A jacking construction device and construction method for a box culvert under a railway frame
By using simple shield mechanisms and cantilever beams to achieve integrated construction of side-heading and overhead overhead in the underpass railway construction, the problems of complicated line overhead and demolition and high risk of manual holes in the existing construction methods are solved, and the construction period is achieved The effects of shortening, cost reduction and safety improvement.
Patent Information
- Application Number
- CN202010027326.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-01-10
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2040-01-10
AI Technical Summary
The existing underpass railway top-up construction methods have problems such as cumbersome line elevation and demolition, high risk of manual hole-drilling piles, long construction period and high cost.
A construction device for overheading the railway frame box culvert is adopted, including a simple shield machine, a base beam and a cantilever beam. The steel pillows extend on the frame box culvert through the cantilever beam for overhead and rushing, and the support piles are cancelled. With the cumbersome construction of overhead beams, integrated construction of overhead while being pushed into is realized.
Shorten the construction period by 50-70%, reduce the construction cost by more than 50%, reduce the impact on driving, improve safety and mechanized construction, and reduce the risk of personal casualties.
Smart Images

Figure CN111119912B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of jacking construction of a frame box culvert under a railway line, and in particular relates to a jacking construction device for a frame box culvert under a railway and a construction method thereof. Background Art
[0002] With the rapid development of urban construction and roads, existing railways often need to be rebuilt or newly built with some engineering facilities. The frame bridge culvert passes under the existing railway, and the jacking construction technology is often used. The existing jacking box culvert construction method under the railway must be divided into two steps, that is, first the line is overhead, and then the jacking excavation. The overhead beam of the line is a special construction beam. There must be supporting piles at both ends of the overhead beam. The supporting piles are very close to the line and can only be manually dug piles. The overhead line also requires the procedures of pulling out sleepers, moving sleepers horizontally, passing crossbeams, erecting longitudinal beams, and buckling rails. The order of removing overhead beams is the opposite; the jacking excavation uses hydraulic oil as the power, and the excavator is used to take soil manually. In order to ensure the stability of the roadbed during excavation and jacking, a certain number of manually dug support piles must be preset on the roadbed outside the jacking range; the supporting piles, support piles and jacking construction lines must be slow and limited in speed, and the line must be blocked for overhead installation and removal. The existing jacking construction process and construction technology have the following disadvantages: 1. The manual bored piles, overhead lines, overhead demolition, and overhead support point conversion near the line are cumbersome and have a great impact on the line, posing a high risk to driving safety and personal safety; 2. The construction period is long and the project cost is high. Summary of the invention
[0003] In order to solve the problems existing in the existing construction technology, the present invention provides a jacking construction device for underpass railway frame box culvert and a construction method thereof. The present invention realizes integrated construction of jacking and overhead construction. When the box culvert is jacked to the edge of the line sleeper, the frame box culvert is used to bear the load itself and a cantilever beam is extended from the frame box culvert to overhead the rails, thereby eliminating the cumbersome construction of supporting piles, supporting piles and overhead beams. The present invention has the advantages of short construction period, low cost, little impact on driving and low safety risk.
[0004] In order to solve the above technical problems, this application adopts the following technical solutions:
[0005] A jacking construction device for underpass railway frame box culvert, comprising a simple shield machine, a base beam and a cantilever beam;
[0006] The shield machine is arranged at the front end of the frame box culvert, the base beams are arranged in a row on the top of the frame box culvert, and the cantilever beams are slidably sleeved in the base beams;
[0007] The top of the base beam is provided with a through groove extending along its length direction, and the top of the front end of the cantilever beam is provided with a steel sleeper slidably matched with the through groove. The cantilever beam can be extended from the front end of the frame culvert by driving the oil cylinder to insert the steel sleeper under the rail.
[0008] Furthermore, a cushion beam for supporting the steel sleeper is provided at the tail end of the base beam on the frame box culvert.
[0009] Furthermore, a plurality of steel sleeper fixing assemblies for fixing steel sleepers are provided on the cantilever beam along the extending direction of the through slot;
[0010] The steel sleeper fixing assembly comprises a pair of horizontal clamping cylinders symmetrically arranged on both sides of the through slot and a pair of vertical supporting cylinders for pressing and fixing the steel sleeper on the cantilever beam.
[0011] Furthermore, the cushion beam is provided with a steel sleeper fixing assembly having the same structure as the steel sleeper fixing assembly on the cantilever beam.
