Flexible anti-collision wall of water bridge and construction method thereof

By using flexible collision walls in bridge navigation, using steel sheet pile cofferdams and lightweight high-strength fills to reduce the self-weight and construction load of the collision wall, the problems of high construction costs and large loads during bridge navigation are solved, and the impact of high construction costs and large loads of the collision walls in bridge navigation are achieved. Cost and technical advantages.

CN110578320BActive Publication Date: 2024-11-19HENAN GUXUAN CONSTRUCTION ENGINEERING CO LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN201910925924.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-09-27
Publication Date
2024-11-19
Estimated Expiration
2039-09-27

AI Technical Summary

Technical Problem

The construction cost of anti-collision walls during bridge navigation is high, and the traditional anti-collision steel case causes excessive construction load and negative friction resistance to the bridge pier bearing platform when it is lowered, affecting the stress of the bridge pier.

Method used

Flexible anti-collision walls of water bridges, including steel sheet pile cofferdams, anti-collision steel structures and lightweight high-strength fillings, the self-weight weight is reduced through fixed support of steel sheet pile cofferdams, lightweight high-strength fillings, and the anti-collision steel structure is lowered through floating hanging , reduce construction load and material use.

Benefits of technology

The self-weight of the anti-collision wall is reduced, the load and construction difficulty of the bridge pier bearing platform are reduced, the cost advantage is achieved, and the economic benefits are further improved through the recycling and utilization of steel sheet pile cofferdams.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110578320B_ABST
    Figure CN110578320B_ABST
Patent Text Reader

Abstract

The present invention relates to a flexible anti-collision wall for bridges in water areas, including a steel sheet pile cofferdam, a bridge pier cap, a support, a concrete bottom seal, an expansion bolt, a light high-strength filler, an anti-collision steel structure and an anti-collision mark; the anti-collision steel structure is fixed to the periphery of the bridge pier cap, and the anti-collision steel structure is mainly composed of a single-frame frame, a connecting beam and an anti-collision ring beam; the single-frame frame is fixed to the bridge pier cap by expansion bolts, the anti-collision ring beam is fixed to the outside of the single-frame frame, and adjacent single-frame frames are connected by connecting beams; the single-frame frame is composed of a connecting plate, a cross bar, a vertical bar, an intermediate diagonal bar and a bottom diagonal bar. The beneficial effects of the present invention are as follows: the present invention is suitable for the construction of anti-collision walls of bridge pier caps at the navigation site of bridges in rivers, lakes and seas, and is composed of a steel sheet pile cofferdam, an anti-collision steel structure and a light high-strength filler, and the setting of the steel sheet pile cofferdam does not require the erection of temporary supports and auxiliary trestles around the bridge piers, and will not bring additional construction loads to the bearing force of the bridge piers, and the technical benefits are obvious.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a flexible anti-collision wall, and in particular to a flexible anti-collision wall for a bridge in a water navigation environment and a construction method thereof. Background Art

[0002] With the rapid development of the national economy, more and more long-span bridges are being built in rivers, lakes and seas. Integral anti-collision steel casings are usually used to protect bridge piers and abutments during navigation. The steel casings are usually lowered by large floating cranes, which has high construction costs. The larger the tonnage of the anti-collision steel casings, the larger the large floating crane vessels required, which further increases the cost.

[0003] During construction, traditional anti-collision steel casings require the construction of support systems and auxiliary trestles around the pier caps in advance, which not only increases construction costs but also brings additional construction loads to the piers, increasing the stress burden on the piers. The larger the tonnage of the hoisted anti-collision steel casing, the heavier the burden will be, and sometimes it will even be accompanied by the generation of negative friction.

[0004] The patent number is CN107245949A, and the name is "Construction method of prefabricated middle anti-collision wall in urban bridges". It uses concrete beam embedded parts to install and prefabricate the middle anti-collision wall in the factory to reduce construction links and ensure construction efficiency. However, the patent is composed of cast box beams, concrete beam embedded parts and prefabricated middle anti-collision walls, which require large floating cranes to lower, and all materials are made of concrete.

