Urban underground river desilting system and desilting method using the system
By setting up interception cofferdams and operating foundations in urban underground rivers, combined with excavators and hydraulic dilution equipment, the problems of small space and high risk in underground river dredging construction have been solved, and safe and efficient dredging and garbage sludge separation have been achieved. , improving construction organization and environmental protection.
Patent Information
- Application Number
- CN201910794335.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-08-27
- Publication Date
- 2024-10-08
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In urban underground river dredging construction, the working space is small, the work is highly dangerous, the construction organization is difficult, and there is a lack of systematic complete set of construction methods.
Provide urban underground river desilting system, including setting up interception cofferdams, initial operation foundations and circulation unit operation foundations, using excavators, mud pits, mud pumps and mud conveying pipelines to remove and transport garbage and silt, combined with hydraulic dilution equipment and Steel gratings are used to intercept and separate garbage, and sodium hypochlorite solution is used for disinfection and fan ventilation to gradually promote zoning construction.
Achieve comprehensive disinfection, sterilization and ventilation in a limited space to ensure safe operations, complete desilting and dredging quickly and flexibly, realize step-by-step classification of garbage and silt, improve construction efficiency and safety, and reduce costs and construction schedules.
Smart Images

Figure CN110528612B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of urban underground river dredging, in particular to an urban underground river dredging system and a method for dredging using the system. Background Art
[0002] With the rapid expansion of cities, many rivers in old urban areas of China are covered by buildings or structures to form underground rivers. As the main channel for urban flood discharge and drainage, rivers must be regularly cleaned of silt and floating objects to ensure their flood discharge capacity. Once rivers are seriously silted up and flood discharge is blocked, urban waterlogging will occur, endangering the personal and property safety of surrounding residents.
[0003] River dredging is one of the means of river management. The main problems in urban underground river dredging construction are: first, the operating space for underground river construction is limited, and conventional dredging methods are difficult to implement effectively; second, the space is closed and filled with a large amount of toxic and harmful gases, silt mixed with a large amount of domestic garbage and debris; third, the construction work is highly dangerous; fourth, the industry lacks a systematic set of construction methods. Summary of the invention
[0004] The purpose of the present invention is to provide a city underground river dredging system and a method for dredging using the system, in order to solve the technical problems of small working space, high degree of operational risk and difficult construction organization in the current city underground river dredging construction.
[0005] To achieve the above-mentioned purpose, the present invention adopts the following technical scheme: The present invention provides a system for desilting an underground river in a city, the desilting system comprising a dam arranged at the end of the underground river, an operating foundation, an excavator 3 working on the operating foundation, a trolley 6 for removing garbage, a mud pit 7, a mud pump 4 and a mud delivery pipeline 8,
[0006] The working foundation includes a starting working foundation 1 and a circulation unit working foundation 2. The starting working foundation 1 is rectangular, and the left long side of the rectangle is fitted on the diversion cofferdam, and a group of short sides of the rectangle are respectively set on the riverbanks on both sides of the underground river; the circulation unit working foundation 2 is set on the right side of the starting working foundation 1, and a mud pit 7 is reserved in the circulation unit working foundation 2. The cross-section of the mud pit 7 is rectangular, and the long side direction of the mud pit 7 is the same as the direction of the underground river. Steel grilles 9 are set on the three edges of the mud pit 7 away from the starting working foundation 1; the mud pump 4 is set in the mud pit 7, one end of the mud pipeline 8 is connected to the mud pump 4, and the other end of the mud pipeline 8 leads to the sludge dehydration and solidification field.
[0007] Furthermore, the starting working foundation 1 and the circulating unit working foundation 2 are both composed of crushed stone.
[0008] Furthermore, the length of the starting working foundation 1 is adapted to the width of the underground river, and the width of the starting working foundation 1 is at least 5m.
[0009] Furthermore, a gap is left between the circulation unit operation foundation 2 and the rectangular long side of the mud pit 7 .
[0010] Furthermore, it also includes hydraulic dilution equipment, which can be a high-pressure water gun.
