the smoke inlet of the settling chamber is a flared structure, and a projection area of ​​the smoke inlet at one end close to the quenching chamber on the first plane gradually increases along the direction where the settling chamber is located.

[0013] Optionally, the combustion chamber and the settling chamber are respectively provided with a combustion chamber cleaning door and a settling chamber cleaning door for cleaning.

[0014] Optionally, the spraying direction of the atomizing spray gun is toward the settling chamber, which is consistent with the direction of smoke flow.

[0015] Optionally, the positions of the smoke inlet of the combustion chamber and the smoke outlet of the settling chamber are both perpendicular to the first direction and have the same direction.

[0016] A process flow of a horizontal rapid cooling and settling device for primary flue gas of an electric furnace, using a horizontal rapid cooling and settling device for primary flue gas of an electric furnace, comprising the following steps:

[0017] Supplementary heating: The primary flue gas of the electric furnace enters from the flue gas inlet of the combustion chamber. When the inlet temperature sensor detects that the inlet temperature of the flue gas in the combustion chamber is lower than 850℃, the supplementary burner is opened to increase the primary flue gas temperature to above 850℃;

[0018] Decomposition: The flue gas enters the combustion chamber and stays in the combustion chamber for more than 2 seconds to ensure that the dioxins in the flue gas are fully decomposed;

[0019] Rapid cooling: The flue gas reaches the rapid cooling chamber through the combustion chamber outlet, the flow area is reduced, the flue gas velocity is increased, and the atomizing spray gun is turned on to quickly cool the flue gas;

[0020] Sedimentation: The flue gas enters the settling chamber from the quenching chamber through the flue gas inlet of the settling chamber, the flow rate is reduced, the dust in the flue gas settles, and is discharged through the flue gas outlet of the settling chamber.

[0021] Optionally, when the outlet temperature sensor detects that the flue gas temperature is higher than a set value, the atomizing spray gun is turned on.

[0022] The beneficial effects of the present invention are as follows: the horizontal rapid cooling and settling device for primary flue gas of an electric furnace and its process flow disclosed in the present invention adopt a horizontal arrangement different from that in the prior art, which greatly reduces the height of the rapid cooling and settling system layout, greatly improves the settling efficiency of dust in the flue gas after rapid cooling, and can also achieve better settling and capture of unevaporated droplets in the settling chamber under abnormal conditions (such as excessive spray water, poor spray atomization effect, etc.), effectively preventing dust accumulation and compaction inside the subsequent dust removal pipeline, reducing the operating load of the bag filter and increasing the operating life of the bag filter.

[0023] Other advantages, objectives and features of the present invention will be described in the following description to some extent, and to some extent, will be obvious to those skilled in the art based on the following examination and study, or can be taught from the practice of the present invention. The objectives and other advantages of the present invention can be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention will be described in detail below in conjunction with the accompanying drawings, wherein:

[0025] Figure 1 It is an overall schematic diagram of a horizontal rapid cooling and settling device for primary flue gas of an electric furnace according to the present invention.

[0026] Figure numerals: combustion chamber 1, combustion chamber smoke inlet 11, combustion chamber smoke outlet 12, combustion chamber cleaning door 13, supplementary burner 14, inlet temperature sensor 15, quenching chamber 2, atomizing spray gun 21, settling chamber 3, settling chamber smoke inlet 31, settling chamber smoke outlet 32, settling chamber cleaning door 33, outlet temperature sensor 34. DETAILED DESCRIPTION

[0027] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the illustrations provided in the following embodiments only illustrate the basic concept of the present invention in a schematic manner, and the following embodiments and features in the embodiments can be combined with each other without conflict.

[0028] Among them, the drawings are only used for illustrative explanations, and they only represent schematic diagrams rather than actual pictures, and should not be understood as limitations on the present invention. In order to better illustrate the embodiments of the present invention, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of actual products. For those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted.

