A slender caisson structure and a method for sinking the caisson in sections

Through the design of the slender caisson structure, the self-weight and friction resistance transmission force are used, combined with the auxiliary sinking of the double-acting jack, the problems of sinking of the caisson and the ballast occupying space are solved, and the controllability of sinking of the caisson is realized and The open construction space is suitable for the construction of circular caissons.

CN111441359BActive Publication Date: 2024-11-15CCCC SECOND HARBOR CONSULTANTS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010349075.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-04-28
Publication Date
2024-11-15
Estimated Expiration
2040-04-28

AI Technical Summary

Technical Problem

In caisson construction, a large amount of ballast material is often required due to insufficient sinking coefficient when sinking, resulting in large construction space occupation, unbalanced ballast causing adverse phenomena such as caisson tilt and sudden sinking. Influence construction control.

Method used

The design of slender caisson structure is the upper and lower section caisson sections, and the lower section length accounts for 2/5 of the total length. The self-weight and friction resistance transmit force through the double-acting jack to sink the lower section caisson section and the lower section is After the joint sinks, pull the upper section to sink to avoid sudden sinking and rotation, reduce or eliminate ballast, and use one-sided thrust to correct the sinking.

Benefits of technology

The controllable state of sinking of the caisson is achieved, which avoids sudden sinking and rotation, reduces construction space occupation, improves construction controllability, and is suitable for the construction of circular caissons.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111441359B_ABST
    Figure CN111441359B_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of caisson engineering, and in particular to a slender caisson structure and a method for sinking a caisson in sections. According to the characteristics of high pressure at the bottom and low pressure at the top of the caisson, the caisson is designed to be an upper caisson section and a lower caisson section. The length of the lower caisson section accounts for 2 / 5 of the total length. Under the action of its own weight, the caisson can basically sink the upper caisson to a certain depth below the mud surface. At this time, the friction between the upper caisson and the soil and its own weight can be used to transfer force to the lower caisson through a double-acting jack to make the lower caisson sink. After the lower caisson sinks to a certain depth, the double-acting jack is used to pull the upper caisson to sink with the help of the gravity and friction of the lower caisson. Since the upper and lower caissons are assisted by the double-acting jack, the sinking of the caisson is in a controllable state, and sudden sinking and rotation can be avoided. Since no ballast is required, the construction space is wide, and the eccentric sinking of the caisson can also be corrected with the help of a single-sided thrust.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of caisson engineering, in particular to a slender caisson structure and a method for sinking a caisson in sections. Background Art

[0002] Caisson construction, especially long caissons, often cannot sink by their own weight during sinking because the sinking coefficient is not large enough, and often requires ballasting. A large amount of ballast material is needed for ballasting, and the ballast material takes up a large amount of construction space, which has an adverse effect on the caisson construction. Unbalanced ballasting can also cause the caisson to tilt, and ballasting can cause adverse phenomena such as sudden sinking, which is not conducive to the construction control of the caisson. Summary of the invention

[0003] In view of the above problems, the present invention provides a slender caisson structure and a method for sinking a caisson in sections. According to the characteristics of high pressure at the bottom and low pressure at the top of the caisson, the caisson is designed to be divided into an upper caisson section and a lower caisson section. The length of the lower caisson section accounts for 2 / 5 of the total length. Under the action of its own weight, the caisson can basically sink the upper caisson section to a certain depth below the mud surface. At this time, the frictional resistance between the upper caisson section and the soil and its own weight can be used to transfer force to the lower caisson section through a double-acting jack to make the lower caisson section sink. After the lower caisson section sinks to a certain depth, the double-acting jack is used to pull the upper caisson section to sink with the help of the gravity and frictional resistance of the lower caisson section. Since the upper and lower caisson sections are assisted by the double-acting jacks, the sinking of the caisson is in a controllable state, which can avoid sudden sinking and rotation. Since no ballast is required, the construction space is wide, and the eccentric sinking of the caisson can also be corrected with the help of a single-sided thrust.