[0005] The patent number is CN207143726U, and the name is "FRP flexible anti-collision wall bridge guardrail". It uses FRP flexible thin shell block components to reduce the negative impact of the heavy weight of concrete wall guardrails.

[0006] Therefore, it is very important to build crash barriers in bridge construction under the premise of high efficiency and environmental protection. Summary of the invention

[0007] The present invention mainly aims at the problems of high construction cost and large construction load in the construction of crash barriers, and provides a flexible crash barrier for water bridges and a construction method thereof, which can reduce the dead weight of the crash barrier, reduce the excessive load or negative friction caused to the bridge pier cap, and at the same time recycle the building materials, reduce the construction difficulty, achieve technical progress, and realize cost advantages.

[0008] The flexible anti-collision wall of a bridge in water area comprises a steel sheet pile cofferdam, a pier cap, a support, a concrete bottom seal, expansion bolts, a lightweight high-strength filler, an anti-collision steel structure and an anti-collision mark; the anti-collision steel structure is fixed around the pier cap, and is mainly composed of a single-frame frame, a connecting beam and an anti-collision ring beam; the single-frame frame is fixed to the pier cap by expansion bolts, the anti-collision ring beam is fixed to the outer side of the single-frame frame, and adjacent single-frame frames are connected by connecting beams; the single-frame frame is composed of a connecting plate, a cross bar, a vertical bar, an intermediate diagonal bar and a bottom diagonal bar, the connecting plate is provided with bolt holes and is fixed to the pier cap by expansion bolts; a support is built between the steel sheet pile cofferdam and the pier cap, and a concrete bottom seal is provided in the internal space formed by the steel sheet pile cofferdam; the lightweight high-strength filler is filled in the space formed by the steel sheet pile cofferdam, the pier cap, the support and the concrete bottom seal; an anti-collision mark is provided on the lightweight high-strength filler.

[0009] As a preferred embodiment: the connecting plate is fixed to the pier cap by expansion bolts and nuts, the upper end of the connecting plate is connected to the cross bar, and the cross bar is vertically connected to the vertical bar; one end of the bottom diagonal bar is connected to the bottom end of the vertical bar, and the other end is connected to the bottom end of the connecting plate; one end of the middle diagonal bar is connected to the upper end of the connecting plate, and the other end is connected to the bottom end of the vertical bar.

[0010] Preferably, the lightweight and high-strength filler is foam concrete, lightweight concrete, EPS or fiber-reinforced composite material.

[0011] As a preferred embodiment: the anti-collision ring beam is composed of two anti-collision half circles, which are welded to a single frame, and the two anti-collision ring beams are respectively located at the upper and lower ends of the vertical rod.

[0012] The construction method of the flexible anti-collision wall of the water bridge comprises the following steps:

[0013] 1) Static pressure is used to drive a steel sheet pile cofferdam around the bridge pier cap in the water area, where the steel sheet piles are driven to a certain depth on the land bed;

[0014] 2) After the steel sheet pile cofferdam is built, support is set between the steel sheet pile cofferdam and the bridge pier cap;

[0015] 3) Drain the water in the space enclosed by the steel sheet pile cofferdam and the bridge pier cap, and set a concrete bottom seal at the bottom of the land bed;

[0016] 4) After the concrete bottom is sealed, three circles of expansion bolts are evenly planted around the pier cap according to the height structure of the bottom. The bolt spacing of the upper two circles is smaller, while the bolt spacing of the lower two circles is larger.

[0017] 5) Fix the connection plate with bolt holes on the pier cap by expansion bolts, weld the connection plate to the crossbar, bottom diagonal bar, vertical bar and middle diagonal bar in sequence, assemble the above components into a single frame, and weld the connecting beams between adjacent single frames to make them a whole;

[0018] 6) The four anti-collision half circles are lowered to the concrete bottom by floating crane, and then hoisted and welded to the single frame to assemble into an anti-collision ring beam. The anti-collision steel structure is composed of a single frame, a connecting beam and an anti-collision ring beam;

[0019] 7) Anti-corrosion treatment is carried out on the anti-collision steel structure, and other parts that need anti-corrosion are also treated to a certain extent;

[0020] 8) Pour lightweight high-strength filler into the space enclosed by the steel sheet pile cofferdam and the bridge pier cap. The pouring height of the lightweight high-strength filler reaches the top of the bridge pier cap, so that the entire anti-collision steel structure is wrapped in the lightweight high-strength filler;

[0021] 9) Remove the supports and steel sheet pile cofferdams, and set anti-collision marks on the lightweight and high-strength filling materials to complete the construction of the flexible anti-collision wall of the water bridge.

