Trackless measurement device for the entire system of subway power supply project

By designing a system-free trackless measurement device for subway power supply engineering including hydraulic lifting module, leveling moving module and three-dimensional translation system, the measurement problem under trackless conditions in electrified railway and rail transit construction was solved, and the subway tunnel was realized The measurement of efficient power supply system avoids slow construction progress and safety hazards.

CN111619634BActive Publication Date: 2024-11-22CHINA RAILWAY CONSTR ELECTRIFICATION BUREAU GRP SOUTH ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010463581.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-05-27
Publication Date
2024-11-22
Estimated Expiration
2040-05-27

AI Technical Summary

Technical Problem

In the construction of electrified railways and rail transit, it is difficult for the prior art to effectively measure the power supply system in subway tunnels under trackless conditions, resulting in slow construction progress and increased safety risks.

Method used

A trackless measurement device for the entire system of subway power supply engineering is designed, including walking modules, simulated track devices and measurement devices. It adopts hydraulic lifting modules, leveling moving modules and three-dimensional translation systems, and can install measuring devices on simulated tracks to achieve height. Adjustable simulated tracks and flexible three-dimensional translation are suitable for power supply system measurements within subway tunnels.

Benefits of technology

The device can flexibly position, save manpower, improve measurement efficiency, and avoid safety hazards and slow progress caused by tight track laying construction and insufficient construction period. It is suitable for trackless measurement of power supply systems in subway tunnels.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111619634B_ABST
    Figure CN111619634B_ABST
Patent Text Reader

Abstract

The present invention provides a trackless measuring device for the whole system of a subway power supply project, comprising a walking module, a simulated track device and a measuring device, wherein the simulated track device is installed on the walking module, and the measuring device is installed in the middle of the simulated track device. The present invention has wide versatility and is used to measure and simulate the data of tracks at various points in a subway tunnel, and then cooperate with a total station and a laser measuring instrument to measure the positioning points of contact network, ring network support points, evacuation platform points, communications, signals and other pipelines in the power supply system. Since there are many measuring points and the travel is long, the application of the trolley can be flexible in positioning, convenient for adjustment, and save manpower.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of trackless measurement in tunnels during electrified railway and rail transit construction, and in particular to a full-system trackless measurement device for a subway power supply project. Background Art

[0002] In the construction of electrified railway and rail transit power supply system, it is usually necessary to carry out construction according to the progress of track laying construction, which often compresses the construction period of the power supply system. Measurement is the first step in the construction of the power supply system and is also the most critical. Completing the measurement in advance before track laying will greatly improve the construction progress and avoid the safety risks of rushing work due to tight construction period. Therefore, a suitable trackless measurement device for the whole system of subway power supply engineering is invented for trackless conditions. Summary of the invention

[0003] The purpose of the present invention is to provide a trackless measurement device for the entire system of a subway power supply project, which can be effectively used in the trackless measurement of the power supply system in a subway tunnel, avoiding the safety hazards and slow progress caused by some uncontrollable factors due to tight track laying construction, insufficient construction period and working surface.

[0004] The technical solution of the present invention:

[0005] A full-system trackless measuring device for a subway power supply project comprises a walking module, a simulated track device and a measuring device, wherein the simulated track device is installed on the walking module, and the measuring device is installed in the middle of the simulated track device. The simulated track device comprises a hydraulic jacking module, a leveling movement module and a simulated track module, wherein the hydraulic jacking module comprises a multi-section hydraulic cylinder system and a jacking frame system, wherein a leveling movement module is installed above the jacking frame system, wherein the simulated track module is installed above the leveling movement module to form a simulated track device with adjustable height, wherein the measuring device comprises a three-dimensional translation system, wherein the three-dimensional translation system comprises a Y-axis translation stage, an X-axis movement module and a Z-axis translation stage, wherein the Y-axis translation stage is installed on the X-axis movement module and moves along the X-axis direction, and wherein the Z-axis translation stage is installed on the Y-axis translation stage and moves along the Y-axis direction.

[0006] The multi-section hydraulic cylinder system includes a multi-section hydraulic cylinder, a hydraulic cylinder joint and a manual hydraulic pump, wherein the multi-section hydraulic cylinder is connected to the chassis, the multi-section hydraulic cylinder system is connected to the jacking frame system through the hydraulic cylinder joint, and the multi-section hydraulic cylinder is driven by the manual hydraulic pump to adjust the jacking frame system. The jacking frame system includes a jacking frame, 3 sets of vertical linear guide systems and a vertical steel plate ruler measuring device. The center position of the jacking frame is fixedly connected to the hydraulic cylinder joint, the vertical linear guide system is fixedly installed on the jacking frame, and the vertical steel plate ruler measuring device is fixedly installed on the chassis and is located on the outside of the jacking frame.

