A plug-and-play dynamic capacity expansion device and control method for distribution transformer
Through the plug-and-play dynamic capacity increase device of the distribution transformer, the power collection and control system is used to dynamically adjust the distribution transformer load, which solves the problems of distribution transformer overload and low load rate in rural power grid areas, and improves the stability and economy of power supply. .
Patent Information
- Application Number
- CN202010477478.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-05-29
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2040-05-29
AI Technical Summary
In rural power grid areas, distribution transformers in Taiwan areas are overloaded due to seasonal or periodic peak power consumption, resulting in unstable power supply. When the load factor is low, the transformer is idle, resulting in increased line losses and low economic benefits.
A plug-and-play dynamic capacity increase device for distribution transformers is designed, including a power collection device, a main controller, a high-voltage switch, a low-voltage switch, a phase sequence protector and a communication device. By collecting the load voltage and current in real time, the load rate is calculated. When the preset value is reached, it is dynamically put in or out to share the load of the transformer and ensure the reliability of power supply.
When the distribution transformer is overloaded, it dynamically increases the capacity to share the load to ensure safe and stable operation. When the load returns to normal, it exits the dynamic capacity increase to reduce power loss and improve the economy and flexibility of the power grid.
Smart Images

Figure CN111446720B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of intelligent power distribution, and in particular to a plug-and-play dynamic capacity increasing device for a distribution transformer and a control method. Background Art
[0002] With the economic development and social progress of my country, the electricity consumption of industrial and agricultural production and people's livelihood is also rising year by year, and the demand for electricity is showing a diversified trend, and the power supply requirements of the power sector are also getting higher and higher. In many rural power grid areas covered by the State Grid Corporation, due to the weak local grid structure, the guarantee of power supply is still a prominent problem. In particular, the annual electricity load rate is low, the peak electricity consumption is time-based or seasonal, and the peak load is prominent during a specific period, which often causes the distribution transformer in the substation to be overloaded, and even burns out the transformer and the reliability of power supply cannot be guaranteed. At present, the use of replacing a large transformer or splitting the substation to add a transformer will cause the substation load rate to be in a light load state for a long time, resulting in increased line losses, idle capacity, and low economic benefits. Therefore, a device is needed that can be flexibly put into and withdrawn to share the transformer load when the transformer is heavily overloaded. Summary of the invention
[0003] The present invention provides a plug-and-play dynamic capacity expansion device and a control method for distribution transformers, which are used to solve the problems of seasonal overload and long-term overload throughout the year in distribution transformers in distribution stations. When the distribution transformers in the distribution stations are heavily overloaded, the load is shared to ensure the safe and stable operation of the distribution transformers in the distribution stations and improve the power supply reliability.
[0004] In a first aspect, a distribution transformer plug-and-play dynamic capacity expansion device is provided, comprising a power collection device, a main controller, a high-voltage switch, a low-voltage switch, a distribution transformer, a phase sequence protector, and a communication device;
[0005] The power collection device is connected to the main line on the low-voltage side of the substation distribution transformer, and the secondary output line of the power collection device is connected to the input of the main controller; the high-voltage switch is connected in series between the high-voltage side of the distribution transformer and the high-voltage side of the substation distribution transformer, and the low-voltage switch is connected in series between the low-voltage side of the distribution transformer and the low-voltage side of the substation distribution transformer, and the main controller is communicatively connected to the control ends of the high-voltage switch and the low-voltage switch; the phase sequence protector is connected in series between the low-voltage side of the distribution transformer and the low-voltage switch, and the phase sequence protector is also communicatively connected to the main controller; the communication device is communicatively connected to the main controller.
[0006] During operation, the load voltage and current on the low-voltage side of the distribution transformer in the substation are collected through the power collection device and transmitted to the main controller. The main controller calculates the load rate of the distribution transformer in the substation based on the load voltage and current on the low-voltage side of the distribution transformer in the substation. When the load rate of the distribution transformer in the substation is greater than the first preset value stored in the main controller, that is, when the distribution transformer in the substation is heavily overloaded, the main controller first sends a closing instruction to the control end of the high-voltage switch to control the closing of the high-voltage switch, and then sends a closing instruction to the control end of the low-voltage switch after a preset delay to control the closing of the low-voltage switch, so as to realize the input of the dynamic capacity increase device, share the load, ensure the stable operation of the distribution transformer in the substation, and improve the power supply reliability. When the high-voltage switch and the low-voltage switch are in the closed state, and the load rate of the distribution transformer in the substation is less than the second preset value stored in the main controller, that is, the peak of power consumption in the substation has passed, and the load of the distribution transformer in the substation has returned to normal, at this time, the main controller first sends a disconnection instruction to the control end of the low-voltage switch to control the disconnection of the low-voltage switch, and then sends a disconnection instruction to the control end of the high-voltage switch after a preset delay to control the disconnection of the high-voltage switch, so as to realize the exit of the dynamic capacity increase device.