[0004] In order to achieve the above object, the technical solution applied by the present invention is as follows:

[0005] A slender caisson structure comprises a caisson formed by a fixed connection between an upper caisson section and a lower caisson section, embedded steel plates are respectively fixed on the inner walls near the joint between the upper caisson section and the lower caisson section, steel bull legs are fixed on the embedded steel plates, and the steel bull legs on the upper caisson section and the steel bull legs on the lower caisson section are fixedly connected by double-acting jacks, embedded angle steels are respectively fixed on the joint ends between the upper caisson section and the lower caisson section, a steel plate ring is fixed on the outer side of the joint between the upper caisson section and the lower caisson section, the lower end of the steel plate ring is welded to the embedded angle steel on the lower caisson section, and a V-shaped rubber water seal is provided between the upper end of the steel plate ring and the upper caisson section.

[0006] Furthermore, the lower caisson section is provided with a drag reduction platform, a bottom plate groove and a caisson blade foot, and the lower caisson section accounts for 2 / 5 of the total length of the caisson.

[0007] Furthermore, the steel corbel is composed of a reinforcing plate and a supporting plate fixedly connected, the reinforcing plate is respectively fixed to the supporting plate and the embedded steel plate, and the supporting plate is fixed to the double-acting jack.

[0008] Furthermore, the reinforcing plate adopts a right-angled triangle structure, and two right-angled sides of the reinforcing plate are respectively fixed to the support plate and the embedded steel plate.

[0009] Furthermore, the double-acting jack is fixed to the steel bracket between the upper caisson section and the lower caisson section by bolts.

[0010] Furthermore, the V-shaped rubber water seal includes an upper V-shaped rubber water seal and a lower V-shaped rubber water seal. The upper V-shaped rubber water seal is adhered to the inner wall of the steel plate ring by adhesive, and the lower V-shaped rubber water seal is adhered to the outer wall of the lower end of the upper caisson section by adhesive.

[0011] Furthermore, the height of the steel plate ring is about 1000 mm.

[0012] A slender caisson structure, and a method for sinking the caisson structure, comprising the following steps:

[0013] Step 1: Prepare according to the caisson construction steps, and then prefabricate the lower caisson section. When the strength of the lower caisson section reaches the requirements, start sinking the lower caisson section according to the conventional process. When the lower caisson section sinks to a certain depth, stop sinking. Place partition materials on the top of the lower caisson section to prefabricate the upper caisson. The embedded parts must be buried during the prefabrication construction;

[0014] Step 2: After removing the template of the upper caisson section, weld the steel plate ring to the embedded angle steel on the upper part of the lower caisson section, apply adhesive to the outer lower end of the upper caisson section within about 100mm, push the lower V-shaped rubber water seal from top to bottom along the outer wall of the upper caisson section to the lowest end of the upper caisson section, so that the adhesive will bond the lower V-shaped rubber water seal to the outer wall of the upper caisson, and use the same method to bond the upper V-shaped rubber water seal to the upper part of the inner wall of the steel plate ring;

[0015] Step 3: Weld the steel bracket to the embedded steel plate on the inner wall of the caisson, connect the two ends of the double-acting jack to the two corresponding steel brackets on the upper and lower caisson sections with bolts, and connect the double-acting jack and the oil pump with a pressure pipe;

[0016] Step 4: Continue to sink the caisson by its own weight under excavation construction until the upper caisson section enters the soil for a certain length, until the caisson cannot sink under its own weight, start the oil pump to supply oil to the double-acting jack, so that the double-acting jack pushes the lower caisson section to continue to sink under excavation construction. When it sinks about 800mm, the push should be stopped, and the oil should be supplied in the reverse direction to retract the double-acting jack, pulling the upper caisson section to sink about 800mm. Repeat this process several times to sink the caisson to the designed elevation;

[0017] Step 5: Weld the upper caisson section and the lower caisson section into a whole through embedded angle steel, remove the double-acting jack and steel bracket in the well, and carry out the remaining caisson construction.

[0018] Beneficial effects of the present invention:

[0019] 1) The present invention adopts such a structural arrangement. According to the characteristics of large pressure at the bottom of the caisson and small pressure at the top, the caisson is designed to be two caisson sections, an upper caisson section and a lower caisson section. The length of the lower caisson section accounts for 2 / 5 of the total length. Under the action of its own weight, the caisson can basically sink the upper caisson section to a certain depth below the mud surface. At this time, the frictional resistance between the upper caisson section and the soil and its own weight can be used to transmit force to the lower caisson section through a double-acting jack to make the lower caisson section sink. After the lower caisson section sinks to a certain depth, the double-acting jack is used to pull the upper caisson section to sink with the help of the gravity and frictional resistance of the lower caisson section. Since the upper caisson section and the lower caisson section are assisted by the double-acting jack, the sinking of the caisson is in a controllable state, which can avoid sudden sinking and rotation. Since no ballast is required, the construction space is wide, and the eccentric sinking of the caisson can also be corrected with the help of a single-sided thrust force.

