Prefabricated concrete foundation column structural system and construction method
By using structural reinforcement measures such as reserved ribs and shear nails between the prefabricated concrete columns and the cup-shaped foundation, the problem of insufficient structural strength in the existing technology is solved, and higher construction flexibility and structural stability are achieved.
Patent Information
- Application Number
- CN201911421520.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-12-31
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2039-12-31
AI Technical Summary
The structural strength between the existing prefabricated concrete columns and cup-shaped foundations is poor, and cannot be applied to situations where the process needs to be staggered, and the flexibility is poor.
The connection between the column and the cup-shaped foundation is strengthened by structures such as reserved ribs, shear nails, pipes, mounting plates and fixed ribs, and the structural strength is improved by concrete filling and vibration, and the reserved screws and welding fixing shear nails are used to simplify Installation and improve construction efficiency.
The structural strength and construction flexibility between the column and the cup-shaped foundation are significantly improved, the feasibility of phased construction is realized, and the construction efficiency and concrete pouring quality are improved.
Smart Images

Figure CN111042182B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to civil engineering, and in particular to an assembled concrete foundation column structural system and a construction method. Background Art
[0002] Cast-in-place concrete columns have the characteristics of beautiful structure, large bearing capacity and good overall performance. However, the upper and lower foundations of cast-in-place concrete columns need to be constructed at the same time and the processes cannot be staggered. Therefore, the construction requirements of cast-in-place concrete columns are relatively stringent, and they cannot be applied to situations where staggered processes are required, and their flexibility is poor.
[0003] The assembled concrete column can construct the upper and lower foundations of the concrete column at different times. The cup-shaped foundation, also known as the cup-shaped foundation, is a type of independent foundation. The assembled concrete column foundation construction system usually includes a column and a cup-shaped foundation, and concrete is filled between the column and the cup-shaped foundation. The technical defect of the assembled concrete column in the prior art is that the structural strength between the column and the cup-shaped foundation is poor. Summary of the invention
[0004] The purpose of the present invention is to solve at least one of the technical problems existing in the prior art and to provide a prefabricated concrete foundation column construction system and a construction method with good structural strength between the column and the cup-shaped foundation.
[0005] The technical solutions adopted to solve the above technical problems are:
[0006] The assembled concrete foundation column construction system includes:
[0007] A cup-shaped foundation, wherein a plurality of reserved ribs are arranged on the inner side of the cup-shaped foundation, and the reserved ribs protrude from the inner side of the cup-shaped foundation;
[0008] A column, wherein the column is set in the cup-shaped foundation, and the space between the column and the cup-shaped foundation is filled with concrete;
[0009] A plurality of mounting plates, the mounting plates covering the side surfaces of the columns, the mounting plates being provided with a plurality of shear nails, the roots of the shear nails intersecting with the mounting plates, and the ends of the shear nails extending outward from the columns;
[0010] A pipe is arranged in the column, the pipe intersects with the side surface of the column to form a first pipe opening, the pipe intersects with the end surface of the column to form a second pipe opening, and the first pipe opening is connected with the second pipe opening;
[0011] A plurality of grooves are arranged on the end surface of the column, each groove intersects with each side surface of the column respectively, and the second pipe opening is arranged in the groove, and the groove enables the second pipe opening to communicate with each side surface of the column respectively.
[0012] The above-mentioned assembled concrete foundation column construction system has at least the following beneficial effects:
[0013] The reserved reinforcement can strengthen the structural strength between the concrete and the cup-shaped foundation. The shear nails are conducive to strengthening the structural strength between the column and the concrete. The pipe allows the concrete to enter from the first pipe opening and exit from the second pipe opening, so that the concrete can easily fill the groove and the unevenness between the column and the cup-shaped foundation, which is conducive to strengthening the structural strength between the column and the cup-shaped foundation. A number of shear nails can be pre-welded on the mounting plate, and the shear nails can be fixed by fixing the mounting plate on the surface of the column, thereby making the connection operation between the shear nails and the column easier.
[0014] In a possible implementation of the present invention, the mounting plate is a steel plate, the roots of the shear nails intersect with the mounting plate, the shear nails are arranged in a rectangular array on the mounting plate, and the mounting plate covers the side of the column and the end of the groove. The shear nails are arranged in a rectangular array on the mounting plate, and multiple shear nails can be installed at one time by fixing the mounting plate on the column; the mounting plate can cover the end of the groove, which can prevent concrete from overflowing from the end of the groove to the periphery of the column.
