Crane trolley, lifting system and lifting method

By designing the alternating use of the main grab and auxiliary grab on the crane trolley, combined with the design of the hoist and grab frame, the problem of traditional bridge crane trolleys needing to replace the grab when dealing with different materials is solved, improving productivity and construction efficiency.

CN110422759BActive Publication Date: 2024-11-08BEIJING MATERIALS HANDLING TECH INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910790571.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-08-26
Publication Date
2024-11-08
Estimated Expiration
2039-08-26

AI Technical Summary

Technical Problem

Traditional bridge crane trolleys need to replace the grab when handling different materials, resulting in high construction difficulty and low productivity.

Method used

A crane truck was designed, equipped with a main grab and an auxiliary grab. The main grab is located inside the track, and the auxiliary grab is located outside the track. It is used alternately through the main lifting mechanism and the auxiliary lifting mechanism. The auxiliary lifting mechanism includes a hoist. The grab frame is used to store and fix the auxiliary grab, and the counterweight is used to keep the frame balanced.

Benefits of technology

It realizes the use of multiple different grabs at the same material level, reducing or avoiding grab replacement, reducing construction difficulty, saving construction time, improving productivity, and providing supplements to the traditional intra-rail lifting method.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110422759B_ABST
    Figure CN110422759B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of lifting machinery, and discloses a crane trolley, a lifting system and a lifting method, wherein the crane trolley includes a frame body and a main grab, the bottom two sides of the frame body are respectively connected to the track for movement, the main grab is connected to the frame body between the two side tracks, and further includes: an auxiliary grab; an auxiliary grab is provided on one or both sides of the frame body, the auxiliary grab is located on the outside of the track, and the auxiliary grab is different in form from the main grab. A crane trolley, a lifting system and a lifting method provided by the present invention are provided with an auxiliary grab on the side of the frame body, so that a variety of different grabs can be used at the same material level to achieve different lifting and grabbing requirements, and the replacement of grabs can be reduced or avoided for different goods, thereby reducing the construction difficulty, saving construction time, and improving productivity, and providing a powerful supplement to the traditional in-track lifting method.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of lifting machinery, and in particular to a crane trolley, a lifting system and a lifting method. Background Art

[0002] With the continuous development of the economy and the continuous improvement of people's living standards, people's consumption capacity has also been rapidly improved. Therefore, a large amount of domestic garbage and industrial garbage are generated every year in industrial production and life, making the environment increasingly serious. Therefore, it is necessary to centrally treat the garbage. Most of the garbage treatment processes require operations such as transportation, mixing, stacking, and feeding. Grab cranes are usually used for transportation during the transportation process.

[0003] Traditional bridge crane trolleys are usually equipped with grab buckets, and the running track of the grab bucket is located inside the two tracks. With the improvement of the operating technology of bridge crane applications, at the same material level, the type of material that the crane grabs is not limited to one type, and the same grab bucket can no longer meet the grabbing requirements of different materials.

[0004] In order to solve this problem, the usual approach is to change the grab bucket type according to the grab requirements. However, this method is not only difficult to construct, but also takes a long time to construct, which seriously affects productivity. Summary of the invention

[0005] 1. Technical issues to be resolved

[0006] The object of the present invention is to provide a crane trolley, a lifting system and a lifting method, which are used to solve or partially solve the problem that the grabbing of different materials requires the replacement of the grabbing bucket, resulting in great construction difficulty and low productivity.

[0007] (II) Technical solution

[0008] In order to solve the above technical problems, the first aspect of the present invention provides a crane trolley, including a frame body and a main grab, wherein the bottom two sides of the frame body are respectively movably connected to the track, and the main grab is connected to the frame body between the two side tracks, and also includes: an auxiliary grab; an auxiliary grab is provided on one side or both sides of the frame body, the auxiliary grab is located on the outside of the track, and the auxiliary grab is different in form from the main grab.