[0007] Furthermore, the power collection device includes a voltage transformer and a current transformer, both of which are connected to the low-voltage side main line of the distribution transformer in the substation, and the secondary output lines of the voltage transformer and the current transformer are connected to the input of the main controller. The voltage transformer is used to detect the load voltage on the low-voltage side of the distribution transformer in the substation and transmit it to the main controller, and the current transformer is used to detect the load current on the low-voltage side of the distribution transformer in the substation and transmit it to the main controller.
[0008] Furthermore, the high-voltage switch is a contactor.
[0009] Furthermore, the low-voltage switch is a contactor.
[0010] Furthermore, the phase sequence protector is a phase sequence relay, which is used to detect the phase sequence on the low-voltage side of the distribution transformer and send the detection result to the main controller. If the phase sequence at both ends of the phase sequence protector does not match, the output relay of the phase sequence protector cannot be connected, thereby playing a protective role and avoiding the occurrence of accidents.
[0011] Furthermore, the communication device is a 4G router, which is used to realize 4G wireless communication between the main controller and the outside.
[0012] Furthermore, the communication device is connected to the main controller via Ethernet communication.
[0013] In a second aspect, a control method for the plug-and-play dynamic capacity expansion device of a distribution transformer as described above is provided, comprising:
[0014] The main controller obtains the low-voltage side load voltage and current of the distribution transformer in the substation in real time through the power collection device, and calculates the load rate of the distribution transformer in the substation accordingly;
[0015] When the high-voltage switch and the low-voltage switch are in the disconnected state, the load rate of the distribution transformer in the substation is greater than the first set value, and there is no abnormal alarm, the main controller first controls the high-voltage switch to close, and then controls the low-voltage switch to close after a delay;
[0016] When the high-voltage switch and the low-voltage switch are in the closed state and the load rate of the distribution transformer in the substation is less than the second set value, the main controller first controls the low-voltage switch to open, and then controls the high-voltage switch to open after a delay.
[0017] Furthermore, the first set value is 0.9 times the rated capacity of the distribution transformer in the substation, and the second set value is 0.6 times the rated capacity of the distribution transformer in the substation.
[0018] Beneficial Effects
[0019] The present invention proposes a plug-and-play dynamic capacity increasing device and control method for distribution transformers. The load voltage and current on the low-voltage side of the distribution transformer in the substation are collected by an electric quantity collecting device and transmitted to a main controller. The main controller calculates the load rate of the distribution transformer in the substation based on the load voltage and current on the low-voltage side of the distribution transformer in the substation. When the load rate of the distribution transformer in the substation is greater than the first preset value stored in the main controller, that is, when the distribution transformer in the substation is heavily overloaded, the main controller first controls the high-voltage switch to close, and then controls the low-voltage switch to close after a delay of a preset time, so as to realize the input of the dynamic capacity increasing device. When the high-voltage switch and the low-voltage switch are in a closed state, and the load rate of the distribution transformer in the substation is less than the second preset value stored in the main controller, that is, when the load of the distribution transformer in the substation is restored to light load, the main controller first controls the low-voltage switch to open, and then controls the high-voltage switch to open after a delay of a preset time, so as to realize the exit of the dynamic capacity increasing device. When the distribution transformer in the substation is heavily overloaded, the dynamic capacity increasing device is put into operation to share the load, thereby ensuring the safe and stable operation of the distribution transformer in the substation. When the distribution transformer in the substation is lightly loaded, the dynamic capacity increasing device is exited, thereby reducing power loss and improving the economy of the power grid. The dynamic capacity expansion device is plug-and-play, reusable and has good flexibility. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 The present invention provides a schematic diagram of the structure of a plug-and-play dynamic capacity expansion device for a distribution transformer. DETAILED DESCRIPTION
[0021] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.