[0020] 2) The present invention adopts this process to sink the caisson, which can avoid the disadvantages of difficult sinking of the caisson and large-scale ballast construction, and the controllability of the construction is greatly improved, which should have a relatively wide application prospect;

[0021] 3) The present invention is mainly applicable to the construction of circular caissons. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a vertical cross-sectional view of the overall structure of the present invention;

[0023] Figure 2 It is a side view of the overall structure of the present invention;

[0024] Figure 3 It is a top view of the overall structure of the present invention;

[0025] Figure 4 yes Figure 1 Enlarged view of position A in the middle.

[0026] 1. Caisson; 2. Upper caisson section; 3. Lower caisson section; 4. Drag reduction platform; 5. Bottom plate groove; 6. Embedded angle steel; 7. Steel plate ring; 8. Embedded steel plate; 9. Steel corbel; 10. V-shaped rubber water seal; 11. Reinforcement plate; 12. Double-acting jack; 13. Caisson blade foot; 14. Support plate; 100. Upper V-shaped rubber water seal; 101. Lower V-shaped rubber water seal. DETAILED DESCRIPTION

[0027] The technical solution of the present invention is described below in conjunction with the accompanying drawings and embodiments.

[0028] like Figures 1 to 4 As shown, the slender caisson structure of the present invention comprises a caisson 1 formed by a fixed connection between an upper caisson section 2 and a lower caisson section 3, embedded steel plates 8 are respectively fixed on the inner wall near the joint between the upper caisson section 2 and the lower caisson section 3, steel brackets 9 are fixed on the embedded steel plates 8, and the steel brackets 9 on the upper caisson section 2 and the steel brackets 9 on the lower caisson section 3 are fixedly connected by a double-acting jack 12, and the functions of pushing and pulling the upper caisson section 2 and the lower caisson section 3 are realized by the double-acting jack 12. Embedded angle steels 6 are respectively fixed on the joint ends between the upper caisson section 2 and the lower caisson section 3, a steel plate ring 7 is fixed on the outer side of the joint between the upper caisson section 2 and the lower caisson section 3, the lower end of the steel plate ring 7 is welded to the embedded angle steel 6 on the lower caisson section 3, and a V-shaped rubber water seal 10 is provided between the upper end of the steel plate ring 7 and the upper caisson section 2. Effectively prevent water outside the well from flowing into the well.

[0029] More specifically, the lower caisson section 3 is provided with a drag reduction platform 4 , a bottom plate groove 5 and a caisson blade foot 13 , and the lower caisson section 3 accounts for 2 / 5 of the total length of the caisson 1 .

[0030] More specifically, the steel corbel 9 is composed of a reinforcing plate 11 and a supporting plate 14 fixedly connected, the reinforcing plate 11 is fixed to the supporting plate 14 and the embedded steel plate 8 respectively, and the supporting plate 14 is fixed to the double-acting jack 12 .

[0031] More specifically, the reinforcing plate 11 adopts a right-angled triangle structure, and two right-angled sides of the reinforcing plate 11 are respectively fixed to the support plate 14 and the embedded steel plate 8.

[0032] More specifically, the double-acting jack 12 is fixed to the steel bracket 9 between the upper caisson section 2 and the lower caisson section 3 by bolts.

[0033] More specifically, the V-shaped rubber water seal 10 includes an upper V-shaped rubber water seal 100 and a lower V-shaped rubber water seal 101. The upper V-shaped rubber water seal 100 is adhered to the inner wall of the steel plate ring 7 by adhesive, and the lower V-shaped rubber water seal 101 is adhered to the outer wall of the lower end of the upper caisson section 2 by adhesive.

[0034] More specifically, the height of the steel plate ring 7 is about 1000 mm.