[0009] On the basis of the above scheme, it also includes: a main lifting mechanism and an auxiliary lifting mechanism; the main lifting mechanism is arranged at the position of the frame body located between the two side rails, and the main lifting mechanism is connected to the main grab; the auxiliary lifting mechanism is arranged at the position of the frame body located outside the rails, and the auxiliary lifting mechanism is connected to the auxiliary grab.

[0010] On the basis of the above solution, the auxiliary lifting mechanism includes a winch, and the winch of the auxiliary lifting mechanism is arranged along the length direction of the track.

[0011] On the basis of the above scheme, it also includes: a grab bucket frame; the grab bucket frame is arranged above the lifting path of the auxiliary grab bucket and below the frame body, and the auxiliary grab bucket passes through the inside of the grab bucket frame.

[0012] Based on the above solution, a plurality of fixing blocks are provided on the inner side of the bottom of the grab frame along the circumferential direction.

[0013] On the basis of the above solution, when an auxiliary grab bucket is provided on one side of the frame body, a counterweight block is provided on the other side of the frame body.

[0014] On the basis of the above solution, the main grab bucket and the auxiliary grab bucket are staggered in the length direction of the track.

[0015] On the basis of the above solution, the auxiliary lifting mechanism is connected to the auxiliary grab bucket through at least two steel wire ropes, and the at least two steel wire ropes are arranged in parallel along the length direction of the track.

[0016] A second aspect of the present invention provides a lifting system, comprising the above-mentioned crane trolley.

[0017] The third aspect of the present invention is a lifting method based on the above-mentioned crane trolley, comprising: using a main grab and an auxiliary grab to grab different materials alternately; when the main grab is working, the auxiliary grab is lifted and stored in the grab frame, and the auxiliary grab is opened so that the bucket body of the auxiliary grab is against the fixed block; when the auxiliary grab is working, the main grab is closed and lifted to a safe height position.

[0018] (III) Beneficial effects

[0019] The present invention provides a crane trolley, a lifting system and a lifting method, wherein an auxiliary grab is arranged on the side of the frame body, so that a plurality of different grabs can be used at the same material level to meet different lifting and grasping requirements, and the replacement of the grabs can be reduced or avoided for different goods, thereby reducing the construction difficulty, saving construction time, improving productivity, and providing a powerful supplement to the traditional in-rail lifting method. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 A front schematic diagram of a crane trolley provided in an embodiment of the present invention;

[0021] Figure 2 A side schematic diagram of a crane trolley provided in an embodiment of the present invention;

[0022] Figure 3A schematic top view of a crane trolley provided in an embodiment of the present invention;

[0023] Figure 4 A structural schematic diagram of a middle grab bucket frame is provided for an embodiment of the present invention;

[0024] Figure 5 A schematic diagram of the installation of a middle counterweight block is provided for an embodiment of the present invention.

[0025] Description of reference numerals:

[0026] 1—Frame body; 2—Track; 3—Main grab bucket;

[0027] 4—Auxiliary grab; 5—Main lifting mechanism; 6—Auxiliary lifting mechanism;

[0028] 7—grab bucket frame; 8—counterweight block; 9—trolley running mechanism;

[0029] 10—Fixed block. DETAILED DESCRIPTION

[0030] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0031] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0032] The embodiment of the present invention provides a crane trolley, referring to Figure 1 and Figure 2 , including a frame body 1 and a main grab 3, the bottom two sides of the frame body 1 are respectively connected to the track 2 for movement, and the main grab 3 is connected to the frame body 1 between the two side tracks 2. The frame body 1 can move along the length direction of the track 2. The main grab 3 grabs the target goods between the two side tracks 2. The crane trolley also includes: an auxiliary grab 4; an auxiliary grab 4 is provided on one or both sides of the frame body 1, and the auxiliary grab 4 is located outside the track 2, and the auxiliary grab 4 is different from the main grab 3 in form.