[0029] The same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right", "front", "rear", etc. indicate the orientation or position relationship, they are based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, the terms describing the position relationship in the drawings are only used for illustrative purposes and cannot be understood as limiting the present invention. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0030] See also Figure 1 , which is a horizontal rapid cooling and settling device for primary flue gas of an electric furnace, comprising a rapid cooling chamber 2, wherein both ends of the rapid cooling chamber 2 are respectively connected to a combustion chamber 1 and a settling chamber 3;

[0031] The combustion chamber 1 includes a combustion chamber flue gas inlet 11 arranged on the combustion chamber 1, and a supplementary burner 14 and an inlet temperature sensor 15 are arranged inside the combustion chamber flue gas inlet 11, and a combustion chamber flue gas outlet 12 is also provided on the side of the combustion chamber 1; the settling chamber 3 includes a settling chamber flue gas inlet 31 arranged on the side of the settling chamber 3, and a settling chamber flue gas outlet 32 ​​is also provided on the settling chamber 3, and an outlet temperature sensor 34 is arranged inside the settling chamber flue gas outlet 32; the combustion chamber 1 and the settling chamber 3 are respectively provided with a combustion chamber ash cleaning door 13 and a settling chamber ash cleaning door 33 for ash cleaning; one end of the quenching chamber 2 is connected to the combustion chamber 1 through the combustion chamber flue gas outlet 12, and the other end is connected to the settling chamber 3 through the settling chamber flue gas inlet 31; the quenching chamber 2 is also provided inside An atomizing spray gun 21 for spraying is provided, and the spraying direction of the atomizing spray gun 21 is toward the settling chamber 3, which is consistent with the direction of smoke flow; the flow direction of smoke in the quenching chamber 2 is a first direction, and the plane perpendicular to the first direction is the first plane. The projection area of ​​the quenching chamber 2 on the first plane is smaller than the projection area of ​​the combustion chamber 1 on the first plane, and the projection area of ​​the quenching chamber 2 on the first plane is smaller than the projection area of ​​the settling chamber 3 on the first plane. The smoke outlet 12 of the combustion chamber is a contracting structure, and its projection area on the first plane at one end close to the quenching chamber 2 gradually increases along the direction where the combustion chamber 1 is located, and the smoke inlet 31 of the settling chamber is an expanding structure, and its projection area on the first plane at one end close to the quenching chamber 2 gradually increases along the direction where the settling chamber 3 is located.

[0032] In this embodiment, the positions of the combustion chamber smoke inlet 11 and the settling chamber smoke outlet 32 ​​are both perpendicular to the first direction and have the same orientation.

[0033] A process flow of a horizontal rapid cooling and settling device for primary flue gas of an electric furnace, using a horizontal rapid cooling and settling device for primary flue gas of an electric furnace, comprising the following steps:

[0034] Supplementary heating: The primary flue gas of the electric furnace enters from the flue gas inlet 11 of the combustion chamber. When the inlet temperature sensor 15 detects that the temperature of the flue gas inlet 11 of the combustion chamber is lower than 850°C, the supplementary burner 14 is opened to increase the primary flue gas temperature to above 850°C.

[0035] Decomposition: The flue gas enters the combustion chamber 1 and stays in the combustion chamber 1 for more than 2 seconds to ensure that the dioxins in the flue gas are fully decomposed;

[0036] Rapid cooling: The flue gas reaches the rapid cooling chamber 2 through the outlet of the combustion chamber 1, the flow area is reduced, the flue gas flow rate is increased, and the atomizing spray gun 21 is turned on to quickly cool the flue gas;

[0037] Sedimentation: The flue gas enters the settling chamber 3 from the quenching chamber 2 through the flue gas inlet 31 of the settling chamber, the flow rate is reduced, the dust in the flue gas is settled, and is discharged through the flue gas outlet 32 ​​of the settling chamber.

[0038] In this embodiment, when the outlet temperature sensor 34 detects that the flue gas temperature is higher than a set value, the atomizing spray gun 21 is turned on.