[0022] The beneficial effects of the present invention are:

[0023] (1) The present invention is suitable for the construction of anti-collision walls at pier foundations at the navigation sites of bridges in rivers, lakes and seas. It is composed of a steel sheet pile cofferdam, an anti-collision steel structure and a lightweight high-strength filler. The setting of the steel sheet pile cofferdam does not require the construction of temporary supports and auxiliary trestles around the piers, and will not bring additional construction loads to the bearing force of the piers. The technical benefits are obvious.

[0024] (2) Using lightweight and high-strength materials as fillers instead of traditional concrete materials greatly reduces the deadweight of the flexible crash barrier and will not cause excessive load or negative friction on the bridge pier cap.

[0025] (3) Replacing the traditional large-tonnage anti-collision steel casing with flexible anti-collision walls not only reduces the construction difficulty but also greatly reduces the construction cost, with obvious economic benefits.

[0026] (4) The steel sheet pile cofferdam used can be recycled and reused after the construction is completed, further enhancing the economic benefits of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 This is a schematic diagram of the construction of a steel sheet pile cofferdam for a flexible crash wall of a bridge in waters;

[0028] Figure 2 This is a schematic diagram of the support construction of the flexible anti-collision wall of the water bridge;

[0029] Figure 3 This is a schematic diagram of the concrete bottom cover of the flexible anti-collision wall of the water bridge;

[0030] Figure 4 This is a schematic diagram of the expansion bolt implantation of the flexible anti-collision wall of the water bridge;

[0031] Figure 5 A top view of the anti-collision steel structure of the flexible anti-collision wall of the water bridge;

[0032] Figure 6 This is the elevation drawing of the single frame installation of the flexible crash barrier of the water bridge;

[0033] Figure 7 This is an enlarged view of the details of a single frame of the flexible anti-collision wall of a water bridge;

[0034] Figure 8 Schematic diagram of pouring lightweight high-strength filling material for flexible crash barriers of bridges in water areas;

[0035] Fig. 9 Schematic diagram of the completed construction of the flexible crash barrier for water bridges.

[0036] Explanation of the reference numerals in the accompanying drawings: 1—steel sheet pile cofferdam; 2—bridge pier; 3—bridge pier cap; 4—water level; 5—land bed; 6—support; 7—concrete bottom seal; 8—expansion bolt; 9—single-frame frame; 10—cross bar; 11—vertical bar; 12—middle diagonal bar; 13—bottom diagonal bar; 14—anti-collision ring beam; 15—connecting plate; 16—lightweight and high-strength filler; 17—anti-collision steel structure; 18—anti-collision mark; 19—nut; 20—connecting beam. DETAILED DESCRIPTION

[0037] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for those of ordinary skill in the art, without departing from the principles of the present invention, several improvements and modifications may be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

[0038] like Figure 6 , Fig. 9 As shown, the flexible anti-collision wall of the water bridge comprises a steel sheet pile cofferdam 1, a single frame 9 composed of a connecting plate 15, a horizontal bar 10, a vertical bar 11, an intermediate diagonal bar 12 and a bottom diagonal bar 13, a connecting beam 20 connecting adjacent single frames 9, an anti-collision ring beam 14 fixed on the outside of the single frame 9, a support 6 for maintaining the lateral stability of the steel sheet pile cofferdam, a bottom sealing concrete 7, a lightweight high-strength filler 16, and an anti-collision mark 18. The wall is formed by arranging an anti-collision steel structure 17 in the area enclosed by the steel sheet pile cofferdam 1 and pouring the lightweight high-strength filler 16.