[0033] The crane trolley is provided with an auxiliary grab 4 on the side of the frame body 1, and the auxiliary grab 4 corresponds to the goods on the outside of the track 2, and can grab the goods on the outside of the track 2. The outside of the track 2 is the side of the track 2 on one side away from the track 2 on the other side. The auxiliary grab 4 can be provided to grab goods at different parts at the same material level of the frame body 1 with the main grab 3. Moreover, the auxiliary grab 4 and the main grab 3 have different forms, and can also adapt to different goods.

[0034] A crane trolley provided in this embodiment has an auxiliary grab 4 arranged on the side of the frame body 1, which enables the use of multiple different grabs at the same material level to achieve different lifting and grasping requirements. The replacement of the grab can be reduced or avoided for different goods, thereby reducing the construction difficulty, saving construction time, improving productivity, and providing a powerful supplement to the traditional in-rail lifting method.

[0035] Furthermore, an auxiliary grab 4 can be provided on one side of the frame body 1 to realize two different grabs for the same material level; auxiliary grabs 4 can also be provided on both sides of the frame body 1 to realize three different grabs for the same material level, without specific limitation.

[0036] Furthermore, the width of the frame body 1 can be set to be greater than the width between the two side rails 2, so that the side of the frame body 1 extends out of the rails 2, which is convenient for setting the auxiliary grab 4. A mounting frame can also be connected to the side of the frame body 1 for setting the auxiliary grab 4, which is not specifically limited.

[0037] On the basis of the above embodiment, a crane trolley further includes: a main lifting mechanism 5 and an auxiliary lifting mechanism 6; the main lifting mechanism 5 is arranged at a portion of the frame body 1 between the two side rails 2, and the main lifting mechanism 5 is connected to the main grab 3; the auxiliary lifting mechanism 6 is arranged at a portion of the frame body 1 outside the rails 2, and the auxiliary lifting mechanism 6 is connected to the auxiliary grab 4. The main lifting mechanism 5 is used to lift or lower the main grab 3; the auxiliary lifting mechanism 6 is used to lift or lower the auxiliary grab 4.

[0038] On the basis of the above embodiments, further, referring to Figure 3 The auxiliary lifting mechanism 6 includes a winch, and the winch of the auxiliary lifting mechanism 6 is arranged along the length direction of the track 2. Specifically, the axial direction of the drum of the winch of the auxiliary lifting mechanism 6 is arranged along the length direction of the track 2. This arrangement can reduce the width of the auxiliary grab 4 in the width direction of the track 2 required for installation. The width of the frame body 1 can be reduced, which is conducive to improving the overall stability of the crane trolley.

[0039] Furthermore, the main lifting mechanism 5 may also include a winch; the winch of the main lifting mechanism 5 is preferably arranged in the middle position between the two side rails 2, and can be arranged along the length direction of the rail 2 or along the width direction of the rail 2, which is beneficial to the stability of the overall structure.

[0040] On the basis of the above embodiment, further, a crane trolley also includes: a grab frame 7; the grab frame 7 is arranged above the lifting path of the auxiliary grab 4 and below the frame body 1, and the auxiliary grab 4 passes through the inside of the grab frame 7.

[0041] The grab frame 7 is a frame structure and at least the bottom is open. The grab frame 7 is fixedly arranged below the frame body 1 and outside the track 2. When the auxiliary grab 4 is lifted under the drive of the auxiliary lifting mechanism 6, it can be retracted into the grab frame 7. When the main grab 3 is required to work, the auxiliary grab 4 can be retracted into the upper grab frame 7 to prevent affecting the normal operation of the main grab 3. Furthermore, the height of the grab frame 7 is not limited for the purpose of not affecting the operation of the main grab 3.

[0042] On the basis of the above embodiments, further, referring to Figure 4 A plurality of fixing blocks 10 are provided along the circumferential direction on the inner side of the bottom of the grab frame 7. When the auxiliary grab 4 is located inside the grab frame 7, the auxiliary grab 4 can be opened so that the bucket body of the auxiliary grab 4 abuts against the fixing blocks 10, thereby fixing the auxiliary grab 4 to prevent it from shaking inside the grab frame 7 and causing damage to the bucket body.