[0011] Another aspect of the present invention provides a method for dredging and silting using the above-mentioned urban underground river silt removal system, the method comprising the following steps:
[0012] Step 1: Spray sodium hypochlorite solution on the underground river to be desilted to carry out comprehensive disinfection and sterilization;
[0013] Step 2: Use fans to ventilate the disinfected underground river in the city, and test the concentration of toxic and harmful gases in the river every 30 minutes. When the test results meet the relevant national safety regulations, start the next step of construction;
[0014] Step 3: Underground river dredging construction:
[0015] s1, build a cofferdam at the end of the underground river to intercept the flow;
[0016] s2, fill and pave a starting working foundation 1 with a width of at least 5m for the excavator 3 to enter the construction site, clean out a mud pit 7 with a depth of not less than 40cm in the middle of the starting working foundation 1, away from the end of the dark river, and use the excavator 3 to assist in cleaning the mud pit 7;
[0017] In order to facilitate the hydraulic flushing and excavation construction, the mud pit 7 is preferably arranged on the left side of the hydraulic flushing and excavation area.
[0018] s3, process the area of the cycle unit operation foundation 2; use manual labor and excavator 3 to clean up the garbage and debris accumulated in the area 3m wide on the right side of the starting operation foundation 1;
[0019] s4, through hydraulic excavation, the silt in the rectangular area of the circulation unit operation foundation 2 is converted into mud and collected in the mud pit 7;
[0020] s5, a steel grille 9 is set at the three edges of the mud pit 7 away from the starting working foundation 1, and the steel grille 9 is used to intercept garbage and debris in the sludge;
[0021] s6, manual dredging and small transport vehicle 6 are used to collect and transport the garbage and debris to the garbage treatment center;
[0022] s7, using a mud pump 4 disposed in the mud pit 7, the sludge in the mud pit 7 is pumped through a mud delivery pipeline 8 to a sludge dehydration and solidification area for dehydration and solidification treatment;
[0023] s8, the area of the base 2 of the cycle unit operation is filled with crushed stone;
[0024] s9, the mud pit 7 set in the starting working foundation 1 is advanced to the right along the central axis of the underground river;
[0025] s10, repeat s3-s9 until the end of the dark river.
[0026] Furthermore, in step one, the concentration of the sodium hypochlorite solution is 10%, and the volume of the water body sprayed with 1 t of the solution is not greater than 500 m³.
[0027] Furthermore, during construction, 12V low-voltage moisture-proof and explosion-proof lamps are used for lighting, and are arranged every 20 meters.
[0028] Furthermore, the length of the mud pit 7 is adapted to the width of the circulation unit operation foundation 2 .
[0029] Furthermore, the width of the circulation unit operation foundation 2 is 2.5m-3m.
[0030] Furthermore, there are at least two excavators 3 and at least four trolleys 6 for removing garbage.
[0031] The beneficial effects of the present invention are embodied in:
[0032] 1. The urban underground river desilting system and the method for desilting and dredging using the system provided by the present invention can complete the desilting and dredging construction of the underground river in a limited space, carry out comprehensive disinfection, sterilization and ventilation of the underground river, and monitor the gas in the underground river space throughout the construction process, thereby avoiding the threat of toxic and harmful gases to the personal safety of operators.
[0033] 2. The urban underground river desilting system and the method for desilting and dredging using the system provided by the present invention adopt manual operation in cooperation with a small excavator, a transport tricycle, and hydraulic flushing and excavation to carry out the operation. The construction organization is rapid, flexible and orderly, which solves the problems of limited underground river space, inaccessibility of large machinery, and difficulty in construction organization.
[0034] 3. Use grid interception and manual dredging to separate garbage and debris from riverbed sludge, so as to achieve step-by-step classification and treatment of garbage and sludge, making the treatment method more targeted and environmentally friendly.
[0035] 4. Divide the river channel into 2.5m wide strips along its length for zoned construction, gradually advance forward, and fill the dredged areas with gravel as the basis for mechanical movement, which improves construction efficiency and enhances organizational order.
[0036] The construction method provided by the invention has controllable cost, short construction period, good effect and good promotional potential.