[0039] The present invention adopts a horizontal arrangement different from the prior art, which greatly reduces the height of the rapid cooling and settling system, greatly improves the settling efficiency of dust in the flue gas after rapid cooling, and can also achieve better settling and capture of unevaporated droplets in the settling chamber 3 under abnormal conditions (such as excessive spray water, poor spray atomization effect, etc.), effectively preventing dust accumulation and compaction inside the subsequent dust removal pipeline, reducing the operating load of the bag filter and increasing the operating life of the bag.

[0040] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution, which should be included in the scope of the claims of the present invention.

Claims

1. A horizontal rapid cooling and settling device for primary flue gas of an electric furnace, characterized in that: It includes a quenching chamber, and the two ends of the quenching chamber are respectively connected to the combustion chamber and the settling chamber; the combustion chamber includes a combustion chamber smoke inlet arranged on the combustion chamber, and a supplementary burner and an inlet temperature sensor are arranged inside the combustion chamber smoke inlet, and a combustion chamber smoke outlet is also opened on the side of the combustion chamber; the settling chamber includes a settling chamber smoke inlet arranged on the side of the settling chamber, and a settling chamber smoke outlet is also opened on the settling chamber, and an outlet temperature sensor is arranged inside the settling chamber smoke outlet; one end of the quenching chamber is connected to the combustion chamber through the combustion chamber smoke outlet, and the other end is connected to the settling chamber through the settling chamber smoke inlet; an atomizing spray gun for spraying is also arranged inside the quenching chamber; the spraying direction of the atomizing spray gun is toward the settling chamber, which is consistent with the direction of smoke flow; The flow direction of the flue gas in the quenching chamber is the first direction, and the plane perpendicular to the first direction is the first plane. The projection area of ​​the quenching chamber on the first plane is smaller than the projection area of ​​the combustion chamber on the first plane, and the projection area of ​​the quenching chamber on the first plane is smaller than the projection area of ​​the settling chamber on the first plane; the flue gas outlet of the combustion chamber is a contracting structure, and its projection area on the first plane close to one end of the quenching chamber gradually increases along the direction where the combustion chamber is located; the flue gas inlet of the settling chamber is an expanding structure, and its projection area on the first plane close to one end of the quenching chamber gradually increases along the direction where the settling chamber is located.

2. The horizontal rapid cooling and settling device for primary flue gas of an electric furnace according to claim 1, characterized in that: The combustion chamber and the settling chamber are respectively provided with a combustion chamber cleaning door and a settling chamber cleaning door for cleaning.

3. The horizontal rapid cooling and settling device for primary flue gas of an electric furnace according to claim 1, characterized in that: The positions of the smoke inlet of the combustion chamber and the smoke outlet of the settling chamber are both perpendicular to the first direction and have the same orientation.

4. A process flow of a horizontal rapid cooling and settling device for primary flue gas of an electric furnace, using a horizontal rapid cooling and settling device for primary flue gas of an electric furnace as claimed in any one of claims 1 to 3, characterized in that: The following steps are involved: Supplementary heating: The primary flue gas of the electric furnace enters from the flue gas inlet of the combustion chamber. When the inlet temperature sensor detects that the inlet temperature of the flue gas in the combustion chamber is lower than 850℃, the supplementary burner is opened to increase the primary flue gas temperature to above 850℃; Decomposition: The flue gas enters the combustion chamber and stays in the combustion chamber for more than 2 seconds to ensure that the dioxins in the flue gas are fully decomposed; Rapid cooling: The flue gas reaches the rapid cooling chamber through the combustion chamber outlet, the flow area is reduced, the flue gas velocity is increased, and the atomizing spray gun is turned on to quickly cool the flue gas; Sedimentation: The flue gas enters the settling chamber from the quenching chamber through the flue gas inlet of the settling chamber, the flow rate is reduced, the dust in the flue gas settles, and is discharged through the flue gas outlet of the settling chamber.

5. The process flow of a horizontal rapid cooling and settling device for primary flue gas of an electric furnace according to claim 4, characterized in that: When the outlet temperature sensor detects that the flue gas temperature is higher than the set value, the atomizing spray gun is turned on.