[0007] The leveling mobile module includes three leveling systems and a mobile frame system, wherein the lower parts of the three leveling systems are connected to the jacking frame system, and the upper parts are connected to the mobile frame system. The mobile frame system includes a mobile operating system, a mobile frame and a connecting frame, wherein two sets of horizontal linear guide rail systems are installed on both sides of the mobile frame for moving in coordination with the mobile operating system, the guide rails of the horizontal linear guide rail system are fixedly connected to the mobile frame, the sliders of the horizontal linear guide rail system are fixed to the connecting frame, and the connecting frame is provided with a horizontal display bubble.

[0008] The simulated track module includes a track frame and an elevator system. One end of the track frame is connected to the moving frame, and the other end is connected to the top of the elevator system.

[0009] The walking module includes a handrail system, a chassis system and a wheelset system. The handrail system includes a handle, two pull rods are welded below the handle, and a connecting single ear is arranged at the bottom of the pull rod. The chassis system includes an upper aluminum alloy tube group and a lower aluminum alloy tube group. One end of the upper aluminum alloy tube group is provided with a connecting double ear, and the connecting single ear is connected to the connecting double ear through a pin shaft. The four ends at the bottom of the upper aluminum alloy tube group are respectively welded with wheelset flange plates. The wheelset system is installed below the wheelset flange plate. The pipe group is also provided with two first guide rail link block flange plates and a second guide rail link block flange plate for connecting the leveling moving module, the upper aluminum alloy pipe group is also provided with a two-hole boss flange plate for connecting the steel ruler support of the trackless measuring device, the middle aluminum square pipe of the lower aluminum alloy pipe group is welded with a square boss plate for connecting to the multi-section hydraulic cylinder of the trackless measuring device, and the end of the lower aluminum alloy pipe group away from the handrail system is welded with a long boss plate for connecting to the manual hydraulic pump of the trackless measuring device.

[0010] The wheelset system includes fixed casters installed on two wheelset flange plates away from the handrail system and movable casters installed on two wheelset flange plates close to the handrail system. A brake device is also installed on the movable casters. A support rod is welded under the two pull rods. Pin holes are provided on the single connecting ear and the double connecting ears for convenient passage of the pin shaft.

[0011] The X-axis moving module includes two X-axis linear horizontal guide rails installed on the mobile frame system, a slider and a locking device are installed on the X-axis linear horizontal guide rails, the slider and the locking device slide along the X-axis linear horizontal guide rails, a steel ruler is arranged next to the X-axis linear horizontal guide rail, the steel ruler is arranged parallel to the X-axis linear horizontal guide rail, a pointer is installed on the slider and the locking device, and the pointer is facing the steel ruler.

[0012] The Y-axis translation stage includes a Y-axis base plate, which is installed between two sliders and a locking device. A Y-axis slider is installed on the Y-axis base plate, and the Y-axis slider is connected to a Y-axis handwheel. The Y-axis handwheel is adjusted to control the distance the Y-axis slider moves along the Y-axis.

[0013] The Z-axis translation stage includes a Z-axis connecting plate, the bottom surface of which is connected to the Y-axis slider, the Z-axis slider is installed on the Z-axis connecting plate, the Z-axis slider is connected to the Z-axis handwheel, and the Z-axis base plate is installed on the Z-axis slider. The Z-axis handwheel is adjusted to control the movement distance of the Z-axis slider and the Z-axis base plate along the Z-axis.

[0014] The three leveling systems are arranged in an equilateral triangle.

[0015] Compared with the prior art, the beneficial effects of the present invention are: wide versatility is used to measure and simulate the data of various track points in subway tunnels, and then cooperate with the total station and laser measuring instrument to measure the power supply system including contact network positioning points, ring network support points, evacuation platform points, communications, signals and other pipeline positioning points. Due to the large number of measuring points and the long travel distance, the application of this trolley can be flexibly positioned, conveniently adjusted, and save manpower. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the overall structure of the present invention.

[0017] Figure 2 It is a schematic diagram of the overall structure of the walking module of the present invention.

