A load-built-in transparent sealed cabin rock mass testing system and method

Through the sealed cabin rock mass testing system, the ring frame and square frame are used to provide reaction force, combined with the automated control system, the installation difficulties and result authenticity problems of large-scale rock mass triaxial testing are solved, and efficient and stable multi-field testing is achieved. Coupling test.

CN111257124BActive Publication Date: 2024-10-01CHANGJIANG RIVER SCI RES INST CHANGJIANG WATER RESOURCES COMMISSION
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010207282.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-03-23
Publication Date
2024-10-01
Estimated Expiration
2040-03-23

AI Technical Summary

Technical Problem

The existing rock mass multi-field coupling test system is difficult to conduct large-scale rock mass triaxial tests. The traditional system is bulky and difficult to install, and cannot effectively reflect the true state of the rock mass temperature field and seepage field.

Method used

A sealed cabin-type rock mass testing system is designed, which uses a ring frame and a square frame to provide reaction force, and realizes automatic pressurization, temperature control and seepage pressure through a transmission device and computer control system. The test cabin does not require external reaction force support. The force is evenly distributed within the frame, and the test chamber occupies a small area and is stable.

Benefits of technology

The stability and reliability of large-scale rock mass testing are achieved, the test results are more realistic, the system is highly operable, and the mechanical properties of rock mass can be studied under different chemical and physical conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111257124B_ABST
    Figure CN111257124B_ABST
Patent Text Reader

Abstract

The present invention provides a sealed cabin type rock mass test system and method, the system includes a test cabin, a square frame, an annular frame, a rock mass sample, a transmission device, a stress loading device, and a control system; the rock mass sample is a cuboid with six faces, the square frame is used to apply axial confining pressure to the rock mass sample, the annular frame is used to apply lateral confining pressure to the rock mass sample, the transmission device is used to transport the rock mass sample to the middle of the annular frame, install a stress loading device for applying lateral stress to the rock mass sample and then transport the annular frame to the middle of the square frame, install a stress loading device for applying axial stress to the rock mass sample and then transport the square frame to the test cabin, the control system includes a computer and a pressurization system, a temperature control system, a seepage pressure system, and a measurement system connected to the computer. The present invention does not require external reaction force support and the test cabin does not bear reaction force load, and has the characteristics of small space occupied by the test cabin and convenient installation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of geotechnical engineering, and in particular to a sealed cabin type rock mass test system and method, which are suitable for multi-field coupled triaxial tests of large-scale rock mass samples. Background Art

[0002] Hydropower projects are mostly built in deep mountains and valleys, and the depth of hydraulic structures is gradually increasing. For example, the maximum depth of the Jinping II water diversion tunnel is 2,525 meters. Mineral resources and oil mining are also extending to deep areas, and many mines have reached a depth of more than 1,200 meters. Emerging industries such as underground energy storage, deep geological disposal of high-level nuclear waste, exploration and safe mining of natural gas hydrates, CO 2 The development of rock mass multi-field coupling theory and breakthroughs in related technologies are also urgently needed in fields such as underground isolation. Due to the high stress state, high temperature state, high osmotic pressure state and structural characteristics of deep rock mass, its mechanical properties are significantly different from those of shallow rock mass. Mechanical tests can objectively observe the changing laws of the strength and deformation parameters of rock mass under multi-field coupling conditions, providing a scientific basis for development design and engineering stability evaluation.

[0003] The multi-field coupling tests of rock mass at home and abroad mostly use small-sized rock block specimens (length, width and height of 5cm×5cm×10cm). The specimens generally do not contain cracks or only contain a single crack. The test results cannot reflect the true state of the temperature field and seepage field of the rock mass. In large-scale triaxial tests of rock mass, in order to apply sufficient load to the rock mass test, it is necessary to provide a sufficiently large reaction force to the stress loading system. The traditional triaxial test system of rock mass uses the test frame as the reaction beam and is supported by large steel rods to provide sufficient reaction force. Therefore, the test system is bulky and difficult to install. At present, there is no multi-field coupling triaxial test system and scheme for large-scale (length, width and height of 30cm×30cm×60cm and above) rock mass specimens. Summary of the invention

[0004] The technical problem to be solved by the present invention is to overcome the shortcomings of the prior art and provide a sealed cabin type rock test system and method, which does not require external reaction force support and the test cabin does not bear reaction force load, and has the characteristics of small test cabin footprint and easy installation.