[0015] In a possible implementation of the present invention, the mounting plate is a steel bar, at least two mounting plates are provided on each side of the column, at least two shear nails are provided on each mounting plate, and each shear nail is arranged in a linear array on the mounting plate. The mounting plate is a steel bar, and the shear nails are arranged in a linear array on the mounting plate, which is conducive to further simplifying the structure of the mounting plate and making the mounting plate easier to process and manufacture.
[0016] In a possible implementation of the present invention, the angle between the shear stud and the mounting plate is 45° to 90°. Adjusting the angle between the shear stud and the mounting plate can achieve different mechanical properties, thereby expanding the scope of application of the assembled concrete foundation column construction system.
[0017] In a possible implementation manner of the present invention, the structure of the mounting plate satisfies one of the following types:
[0018] Type 1: A plurality of reserved screws are provided on the side of the column, one end of the reserved screw is fixed on the column and the other end can pass through the mounting plate, and a nut is also provided on the reserved screw, which can be threadedly matched with the reserved screw to fix the mounting plate on the side of the column;
[0019] In type 2, the mounting plate covers the side of the column, and the edges of each mounting plate intersect at the ridge of the column, and the intersections between each mounting plate are fixed by welding. In type 1, the reserved screw can be directly inserted into the column, and the mounting plate can be fixed to the reserved screw by a nut, so that each shear nail is also fixed on the side of the column, which is conducive to simplifying the connection relationship between the shear nail and the column; the edges of the mounting plates in type 2 can be fixed to each other by welding, which can replace the nuts and reserved screws in type 1.
[0020] In a possible implementation of the present invention, a plurality of fixing ribs are further provided on the column, each fixing rib is fixed to the column by means of anchoring, and a bottom plate rib is further provided between the column and the cup-shaped foundation, one end of the bottom plate rib is inserted into the cup-shaped foundation and the other end intersects with the fixing rib. The intersection of the fixing rib and the bottom plate rib can further strengthen the structural strength between the column and the cup-shaped foundation, which is beneficial to improving the structural stability of the column.
[0021] In a possible implementation of the present invention, a plurality of annular steel bars are further provided on the column, each of which is sleeved outside the column and intersects with each fixed bar. The annular steel bars surround the column and intersect with the fixed bars, which is conducive to improving the structural stability of the column.
[0022] In a possible implementation of the present invention, a quick-closing net is further provided on the inner side of the cup-shaped foundation, which can strengthen the structural strength between the concrete and the cup-shaped foundation.
[0023] The construction method of the assembled concrete foundation column, based on the assembled concrete foundation column construction system, also includes the following steps:
[0024] Step A, reserving a cup-shaped pit at the construction site, pouring concrete on the side and bottom of the cup-shaped pit and inserting reserved reinforcement into the concrete, so that the cup-shaped pit forms a cup-shaped foundation;
[0025] Step B, draw positioning axes on the end face of the column and in the cup-shaped foundation respectively, put the column into the cup-shaped foundation, then check the alignment degree of the positioning axis on the column and the positioning axis in the cup-shaped foundation, and calibrate the verticality of the column with a plumb bob;
[0026] Step C, fixing the shear nails on the column;
[0027] Step D, pouring concrete into the first pipe opening, so that the concrete flows into between the column and the cup-shaped foundation through the pipe, the second pipe opening and the groove;
[0028] Step E, pouring concrete into the cup-shaped foundation so that the concrete fills around the column.
[0029] The assembled concrete foundation column construction method allows the cup-shaped foundation and the column to be constructed in stages, and the shear nails can be pre-fixed on the mounting plate. During the construction process, the mounting plate can be easily and quickly fixed to the column by the reserved screw rod, so that the shear nails are fixed to the column, which is conducive to preventing the shear nails from being damaged during the construction process and improving the construction efficiency.