[0018] Figure 3 It is a schematic diagram of the structure of the hand-held system of the present invention.

[0019] Figure 4 It is a schematic diagram of the chassis system structure of the present invention.

[0020] Figure 5 It is a schematic diagram of the connection structure of the hydraulic jacking module and the leveling movement module of the present invention.

[0021] Figure 6 It is a schematic diagram of the structure of the three-dimensional translation system of the present invention.

[0022] Figure 7 It is a schematic diagram of the jacking frame structure of the present invention.

[0023] Figure 8 It is a schematic diagram of the mobile frame structure of the present invention.

[0024] Fig. 9 It is a schematic diagram of the connection frame structure of the present invention.

[0025] Fig.10 It is a schematic diagram of the track frame structure of the present invention. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0027] See also Figure 1-Figure 10 , the present invention provides a technical solution:

[0028] A full-system trackless measuring device for a subway power supply project comprises a walking module 1, a simulated track device 2 and a measuring device 3, wherein the simulated track device 2 is mounted on the walking module 1, and the measuring device 3 is mounted in the middle of the simulated track device 2, wherein the simulated track device comprises a hydraulic jacking module 21, a leveling movement module 22 and a simulated track module 23, wherein the hydraulic jacking module 21 comprises a multi-section hydraulic cylinder system 211 and a jacking frame system 212, wherein the leveling movement module 22 is mounted above the jacking frame system 212, wherein the simulated track module 23 is mounted above the leveling movement module 22 to form a simulated track device 2 with adjustable height, wherein the measuring device 3 comprises a three-dimensional translation system 31, wherein the three-dimensional translation system 31 comprises a Y-axis translation stage 311, an X-axis movement module 312 and a Z-axis translation stage 313, wherein the Y-axis translation stage 311 is mounted on the X-axis movement module 312 and moves along the X-axis direction, and the Z-axis translation stage 313 is mounted on the Y-axis translation stage 311 and moves along the Y-axis direction.

[0029] The multi-section hydraulic cylinder system 211 includes a multi-section hydraulic cylinder 2111, a hydraulic cylinder joint 2112 and a manual hydraulic pump 2113, wherein the multi-section hydraulic cylinder 2111 is connected to the chassis, and the multi-section hydraulic cylinder system 211 is connected to the jacking frame system 212 through the hydraulic cylinder joint 2112. The multi-section hydraulic cylinder 2111 is driven by the manual hydraulic pump 2113 to adjust the jacking frame system 212. The jacking frame system 212 includes a jacking frame 2121, 3 sets of vertical linear guide systems 2122 and a vertical steel plate ruler measuring device 2123. The center position of the jacking frame 2121 is fixedly connected to the hydraulic cylinder joint 2112, the vertical linear guide system 2122 is fixedly installed on the jacking frame 2121, and the vertical steel plate ruler measuring device 2123 is fixedly installed on the chassis and is located on the outside of the jacking frame 2121.

[0030] The leveling mobile module 22 includes three leveling systems 221 and a mobile frame system 222, wherein the lower parts of the three leveling systems 221 are connected to the jacking frame system 212, and the upper parts are connected to the mobile frame system 222, and the mobile frame system 222 includes a mobile operating system 2221, a mobile frame 2222 and a connecting frame 2223, wherein two sets of horizontal linear guide systems 22221 are installed on both sides of the mobile frame 2222 for cooperating with the mobile operating system 2221 for movement, the guide rails of the horizontal linear guide system 22221 are fixedly connected to the mobile frame 2222, the sliders of the horizontal linear guide system 22221 are fixed to the connecting frame 2223, and the connecting frame 2223 is provided with a horizontal display bubble.

[0031] The simulated track module 23 includes a track frame 231 and an elevator system 232 . One end of the track frame 231 is connected to the moving frame 2222 , and the other end is connected to the top of the elevator system 232 .