[0005] The technical solution adopted by the present invention is as follows:

[0006] A sealed cabin rock test system comprises a test cabin, a square frame, an annular frame, a rock sample, a transmission device, a stress loading device, and a control system; the rock sample is a cuboid with six faces, the square frame is used to apply axial confining pressure to the rock sample, the annular frame is used to apply lateral confining pressure to the rock sample, the transmission device is used to transport the rock sample to the middle of the annular frame, install a stress loading device for applying lateral stress to the rock sample and then transport the annular frame to the middle of the square frame, install a stress loading device for applying axial stress to the rock sample and then transport the square frame to the test cabin, and the control system comprises a computer and a pressurization system, a temperature control system, a seepage pressure system, and a measurement system connected to the computer.

[0007] Furthermore, the pressurization system is used to inject and draw out hydraulic oil to the jack of the stress loading device to control the lateral and axial confining pressures of the rock sample; the temperature control system is used to adjust the temperature in the test chamber; the seepage pressure system is used to control the liquid pressure in the test chamber; the measurement system is used to measure the lateral and axial deformations of the rock sample during the test. The pressurization system, temperature control system, seepage pressure system, and measurement system are all automatically controlled by computers.

[0008] Furthermore, the test cabin includes a cabin shell, a cabin door, a sealing ring, and a test bench. The cabin door is arranged on the side wall of the cabin shell. The sealing ring is used to improve the sealing of the cabin door. The test bench is arranged at the bottom of the cabin shell and is used to place a square frame.

[0009] Furthermore, the rock sample has six surfaces, namely a first side surface, a second side surface, a third side surface, a fourth side surface, an upper end surface and a lower end surface. The side surfaces are used to apply confining pressure, and the end surfaces are used to apply axial pressure.

[0010] Furthermore, a stress loading device is provided in the left and right frame sides of the square frame respectively, and is in contact with the axial upper end face and the lower end face of the rock sample.

[0011] Furthermore, there are two annular frames, each of which is provided with four mutually symmetrical stress loading devices, which respectively apply force to the first side, second side, third side and fourth side of the rock sample. A certain distance is spaced between the stress loading devices in the two annular frames for installing the rock sample deformation measurement system.

[0012] Furthermore, the transmission device has three pads, namely, a first pad for placing the rock sample, a second pad for placing the square frame and a third pad for placing the annular frame. A turntable is provided inside the second pad to facilitate the rotation of the annular frame. The first pad is transported by the first transmission shaft on the first track, the second pad is transported by the second transmission shaft on the second track, and the third pad is transported by the third transmission shaft on the third track. During transportation, the rock sample is placed on the first pad of the transmission device, transported to the middle of the annular frame by the first transmission shaft, a stress loading device for applying lateral stress to the rock sample is installed, the annular frame is transported to the middle of the square frame by the second transmission shaft, a stress loading device for applying axial stress to the rock sample is installed, and the square frame is transported to the test chamber by the third transmission shaft.

[0013] Furthermore, the stress loading device includes a liquid-permeable steel plate, a force-transmitting steel plate, a jack, and a cushion steel plate. The liquid-permeable steel plate is adjacent to the rock sample and has grooves engraved on its surface for uniformly applying the liquid in the cabin to the surface of the rock sample. The force-transmitting steel plate is used to transfer the load applied by the jack to the liquid-permeable steel plate, and the cushion steel plate is used to fill the gap between the jack and the annular frame.