[0035] The present invention adopts such a structural arrangement. According to the characteristics of high pressure at the bottom and low pressure at the top of the caisson 1, the caisson 1 is designed to be a two-section caisson, namely an upper caisson section 2 and a lower caisson section 3. The length of the lower caisson section 3 accounts for 2 / 5 of the total length. Under the action of its own weight, the caisson 1 can basically sink the upper caisson section 2 to a certain depth below the mud surface. At this time, the frictional resistance between the upper caisson section 2 and the soil and its own weight can be used to transfer force to the lower caisson section 3 through the double-acting jack 12, so that the lower caisson section 3 sinks. After the lower caisson section 3 sinks to a certain depth, the double-acting jack 12 is used to pull the upper caisson section 2 to sink with the help of the gravity and frictional resistance of the lower caisson section 3. Since the upper caisson section 2 and the lower caisson section 3 are assisted in sinking by the double-acting jack 12, the sinking of the caisson 1 is in a controllable state, sudden sinking can be avoided, the construction site is open, and the eccentric sinking of the caisson can also be corrected with the help of a unilateral thrust.

[0036] The present invention adopts this process to sink the caisson 1, which can avoid the disadvantages of difficult sinking of the caisson 1 and large-scale ballast construction, greatly improve the controllability of the construction, and should have a relatively wide application prospect;

[0037] The present invention is mainly applicable to the construction of a circular caisson 1 .

[0038] A slender caisson structure, and a method for sinking the caisson structure, comprising the following steps:

[0039] Step 1: Prepare according to the construction steps of caisson 1, and then prefabricate the lower caisson section 3. After the strength of the lower caisson section 3 reaches the requirement, start sinking the lower caisson section 3 according to the conventional process. After the lower caisson section 3 sinks to a certain depth, stop sinking. Place partition materials on the top of the lower caisson section 3 to prefabricate the upper caisson section 2. The embedded parts must be buried during the prefabrication construction;

[0040] Step 2: After the template of the upper caisson section 2 is removed, the steel plate ring 7 is welded to the embedded angle steel 6 on the upper part of the lower caisson section 3, and the adhesive is applied within a range of about 100 mm from the outer lower end of the upper caisson section 2, and the lower V-shaped rubber water seal 101 is pushed from top to bottom along the outer wall of the upper caisson section 2 to the lower end of the upper caisson section 2, so that the adhesive bonds the lower V-shaped rubber water seal 101 to the outer wall of the upper caisson section 2, and the upper V-shaped rubber water seal 100 is bonded to the upper part of the inner wall of the steel plate ring 7 by the same method;

[0041] Step 3: Weld the steel bracket 9 to the embedded steel plate 8 on the inner wall of the caisson 1, connect the two ends of the double-acting jack 12 to the two corresponding steel brackets 9 on the upper caisson section 2 and the lower caisson section 3 with bolts, and connect the double-acting jack 12 with the oil pump with a pressure pipe;

[0042] Step 4: Continue to sink the caisson 1 by its own weight under excavation construction until the upper caisson section 2 enters the soil for a certain length, until the caisson 1 cannot sink under its own weight, start the oil pump to supply oil to the double-acting jack 12, so that the double-acting jack 12 pushes the lower caisson section 3 to continue to sink under excavation construction, and stop pushing when it sinks about 800mm, reverse the supply of oil, so that the double-acting jack 12 retracts, and pulls the upper caisson section 2 to sink about 800mm, and repeat this process several times to sink the caisson 1 to the designed elevation;

[0043] Step 5: Weld the upper caisson section 2 and the lower caisson section 3 into a whole through the embedded angle steel 6, remove the double-acting jack 12 and steel bracket 9 in the well, and carry out the remaining caisson 1 construction.

[0044] The embodiments of the present invention are described above in conjunction with the accompanying drawings, but the present invention is not limited to the above-mentioned specific implementation methods. The above-mentioned specific implementation methods are merely illustrative and not restrictive. Under the enlightenment of the present invention, ordinary technicians in this field can also make many forms without departing from the scope of protection of the present invention and the claims, which all belong to the protection scope of the present invention.