[0030] In a possible implementation of the present invention, in step E, the concrete is vibrated while pouring the concrete into the cup-shaped foundation. Vibrating the concrete during the concrete pouring process can discharge the gas in the concrete mortar, which is beneficial to improving the pouring quality and the structural strength between the column and the cup-shaped foundation. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0032] Figure 1 This is a schematic diagram of the shape of the pipeline in Example 1 of the present invention;
[0033] Figure 2 This is a schematic diagram of the arrangement of the bottom plate ribs of Example 1 of the present invention;
[0034] Figure 3 It is a schematic diagram of the completed state of the assembled concrete foundation column construction system of Example 1 of the present invention;
[0035] Figure 4 This is a schematic diagram of the structure of a column according to Example 1 of the present invention;
[0036] Figure 5 This is a schematic diagram of the assembly state between the mounting plate and the column according to Embodiment 1 of the present invention;
[0037] Figure 6 For Example 1 of the present invention Figure 4 A top view of
[0038] Figure 7 For Example 1 of the present invention Figure 4 Bottom view of
[0039] Figure 8 It is a three-dimensional schematic diagram of a column according to Example 1 of the present invention;
[0040] Fig. 9 Schematic diagram of the relative position between the shear studs and the column in Example 2 of the present invention;
[0041] Fig.10 Schematic diagram of the relative position between the shear studs and the column in Example 3 of the present invention;
[0042] Reference numerals:
[0043] Cup-shaped foundation 1, reserved reinforcement 2, column 3, shear nail 4, pipe 5, first pipe opening 6, second pipe opening 7, groove 8, quick-closing net 9, mounting plate 10, annular reinforcement 11, fixing reinforcement 12, bottom plate reinforcement 13, reserved screw 14, nut 15. DETAILED DESCRIPTION
[0044] Embodiment 1:
[0045] This section will describe in detail the specific embodiments of the present invention. The preferred embodiments of the present invention are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the present invention, but it cannot be understood as a limitation on the scope of protection of the present invention.
[0046] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, etc., and orientations or positional relationships indicated are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0047] In the description of the present invention, "several" means one or more, "more" means more than two, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0048] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.
[0049] Reference Figures 1 to 8 , the prefabricated concrete foundation column construction system includes:
[0050] A cup-shaped foundation 1, wherein a plurality of reserved ribs 2 are arranged on the inner side of the cup-shaped foundation 1, and the reserved ribs 2 protrude from the inner side of the cup-shaped foundation 1;
[0051] A column 3, wherein the column 3 is arranged in the cup-shaped foundation 1, and the space between the column 3 and the cup-shaped foundation 1 is filled with concrete;
[0052] A plurality of mounting plates 10, the mounting plates 10 covering the side surfaces of the columns 3, the mounting plates 10 being provided with a plurality of shear nails 4, the roots of the shear nails 4 intersecting with the mounting plates 10, and the ends of the shear nails 4 extending outward from the columns 3;
[0053] Pipe 5, the pipe 5 is arranged in the column 3, the pipe 5 intersects with the side surface of the column 3 to form a first pipe opening 6, the pipe 5 intersects with the end surface of the column 3 to form a second pipe opening 7, and the first pipe opening 6 is connected to the second pipe opening 7;
[0054] A plurality of grooves 8 are provided on the end surface of the column 3 , each groove 8 intersects with each side surface of the column 3 , and the second pipe opening 7 is provided in the groove 8 , and the groove 8 enables the second pipe opening 7 to communicate with each side surface of the column 3 .
[0055] The above-mentioned assembled concrete foundation column construction system has at least the following beneficial effects:
[0056] The reserved reinforcement 2 can strengthen the structural strength between the concrete and the cup-shaped foundation 1. The shear nail 4 is conducive to strengthening the structural strength between the column 3 and the concrete. The pipe 5 allows the concrete to enter from the first pipe opening 6 and be discharged from the second pipe opening 7, so that the concrete can easily fill the groove 8 and the unevenness between the column 3 and the cup-shaped foundation 1, which is conducive to strengthening the structural strength between the column 3 and the cup-shaped foundation 1. A plurality of shear nails 4 can be pre-welded on the mounting plate 10, and the fixing of the shear nails 4 can be completed by fixing the mounting plate 10 on the surface of the column 3, thereby making the connection operation between the shear nails 4 and the column 3 easier.
[0057] Regarding the cup-shaped foundation 1, in the present embodiment, the cup-shaped foundation 1 is a truncated cone-shaped depression.
[0058] Regarding the pillar 3 , the pillar 3 has a rectangular parallelepiped shape.
[0059] Regarding the shear studs 4, the shear studs 4 are respectively arranged on the four sides of the column 3. The shear studs 4 are distributed in a matrix or plum blossom shape on the sides of the column 3. The shear studs 4 are perpendicular to the mounting plate 10.
[0060] Regarding the pipeline 5 , the pipeline 5 can be implemented by a tubular object, and the pipeline 5 can be pre-buried inside the column 3 during the casting process of the column 3 .