[0022] like Figure 1 As shown, this embodiment provides a distribution transformer plug-and-play dynamic capacity expansion device, including an electric quantity collection device 3, a main controller 2, a high-voltage switch 4, a low-voltage switch 6, a distribution transformer 1, a phase sequence protector 5, and a communication device 7;
[0023] The power collection device 3 is connected to the main line on the low-voltage side of the substation distribution transformer, and the secondary output line of the power collection device 3 is connected to the input of the main controller 2; the high-voltage switch 4 is connected in series between the high-voltage side of the distribution transformer 1 and the high-voltage side of the substation distribution transformer, and the low-voltage switch 6 is connected in series between the low-voltage side of the distribution transformer 1 and the low-voltage side of the substation distribution transformer, and the main controller 2 is communicatively connected to the control ends of the high-voltage switch 4 and the low-voltage switch 6; the phase sequence protector 5 is connected in series between the low-voltage side of the distribution transformer 1 and the low-voltage switch 6, and the phase sequence protector 5 is also communicatively connected to the main controller 2; the communication device 7 is communicatively connected to the main controller 2.
[0024] During operation, the load voltage and current on the low-voltage side of the distribution transformer in the substation are collected through the power collection device 3 and transmitted to the main controller 2. The main controller 2 calculates the load rate of the distribution transformer in the substation based on the load voltage and current on the low-voltage side of the distribution transformer in the substation. When the load rate of the distribution transformer in the substation is greater than the first preset value stored in the main controller 2, that is, when the distribution transformer in the substation is heavily overloaded, the main controller 2 first sends a closing command to the control end of the high-voltage switch 4 to control the high-voltage switch 4 to close, and then sends a closing command to the control end of the low-voltage switch 6 after a delay of a preset time to control the low-voltage switch 6 to close, so as to realize the input of the dynamic capacity increase device, share the load, ensure the stable operation of the distribution transformer in the substation, and improve the reliability of power supply. When the high-voltage switch 4 and the low-voltage switch 6 are in the closed state, and the load rate of the distribution transformer in the substation is less than the second preset value stored in the main controller 2, that is, the peak of power consumption in the substation has passed and the load of the distribution transformer in the substation has returned to normal, at this time, the main controller 5 first sends a disconnection command to the control end of the low-voltage switch 6 to control the low-voltage switch 6 to disconnect, and then sends a disconnection command to the control end of the high-voltage switch 4 after a preset delay to control the high-voltage switch 4 to disconnect, thereby realizing the exit of the dynamic capacity expansion device.
[0025] Specifically, the power collection device 3 includes a voltage transformer and a current transformer, both of which are connected to the low-voltage side main line of the distribution transformer in the substation, and the secondary output lines of the voltage transformer and the current transformer are connected to the input of the main controller 2. The voltage transformer is used to detect the load voltage on the low-voltage side of the distribution transformer in the substation and transmit it to the main controller 2, and the current transformer is used to detect the load current on the low-voltage side of the distribution transformer in the substation and transmit it to the main controller 2.
[0026] In the specific implementation, the high-voltage switch 4 and the low-voltage switch 6 are both contactors; the phase sequence protector 5 is a phase sequence relay, which is used to detect the phase sequence on the low-voltage side of the distribution transformer 1, and send the detection result to the main controller 2. If the phase sequence at both ends of the phase sequence protector 5 does not match, the output relay of the phase sequence protector 5 cannot be connected, thereby playing a protective role to avoid accidents. At the same time, when the main controller 2 receives the phase sequence error signal sent by the phase sequence protector 5, it sends an alarm signal to stop controlling the high-voltage switch 4 and the low-voltage switch 6; the communication device 7 is a 4G router, which is connected to the main controller 2 through Ethernet communication, and is used to realize 4G wireless communication between the main controller 2 and the outside, and realize wireless communication between the main controller 2 and the remote monitoring platform, so as to realize remote monitoring and control; the main controller 2 adopts an embedded microprocessor to obtain the voltage and current values collected by the power collection device 3, compare them with the preset values, and control the opening and closing of the high-voltage switch 4 and the low-voltage switch 6 according to the switch and the phase sequence protector status.