[0043] Furthermore, the fixing block 10 can be a flexible fixing block 10 or a rigid fixing block 10 , without limitation. The fixing block 10 can be arranged at a position corresponding to the bucket body of the auxiliary grab bucket 4 on the inner side of the grab bucket frame 7 .

[0044] On the basis of the above embodiments, further, referring to Figure 1 and Figure 5 When the auxiliary grab 4 is provided on one side of the frame body 1, a counterweight 8 is provided on the other side of the frame body 1. That is, when the auxiliary grab 4 is provided on only one side of the frame body 1, the weight of the frame body 1 is unbalanced. The counterweight 8 is provided on the other side to maintain the balance of the frame body 1, which is beneficial to the smooth operation of the crane trolley. The specific weight of the counterweight 8 is set according to the auxiliary grab 4, so as to maintain the balance of the frame body 1.

[0045] On the basis of the above embodiment, further, the main grab bucket 3 and the auxiliary grab bucket 4 are staggered in the length direction of the track 2. This can reduce the mutual influence between the two and ensure that the main grab bucket 3 and the auxiliary grab bucket 4 can work smoothly.

[0046] On the basis of the above embodiment, further, the auxiliary lifting mechanism 6 is connected to the auxiliary grab 4 through at least two steel wires, and the at least two steel wires are arranged in parallel along the length direction of the track 2. That is, at least two steel wires are located on a straight line parallel to the length direction of the track 2. The space required for installing the auxiliary grab 4 in the width direction of the track 2 can be reduced, which is convenient for installation and conducive to improving the stability of the overall structure.

[0047] On the basis of the above embodiments, further, this embodiment provides a lifting system, including the crane trolley described in any of the above embodiments.

[0048] On the basis of the above embodiments, further, this embodiment provides a lifting method of the crane trolley based on any of the above embodiments, and the lifting method includes: using the main grab 3 and the auxiliary grab 4 to grab different materials alternately; when the main grab 3 is working, the auxiliary grab 4 is lifted and stored in the auxiliary grab 4 frame, and the auxiliary grab 4 is opened so that the bucket body of the auxiliary grab 4 is against the fixed block 10; when the auxiliary grab 4 is working, the main grab 3 is closed and lifted to a safe height position.

[0049] On the basis of the above embodiment, further, this embodiment provides a double grab single operation crane trolley, which is mainly composed of a main grab 3, an auxiliary grab 4, a frame body 1, a main lifting mechanism 5, an auxiliary lifting mechanism 6, a trolley running mechanism 9, a counterweight, an auxiliary grab 4 frame, etc. The crane trolley is a crane trolley with two different lifting mechanisms arranged on the same trolley.

[0050] The two sets of winch systems of different lifting mechanisms on the trolley are arranged perpendicular to each other. The running track of the main grab 3 is on the inner side of the two tracks 2 in the length direction, and the running track of the auxiliary grab 4 is on the outer side of the single-side track 2. When the auxiliary grab 4 is not needed, it can be stored in the grab frame 7. In order to evenly distribute the wheel pressure of the trolley, a counterweight is set on the side opposite to the auxiliary grab 4 on the trolley. The main grab 3 adopts a four-wire multi-petal form, and the auxiliary grab 4 adopts a two-or four-wire double-petal form. The main grab 3 and the auxiliary grab 4 can also be in other forms, which can be determined according to the type of goods to be grabbed, and are not limited.

[0051] The opening direction of the auxiliary grab 4 is consistent with the running direction of the trolley. In the direction perpendicular to the running track 2, the grab centers of the main grab 3 and the auxiliary grab 4 do not overlap. The main grab 3 and the auxiliary grab 4 are connected to the trolley through the wire rope in the lifting mechanism, respectively. The running track of the main grab 3 is inside the length direction of the two tracks 2, and the running track of the auxiliary grab 4 is outside the single-side track 2. When the auxiliary grab 4 is not needed, it can be stored in the grab frame 7 to avoid collision accidents.