[0037] Other features and advantages of the present invention will be described in the following description, and partly become obvious from the description, or be understood by practicing the present invention. The main purpose and other advantages of the present invention can be realized and obtained by the schemes particularly pointed out in the description. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] The present invention will be further described in detail below in conjunction with the accompanying drawings.
[0039] Figure 1 It is a schematic diagram of step three S2 of the present invention.
[0040] Figure 2 It is a schematic diagram of the mud pit advancing to the right in step three of the present invention.
[0041] Figure 3 It is a schematic diagram of the foundation for the second application of the cycle unit operation.
[0042] Figure 4 This is a schematic diagram of the foundation for the third application of the cycle unit operation.
[0043] Figure numerals: 1-starting operation basis, 2-circulation unit operation basis, 3-excavator, 4-mud pump, 5-undrained area, 6-tricycle, 7-mud pit, 8-mud pipeline, 9-steel grille. DETAILED DESCRIPTION
[0044] The technical solution of the present invention is described in detail below through examples. The following examples are merely exemplary and can only be used to explain and illustrate the technical solution of the present invention, but cannot be interpreted as limiting the technical solution of the present invention. Example
[0045] It is mainly aimed at the construction organization method and comprehensive construction technology of the limited space of urban underground rivers: first, the underground river is thoroughly disinfected, sterilized, ventilated and gas detected to ensure the safety of the operation; then manual work is combined with small machinery and hydraulic flushing to separate garbage and debris from the riverbed silt, so as to realize the step-by-step classification and treatment of garbage and silt, and the treatment method is more targeted and environmentally friendly; the river channel is divided into multiple rectangular areas along the length direction for zoned construction, which is gradually advanced, and the areas where dredging has been completed are filled with gravel to facilitate mechanical operations, so as to complete the dredging construction of the underground river safely, orderly and efficiently.
[0046] Specifically: The present invention provides an urban underground river dredging system, which includes a diversion cofferdam arranged at the end of the underground river, an operating foundation, an excavator 3 working on the operating foundation, a trolley 6 for transporting garbage, a mud pit 7, a mud pump 4 and a mud delivery pipeline 8.
[0047] like Figure 1As shown, the working foundation includes a starting working foundation 1 and a circulating unit working foundation 2. The starting working foundation 1 is rectangular, the long side of the left side of the rectangle is set on the interception cofferdam, and a group of short sides of the rectangle are set on the riverbanks on both sides of the underground river; the circulating unit working foundation 2 is set on the right side of the starting working foundation 1, and a mud pit 7 is reserved in the circulating unit working foundation 2. The cross section of the mud pit 7 is rectangular, and the long side direction of the mud pit 7 is the same as the direction of the underground river. The three edges of the mud pit 7 away from the starting working foundation 1 are provided with steel grilles 9; the mud pump 4 is set in the mud pit 7, one end of the mud pipeline 8 is connected to the mud pump 4, and the other end of the mud pipeline 8 leads to the sludge dehydration and solidification field. There is a gap between the circulating unit working foundation 2 and the rectangular long side of the mud pit 7.
[0048] The mud pit 7 has a rectangular cross section, and the long side direction of the mud pit 7 is the same as the direction of the underground river. There are two circulation unit operation foundations 2 and they are symmetrically arranged on a set of long sides of the mud pit 7. The three edges of the mud pit 7 away from the starting operation foundation 1 are provided with steel grilles 9. The length of the starting operation foundation 1 is adapted to the width of the underground river, and the width of the starting operation foundation 1 is at least 5m. It also includes hydraulic dilution equipment, such as a high-pressure water gun.
[0049] The above-mentioned urban underground river desilting system performs desilting and dredging, and the method comprises the following steps:
[0050] like Figure 1 As shown, step one is to spray sodium hypochlorite solution to disinfect and sterilize the underground urban river to be dredged; the concentration of sodium hypochlorite solution is 10%, and the volume of water sprayed with 1t solution is no more than 500m³. During the construction period, 12V low-voltage moisture-proof and explosion-proof lamps are used for lighting, and one is arranged every 20 meters.