[0061] Regarding the groove 8, there are two grooves 8. The two grooves 8 are cross-shaped, and the second pipe opening 7 is arranged at the intersection of the two grooves 8. The second pipe opening 7 can output concrete to the four sides of the column 3 through the two grooves 8.
[0062] In this embodiment, the mounting plate 10 is a steel plate, the roots of the shear studs 4 intersect with the mounting plate 10, and the shear studs 4 are arranged in a rectangular array on the mounting plate 10, and the mounting plate 10 covers the side of the column 3 and the port of the groove 8. The shear studs 4 are arranged in a rectangular array on the mounting plate 10, and multiple shear studs 4 can be installed at one time by fixing the mounting plate 10 on the column 3; the mounting plate 10 can cover the port of the groove 8, and can prevent concrete from overflowing from the port of the groove 8 to the periphery of the column 3.
[0063] Regarding the mounting plate 10, the mounting plate 10 of this embodiment is a steel plate, and the number of the mounting plates 10 is four. A mounting plate 10 is respectively provided on the four sides of the column 3. The root of the shear nail 4 is fixed to the mounting plate 10 by welding. In this embodiment, as shown in FIG. Figure 5 As shown, sixteen shear studs 4 are welded on a mounting plate 10 , and the sixteen shear studs 4 are distributed on the same mounting plate 10 in a rectangular array of four rows by four columns.
[0064] In this embodiment, the structure of the mounting plate 10 satisfies one of the following types:
[0065] Type 1: A plurality of reserved screws 14 are provided on the side of the column 3, one end of the reserved screw 14 is fixed on the column 3 and the other end can pass through the mounting plate 10, and a nut 15 is also provided on the reserved screw 14, and the nut 15 can be threadedly matched with the reserved screw 14 to fix the mounting plate 10 on the side of the column 3;
[0066] In type 2, the mounting plate 10 covers the side of the column 3, and the edges of each mounting plate 10 intersect at the ridge of the column 3, and the intersections between each mounting plate 10 are fixed by welding. In type 1, the reserved screw 14 can be directly inserted into the column 3, and the mounting plate 10 can be fixed on the reserved screw 14 by the nut 15, so that each shear stud 4 is also fixed on the side of the column 3, which is conducive to simplifying the connection relationship between the shear stud 4 and the column 3; the edges of the mounting plates 10 in type 2 can be fixed to each other by welding, which can replace the nut 15 and the reserved screw 14 in type 1.
[0067] Regarding the reserved screw rod 14, the reserved screw rod 14 can be pre-buried in the column 3 during the pouring process of the column 3. The fixing method selected in this embodiment is type one.
[0068] In this embodiment, a plurality of fixing ribs 12 are further provided on the column 3, each fixing rib 12 is fixed on the column 3 by planting ribs, and a bottom plate rib 13 is further provided between the column 3 and the cup-shaped foundation 1, one end of the bottom plate rib 13 is inserted into the cup-shaped foundation 1 and the other end intersects with the fixing rib 12. The intersection of the fixing rib 12 and the bottom plate rib 13 can further strengthen the structural strength between the column 3 and the cup-shaped foundation 1, which is conducive to improving the structural stability of the column 3.
[0069] Regarding the fixing bars 12, the fixing bars 12 are arranged parallel to the ridges of the column 3. Each fixing bar 12 is arranged near the four ridges of the column 3. Planting bars, also known as planting bars, are a common steel bar anchoring connection technology in the earthquake-resistant reinforcement engineering of building structures. The fixing bars 12 are fixed to the column 3 in the form of planting bars.
[0070] Regarding the bottom plate ribs 13, the bending angle of the bottom plate ribs 13 is 90 degrees, one end of the bottom plate ribs 13 is arranged in the horizontal direction and the other end is arranged in the vertical direction. The arrangement of the bottom plate ribs 13 is conducive to strengthening the structural strength between the column 3 and the cup-shaped foundation 1.
[0071] In this embodiment, a plurality of annular steel bars 11 are further provided on the column 3, each of which is sleeved outside the column 3 and intersects with each of the fixing bars 12. The annular steel bars 11 surround the column 3 and intersect with the fixing bars 12, which is beneficial to improving the structural stability of the column 3.
[0072] As for the circular reinforcement 11, there are eight circular reinforcements 11. Each circular reinforcement 11 intersects with each fixing bar 12 and is fixed by welding. The circular reinforcement 11 surrounds the column 3, and each circular reinforcement 11 is arranged in parallel and at equal intervals.