[0014] A sealed chamber rock mass test method is carried out using the above test system, and the method comprises the following steps:

[0015] Step 1: Prepare rock samples: Select representative rock mass, prepare rectangular rock samples on site, polish and smooth the six surfaces of the rock samples, apply vaseline on them respectively, and then place them on the first pad of the transmission device, and push the first pad to slide to the middle of the two annular frames on the first track through the first transmission shaft of the transmission device;

[0016] Step 2: Assemble the lateral confining pressure stress loading device:

[0017] 1) Install the rock mass horizontal confining pressure stress loading device

[0018] First, install the stress loading device on the horizontal side of the rock sample, and simultaneously install the first stress loading device and the second stress loading device on the second side and the fourth side of the rock sample in the left annular frame, and simultaneously install the third stress loading device and the fourth stress loading device on the second side and the fourth side of the rock sample in the right annular frame. After the installation is completed, use the jack to appropriately pressurize so that the installed stress loading devices are tightly connected;

[0019] 2) Install the rock mass vertical confining pressure stress loading device:

[0020] Install stress loading devices on the vertical side of the rock sample, first pull out the first pad from the annular frame through the first transmission shaft of the transmission device, install the fifth stress loading device and the sixth stress loading device on the first side of the rock sample in the left and right annular frames, respectively, and install the seventh stress loading device and the eighth stress loading device on the third and fourth sides of the rock sample in the left and right annular frames, respectively;

[0021] 3) rotating the rotating table inside the second pad to rotate the annular frame 90 degrees, and pushing the second pad to slide into the square frame on the second track through the second transmission shaft of the transmission device;

[0022] Step 3: Assemble the axial pressure stress loading device:

[0023] The ninth stress loading device and the tenth stress loading device are respectively installed on the upper end surface and the lower end surface of the rock mass sample in the square frame; after the installation is completed, the installed stress loading devices are properly pressurized with a jack to make them tightly connected, and the third pad is pushed to slide on the third track into the test cabin through the third transmission shaft of the transmission device;

[0024] Step 4: Assemble the test chamber control system;

[0025] Step 5: After the sealed cabin rock test system is installed, a computer is used to control the pressurization system, temperature control system, seepage pressure system and measurement system to carry out multi-field coupled triaxial tests on large-scale rock samples.

[0026] Furthermore, the step four is specifically as follows: a jack of the stress loading device is connected by a hydraulic pipeline, and is connected to an external oil pump through a sealed channel of the test cabin to form a pressurization system and is connected to a computer for control; a temperature regulating device is arranged in the test cabin and is connected to a computer through a sealed channel of the test cabin to form a temperature control system; the injection pipeline and the extraction pipeline on the sealed channel of the test cabin are respectively connected to an external circulating hydraulic pump to form a seepage pressure system and are connected to a computer for control; measuring elements are respectively installed on the six surfaces of the rock sample; the measuring cable is connected to the measuring system through the sealed channel of the test cabin to form a measuring system and is connected to a computer for control.

[0027] Beneficial effects of the present invention:

[0028] (1) The present invention adopts a ring frame and a square frame to provide a reaction force. The frame is evenly stressed and can be self-balanced. No external reaction force support is required and the test chamber does not bear the reaction force load. The test chamber occupies a small space and can be made of transparent glass material to better seal the liquid filled in the chamber. The test chamber has strong airtightness and observation performance.

[0029] (2) The deformation during the test of the present invention occurs inside the annular frame and the square frame. The test chamber is only subjected to the internal liquid pressure and has a small deformation. The measuring device, temperature control device, water pressure regulating device, etc. will not be squeezed or disturbed. The test system has strong stability and reliability.

[0030] (3) The present invention adopts a transmission device to transport rock samples, annular frames and square frames, and adopts a computer to control the pressurization system, temperature control system, seepage pressure system and measurement system. The rock test system has strong operability and a high degree of automation;

[0031] (4) The load can be applied synchronously on the six surfaces of the rock sample of the present invention. Compared with the traditional five-surface loading method, the stress condition of the rock sample is more consistent with the in-situ rich condition of the rock mass, and the simulation result is more realistic;

[0032] (5) The test chamber liquid of the present invention can be selected from rocks with different pH values ​​or different electrolytes, and the mechanical properties of rocks under different chemical and physical conditions can be studied;