[0052] The main lifting mechanism 5 is used for the lifting of the main grab 3, and the auxiliary lifting mechanism 6 is used for the lifting of the auxiliary grab 4. The hoisting systems of the two lifting mechanisms are arranged perpendicular to each other. In the direction perpendicular to the running track 2, the grabbing centers of the main grab 3 and the auxiliary grab 4 do not overlap. When the main grab 3 is working, the auxiliary grab 4 is fully opened and lifted and stored in the auxiliary grab 4 frame; when the auxiliary grab 4 is working, the main grab 3 is fully closed and lifted to a safe height position, which can realize the function of alternately grabbing different materials. The main grab 3 adopts a four-wire multi-petal form, and the auxiliary grab 4 adopts a two-or four-wire double-petal form. The opening direction of the auxiliary grab 4 is consistent with the running direction of the trolley. In order to evenly distribute the wheel pressure of the trolley, a counterweight is set on the side of the trolley opposite to the auxiliary grab 4 to prevent the trolley running mechanism 9 from slipping when starting.

[0053] The trolley running mechanism 9 is a driving mechanism for driving the frame body 1 to move along the track 2. The frame body 1 can be connected to the track 2 through rollers, and the frame body 1 moves along the track 2 driven by the motor. The trolley running mechanism 9 can also be other structures, such as a synchronous belt, etc., which are not limited.

[0054] In order to meet the requirement of grabbing materials of different properties at the same material level, this embodiment installs two different lifting mechanisms on the same crane trolley, and is equipped with different types of grabs. The two different grabs are used to achieve different lifting requirements and meet the requirements of grabbing two materials of different properties. The crane trolley provided by this embodiment achieves different lifting by using two different grabs at the same material level, meets different grabbing requirements, improves productivity, and provides a powerful supplement to the traditional in-rail lifting method.

[0055] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A crane trolley, comprising a frame body, a main grab, a grab frame, a main lifting mechanism and an auxiliary lifting mechanism, wherein the bottom two sides of the frame body are movably connected to the track respectively, and the main grab is connected to the frame body between the two side tracks, It is characterized in that Also includes: Auxiliary grab bucket; An auxiliary grab is provided on one or both sides of the frame body, the auxiliary grab is located outside the track, and the auxiliary grab is different from the main grab; The grab frame is arranged above the lifting path of the auxiliary grab and below the frame body, and the auxiliary grab passes through the inside of the grab frame; the grab frame is a frame structure and at least the bottom is open; the grab frame is fixedly arranged below the frame body; The main lifting mechanism is arranged at the part of the frame body between the two side rails, and the main lifting mechanism is connected to the main grab; the auxiliary lifting mechanism is arranged at the part of the frame body outside the rails, and the auxiliary lifting mechanism is connected to the auxiliary grab; A plurality of fixing blocks are provided on the inner side of the bottom of the grab frame along the circumferential direction; The main grab bucket and the auxiliary grab bucket are staggered in the length direction of the track.

2. The crane trolley according to claim 1, It is characterized in that The auxiliary lifting mechanism comprises a winch, and the winch of the auxiliary lifting mechanism is arranged along the length direction of the track.

3. The crane trolley according to claim 1, It is characterized in that When an auxiliary grab bucket is provided on one side of the frame body, a counterweight block is provided on the other side of the frame body.

4. The crane trolley according to claim 1, It is characterized in that The auxiliary lifting mechanism is connected to the auxiliary grab bucket through at least two steel wire ropes, and the at least two steel wire ropes are arranged in parallel along the length direction of the track.

5. A lifting system, It is characterized in that It comprises the crane trolley as described in any one of claims 1 to 4 above.

6. A lifting method based on the crane trolley according to any one of claims 1 to 4 above, It is characterized in that include: Use the main grab bucket and auxiliary grab bucket to grab different materials alternately; When the main grab bucket is working, the auxiliary grab bucket is lifted and stored in the grab bucket frame, and the auxiliary grab bucket is opened so that the bucket body of the auxiliary grab bucket abuts against the fixed block; When the auxiliary grab is working, close the main grab and lift it to a safe height.