[0027] The present invention also provides a control method for the plug-and-play dynamic capacity expansion device of the distribution transformer provided in the above embodiment, comprising:
[0028] The main controller obtains the low-voltage side load voltage and current of the distribution transformer in the substation in real time through the power collection device, and calculates the load rate of the distribution transformer in the substation accordingly;
[0029] When the high-voltage switch and the low-voltage switch are in the disconnected state, the load rate of the distribution transformer in the substation area is greater than the first set value, and there is no abnormal alarm, the main controller first controls the high-voltage switch to close, and then controls the low-voltage switch to close after a delay; the abnormal alarm refers to the main controller issuing an abnormal alarm when the phase sequence protector detects that the phase sequence at both ends does not match;
[0030] When the high-voltage switch and the low-voltage switch are in the closed state and the load rate of the distribution transformer in the substation is less than the second set value, the main controller first controls the low-voltage switch to open, and then controls the high-voltage switch to open after a delay.
[0031] During specific implementation, the first set value is set to 0.9 times the rated capacity of the distribution transformer in the substation, and the second set value is set to 0.6 times the rated capacity of the distribution transformer in the substation.
[0032] The plug-and-play dynamic capacity increasing device and control method provided by the present invention can be put into operation when the distribution transformer in the substation is overloaded to share the load, thereby ensuring the safe and stable operation of the distribution transformer in the substation, and can be withdrawn when the distribution transformer in the substation is lightly loaded, thereby reducing power loss and improving the economy of the power grid. The device is plug-and-play, reusable, and has good flexibility.
[0033] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A control method for a plug-and-play dynamic capacity expansion device for a distribution transformer, characterized in that: The distribution transformer plug-and-play dynamic capacity expansion device includes an electric quantity collection device, a main controller, a high-voltage switch, a low-voltage switch, a distribution transformer, a phase sequence protector, and a communication device; The power collection device is connected to the main line on the low-voltage side of the distribution transformer in the substation, and the secondary output line of the power collection device is connected to the input of the main controller; the high-voltage switch is connected in series between the high-voltage side of the distribution transformer and the high-voltage side of the distribution transformer in the substation, and the low-voltage switch is connected in series between the low-voltage side of the distribution transformer and the low-voltage side of the distribution transformer in the substation, and the main controller is connected in communication with the control end of the high-voltage switch and the low-voltage switch; the phase sequence protector is connected in series between the low-voltage side of the distribution transformer and the low-voltage switch, and the phase sequence protector is also connected in communication with the main controller; The communication device is communicatively connected with the main controller; The control method comprises: The main controller obtains the low-voltage side load voltage and current of the distribution transformer in the substation in real time through the power collection device, and calculates the load rate of the distribution transformer in the substation accordingly; When the high-voltage switch and the low-voltage switch are in the disconnected state, the load rate of the distribution transformer in the substation is greater than the first set value, and there is no abnormal alarm, the main controller first controls the high-voltage switch to close, and then controls the low-voltage switch to close after a delay; When the high-voltage switch and the low-voltage switch are in the closed state and the load rate of the distribution transformer in the substation is less than the second set value, the main controller first controls the low-voltage switch to open, and then controls the high-voltage switch to open after a delay.
2. The control method of the distribution transformer plug-and-play dynamic capacity expansion device according to claim 1 is characterized in that: The power collection device includes a voltage transformer and a current transformer, both of which are connected to the low-voltage main line of the distribution transformer in the substation, and the secondary output lines of the voltage transformer and the current transformer are connected to the input of the main controller.
3. The control method of the distribution transformer plug-and-play dynamic capacity expansion device according to claim 1, characterized in that: The high voltage switch is a contactor.
4. The control method of the distribution transformer plug-and-play dynamic capacity expansion device according to claim 1, characterized in that: The low voltage switch is a contactor.
5. The control method of the distribution transformer plug-and-play dynamic capacity expansion device according to claim 1, characterized in that: The phase sequence protector is a phase sequence relay.
6. The control method of the distribution transformer plug-and-play dynamic capacity expansion device according to claim 1, characterized in that: The communication device is a 4G router.
7. The control method of the distribution transformer plug-and-play dynamic capacity expansion device according to claim 6, characterized in that: The communication device is connected to the main controller via Ethernet communication.
8. The control method of the distribution transformer plug-and-play dynamic capacity expansion device according to claim 1, characterized in that: The first set value is 0.9 times the rated capacity of the distribution transformer in the substation, and the second set value is 0.6 times the rated capacity of the distribution transformer in the substation.