[0032] The walking module includes a handrail system 11, a chassis system 12 and a wheelset system 13. The handrail system 11 includes a handle 110, two pull rods 111 are welded below the handle 110, and a connecting single ear 113 is arranged at the bottom of the pull rod 111. The chassis system 12 includes an upper aluminum alloy tube group 121 and a lower aluminum alloy tube group 122. One end of the upper aluminum alloy tube group 121 is provided with a connecting double ear 1211, and the connecting single ear 113 is connected to the connecting double ear 1211 through a pin shaft. The four ends at the bottom of the upper aluminum alloy tube group 121 are respectively welded with wheelset flange plates 1215, and the wheelset system 13 is installed below the wheelset flange plate 1215. The upper aluminum alloy tube group 121 is also provided with two first guide rail link block flange plates 1212 and a second guide rail link block flange plate 1212 for connecting the leveling moving module 22, and the upper aluminum alloy tube group 121 is also provided with a two-hole boss flange plate 1214 for connecting the steel ruler support of the trackless measuring device, and a square boss plate 1221 for connecting to the multi-section hydraulic cylinder 2111 of the trackless measuring device is welded on the middle aluminum square tube of the lower aluminum alloy tube group 122, and a long boss plate 1222 is welded on the end of the lower aluminum alloy tube group 122 away from the handrail system 11 for connecting to the manual hydraulic pump 2113 of the trackless measuring device.

[0033] The wheel pair system 13 includes a fixed caster 131 installed on two wheel pair flange plates 1215 away from the handrail system 11 and a movable caster 132 installed on two wheel pair flange plates 1215 close to the handrail system 11. A brake device 133 is also installed at the movable caster 132. A support rod 112 is also welded under the two pull rods 111. The connecting single ear 113 and the connecting double ears 1211 are both provided with a pin hole 114 for facilitating the passage of the pin shaft.

[0034] The chassis and the handle of the trolley are made of aluminum alloy, which reduces the overall weight of the vehicle. The trolley is mainly suitable for traveling in circular tunnels and general roads, and can be fixed by two brake casters when reaching the designated point.

[0035] The X-axis moving module 312 includes two X-axis linear horizontal guide rails 3121 installed on the mobile frame system 222, and a slider and a locking device 3124 are installed on the X-axis linear horizontal guide rails 3121. The slider and the locking device 3124 slide along the X-axis linear horizontal guide rails 3121. A steel ruler 3122 is arranged next to the X-axis linear horizontal guide rails 3121. The steel ruler 3122 is arranged parallel to the X-axis linear horizontal guide rails 3121. A pointer 3123 is installed on the slider and the locking device 3124, and the pointer 3123 is directly opposite to the steel ruler 3122.

[0036] The Y-axis translation stage 311 includes a Y-axis base plate 3112, which is installed between two sliders and a locking device 3124. A Y-axis slider 3111 is installed on the Y-axis base plate 3112. The Y-axis slider 3111 is connected to a Y-axis handwheel 3113. The Y-axis handwheel 3113 is adjusted to control the movement distance of the Y-axis slider 3111 along the Y-axis.

[0037] The Z-axis translation stage 313 includes a Z-axis connecting plate 3131, the bottom surface of which is connected to the Y-axis slider 3111, a Z-axis slider 3132 is installed on the Z-axis connecting plate 3131, the Z-axis slider 3132 is connected to the Z-axis handwheel 3133, and a Z-axis base plate 3134 is installed on the Z-axis slider 3132. The Z-axis handwheel 3133 is adjusted to control the movement distance of the Z-axis slider 3132 and the Z-axis base plate 3134 along the Z-axis.

[0038] The three leveling systems 221 are arranged in an equilateral triangle.

[0039] The simulated track device is mainly composed of a simple simulated track and an adjustment part. The simulated track and the main connecting parts are made of aluminum alloy to reduce the overall weight of the vehicle body. The simulated track is used to place the DJJ-8 laser measuring instrument. The simple track surface is about 1500mm long and 1435mm wide. The simulated track and the manual worm gear elevator are connected together through the capstan and the shaft to form a movable hinge structure. The outer rail of the simulated track can be adjusted by shaking the hand wheel. The height can be read out through the scale ruler. The maximum adjustment is 150mm.

[0040] The entire track surface platform can be adjusted to absolute level. There is a bubble display on the plane, and in the middle is an adjusting handwheel. The two ends of the adjusting handwheel are connected to a positive screw rod and a negative screw rod respectively. The two ends of the screw rod are connected to a universal joint and a one-way joint respectively. The universal joint and the support seat are connected together through the supporting shaft. When the adjusting handwheel is turned, the screw rod will move up or down at the same time, and the height of the corresponding simulated track point can be adjusted. The universal joint can adapt to a certain tilt angle. There are two adjusting handwheels in total, and the track surface level can be adjusted by observing the horizontal bubble.