[0073] In this embodiment, a quick-closing net 9 is also provided on the inner side of the cup-shaped foundation 1. The quick-closing net 9 can strengthen the structural strength between the concrete and the cup-shaped foundation 1.
[0074] About the quick and easy closing net 9, the quick and easy closing net 9 refers to the mesh that does not need to be disassembled for formwork, which can enhance the strength of the concrete joint.
[0075] The construction method of the assembled concrete foundation column, based on the assembled concrete foundation column construction system, also includes the following steps:
[0076] Step A, reserving a cup-shaped pit at the construction site, pouring concrete on the side and bottom of the cup-shaped pit and inserting reserved reinforcement 2 into the concrete, so that the cup-shaped pit forms a cup-shaped foundation 1;
[0077] Step B, draw positioning axes on the end face of the column 3 and in the cup-shaped foundation 1 respectively, put the column 3 into the cup-shaped foundation 1, then check the alignment degree between the positioning axis on the column 3 and the positioning axis in the cup-shaped foundation 1, and calibrate the verticality of the column 3 with a plumb bob;
[0078] Step C, fixing the shear nail 4 on the column 3;
[0079] Step D, pouring concrete into the first pipe opening 6, so that the concrete flows into between the column 3 and the cup-shaped foundation 1 through the pipe 5, the second pipe opening 7 and the groove 8;
[0080] Step E: pouring concrete into the cup-shaped foundation 1 so that the concrete fills around the pillars 3 .
[0081] The assembled concrete foundation column construction method enables the cup-shaped foundation 1 and the column 3 to be constructed in stages, and the shear nails 4 can be pre-fixed on the mounting plate 10. During the construction process, the mounting plate 10 can be simply and quickly fixed on the column 3 by the reserved screw rods 14, so that the shear nails 4 are fixed on the column 3, which is conducive to preventing the shear nails 4 from being damaged during the construction process and can also improve the construction efficiency.
[0082] Regarding step A, in the process of pouring concrete into the cup-shaped pit, it is also necessary to lay a quick-closing net 9 on the concrete and insert reserved ribs into the concrete.
[0083] Regarding step B, before placing the column 3 into the cup-shaped foundation 1, the surface of the cup-shaped foundation 1 may be roughened. In step B, when the verticality of the column 3 deviates, a number of spacers are inserted between the column 3 and the cup-shaped foundation 1, so that the verticality of the column 3 meets expectations.
[0084] Regarding step C, the shear studs 4 are pre-welded on the mounting plate 10. A reserved screw 14 is pre-buried in the column 3. The reserved screw 14 can pass through the mounting plate 10, and the mounting plate 10 can be fixed to the reserved screw 14 using a nut 15, so that the shear studs 4 are fixed on the column 3.
[0085] Regarding step D, before pouring concrete into the pipe 5, it is necessary to paste concrete at the junction of the bottom end of the column 3 and the cup-shaped foundation 1 in advance, so as to block the gap between the edge of the end face of the column 3 and the cup-shaped foundation 1, which is conducive to preventing concrete from overflowing around the column 3. The mounting plate 10 covering the end of the groove 8 can also prevent concrete from overflowing.
[0086] Regarding step E, before pouring concrete into the cup-shaped foundation 1, it is also necessary to insert the bottom plate reinforcement 13, the annular reinforcement 11 and the fixing reinforcement 12 into the cup-shaped foundation 1. The annular reinforcement 11 needs to be welded to each shear nail 4, the fixing reinforcement 12 needs to be welded to each annular reinforcement 11, and the bottom plate reinforcement 13 needs to be welded to the fixing reinforcement 12.
[0087] In this embodiment, in step E, the concrete is vibrated while pouring concrete into the cup-shaped foundation 1. Vibrating the concrete during the concrete pouring process can discharge the gas in the concrete mortar, which is beneficial to improving the pouring quality and the structural strength between the column 3 and the cup-shaped foundation 1.
[0088] Embodiment 2:
[0089] like Fig. 9 As shown, the difference between this embodiment and embodiment 1 is that:
[0090] In this embodiment, the mounting plate 10 is a steel bar, at least two mounting plates 10 are provided on each side of the column 3, at least two shear nails 4 are provided on each mounting plate 10, and each shear nail 4 is arranged in a linear array on the mounting plate 10. The mounting plate 10 is a steel bar, and the shear nails 4 are arranged in a linear array on the mounting plate 10, which is conducive to further simplifying the structure of the mounting plate 10 and making the mounting plate 10 easier to process and manufacture.