[0033] (6) The test chamber of the present invention is provided with a temperature control device, which is convenient for adjusting the temperature change of the test chamber and can be used as an effective means to study the mechanical properties of rock mass under multi-field coupling conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 It is a schematic diagram of the axial section of the test chamber when the present invention is tested;

[0035] Figure 2 A schematic longitudinal section of the annular frame during the test of the present invention;

[0036] Figure 3 It is a structural schematic diagram of the sealed cabin type rock mass testing system of the present invention;

[0037] Figure 4 A top view of the transmission device of the present invention;

[0038] Figure 5 It is a structural schematic diagram of the rock sample in the present invention;

[0039] Figure 6 It is a schematic diagram of the circuit principle of the control system in the present invention.

[0040] In the figure: 1—test cabin, 1a—cabin shell, 1b—hatch door, 1c—sealing ring, 1d—test bench, 1e—sealing channel, 2—square frame, 3—annular frame, 4—rock sample, 4a—first side surface, 4b—second side surface, 4c—third side surface, 4d—fourth side surface, 4e—upper end surface, 4f—lower end surface, 5—transmission device, 5a—first pad, 5b—second pad, 5c—third pad, 5d—first transmission shaft, 5e—second transmission shaft, 5f—third transmission shaft, 5g—first track, 5h—second track, 5i—third track, 6—stress loading device, 6a—liquid-permeable steel plate, 6b—force transmission steel plate, 6c—jack, 6d—seat steel plate, 7—control system, 7a—pressurization system, 7b—temperature control system, 7c—seepage pressure system, 7d—measurement system, 7e—computer. DETAILED DESCRIPTION

[0041] The technical solution of the present invention will be clearly and completely described below in conjunction with the accompanying drawings of the present invention.

[0042] See also Figure 3 An embodiment of the present invention provides a sealed cabin rock test system, including a test cabin 1, a square frame 2, a ring frame 3, a rock sample 4, a transmission device 5, a stress loading device 6, and a control system 7.

[0043] The test chamber 1 includes a chamber shell 1a, a chamber door 1b, a sealing ring 1c, and a test bench 1d. The chamber door 1b is arranged on the side wall of the chamber shell 1a, and can be opened and closed to transport other test devices (square frame 2, annular frame 3, stress loading device 6, etc.) and rock sample 4 into the chamber shell 1a. The sealing ring 1c is used to improve the sealing of the chamber door 1b. The test bench 1d is arranged at the bottom of the chamber shell 1a and is used to place the square frame 2. The chamber shell 1a and the chamber door 1b of the test chamber 1 are made of high-strength transparent glass material, so that the progress of the multi-field coupled triaxial test in the test chamber 1 can be observed from the outside and the rock sample failure process can be described.

[0044] like Figure 5 As shown, the rock sample 4 has six surfaces, namely the first side surface 4a, the second side surface 4b, the third side surface 4c, the fourth side surface 4d, the upper end surface 4e and the lower end surface 4f. The side surfaces are used to apply confining pressure, and the end surfaces are used to apply axial pressure.

[0045] The square frame 2 is used to apply axial confining pressure to the rock sample 4. A stress loading device 6 is respectively provided in the left and right frame edges of the square frame 2, and is in contact with the two axial end faces (upper end face 4e and lower end face 4f) of the rock sample 4 (such as Figure 1 shown).

[0046] like Figure 2As shown, the annular frame 3 is used to apply lateral confining pressure to the rock sample 4. There are two annular frames 3 (the number can be set according to actual needs). Four mutually symmetrical stress loading devices 6 are arranged in each annular frame 3, which is conducive to uniform force on the annular frame 3. The stress loading devices 6 apply force to the four sides (first side 4a, second side 4b, third side 4c, fourth side 4d) of the rock sample 4 respectively. The stress loading devices 6 in the two annular frames are spaced apart by a distance of about 2 cm, which are used to install the rock sample deformation measurement system.