[0012] Furthermore, a lifting cylinder is connected between the steel sleeper and the steel rail.
[0013] Furthermore, the top end of the lifting cylinder fixes the rail via a fastener, and the steel sleeper is fixed to the cantilever beam via bolts.
[0014] Furthermore, a plurality of support seats with top openings are provided on the frame box culvert, and the base beams are erected on the support seats and fixed by T-shaped stiffening beams detachably connected to the support seats.
[0015] Furthermore, the support seat is fastened and connected to the frame box culvert by bolts, and the T-shaped stiffening beam is fastened and connected to the support seat by bolts.
[0016] Furthermore, a track elevation monitoring sensor is also provided on the outer waist of the rail.
[0017] A jacking construction method for underpass railway frame box culvert, using the jacking construction device, comprises the following steps:
[0018] 1) Excavate the working pit, install the cantilever beam into the base beam, and fix the base beam and cushion beam to the concrete frame box culvert in sequence with high-strength bolts. The spacing of the cantilever beam is the same as the spacing of the sleepers and is staggered with the sleepers, so that the cantilever rail construction device can be inserted between the sleepers during the jacking process, and the shield machine is installed at the front end of the frame box culvert;
[0019] 2) Apply for the train to slow down and pass, arrange the track elevation monitoring device on the rail, push the frame box culvert forward and cut the soil until its front end stops at a set distance from the outside of the sleeper, and pour a concrete retaining beam between the two lines;
[0020] 3) In the skylight point of the line blockade, complete the top push of the cantilever beam to the concrete retaining beam, install the steel sleeper on the cantilever beam, fix the steel sleeper and the rail firmly, and adjust the rail elevation to the state before the blockade through the lifting cylinder on the steel sleeper. Install the connecting beam at the end of the cantilever beam to connect all the cantilever beams into a whole, fix the connecting beam and the concrete retaining beam in one direction so that the connecting beam can only move vertically but not longitudinally, and restore the line to unblock;
[0021] 4) When the train slows down and passes, the concrete frame box culvert continues to cut the soil and excavate forward. When the train passes, the excavation is suspended and the excavation continues after the train passes. The steel sleeper slides into the base beam along with the cantilever beam. When the cantilever beam slides completely into the base beam, the frame box culvert has been pushed forward to the concrete retaining beam.
[0022] 5) Remove the connecting beam and concrete retaining beam, release the fixation of the steel sleeper and the cantilever beam, install the steel sleeper fixing components on the base beam and the cushion beam respectively, and continue to push the frame box culvert forward. The steel sleeper slides along the cantilever beam, base beam and cushion beam in turn. When the train passes, stop pushing forward, and temporarily fix the steel sleeper to the base beam or cushion beam through the steel sleeper fixing component. After the train passes, release the fixation and continue pushing forward until the frame box culvert is pushed forward to the set distance from the sleeper of the next line;
[0023] 6) Repeat the above operation process to carry out the cantilevered overhead rails and jacking of the remaining lines until the jacking is completed at the terminal position, backfill the roadbed and ballast bed, and remove the steel sleepers, base beams and cushion beams one by one within the line blocking skylight points.
[0024] The jacking construction method provided by the present invention has the characteristics of integrated jacking construction, that is, jacking, line reinforcement and line maintenance at the same time, without the construction of overhead lines with temporary beams, supporting piles and supporting piles. It adopts shield tunneling technology and earth pressure balance principle to carry out jacking and soil excavation while reinforcing the line. The whole construction is completed by a special device, namely, an integrated jacking device. Compared with the traditional jacking method, the construction method of the present invention has the following advantages: 1. The operations on the line are greatly reduced, the impact on driving is greatly reduced, and driving safety can be better guaranteed; 2. The mechanized construction degree is very high, the work efficiency is high, and the risk of personal injury and death is greatly reduced; 3. Compared with traditional construction, the construction period is shortened by 50-70%, and the cost is reduced by more than 50%. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a structural schematic diagram of the present invention;
[0026] Figure 2 It is a plan view of the steel sleeper;
[0027] Figure 3 This is a schematic diagram of the steel sleeper position;
[0028] Figure 4 This is a schematic diagram of the lifting cylinder of the steel sleeper;
[0029] Figure 5 is a schematic diagram of the cross section of the base beam;
[0030] Figure 6 It is a three-dimensional schematic diagram of the base beam;
[0031] Figure 7 It is a three-dimensional schematic diagram of the cushion beam;
[0032] Figure 8 It is a cross-sectional view of a type I fixing component;
[0033] Fig. 9 It is a schematic diagram of the rail cantilever device group;
[0034] Fig.10 This is the plan view of the concrete retaining beam;
[0035] Fig.11 Schematic diagram of construction step 2);
[0036] Fig.12 Schematic diagram of construction step 3);
[0037] Fig.13 Schematic diagram of construction step 4);
[0038] Fig.14 It is a schematic diagram of construction step 6);
[0039] Fig.15 This is a schematic diagram of construction step 6). DETAILED DESCRIPTION
[0040] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0041] See also Figure 1 and Figure 2 A jacking construction device for underpass railway frame box culvert includes a steel sleeper 1, a cantilever beam 2, a base beam 3, a cushion beam 4, a driving cylinder 5, a steel sleeper fixing assembly 6 and a simple shield machine 8.