[0051] Step 2: Use fans to ventilate the disinfected underground river in the city, and test the concentration of toxic and harmful gases in the river every 30 minutes. When the test results meet the relevant national safety regulations, start the next step of construction;
[0052] Step 3: Underground river dredging construction:
[0053] s1. Build a cofferdam at the end of the underground river to intercept the flow; the cofferdam can also be a water-stopping curtain, similar to a rubber dam or an earth dam.
[0054] s2, fill and pave a starting working foundation 1 with a width of at least 5m for the excavator 3 to enter the construction site, clean out a mud pit 7 with a depth of not less than 40cm in the middle of the starting working foundation 1, away from the end of the dark river, and use the excavator 3 to assist in cleaning the mud pit 7;
[0055] In order to facilitate the hydraulic flushing and excavation construction, the mud pit 7 is preferably arranged on the left side of the hydraulic flushing and excavation area.
[0056] s3, process the area of the cycle unit operation foundation 2; use manual labor and excavator 3 to clean up the garbage and debris accumulated in the area 3m wide on the right side of the starting operation foundation 1;
[0057] s4, through hydraulic excavation, the silt in the rectangular area of the circulation unit operation foundation 2 is converted into mud and collected in the mud pit 7;
[0058] s5, a steel grille 9 is set at the three edges of the mud pit 7 away from the starting working foundation 1, and the steel grille 9 is used to intercept garbage and debris in the sludge;
[0059] s6, manual dredging and small transport vehicle 6 are used to collect and transport the garbage and debris to the garbage treatment center;
[0060] s7, using a mud pump 4 disposed in the mud pit 7, the sludge in the mud pit 7 is pumped through a mud delivery pipeline 8 to a sludge dehydration and solidification area for dehydration and solidification treatment;
[0061] s8, the area of the base 2 of the cycle unit operation is filled with crushed stone;
[0062] like Figure 2 As shown, s9, the mud pit 7 set in the starting working foundation 1 is pushed to the right along the central axis of the underground river. At this time, the mud pit 7 is set at the midpoint of the right long side of the starting working foundation 1, that is, the old mud pit 7 in the area of the starting working foundation 1 is filled with gravel, and at the same time, a new mud pit 7 is dug in the circulating unit working foundation 2, and the mud pit 7 is pushed to the right along the central axis of the underground river.
[0063] The mud pump 4 is arranged in the mud pit 7, one end of the mud delivery pipeline 8 is connected to the mud pump 4, and the other end of the mud delivery pipeline 8 leads to the mud dehydration and solidification field; there is a gap between the circulation unit operation foundation 2 and the rectangular long side of the mud pit 7. The cross section of the mud pit 7 is rectangular, and the direction of the long side of the mud pit 7 is the same as the direction of the underground river. The circulation unit operation foundation 2 has two pieces and is symmetrically arranged on a set of long sides of the mud pit 7. The three edges of the mud pit 7 away from the starting operation foundation 1 are provided with steel grilles 9.
[0064] The length of the mud pit 7 is adapted to the width of the circulating unit operation base 2. The width of the circulating unit operation base 2 is 2.5m-3m. The excavator 3 moves from the starting operation base 1 to the circulating unit operation base 2, and the garbage removal vehicle 6 also moves to the circulating unit operation base 2 to start the construction work of the un-dredged area 5.
[0065] See also Figure 3 and Figure 4 As shown. S10, repeat S3-S9 until the end of the dark river.
[0066] There are at least two excavators 3 and at least four garbage removal vehicles 6. The number of excavators 3, the number of garbage removal vehicles 6, and the number of mud pits 7 can be flexibly adjusted according to the confluence width and the number of pollutants.
[0067] Through the above method, the air quality inside the underground river space can be monitored throughout the construction process, ensuring the safety of the workers. At the same time, the silt and garbage are separated by manual cooperation with the small excavator 3 and the steel grid 9 net interception, and the classification and treatment of different pollutants are achieved, ensuring environmentally friendly construction and solving the problem of limited underground river space and inconvenient access for large machinery and equipment. In addition, the river channel is divided horizontally into multiple rectangular circulation unit operation foundation 2 areas for zoning construction, gradually moving forward, and filling the dredged areas with gravel to facilitate mechanical operations and improve construction efficiency.