[0047] like Figure 3 and 4 As shown, the transmission device 5 has three pads, namely, the first pad 5a for placing the rock sample 4, the second pad 5b for placing the square frame 2, and the third pad 5c for placing the ring frame 3. The second pad 5b is provided with a rotating platform inside to facilitate the rotation of the ring frame 3. The first pad 5a is transported on the first track 5g by the first transmission shaft 5d, the second pad 5b is transported on the second track 5h by the second transmission shaft 5e, and the third pad 5c is transported on the third track 5i by the third transmission shaft 5f.

[0048] The rock sample 4 is placed on the transmission device 5 and transported to the middle of the annular frame 3 through the first transmission shaft 5d, and a stress loading device 6 for applying lateral stress to the rock sample is installed. The annular frame 3 is transported to the middle of the square frame 2 through the second transmission shaft 5e, and a stress loading device 6 for applying axial stress to the rock sample is installed. The square frame 2 is transported to the test chamber 1 through the third transmission shaft 5f, and the hatch 1d of the test chamber 1 is closed, so that a multi-field coupled triaxial test can be carried out.

[0049] The stress loading device 6 includes a liquid-permeable steel plate 6a, a force-transmitting steel plate 6b, a jack 6c, and a cushion steel plate 6d. The liquid-permeable steel plate 6a is adjacent to the rock sample 4 and has grooves engraved on its surface for uniformly applying the liquid in the cabin to the surface of the rock sample 4. The force-transmitting steel plate 6b is used to transfer the load applied by the jack 6c to the liquid-permeable steel plate 6a. The cushion steel plate 6d is used to fill the gap between the jack 6c and the annular frame 3.

[0050] like Figure 6 As shown, the control system 7 includes a computer 7e and a pressurizing system 7a, a temperature control system 7b, a seepage pressure system 7c, and a measuring system 7d connected to the computer 7e. The pressurizing system 7a is used to inject and draw out hydraulic oil to the jack 6c of the stress loading device 6 to control the lateral and axial confining pressures of the rock sample 4; the temperature control system 7b is used to adjust the temperature in the test chamber 1; the seepage pressure system 7c is used to control the liquid pressure in the test chamber 1; and the measuring system 7d is used to measure the lateral and axial deformations of the rock sample 4 during the test. The above four systems are all automatically controlled by the computer 7e.

[0051] The rock sample 4 is placed on the first pad 5a of the transmission device 5, and is transported to the middle of the annular frame 3 through the first transmission shaft 5d, and a stress loading device for applying lateral stress to the rock sample is installed. The annular frame 3 is transported to the middle of the square frame 2 through the second transmission shaft 5e, and a stress loading device for applying axial stress to the rock sample is installed. The square frame 2 is transported to the test chamber 1 through the third transmission shaft 5f, and the hatch 1b of the test chamber 1 is closed to carry out a multi-field coupled triaxial test.

[0052] The present invention adopts an annular frame 3 and a square frame 2 to provide reaction force. The test cabin 1 does not bear the reaction force load and can be made of transparent glass material. The test cabin 1 has strong airtightness and observability. The measuring device, temperature control device and water pressure regulating device will not be squeezed and disturbed. The test system has strong stability and reliability and can be used as an effective means to study the mechanical properties of rock mass under multi-field coupling conditions.

[0053] The embodiment of the present invention further provides a sealed chamber type rock mass test method, which is performed using the above test system, and the method comprises the following steps:

[0054] Step 1, preparing rock sample 4: Select a representative rock mass, prepare a rectangular parallelepiped rock sample on site, polish and smooth the six surfaces of the rock sample, apply vaseline on each of the six surfaces, and then place the rock sample on the first pad 5a of the transmission device 5, and push the first pad 5a to slide on the first track 5g to the middle of the two annular frames 3 through the first transmission shaft 5d of the transmission device 5;

[0055] Step 2: Assemble the lateral confining pressure stress loading device:

[0056] 1) Install the rock mass horizontal confining pressure stress loading device