Claims

1. A method for sinking a slender caisson structure in sections, comprising the following steps: Step 1: Prepare according to the construction steps of the caisson (1), then prefabricate the lower caisson section (3), wait until the strength of the lower caisson section (3) reaches the required level, start sinking the lower caisson section (3) according to the conventional process, wait until the lower caisson section (3) sinks to a certain depth and stops sinking, place partition materials on the top of the lower caisson section (3) to prefabricate the upper caisson section (2), and bury the embedded parts during the prefabrication construction; Step 2: After the template of the upper caisson section (2) is removed, the steel plate ring (7) is welded to the embedded angle steel (6) at the upper part of the lower caisson section (3), and the adhesive is applied within 100 mm of the lower end of the outer part of the upper caisson section (2). The lower V-shaped rubber water seal (101) is pushed from top to bottom along the outer wall of the upper caisson section (2) to the lower end of the upper caisson section (2), so that the adhesive bonds the lower V-shaped rubber water seal (101) to the outer wall of the upper caisson section (2), and the upper V-shaped rubber water seal (100) is bonded to the upper part of the inner wall of the steel plate ring (7) by the same method; Step 3: Weld the steel bracket (9) to the embedded steel plate (8) on the inner wall of the caisson (1), connect the two ends of the double-acting jack (12) to the two corresponding steel brackets (9) on the upper caisson section (2) and the lower caisson section (3) with bolts, and connect the double-acting jack (12) and the oil pump with a pressure pipe; Step 4: Continue to sink the caisson (1) by its own weight under the excavation construction until the upper caisson section (2) enters the soil for a certain length, until the caisson (1) cannot sink under its own weight, start the oil pump to supply oil to the double-acting jack (12), so that the double-acting jack (12) pushes the lower caisson section (3) to continue to sink under the excavation construction. When it sinks 800mm, the pushing should be stopped, and the oil supply should be reversed to retract the double-acting jack (12) and pull the upper caisson section (2) to sink 800mm. Repeat this process several times to sink the caisson (1) to the designed elevation; Step 5: Weld the upper caisson section (2) and the lower caisson section (3) into a whole by means of embedded angle steel (6), remove the double-acting jack (12) and steel bracket (9) in the well, and proceed with the remaining caisson (1) construction; The slender caisson structure comprises a caisson (1) formed by a fixed connection between an upper caisson section (2) and a lower caisson section (3), wherein embedded steel plates (8) are respectively fixed on the inner walls near the joint between the upper caisson section (2) and the lower caisson section (3), and steel brackets (9) are fixed on the embedded steel plates (8), and the steel brackets (9) on the upper caisson section (2) and the steel brackets (9) on the lower caisson section (3) are connected by double-acting jacks ( 12) fixed connection, the joint ends between the upper caisson section (2) and the lower caisson section (3) are respectively fixed with embedded angle steels (6), the outer side of the joint between the upper caisson section (2) and the lower caisson section (3) is fixed with a steel plate ring (7), the lower end of the steel plate ring (7) is welded to the embedded angle steel (6) on the lower caisson section (3), and a V-shaped rubber water seal (10) is provided between the upper end of the steel plate ring (7) and the upper caisson section (2); The lower caisson section (3) is provided with a drag reduction platform (4), a bottom plate groove (5) and a caisson blade foot (13), and the lower caisson section (3) accounts for 2 / 5 of the total length of the caisson (1); The steel bracket (9) is composed of a reinforcing plate (11) and a support plate (14) which are fixedly connected, the reinforcing plate (11) being fixed to the support plate (14) and the embedded steel plate (8) respectively, and the support plate (14) being fixed to the double-acting jack (12); The reinforcing plate (11) adopts a right-angled triangle structure, and two right-angled sides of the reinforcing plate (11) are respectively fixed to the support plate (14) and the embedded steel plate (8); The double-acting jack (12) is fixed to the steel bracket (9) between the upper caisson section (2) and the lower caisson section (3) by bolts; The V-shaped rubber water seal (10) comprises an upper V-shaped rubber water seal (100) and a lower V-shaped rubber water seal (101), wherein the upper V-shaped rubber water seal (100) is adhered to the inner wall of the steel plate ring (7) by adhesive, and the lower V-shaped rubber water seal (101) is adhered to the outer wall of the lower end of the upper caisson section (2) by adhesive; The height of the steel plate ring (7) is 1000 mm.