[0091] Regarding the mounting plate 10, the mounting plate 10 is a steel bar, and each mounting plate 10 is provided with four shear nails 4. The mounting plates 10 on the same side of the column 3 are parallel to each other and have equal spacing.
[0092] Embodiment 3:
[0093] like Fig.10 As shown, the difference between this embodiment and embodiment 2 is that:
[0094] In this embodiment, the angle between the shear stud 4 and the mounting plate 10 is 82°. Adjusting the angle between the shear stud 4 and the mounting plate 10 can achieve different mechanical properties, thereby expanding the scope of application of the assembled concrete foundation column construction system.
Claims
1. The assembled concrete foundation column construction system is characterized by: include: A cup-shaped foundation, wherein a plurality of reserved ribs are provided on the inner side of the cup-shaped foundation, and the reserved ribs protrude from the inner side of the cup-shaped foundation; A column, wherein the column is arranged in the cup-shaped foundation, and a space between the column and the cup-shaped foundation is filled with concrete; A plurality of mounting plates, wherein the mounting plates cover the side surfaces of the columns, and the mounting plates are provided with a plurality of shear nails, the roots of the shear nails intersect with the mounting plates, and the ends of the shear nails extend outward from the columns; A pipe, wherein the pipe is arranged in the column, the pipe intersects with the side surface of the column to form a first pipe opening, the pipe intersects with the end surface of the column to form a second pipe opening, and the first pipe opening is connected to the second pipe opening; A plurality of grooves, wherein the grooves are arranged on the end surface of the column, each of the grooves intersects with each side surface of the column, the second pipe opening is arranged in the grooves, and the grooves enable the second pipe opening to communicate with each side surface of the column; The mounting plate is a steel plate, the roots of the shear nails intersect with the mounting plate, the shear nails are arranged in a rectangular array on the mounting plate, and the mounting plate covers the side of the column and the port of the groove; The structure of the mounting plate satisfies one of the following types: Type 1: A plurality of reserved screws are provided on the side of the column, one end of the reserved screw is fixed on the column and the other end can pass through the mounting plate, and a nut is also provided on the reserved screw, which can be threadedly matched with the reserved screw to fix the mounting plate on the side of the column; Type 2: the mounting plates cover the sides of the columns, the edges of the mounting plates intersect at the ridges of the columns, and the intersections between the mounting plates are fixed by welding; The column is also provided with a plurality of fixing ribs, each of which is fixed to the column by means of anchoring. A bottom plate rib is also provided between the column and the cup-shaped foundation, one end of the bottom plate rib is inserted into the cup-shaped foundation and the other end intersects with the fixing rib.
2. The assembled concrete foundation column construction system according to claim 1 is characterized in that: The mounting plate is a steel bar, at least two mounting plates are provided on each side of the column, at least two shear nails are provided on each mounting plate, and the shear nails are arranged in a linear array on the mounting plate.
3. The assembled concrete foundation column construction system according to claim 1 is characterized in that: The included angle between the shear studs and the mounting plate is 45° to 90°.
4. The assembled concrete foundation column construction system according to claim 1 is characterized in that: The column is also provided with a plurality of annular steel bars, each of which is sleeved outside the column and intersects with each of the fixed bars.
5. The assembled concrete foundation column construction system according to claim 1 is characterized in that: A quick-closing net is also provided on the inner side surface of the cup-shaped base.
6. The method for constructing a prefabricated concrete foundation column is characterized by: The assembled concrete foundation column construction system according to any one of claims 1 to 5 further comprises the following steps: Step A, reserving a cup-shaped pit at the construction site, pouring concrete on the side and bottom of the cup-shaped pit and inserting the reserved reinforcement into the concrete, so that the cup-shaped pit forms the cup-shaped foundation; Step B, drawing positioning axes on the end face of the column and in the cup-shaped foundation respectively, placing the column in the cup-shaped foundation, then checking the alignment degree of the positioning axis on the column with the positioning axis in the cup-shaped foundation, and calibrating the verticality of the column with a plumb bob; Step C, fixing the shear nails on the columns; Step D, pouring concrete into the first pipe opening, so that the concrete flows into between the column and the cup-shaped foundation through the pipe, the second pipe opening and the groove; Step E, pouring concrete into the cup-shaped foundation so that the concrete fills around the column.