[0042] Among them, the base beams 3 are arranged in a row at the top of the frame culvert 10, which are the supporting and restraining components of the cantilever beam 2 on the frame culvert 10. The cantilever beam 2 is slidably sleeved in the base beam 3, and the cushion beam 4 is located behind the base beam 3. When the steel sleeper 1 passes over the base beam 3 section, it can support the steel sleeper 1. The driving cylinder 5 is located at the tail of the base beam 3 to provide power for the cantilever beam 2 to move forward from the inside of the base beam 3. The top of the base beam 3 is provided with a through groove extending along its length direction, and the front end top of the cantilever beam 2 is provided with a steel sleeper 1 that slides with the through groove. When the driving cylinder 5 drives the cantilever beam 2 to extend from the front end of the frame culvert 10, the steel sleeper 1 is just inserted under the rail 11, which plays a cantilevering role on the rail 11.
[0043] The steel sleeper fixing assembly 6 is used for temporary fixation between the steel sleeper 1 and the base beam 3 or the cushion beam 4. When the steel sleeper fixing assembly 6 releases the steel sleeper 1, the steel sleeper 1 can slide freely on the base beam 3 and the cushion beam 4. When the steel sleeper fixing assembly 6 grasps the steel sleeper 1, the position of the steel sleeper 1 is locked.
[0044] Among them, the simple shield machine 8 is arranged at the front end of the frame culvert 10, and the soil in front can be cut and excavated during the jacking process of the frame culvert. The steel sleeper 1 is a steel component similar to the rail sleeper 12. The rails are fixed by fasteners. The steel sleeper 1 is inserted between the existing rail sleepers. The cantilever beam 2 can slide relative to the base beam 3 and extend out of the front end of the frame culvert by driving the oil cylinder 5, and extend under the steel sleeper 1 to support it.
[0045] The jacking construction device of this embodiment can meet the construction requirements of jacking and simultaneously overheading the line, can effectively simplify the jacking construction process, reduces the operations on the line and the impact on driving, and can better ensure the safe operation of the railway. It has a high degree of mechanized construction, a short construction period, and low construction costs.
[0046] See also Figure 2 and Figure 3 In some embodiments, the steel sleeper fixing assembly 6 includes two types: a. The first type is a fixing component between the steel sleeper 1 and the base beam 3, called a type I fixing component 6-1; b. The second type is a fixing component between the steel sleeper 1 and the cushion beam 4, called a type II fixing component 6-2. The structures and principles of the two types of fixing components are roughly the same. A hydraulic component is provided to tighten the steel sleeper 1 when the jacking is paused and to loosen the steel sleeper 1 when the jacking is in progress. The two types of fixing components are fixed to the cantilever beam 2, the base beam 3 and the cushion beam 4 respectively by bolts.
[0047] Among them, multiple groups of I-type fixing components 6-1 are arranged along the extension direction of the cantilever beam 2, and each group of I-type fixing components 6-1 is fixed to the base beam 3 by bolts 6-3, and there are two groups of hydraulic parts inside, one group is horizontally movable hydraulic parts, named horizontal clamping cylinder 6-4, and the other group is vertical hydraulic parts, named vertical supporting cylinder 6-5; the I-type fixing components 6-1 are fixed to the cantilever beam 2 by bolts, when the cantilever beam 2 moves forward, the hydraulic oil 6-6 in the cylinder drives the piston to retreat, and the hydraulic parts are in a loose state at this time; when the cantilever beam 2 stops moving, the I-type fixing components 6-1 clamp the steel sleeper 1 and press it on the cantilever beam 2 through the hydraulic parts, and the cross-sectional diagram of the I-type fixing components 6-16-1 is shown in Figure 8 shown.