[0041] The distance between the track surface and the bottom surface of the tunnel can be adjusted by driving a multi-section hydraulic cylinder through a manual hydraulic pump. The adjustment height range is 800-1000mm. The bottom of the multi-stage hydraulic cylinder is fixed to the chassis by bolts, and the cylinder rod is connected to the lifting frame system. When the hydraulic cylinder rod is extended, the lifting frame system will be lifted up. The vertical direction is guided by three sets of linear guide sliders to ensure the lifting accuracy. The linear guide and guide support seat are fixed on the chassis, and the slider and the slider fixing bent plate are fixed on the lifting frame system. The upper and lower guides are formed by the cooperation of the guide rails and sliders. The guide sliders have a total of three positions in a triangular shape to ensure stability.

[0042] The Z-axis base plate is used to place the total station prism and emit a completely vertical laser. The three-dimensional translation system is mainly divided into three directions of adjustment: XYZ. The X-axis moves along the line direction. The adjustment method is manual push. The push position is confirmed by a ruler. The adjustment range is ±500mm; the Y-axis is perpendicular to the line direction. The adjustment method is to rotate the slide handwheel. The handwheel drives the screw to rotate. The screw pushes the slider to move. The moving position is confirmed by a ruler. The adjustment range is ±100mm; the vertical direction is the Z-axis. The adjustment method is the same as the Y-axis. It is adjusted by rotating the slide handwheel. The adjustment range is -50~+200mm. The entire measurement module can be adjusted in a direction perpendicular to the track by turning the handwheel. The adjustment method is the same as the Y-axis. The handwheel drives the screw to rotate, and the screw pushes the slider to move. The adjustment range is ±100mm.

[0043] The present invention combines innovation and stability in combination with different actual construction scenarios of tunnel clearance, and can be effectively used in trackless measurement of power supply systems in subway tunnels, avoiding safety hazards and slow progress caused by some uncontrollable factors due to tight track laying construction, insufficient construction period and working surface.

[0044] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A trackless measuring device for the whole system of subway power supply engineering, characterized in that: The invention comprises a walking module (1), a simulation track device (2) and a measuring device (3), wherein the simulation track device (2) is installed on the walking module (1), and the measuring device (3) is installed in the middle of the simulation track device (2). The simulation track device comprises a hydraulic lifting module (21), a leveling movement module (22) and a simulation track module (23), wherein the hydraulic lifting module (21) comprises a multi-section hydraulic cylinder system (211) and a lifting frame system (212), wherein the leveling movement module (22) is installed above the lifting frame system (212), and the The simulation track module (23) is installed above the leveling movement module (22) to form a height-adjustable simulation track device (2); the measuring device (3) comprises a three-dimensional translation system (31); the three-dimensional translation system (31) comprises a Y-axis translation stage (311), an X-axis movement module (312), and a Z-axis translation stage (313); the Y-axis translation stage (311) is installed on the X-axis movement module (312) and moves along the X-axis direction; the Z-axis translation stage (313) is installed on the Y-axis translation stage (311) and moves along the Y-axis direction; The multi-section hydraulic cylinder system (211) comprises a multi-section hydraulic cylinder (2111), a hydraulic cylinder joint (2112) and a manual hydraulic pump (2113), wherein the multi-section hydraulic cylinder (2111) is connected to the chassis, the multi-section hydraulic cylinder system (211) is connected to the jacking frame system (212) via the hydraulic cylinder joint (2112), the multi-section hydraulic cylinder (2111) is driven by the manual hydraulic pump (2113) to adjust the jacking frame system (212), and the jacking frame system (212) comprises a lifting frame (2121), three sets of vertical linear guide rail systems (2122) and a vertical steel plate ruler measuring device (2123), wherein the center position of the lifting frame (2121) is fixedly connected to the hydraulic cylinder joint (2112), the vertical linear guide rail system (2122) is fixedly mounted on the lifting frame (2121), and the vertical steel plate ruler measuring device (2123) is fixedly mounted on the chassis and is located outside the lifting frame (2121); The leveling mobile module (22) comprises three leveling systems (221) and a mobile frame system (222), wherein the lower parts of the three leveling systems (221) are connected to the lifting frame system (212), and the upper parts are connected to the mobile frame system (222), and the mobile frame system (222) comprises a mobile operating system (2221), a mobile frame (2222), and a connecting frame (2223), wherein two sets of horizontal linear guide rail systems (22221) are installed on both sides of the mobile frame (2222) for cooperating with the mobile operating system (2221) for movement, the guide rails of the horizontal linear guide rail system (22221) are fixedly connected to the mobile frame (2222), the sliders of the horizontal linear guide rail system (22221) are fixed to the connecting frame (2223), and the connecting frame (2223) is provided with a level display bubble.