[0039] like Figure 1 As shown, a steel sheet pile cofferdam 1 (the steel sheet pile cofferdam 1 can be recycled and reused) is statically driven around the pier cap 3 in the water area, wherein the steel sheet piles should be driven to a certain depth of the land bed 5 to play a water-blocking role and facilitate the subsequent construction.

[0040] like Figure 2As shown, after the steel sheet pile cofferdam 1 is driven, a support 6 is arranged between the steel sheet pile cofferdam 1 and the pier cap 3 to ensure the lateral stability of the steel sheet cofferdam 1 .

[0041] like Figure 3 As shown, the water in the space enclosed by the steel sheet pile cofferdam 1 and the pier cap 3 is drained, and poured concrete 7 is arranged at the bottom of the land bed 5. The thickness of the formed concrete bottom seal 7 can meet the requirements of normal construction operations, and can be used as a construction platform and provide functions such as scaffolding in the later stage.

[0042] like Figure 4 As shown, after the concrete bottom seal 7 is completed, three circles of large expansion bolts 8 are evenly implanted around the pier cap 3 according to the height structure of the bottom seal, which are used to fix the pier cap 3 and the connecting plate 15; due to the large bending moment in the upper part, when implanting the expansion bolts 8, the bolt spacing of the upper two circles should be smaller, and the bolt spacing of the lower two circles should be larger.

[0043] like Figure 5-7 As shown, a connecting plate 15 with bolt holes is fixed on the pier cap 3 by expansion bolts 8, and the connecting plate 15 is welded to the cross bar 10, the bottom diagonal bar 13, the vertical bar 11, and the middle diagonal bar 12 in sequence by welding technology, and the above components are welded and assembled into a single-frame frame 9, and a connecting beam 20 is welded between adjacent single-frame frames 9 to make them a whole, thereby enhancing the anti-collision effect; four anti-collision half circles are lowered onto the concrete bottom 7 by floating cranes, and are welded to the single-frame frames 9 in batches to form an anti-collision ring beam 14 (in places with deeper waters, scaffolding can be built on the bottom concrete 7 to install the anti-collision ring beam 14); an anti-collision steel structure 17 is composed of the single-frame frame 9, the connecting beam 20 and the anti-collision ring beam 14; the anti-collision steel structure 17 is treated with anti-corrosion, and other components that need to be treated with anti-corrosion are also treated to extend the service life and improve safety.

[0044] like Figure 8 As shown, a lightweight high-strength filler 16 (which may be foamed concrete, lightweight concrete, EPS, fiber-reinforced composite materials, etc.) is poured into the space enclosed by the steel sheet pile cofferdam 1 and the bridge pier cap 3 to replace the traditional concrete material, reduce the deadweight of the flexible anti-collision wall of the water bridge, and reduce the load or negative friction caused to the bridge pier cap. The pouring height of the lightweight high-strength filler 16 is up to the top of the bridge pier cap 3, so that the entire anti-collision steel structure 17 is wrapped in the lightweight high-strength filler 16.

[0045] like Fig. 9 As shown, the support 6 and the steel sheet pile cofferdam 1 are removed, and the anti-collision mark 18 is set, completing the construction of the flexible anti-collision wall of the water bridge.