[0048] Among them, the II-type fixing component 6-2 is also provided with multiple types and is fixed on the cushion beam 4 by bolts. Similar to the I-type fixing component 6-1, the cushion beam 4 is located between the II-type fixing components 6-2, and there are two sets of hydraulic components inside. The II-type fixing component 6-2 clamps the steel sleeper 1 and presses it on the cushion beam 4 through the hydraulic components. The cross-sectional view of the II-type fixing component 6-2 is shown in FIG. Figure 7 shown.
[0049] See also Figure 2 In some embodiments, the steel sleeper 1 fixes the rail 11 through fasteners 1-2, and a rubber gasket is provided between the steel sleeper 1 and the rail 11 to prevent short circuit of the rail current; the steel sleeper 1 is temporarily fixed to the cantilever beam 2 by bolts; the bottom of the steel sleeper 1 has two wings, which can be used for the vertical supporting cylinder to press it down on the cantilever beam 2 or the cushion beam 4.
[0050] Among them, the steel sleeper 1, the cantilever beam 2, the base beam 3, the cushion beam 4, the driving cylinder 5 and the steel sleeper fixing assembly 6 on the same straight line in the longitudinal direction constitute a set of rail cantilever device group, and its schematic diagram is shown as follows Fig. 9 shown.
[0051] In order to facilitate the adjustment of the height of the rail, the steel sleeper 1 is provided with a lifting cylinder 1-1 at the contact position under the rail to ensure that the front and rear height of the rail is smooth. Figure 3 As shown, the cylinder body 1-102 of the lifting cylinder 1-1 is fixedly connected to the steel sleeper 1, and the piston cylinder 1-101 of the lifting cylinder 1-1 is fixedly connected to the rail 11 through the bolt assembly 1-103.
[0052] It is understandable that in the jacking construction device of this embodiment, a track elevation monitoring sensor 7 can also be installed on the outer rail waist of the rail 11 to detect the elevation change of the rail. When the rail has excessive settlement or bulge, an early warning can be issued. As for its specific structure and detection principle, they are all existing technologies and will not be repeated here.
[0053] See also Figure 4 and Figure 5 In this embodiment, the cantilever beam 2 is a steel box beam, and the base beam 3 is a box beam structure with an opening in the middle of the top. The opening runs through the length direction of the base beam 3, allowing the steel sleeper 1 to move forward and backward on the cantilever beam 2 in the base beam 3. A driving cylinder 5 is provided at the tail of the base beam 3 to provide power for the cantilever beam 2 to move forward from the inside of the base beam 3. A plurality of support seats with top openings are provided on the frame box culvert along the length direction of the base beam 3. The base beam 3 is mounted on the support seats and fixed by a T-shaped stiffening beam 3-3 detachably connected to the support seats.
[0054] Specifically, the support seat is made of welded steel plates and is fastened to the frame box culvert by high-strength bolts 3-2. A stiffening rib 3-1 is also provided on the outside of the steel plate. A T-shaped stiffening crossbeam 3-3 is fastened to the support seat by bolts. The T-shaped stiffening crossbeam can maintain the stability of the top of the base beam 3. Among them, the stiffening 3-1 of the base beam 3 at the front end of the concrete frame is gradually widened from top to bottom to resist the torsion caused by the running of the train.
[0055] See also Figure 6 Among them, the main body of the cushion beam 4 is a steel box beam, the top of the cushion beam 4 is flush with the top of the cantilever beam 2, and the cushion beam 4 is provided with steel plates and stiffening ribs 4-1 along the length direction. Long bolts 4-2 are set at the beginning of the upper steel plate, and the bottom of the long bolts is set on the inner side of the concrete frame top plate. The cushion beam 4 is fixed to the concrete frame box culvert by the long bolts.
