Steel pipe pile supporting system with embedded profile steel and rapid construction method

By setting up steel in steel pipe piles and using positioning components and sliding structures, combining the construction methods of cement mortar and concrete crown beams, the problems of insufficient bending resistance of single piles and poor stress coordination between piles are solved. Achieve efficient and stable support effect of steel pipe piles.

CN119083423AActive Publication Date: 2024-12-06CHINA CONSTR THIRD ENG BUREAU GRP CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411517660.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-29
Publication Date
2024-12-06
Estimated Expiration
2044-10-29

AI Technical Summary

Technical Problem

In the existing construction technology, support methods such as sloping spray anchors, pile plate retaining walls and anchor rod retaining walls have insufficient bending ability of single piles, poor stress coordination between piles and misaligned installation of steel pipes. The problem of decreased support capacity.

Method used

The steel pipe pile support system adopts embedded steel. By installing steel in the steel pipe piles and using positioning components and sliding structures to ensure the precise positioning and free movement of the steel, combined with cement mortar filling and concrete crown beam construction methods, the Bending resistance and overall stability of steel pipe piles.

Benefits of technology

It significantly improves the bending and tensile performance of steel pipe piles, enhances the connection between steel pipe piles and backfill soil layer, improves the overall support effect and construction accuracy and efficiency, and is suitable for rescue and reinforcement of urban centers and mountain sites. project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083423A_ABST
    Figure CN119083423A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building construction, in particular to a steel pipe pile supporting system with embedded profile steel and a rapid construction method.The steel pipe pile supporting system comprises a steel pipe pile, the profile steel is arranged in the steel pipe pile, and a through hole is formed in the profile steel; the supporting assembly comprises a positioning transverse rod, fixing nuts and positioning nuts, the positioning transverse rod penetrates through the penetrating hole, the positioning nuts are arranged on the positioning transverse rod and arranged at the two ends of the penetrating hole, and the fixing nuts are arranged on the positioning transverse rod and arranged at the two ends of the penetrating hole and abut against the inner wall of the steel pipe pile during positioning; the supporting system further comprises a positioning assembly arranged at the bottom of the profile steel. Due to the existence of the sliding rod, an extra moving space is provided for the positioning rod, so that the positioning process is more flexible and accurate, and the bending resistance, tensile resistance and other properties of the steel pipe pile can be greatly improved; the steel pipe is filled with cement mortar, the connecting effect of the steel pipe pile and the built-in profile steel can be remarkably enhanced, and the overall bending resistance is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a steel pipe pile supporting system with embedded steel sections and a rapid construction method. Background Art

[0002] Support technologies such as slope spraying, pile-sheet retaining wall, and anchor retaining wall are widely used in engineering practice, but they each have some disadvantages: Slope spraying and anchor support: In rainy season, local collapse is easy to occur due to soaking, and the backfill is large, which has a greater impact on the surrounding environment; it has high requirements for soil layers and groundwater conditions, and dry drilling is used as much as possible; in case of backfill soil and local soft soil layers, it is better to replace reinforced soil nails with steel flower tube soil nails and use an impactor to drive them in for better results.

[0003] Pile-sheet retaining wall support: The construction period is relatively long, and excavation can only be carried out after the mixing pile or rotary jet pile reaches a certain strength; deep mixing piles are more likely to split when constructed in thicker sand layers, and multiple rows of overlaps are required. Due to the poor tensile and shear resistance of mixing piles, steel pipes or steel sections are generally inserted inside, and crown beams are set; for local narrow areas, when mixing pile machinery cannot be constructed, high-pressure rotary jet piles can be used instead.

[0004] Anchor retaining wall support: Soil anchors require relatively good geological conditions, and there must also be sufficiently open site conditions or the anchors can be allowed to extend into the soil layer beyond the red line; in soft soil areas, anchors are rarely used due to the lack of sufficient anchoring force in the soil layer. If the anchor is anchored in a very deep sand layer, the length of the anchor will be very long, which is not an economical solution.

[0005] There is an urgent need for a steel pipe pile support system with embedded steel and a rapid construction method to solve some of the above problems. Summary of the invention

[0006] The present invention aims to provide a steel pipe pile support system with embedded steel sections and a rapid construction method to solve the defects of insufficient bending resistance of single piles, poor force coordination between piles, and reduced support capacity due to misplaced installation of steel pipes.

[0007] The present invention is achieved through the following technical solutions: A steel pipe pile support system with embedded steel sections, comprising a steel pipe pile, wherein a steel section is arranged inside the steel pipe pile, and the steel section is provided with a through hole. The support system also includes support components arranged at the upper and lower ends of the steel pipe pile, and the support components include: a positioning cross bar, a fixing nut and a positioning nut. The positioning cross bar passes through the through hole, and the positioning nut is arranged on the positioning cross bar and placed at both ends of the through hole. The fixing nut is arranged on the positioning cross bar and placed at both ends of the through hole and abuts against the inner wall of the steel pipe pile during positioning; the support system also includes a positioning component arranged at the bottom of the steel section, and the positioning component completes the positioning process as the steel section moves in the steel pipe column.