[0057] First, install the stress loading device 6 on the horizontal side of the rock sample, and simultaneously install the first stress loading device 6 and the second stress loading device 6 on the second side 4b and the fourth side 4d of the rock sample 4 in the left annular frame 3, and simultaneously install the third stress loading device 6 and the fourth stress loading device 6 on the second side 4b and the fourth side 4d of the rock sample 4 in the right annular frame 3. After the installation is completed, use a jack to appropriately pressurize the installed stress loading devices 6 to make them tightly connected;

[0058] 2) Install the rock mass vertical confining pressure stress loading device:

[0059] Then install the stress loading device 6 on the vertical side of the rock sample. First, drag the first pad 5a out from the annular frame 3 through the first transmission shaft 5d of the transmission device 5, and install the fifth stress loading device 6 and the sixth stress loading device 6 on the first side 4a of the rock sample 4 in the left and right annular frames 3 respectively, and install the seventh stress loading device 6 and the eighth stress loading device 6 on the third and fourth side 4c of the rock sample 4 in the left and right annular frames 3 respectively.

[0060] 3) Rotate the rotating table inside the second pad 5b to rotate the annular frame 3 by 90 degrees. Push the second pad 5b to slide into the square frame 2 on the second track 5h through the second transmission shaft 5e of the transmission device 5.

[0061] Step 3: Assemble the axial pressure stress loading device:

[0062] The ninth stress loading device 6 and the tenth stress loading device 6 are respectively installed on the upper end surface 4e and the lower end surface 4f of the rock sample 4 in the square frame 2. After the installation is completed, the installed stress loading devices 6 are tightly connected by applying appropriate pressure with a jack. The third pad 5c is pushed by the third transmission shaft 5f of the transmission device 5 to slide on the third track 5i into the test chamber 1.

[0063] Step 4: Assemble the test chamber control system:

[0064] A hydraulic pipeline is used to connect the jack 6c of the stress loading device 6, and is connected to an external oil pump through a sealed channel 1e of the test cabin 1 to form a pressurization system 7a and connected to a computer 7e for control. A temperature regulating device is arranged in the test cabin and is connected to a computer 7e through a sealed channel 1e of the test cabin 1 to form a temperature control system 7b. The injection pipeline and the extraction pipeline on the sealed channel 1e of the test cabin 1 are respectively connected to an external circulating hydraulic pump to form a seepage pressure system 7c and connected to a computer 7e for control. Measuring elements are respectively installed on the six surfaces of the rock sample, and the measuring cables are connected to the measuring system 7d through the sealed channel 1e of the test cabin 1 to form a measuring system 7d and connected to a computer 7e for control.

[0065] Step 5: After the sealed cabin rock test system is installed, the computer 7e can be used to control the pressurization system 7a, the temperature control system 7b, the seepage pressure system 7c, and the measurement system 7d to perform multi-field coupled triaxial tests on large-scale rock samples.

[0066] The stress loading device 6 is installed in such a way that a liquid-permeable steel plate 6a, a force-transmitting steel plate 6b, a jack 6c and a cushion steel plate 6d are sequentially placed on the surface of the rock mass, the liquid-permeable steel plate 6a is placed close to the surface of the rock mass, the force-transmitting steel plate 6b and the jack 6c are sequentially placed, and the cushion steel plate 6d is placed between the jack and the annular frame 3. The jack 6c is in direct contact with the frame beam of the square frame 2.

[0067] The stress of the rock triaxial test of the present invention is concentrated in the loading frame (square frame 2, annular frame 3) and no external reaction force support is required. The test cabin 1 does not bear the reaction force load and occupies a small space. It can be made of transparent glass material and can better seal the liquid filled in the cabin. Since the deformation during the test occurs in the loading frame (square frame 2, annular frame 3), a temperature control device and a measuring device can be safely installed in the gap between the loading frame and the test cabin 1. When the liquid pressure in the cabin increases, the sealing channel 1e between the test device in the cabin and the control system outside the cabin is easy to block, and there will be no leakage due to deformation of the cabin shell 1a. Therefore, the present invention can be used as a stable, effective and reliable solution for multi-field coupled triaxial testing of rock specimens.