[0056] The following will take the double-track railway as an example to explain in detail the specific process of jacking operation using the above-mentioned jacking construction device for underpass railway frame box culvert:
[0057] 1) excavating a working pit, prefabricating a frame box culvert, installing the cantilever beam 2 into the base beam 3, fixing the base beam 3 and the cushion beam 4 on the concrete frame box culvert in sequence by bolts, the spacing of the cantilever beam 2 is the same as the spacing of the sleepers and is staggered with the sleepers, so that the cantilever rail construction device is inserted between the sleepers 12 during the jacking process, and installing the simple shield machine 8 in the frame box culvert;
[0058] 2) Apply for the train to slow down and pass, arrange the track elevation monitoring device on the rail, push the frame culvert and the device forward as a whole, cut the soil and dig until the front end is 20cm away from the outside of the sleeper, and pour the concrete retaining beam 9 between the two lines. At this time, the device position is as follows: Fig.11 As shown;
[0059] The concrete retaining beam 9 is a concrete beam cast on site, and a connecting beam 13 is provided on its front side. The connecting beam 13 is a steel beam. When the cantilever beam 2 extends to the position of the concrete retaining beam 9, the front end of the cantilever beam 2 is fixed to the connecting beam 13 by bolts. The plan view of the concrete retaining beam 9 is as shown in FIG. Fig.10 shown.
[0060] 3) In the line blocking skylight point, complete the cantilever beam 2 to push up to the concrete retaining beam 9, install the steel sleeper 1 on the cantilever beam 2, the steel sleeper 1 is fixed to the rail by bolts, and the rail elevation is adjusted to the state before blocking by the lifting cylinder on the steel sleeper 1. Install the connecting beam 13 at the end of the cantilever beam 2 to connect all the cantilever beams 2 into a whole. The connecting beam 13 and the concrete retaining beam 9 are fixed in one direction so that the connecting beam 13 can only move vertically but not longitudinally. The line is restored and the blockade is released. At this time, the device position is as follows: Fig.12 As shown;
[0061] 4) When the train decelerates and passes, the concrete frame box culvert continues to cut the soil and excavate forward. When the train passes, the excavation stops. The steel sleeper 1 slowly slides into the base beam 3 together with the cantilever beam 2. Before the steel sleeper 1 hits the T-shaped stiffening beam of the base beam 3, the current T-shaped stiffening beam is removed. The concrete frame box culvert cuts the soil and excavates forward until the cantilever beam 2 slides completely into the base beam 3. At this time, the frame box culvert has been pushed forward to the concrete retaining beam 9. At this time, the device position is as follows: Fig.13 As shown;
[0062] 5) Remove the concrete retaining beam 9 and the connecting beam 13, release the fixation of the steel sleeper 1 and the cantilever beam 2, install the type I fixing component 6-1 and the type II fixing component 6-2 on the base beam 3 and the cushion beam 4 respectively, and continue to push the frame box culvert forward. The steel sleeper 1 slides along the cantilever beam 2, the base beam 3, and the cushion beam 4 in turn. When the train passes, stop pushing forward, and temporarily fix the steel sleeper 1 to the base beam 3 or the cushion beam 4 through the hydraulic parts of the type I fixing component 6-1 or the type II fixing component 6-2. After the train passes, release the fixation and continue pushing forward until the frame box culvert is pushed forward to 20 cm away from the sleeper of the next line;
[0063] 6) Repeat the above operation process to carry out the cantilevered overhead rail and jacking of the second line until the jacking is completed when it reaches the end position, backfill the roadbed and ballast bed, and remove the steel sleeper 1, base beam 3, cushion beam 4 and other devices one by one in the line blocking skylight point. The construction process diagram included in this step is as follows: Fig.14 , Fig.15 shown.
[0064] The jacking construction method provided by the present invention has the characteristics of integrated jacking construction, that is, jacking, line reinforcement and line maintenance at the same time, without the construction of overhead lines with temporary beams, supporting piles and supporting piles. It adopts shield tunneling technology and earth pressure balance principle to carry out jacking and soil excavation while reinforcing the line. The whole construction is completed by a special device, namely, an integrated jacking device. Compared with the traditional jacking method, the construction method of the present invention has the following advantages: 1. The operations on the line are greatly reduced, the impact on driving is greatly reduced, and driving safety can be better guaranteed; 2. The mechanized construction degree is very high, the work efficiency is high, and the risk of personal injury and death is greatly reduced; 3. Compared with traditional construction, the construction period is shortened by 50-70%, and the cost is reduced by more than 50%.
[0065] The above embodiments are merely examples for clearly illustrating the present invention, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. The obvious changes or modifications derived therefrom are still within the scope of protection of the present invention.