2. According to claim 1, a trackless measurement device for the entire system of a subway power supply project is characterized in that: The simulated track module (23) comprises a track frame (231) and an elevator system (232); one end of the track frame (231) is connected to the moving frame (2222), and the other end is connected to the top of the elevator system (232).

3. According to claim 1, a trackless measurement device for the entire system of a subway power supply project is characterized in that: The walking module comprises a handrail system (11), a chassis system (12) and a wheelset system (13); the handrail system (11) comprises a handle (110); two pull rods (111) are welded below the handle (110); a connecting single ear (113) is arranged at the bottom of the pull rod (111); the chassis system (12) comprises an upper aluminum alloy tube group (121) and a lower aluminum alloy tube group (122); one end of the upper aluminum alloy tube group (121) is provided with a connecting double ear (1211); the connecting single ear (113) and the connecting double ear (1211) are connected via a pin shaft; four ends at the bottom of the upper aluminum alloy tube group (121) are respectively welded with wheelset flange plates (1215); a wheelset is installed below the wheelset flange plate (1215). The system (13) comprises two first guide rail link block flange plates (1212) and a second guide rail link block flange plate (1213) for connecting the leveling moving module (22) on the upper aluminum alloy tube group (121), a two-hole boss flange plate (1214) for connecting the steel ruler support of the trackless measuring device on the upper aluminum alloy tube group (121), a square boss plate (1221) for connecting to the multi-section hydraulic cylinder (2111) of the trackless measuring device is welded on the middle aluminum square tube of the lower aluminum alloy tube group (122), and a long boss plate (1222) for connecting to the manual hydraulic pump (2113) of the trackless measuring device is welded on the end of the lower aluminum alloy tube group (122) away from the hand-held system (11).

4. A trackless measurement device for the whole system of a subway power supply project according to claim 3, characterized in that: The wheel pair system (13) comprises a fixed caster (131) mounted on two wheel pair flange plates (1215) away from the handrail system (11) and a movable caster (132) mounted on two wheel pair flange plates (1215) close to the handrail system (11), a brake device (133) is also mounted on the movable caster (132), a support rod (112) is welded below the two pull rods (111), and a pin hole (114) is provided on the connecting single ear (113) and the connecting double ears (1211) for facilitating the passage of a pin shaft.

5. The whole system trackless measurement device for subway power supply engineering according to claim 1 is characterized in that: The X-axis moving module (312) comprises two X-axis linear horizontal guide rails (3121) installed on the moving frame system (222), a slider and a locking device (3124) are installed on the X-axis linear horizontal guide rails (3121), the slider and the locking device (3124) slide along the X-axis linear horizontal guide rails (3121), a steel ruler (3122) is arranged next to the X-axis linear horizontal guide rails (3121), the steel ruler (3122) is arranged parallel to the X-axis linear horizontal guide rails (3121), a pointer (3123) is installed on the slider and the locking device (3124), and the pointer (3123) is directly opposite to the steel ruler (3122).

6. A trackless measurement device for the whole system of a subway power supply project according to claim 5, characterized in that: The Y-axis translation stage (311) comprises a Y-axis base plate (3112), the Y-axis base plate (3112) being mounted between two sliders and a locking device (3124), a Y-axis slider (3111) being mounted on the Y-axis base plate (3112), the Y-axis slider (3111) being connected to a Y-axis hand wheel (3113), and the distance of movement of the Y-axis slider (3111) along the Y-axis being controlled by adjusting the Y-axis hand wheel (3113).

7. The whole system trackless measurement device for subway power supply engineering according to claim 5, characterized in that: The Z-axis translation stage (313) comprises a Z-axis connecting plate (3131), the bottom surface of the Z-axis connecting plate (3131) is connected to a Y-axis slider (3111), a Z-axis slider (3132) is mounted on the Z-axis connecting plate (3131), the Z-axis slider (3132) is connected to a Z-axis handwheel (3133), a Z-axis base plate (3134) is mounted on the Z-axis slider (3132), and the distance of movement of the Z-axis slider (3132) and the Z-axis base plate (3134) along the Z-axis is controlled by adjusting the Z-axis handwheel (3133).

8. The whole system trackless measurement device for subway power supply engineering according to claim 1 is characterized in that: The three leveling systems (221) are arranged in an equilateral triangle.