[0068] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A sealed cabin rock mass testing system, Features: The invention comprises a test chamber (1), a square frame (2), an annular frame (3), a rock sample (4), a transmission device (5), a stress loading device (6), and a control system (7); the rock sample (4) is a cuboid having six faces; the square frame (2) is used to apply axial confining pressure to the rock sample (4); the annular frame (3) is used to apply lateral confining pressure to the rock sample (4); the transmission device (5) is used to transport the rock sample (4) to the middle of the annular frame (3); after installing a stress loading device (6) for applying lateral stress to the rock sample, the annular frame (3) is transported to the middle of the square frame (2); after installing a stress loading device (6) for applying axial stress to the rock sample, the square frame (2) is transported to the test chamber (1); the control system (7) comprises a computer (7e) and a pressurizing system (7a), a temperature control system (7b), a seepage pressure system (7c), and a measuring system (7d) connected to the computer (7e); The pressurizing system (7a) is used to inject and draw out hydraulic oil into the jack (6c) of the stress loading device (6) to control the lateral confining pressure and axial confining pressure of the rock sample (4); the temperature control system (7b) is used to adjust the temperature in the test chamber (1); the seepage pressure system (7c) is used to control the liquid pressure in the test chamber (1); the measuring system (7d) is used to measure the lateral deformation and axial deformation of the rock sample (4) during the test. The pressurizing system (7a), the temperature control system (7b), the seepage pressure system (7c) and the measuring system (7d) are all automatically controlled by a computer (7e); The rock sample (4) has a total of six surfaces, namely a first side surface (4a), a second side surface (4b), a third side surface (4c), a fourth side surface (4d), an upper end surface (4e) and a lower end surface (4f). The side surfaces are used to apply confining pressure, and the end surfaces are used to apply axial pressure.

2. The sealed chamber rock mass testing system according to claim 1, Features: The test cabin (1) comprises a cabin shell (1a), a cabin door (1b), a sealing ring (1c), and a test bench (1d); the cabin door (1b) is arranged on a side wall of the cabin shell (1a); the sealing ring (1c) is used to improve the sealing performance of the cabin door (1b); and the test bench (1d) is arranged at the bottom of the cabin shell (1a) and is used to place a square frame (2).

3. The sealed chamber rock mass testing system according to claim 1, Features: A stress loading device (6) is provided in each of the left and right frame edges of the square frame (2), and is in contact with the axial upper end surface (4e) and lower end surface (4f) of the rock sample (4).

4. The sealed chamber rock mass testing system according to claim 1, Features: The annular frames (3) have two, and each annular frame (3) is provided with four mutually symmetrical stress loading devices (6). The stress loading devices (6) respectively apply pressure to a first side surface (4a), a second side surface (4b), a third side surface (4c), and a fourth side surface (4d) of the rock sample (4). A certain distance is provided between the stress loading devices (6) in the two annular frames (3) for installing a rock sample deformation measurement system.

5. The sealed cabin rock mass testing system according to claim 1, Features: The transmission device (5) has three pads, namely a first pad (5a) for placing the rock sample (4), a second pad (5b) for placing the square frame (2), and a third pad (5c) for placing the annular frame (3). The second pad (5b) is provided with a rotating platform inside so that the annular frame (3) can rotate. The first pad (5a) is transported on a first track (5g) by a first transmission shaft (5d), the second pad (5b) is transported on a second track (5h) by a second transmission shaft (5e), ​​and the third pad (5c) is transported on a second track (5h) by a third transmission shaft (5e). The transmission shaft (5f) is transported on the third track (5i); during transportation, the rock sample (4) is placed on the first pad (5a) of the transmission device (5), and is transported to the middle of the annular frame (3) through the first transmission shaft (5d), and a stress loading device for applying lateral stress to the rock sample is installed. The annular frame (3) is transported to the middle of the square frame (2) through the second transmission shaft (5e), ​​and a stress loading device for applying axial stress to the rock sample is installed. The square frame (2) is transported to the test chamber (1) through the third transmission shaft (5f).