Claims
1. A jacking construction device for underpass railway frame box culvert, characterized in that: Including simple shield machine, base beam and cantilever beam; The shield machine is arranged at the front end of the frame box culvert, the base beams are arranged in a row on the top of the frame box culvert, and the cantilever beams are slidably sleeved in the base beams; The top of the base beam is provided with a through slot extending along its length direction, the top of the front end of the cantilever beam is provided with a steel sleeper slidably matched with the through slot, and the cantilever beam can be extended from the front end of the frame culvert by driving the oil cylinder to insert the steel sleeper under the rail; The frame box culvert is also provided with a cushion beam at the tail end of the base beam for supporting the steel sleeper; The jacking construction device is constructed according to the following method: 1) Excavate the working pit, install the cantilever beam into the base beam, and fix the base beam and cushion beam to the concrete frame box culvert in sequence with high-strength bolts. The spacing of the cantilever beam is the same as the spacing of the sleepers and is staggered with the sleepers, so that the cantilever rail construction device can be inserted between the sleepers during the jacking process, and the shield machine is installed at the front end of the frame box culvert; 2) Apply for the train to slow down and pass, arrange the track elevation monitoring device on the rail, push the frame box culvert forward and cut the soil until its front end stops at a set distance from the outside of the sleeper, and pour a concrete retaining beam between the two lines; 3) In the skylight point of the line blockade, complete the top push of the cantilever beam to the concrete retaining beam, install the steel sleeper on the cantilever beam, fix the steel sleeper and the rail firmly, and adjust the rail elevation to the state before the blockade through the lifting cylinder on the steel sleeper. Install the connecting beam at the end of the cantilever beam to connect all the cantilever beams into a whole, fix the connecting beam and the concrete retaining beam in one direction so that the connecting beam can only move vertically but not longitudinally, and restore the line to unblock; 4) When the train slows down and passes, the concrete frame box culvert continues to cut the soil and excavate forward. When the train passes, the excavation is suspended and the excavation continues after the train passes. The steel sleeper slides into the base beam along with the cantilever beam. When the cantilever beam slides completely into the base beam, the frame box culvert has been pushed forward to the concrete retaining beam. 5) Remove the connecting beam and concrete retaining beam, release the fixation of the steel sleeper and the cantilever beam, install the steel sleeper fixing components on the base beam and the cushion beam respectively, and continue to push the frame box culvert forward. The steel sleeper slides along the cantilever beam, base beam and cushion beam in turn. When the train passes, stop pushing forward, and temporarily fix the steel sleeper to the base beam or cushion beam through the steel sleeper fixing component. After the train passes, release the fixation and continue pushing forward until the frame box culvert is pushed forward to the set distance from the sleeper of the next line; 6) Repeat the above operation process to carry out the cantilevered overhead rails and jacking of the remaining lines until the jacking is completed at the terminal position, backfill the roadbed and ballast bed, and remove the steel sleepers, base beams and cushion beams one by one within the line blocking skylight points.
2. The jacking construction device according to claim 1, characterized in that: A plurality of steel sleeper fixing assemblies for fixing steel sleepers are provided on the cantilever beam along the extending direction of the through slot; The steel sleeper fixing assembly comprises a pair of horizontal clamping cylinders symmetrically arranged on both sides of the through slot and a pair of vertical supporting cylinders for pressing and fixing the steel sleeper on the cantilever beam.
3. The jacking construction device according to claim 2, characterized in that: The cushion beam is provided with a steel sleeper fixing assembly having the same structure as that of the steel sleeper fixing assembly on the cantilever beam.
4. The jacking construction device according to claim 3 is characterized in that: A lifting cylinder is connected between the steel sleeper and the steel rail.
5. The jacking construction device according to claim 4, characterized in that: The top end of the lifting cylinder fixes the rails via fasteners, and the steel sleepers are fixed to the cantilever beams via bolts.
6. The jacking construction device according to claim 4, characterized in that: The frame box culvert is provided with a plurality of support seats with open tops, and the base beam is erected on the support seats and fixed by a T-shaped stiffening cross beam detachably connected to the support seats.
7. The jacking construction device according to claim 6, characterized in that: The support seat is fastened and connected with the frame box culvert by bolts, and the T-shaped stiffening cross beam is fastened and connected with the support seat by bolts.
8. The jacking construction device according to claim 4, characterized in that: A track elevation monitoring sensor is also provided on the outer waist of the rail.