Claims

1. A construction method for a flexible anti-collision wall of a water bridge, characterized by: The invention comprises a steel sheet pile cofferdam (1), a bridge pier cap (3), a support (6), a concrete bottom seal (7), expansion bolts (8), a lightweight high-strength filler (16), an anti-collision steel structure (17) and an anti-collision mark (18); the anti-collision steel structure (17) is fixed to the periphery of the bridge pier cap (3), and the anti-collision steel structure (17) is mainly composed of a single-frame frame (9), a connecting beam (20) and an anti-collision ring beam (14); the single-frame frame (9) is fixed to the bridge pier cap (3) by means of expansion bolts (8), the anti-collision ring beam (14) is fixed to the outer side of the single-frame frame (9), and adjacent single-frame frames (9) are connected by means of a connecting beam (20); the single-frame frame (9) ) is composed of a connecting plate (15), a cross bar (10), a vertical bar (11), an intermediate diagonal bar (12) and a bottom diagonal bar (13); the connecting plate (15) is provided with bolt holes and is fixed to the pier cap (3) by expansion bolts (8); a support (6) is built between the steel sheet pile cofferdam (1) and the pier cap (3); a concrete bottom seal (7) is provided in the internal space formed by the steel sheet pile cofferdam (1); a light high-strength filler (16) is filled in the space formed by the steel sheet pile cofferdam (1), the pier cap (3), the support (6) and the concrete bottom seal (7); an anti-collision mark (18) is provided on the light high-strength filler (16); The steps include: 1) Static pressure driving a steel sheet pile cofferdam (1) around a bridge pier cap (3) in a water area, wherein the steel sheet piles are driven to a certain depth below the land bed (5); 2) After the steel sheet pile cofferdam (1) is installed, a support (6) is provided between the steel sheet pile cofferdam (1) and the bridge pier cap (3); 3) draining the water in the space enclosed by the steel sheet pile cofferdam (1) and the bridge pier cap (3), and setting a concrete bottom seal (7) at the bottom of the land bed (5); 4) After the concrete bottom seal (7) is completed, three circles of expansion bolts (8) are evenly implanted around the pier cap (3) according to the height structure of the bottom seal, wherein the bolt spacing of the upper two circles is smaller, and the bolt spacing of the lower two circles is larger; 5) fixing a connection plate (15) provided with bolt holes on the pier cap (3) by means of expansion bolts (8), welding the connection plate (15) to the crossbar (10), the bottom diagonal bar (13), the vertical bar (11) and the middle diagonal bar (12) in sequence, assembling the above components into a single frame (9), and welding a connecting beam (20) between adjacent single frames (9) to form a whole; 6) four anti-collision half circles are lowered onto the concrete bottom cover (7) by floating hoisting, and are hoisted and welded onto the single frame (9) in batches to form an anti-collision ring beam (14). The single frame (9), the connecting beam (20) and the anti-collision ring beam (14) form an anti-collision steel structure (17); 7) Anti-corrosion treatment is performed on the anti-collision steel structure (17), and other components that require anti-corrosion are also treated to a certain extent; 8) pouring a lightweight high-strength filler (16) into the space enclosed by the steel sheet pile cofferdam (1) and the bridge pier cap (3), wherein the pouring height of the lightweight high-strength filler (16) reaches the top of the bridge pier cap (3), so that the entire anti-collision steel structure (17) is wrapped in the lightweight high-strength filler (16); 9) The support (6) and the steel sheet pile cofferdam (1) are removed, and anti-collision marks (18) are set on the lightweight high-strength filler (16), thereby completing the construction of the flexible anti-collision wall of the water bridge.

2. The construction method of the flexible anti-collision wall of a water bridge according to claim 1 is characterized by: The connecting plate (15) is fixed to the pier cap (3) by means of expansion bolts (8) and nuts (19); the upper end of the connecting plate (15) is connected to the cross bar (10), and the cross bar (10) is vertically connected to the vertical bar (11); one end of the bottom diagonal bar (13) is connected to the bottom end of the vertical bar (11), and the other end is connected to the bottom end of the connecting plate (15); one end of the middle diagonal bar (12) is connected to the upper end of the connecting plate (15), and the other end is connected to the bottom end of the vertical bar (11).

3. The construction method of the flexible anti-collision wall of a water bridge according to claim 1 is characterized by: The light and high-strength filler (16) is foam concrete, lightweight concrete, EPS or fiber-reinforced composite material.

4. The construction method of the flexible anti-collision wall of a water bridge according to claim 1 is characterized by: The anti-collision ring beam (14) is composed of two anti-collision half circles and is welded to the single-frame frame (9). The two anti-collision ring beams (14) are respectively located at the upper and lower ends of the vertical rod (11).

Citation Information

Patent Citations

  • Construction method for application of assembled center anti-collision wall in urban bridge

    CN107245949A

  • FRP flexible anti -collision wall formula bridge railing

    CN207143726U

  • Cylindrical composite material bridge anti-collision device

    CN102535329A

  • FRP (Fiber Reinforce Plastic) and steel board combined type offshore collision preventing device

    CN107119634A

  • Protecting device for preventing falling rocks from colliding with bridge pier column

    CN203307721U