[0068] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that a technician familiar with the technical field can think of within the technical scope disclosed in the present invention should be covered within the protection scope of the present invention.
Claims
1. A method of dredging using an urban underground river dredging system, characterized in that: The desilting system comprises a dam arranged at the end of an underground river, an operating foundation, an excavator (3) working on the operating foundation, a trolley (6) for removing garbage, a mud pit (7), a mud pump (4) and a mud delivery pipeline (8). The working foundation comprises a starting working foundation (1) and a circulating unit working foundation (2). The starting working foundation (1) is rectangular, the left long side of the rectangle is fitted on the interception cofferdam, and a group of short sides of the rectangle are respectively arranged on the riverbanks on both sides of the underground river; the circulating unit working foundation (2) is arranged on the right side of the starting working foundation (1), and a mud pit (7) is reserved in the circulating unit working foundation (2). The cross section of the mud pit (7) is rectangular, and the long side direction of the mud pit (7) is the same as the direction of the underground river. The three edges of the mud pit (7) away from the starting working foundation (1) are provided with steel grilles ( 9); a mud pump (4) is arranged in a mud pit (7); one end of a mud delivery pipeline (8) is connected to the mud pump (4); the other end of the mud delivery pipeline (8) leads to a sludge dehydration and solidification field; the starting operation foundation (1) and the circulation unit operation foundation (2) are both composed of crushed stones; the length of the mud pit (7) is adapted to the width of the circulation unit operation foundation (2); the length of the starting operation foundation (1) is adapted to the width of the underground river, and the width of the starting operation foundation (1) is at least 5m; a gap is left between the circulation unit operation foundation (2) and the rectangular long side of the mud pit (7); The method comprises the following steps: Step 1: Spray sodium hypochlorite solution on the underground river to be desilted to carry out comprehensive disinfection and sterilization; Step 2: Use fans to ventilate the disinfected underground river in the city, and test the concentration of toxic and harmful gases in the river every 30 minutes. When the test results meet the relevant national safety regulations, start the next step of construction; Step 3: Underground river dredging construction: s1, build a cofferdam at the end of the underground river to intercept the flow; s2, using crushed stones to form a starting working foundation (1) with a width of at least 5m for the excavator (3) to enter the construction site, clearing a mud pit (7) with a depth of not less than 40cm in the middle of the starting working foundation (1) and the side away from the end of the underground river, and using the excavator (3) to assist in clearing the mud pit (7); s3, process the area of the cycle unit operation foundation (2); use manual labor and excavator (3) to clean up the garbage and debris accumulated in the area 3m wide on the right side of the starting operation foundation (1); s4, through hydraulic excavation, the silt in the rectangular area of the circulation unit operation foundation (2) is converted into mud and collected in the mud pit (7); s5, setting steel grilles (9) at the three edges of the mud pit (7) away from the starting operation foundation (1), and the steel grilles (9) are used to intercept garbage and debris in the sludge; s6, manual cleaning and small transport vehicles (6) are used to collect and transport the garbage and debris to the garbage treatment center; s7, using a mud pump (4) disposed in the mud pit (7), the sludge in the mud pit (7) is pumped through a mud delivery pipeline (8) to a sludge dehydration and solidification area for dehydration and solidification treatment; s8, the area of the cycle unit operation foundation (2) is filled with crushed stone; s9, a mud pit (7) is set in the initial working foundation (1), and is advanced to the right along the central axis of the underground river; s10, repeat s3-s9 until the end of the dark river.
2. The method according to claim 1, characterized in that: In step 1, the concentration of sodium hypochlorite solution is 10%, and the volume of water sprayed with 1 t of solution is not more than 500 m³.
3. The method according to claim 1, characterized in that: During construction, 12V low-voltage moisture-proof and explosion-proof lamps are used for lighting, and are arranged every 20 meters.
4. The method according to claim 1, characterized in that: The width of the circulation unit operation foundation (2) is 2.5m-3m.
5. The method according to claim 1, characterized in that: There are at least two excavators (3); and at least four trolleys (6) for removing garbage.