6. The sealed chamber rock mass testing system according to claim 1, Features: The stress loading device (6) comprises a liquid-permeable steel plate (6a), a force-transmitting steel plate (6b), a jack (6c), and a cushion steel plate (6d). The liquid-permeable steel plate (6a) is adjacent to the rock sample (4) and has grooves engraved on its surface for uniformly applying liquid in the cabin to the surface of the rock sample (4). The force-transmitting steel plate (6b) is used to transfer the load applied by the jack (6c) to the liquid-permeable steel plate (6a). The cushion steel plate (6d) is used to fill the gap between the jack (6c) and the annular frame (3).

7. A sealed chamber rock mass test method, Features The test system according to any one of claims 1 to 6 is carried out, and the method comprises the following steps: Step 1, preparing a rock sample (4): Select a representative rock mass, prepare a rectangular rock sample on site, polish and smooth the six surfaces of the rock sample, apply vaseline on each surface, and then place the rock sample on a first pad (5a) of a transmission device (5), and push the first pad (5a) to slide on a first track (5g) to the middle of two annular frames (3) via a first transmission shaft (5d) of the transmission device (5); Step 2: Assemble the lateral confining pressure stress loading device: 1) Install the rock mass horizontal confining pressure stress loading device First, a stress loading device (6) is installed on the horizontal side of the rock sample, and a first stress loading device and a second stress loading device are simultaneously installed on the second side (4b) and the fourth side (4d) of the rock sample (4) in the left annular frame (3), and a third stress loading device and a fourth stress loading device are simultaneously installed on the second side (4b) and the fourth side (4d) of the rock sample (4) in the right annular frame (3). After the installation is completed, a jack is used to apply appropriate pressure to tightly connect the installed stress loading devices; 2) Install the rock mass vertical confining pressure stress loading device: Install stress loading devices on the side surfaces of the rock sample in the vertical direction, firstly, pull out the first pad (5a) from the annular frame (3) through the first transmission shaft (5d) of the transmission device (5), respectively install the fifth stress loading device and the sixth stress loading device on the first side surfaces (4a) of the rock sample (4) in the left and right annular frames (3), and respectively install the seventh stress loading device and the eighth stress loading device on the third and fourth side surfaces (4c) of the rock sample (4) in the left and right annular frames (3); 3) rotating the rotating table inside the second pad (5b) to rotate the annular frame (3) by 90 degrees, and pushing the second pad (5b) to slide on the second track (5h) into the square frame (2) through the second transmission shaft (5e) of the transmission device (5); Step 3: Assemble the axial pressure stress loading device: A ninth stress loading device and a tenth stress loading device are respectively installed on the upper end surface (4e) and the lower end surface (4f) of the rock sample (4) in the square frame (2); after the installation is completed, appropriate pressure is applied with a jack to tightly connect the installed stress loading devices, and the third pad (5c) is pushed by the third transmission shaft (5f) of the transmission device (5) to slide on the third track (5i) into the test chamber (1); Step 4: Assemble the test chamber control system; Step 5: After the sealed cabin rock mass test system is installed, a computer (7e) is used to control the pressurization system (7a), the temperature control system (7b), the seepage pressure system (7c) and the measurement system (7d) to carry out a multi-field coupled triaxial test on a large-scale rock mass sample.

8. The sealed chamber rock mass testing method according to claim 7, Features: The step 4 specifically comprises: connecting the jack (6c) of the stress loading device (6) with an oil pressure pipeline, and connecting it to an external oil pump through the sealed channel (1e) of the test cabin (1) to form a pressurization system (7a) and connecting it to a computer (7e) for control; arranging a temperature adjustment device in the test cabin and connecting it to a computer (7e) through the sealed channel (1e) of the test cabin (1) to form a temperature control system (7b); connecting the injection pipeline and the extraction pipeline on the sealed channel (1e) of the test cabin (1) to an external circulating hydraulic pump to form a seepage pressure system (7c) and connecting it to a computer (7e) for control; installing measuring elements on the six surfaces of the rock sample respectively; connecting the measuring cable to the measuring system (7d) through the sealed channel (1e) of the test cabin (1) to form a measuring system (7d) and connecting it to a computer (7e) for control.