[0008] A rapid construction method for a steel pipe pile support system with embedded steel sections, comprising the following steps: step 1, site leveling, wherein the compaction coefficient during the site leveling process is not less than 0.9; step 2, steel pipe pile construction, wherein the construction process sequentially comprises: steel pipe production, measurement and layout, hole spacing positioning, in-place drilling, steel pipe installation, steel section installation, positioning calibration, hole cleaning, grouting machine installation, grouting pipe installation, cement mortar mixing, cement mortar injection and pressure grouting; step 3, crown beam construction, wherein the construction process sequentially comprises: determining the baseline, leveling the earthwork, cleaning the foundation trench and cushion layer construction, steel bar binding template installation, concrete pouring, and template removal and maintenance; step 4, square layer excavation, wherein before excavation, a measurement control network is set to measure and control the control baseline, axis and horizontal reference point; step 5, steel plate wall construction, wherein the construction process sequentially comprises: cleaning the soil between piles, lowering the steel plate and welding; step 6, grouting, wherein during the grouting process, the steel plate ensures that water is discharged through the drainage hole.

[0009] Compared with the prior art, the present invention has the following advantages and beneficial effects: 1. The present invention can greatly improve the bending resistance, tensile resistance and other properties of the steel pipe pile by embedding steel, preferably H-shaped steel, in the steel pipe pile; filling cement mortar inside the steel pipe can significantly enhance the connection effect between the steel pipe pile and the embedded steel, and improve the overall bending resistance; when drilling holes in the steel pipe pile body and filling the steel pipe pile with cement mortar, the gap between the steel pipe pile and the backfill soil layer is filled and compacted at the same time, thereby enhancing the support effect of the steel pipe pile; the upper end of the H-shaped steel, the steel pipe top pipe and the crown beam steel cage are connected, and the whole is cast into a concrete crown beam, which significantly improves the overall stability between the steel pipe piles; 2. The branch pipe of the present invention is arranged at the bottom of the steel section and is slidably arranged with the upper end of the positioning base. This sliding structure allows the positioning assembly to move synchronously when the steel section moves in the steel pipe, ensuring the free movement and precise positioning of the steel section in the steel pipe. A sliding rod is hinged at the middle of the positioning rod, and the free end of the sliding rod is hinged on the outer peripheral surface of the end of the branch pipe, so that the positioning rod can flexibly adjust its position during the movement of the steel section to adapt to different construction environments and requirements. The existence of the sliding rod provides additional activity space for the positioning rod, making the positioning process more flexible and precise; 3. The positioning block of the present invention also includes a moving rod connected to the limit rod, and a positioning ring connected to the moving rod. The positioning ring is a fan ring structure, and the moving rod slides in the slide groove. This design allows the positioning block to move flexibly in the slide groove to achieve precise positioning. The fan ring structure design of the positioning ring enables it to rotate flexibly within a certain angle range to adapt to forces in different directions, thereby increasing the adaptability and stability of the positioning assembly. Through the above-mentioned complex mechanical linkage, the positioning assembly can ensure the precise positioning of the steel section in the steel pipe. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] The drawings described herein are used to provide a further understanding of the embodiments of the present invention, constitute a part of this application, and do not constitute a limitation of the embodiments of the present invention. In the drawings: Figure 1 It is a schematic diagram of the overall structure of the system of the present invention; Figure 2 It is a top view of the overall structure of the system of the present invention; Figure 3 It is a partial cross-sectional view of the overall structure of the system of the present invention; Figure 4 A front view of the positioning assembly of the system of the present invention; Figure 5 An axial view of the positioning assembly of the system of the present invention; Figure 6 A top view of the positioning components of the system of the present invention; Figure 7 It is a schematic diagram of the process of the present invention.

[0011] The reference numerals represent: 1-steel pipe pile, 2-steel, 3-perforation, 4-support component, 5-positioning component; 41-positioning cross bar, 42-fixing nut, 43-positioning nut; 51-positioning base, 52-branch pipe, 53-positioning rod, 54-sliding rod, 55-sliding sleeve plate, 56-sliding groove seat, 57-positioning block, 58-limiting rod, 59-guide groove; 571-moving rod, 572-positioning ring. DETAILED DESCRIPTION

[0012] In order to make the purpose, technical scheme and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments and drawings. The schematic implementation modes and descriptions of the present invention are only used to explain the present invention and are not intended to limit the present invention. It should be noted that the present invention is already in the actual development and use stage.

[0013] Embodiment 1: Please refer to the attached Figures 1 to 6 A steel pipe pile support system with embedded steel, comprising a steel pipe pile 1, wherein a steel section 2 is arranged in the steel pipe pile 1, and a through hole 3 is arranged on the steel section 2. The support system also includes support components 4 arranged at the upper and lower ends of the steel pipe pile 1, and the support component 4 includes: a positioning cross bar 41, a fixing nut 42 and a positioning nut 43. The positioning cross bar 41 passes through the through hole 3, and the positioning nut 43 is arranged on the positioning cross bar 41 and placed at both ends of the through hole 3. The fixing nut 42 is arranged on the positioning cross bar 41 and placed at both ends of the through hole 3 and abuts against the inner wall of the steel pipe pile 1 during positioning; the support system also includes a positioning component 5 arranged at the bottom of the steel section 2, and the positioning component 5 completes the positioning process as the steel section 2 moves in the steel pipe column.

[0014] It should be noted that compared with traditional support technologies such as natural slope spraying, pile-board retaining wall, and anchor retaining wall, the steel pipe pile support system with embedded steel and the rapid construction method used in this embodiment have the outstanding advantages of small hole diameter, efficient and safe construction, short construction period, rapid emergency response for emergency projects, and reliable molding quality. It has little disturbance to the entire geological environment, will not cause secondary damage, and has little impact on the surrounding public facilities, human settlements and travel and other urban environmental disturbances.

[0015] Specifically, the micro steel 2 pipe pile 1 with built-in steel 2 support technology overcomes the defects of insufficient bending resistance of a single pile and poor coordination of forces between piles, and greatly improves the bending resistance, tensile resistance and other properties of the steel pipe pile 1. Compared with traditional anti-slip piles, the micro steel 2 pipe pile 1 occupies a small area, is particularly suitable for urban central areas and mountain sites, and has a fast construction speed, which is suitable for emergency reinforcement projects. However, due to the small diameter of the micro steel 2 pipe pile 1, the bending resistance of a single pile may sometimes appear insufficient, so the micro steel 2 pipe pile 1 with built-in steel 2 overcomes the defects of insufficient bending resistance of a single pile and poor coordination of forces between piles. Reinforced steel 2 is placed in the steel pipe, an outer mortar layer is filled between the steel pipe and the external soil layer, and an inner mortar layer is filled between the steel pipe and the reinforced steel 2. The upper end of the reinforced steel 2 and the steel pipe pile 1 is connected to the horizontal steel cage of the crown beam to cast a concrete crown beam as a whole.

[0016] By embedding steel sections 2, preferably H-shaped steel sections 2, in the steel pipe pile 1, the bending resistance, tensile resistance and other properties of the steel pipe pile 1 can be greatly improved; filling cement mortar inside the steel pipe can significantly enhance the connection effect between the steel pipe pile 1 and the embedded steel sections 2, and improve the overall bending resistance; when drilling holes in the steel pipe pile 1 and filling cement mortar in the steel pipe pile 1, the gap between the steel pipe pile 1 and the backfill soil layer is filled and compacted at the same time, thereby enhancing the support effect of the steel pipe pile 1; the upper end of the H-shaped steel 2 and the steel pipe top pipe are connected to the crown beam steel cage, and the whole is cast as a concrete crown beam, thereby significantly improving the overall stability between the steel pipe piles 1.

[0017] The built-in steel 2 temporary fixing construction technology is adopted to position the exposed part of the H-shaped steel 2 through the hole 3, and the H-shaped steel 2 is temporarily fixed to the top of the steel pipe by using the steel bar to cross the hole 3, and the effect is good.

[0018] Specifically, the H-shaped steel 2 built into the extra-long micro steel pipe can greatly improve the bending and tensile properties of the steel pipe pile 1. Usually, the upper part of the steel pipe is subjected to the greatest stress and deformation. Taking economic savings into full consideration, the H-shaped steel 2 needs to be inserted 9m from the top of the pile and exposed 300mm from the top of the steel pipe. It is cast in the crown beam together with the top of the steel pipe to enhance the bending and tensile properties of the upper part. Since the H-shaped steel 2 does not extend to the bottom of the steel pipe, the H-shaped steel 2 needs to be fixed and suspended inside the steel pipe. In this embodiment, a temporary fixing construction technology of built-in steel 2 is adopted. The positioning ribs are crossed at the drilling position of the H-shaped steel 2 to temporarily fix the H-shaped steel 2 to the top of the steel pipe, and then high-strength cement mortar is poured to bond the H-shaped steel 2 and the steel pipe pile 1 to form a whole. Finally, the H-shaped steel 2 is cast in the crown beam together with the steel pipe pile 1. In addition, a gravity static press is used to press the steel pipe pile 1 into the designed elevation without damaging the pile surface. It has the advantages of efficient and safe construction, stable operation, no noise, and no disturbance to residents. The block welding construction technology is adopted to control the stress and strain of the steel plate retaining wall welding according to the principles of block skip welding and symmetrical welding. The whole is welded from the middle to both sides to achieve the welding effect of a large area of ​​steel plate retaining wall. The blocks are welded in turn to avoid structural deformation caused by welding.

[0019] Finally, the positioning base 51 serves as the basic part of the positioning assembly 5, and its function is to provide a stable support point for the movement of the steel section 2 in the steel pipe; when the positioning base 51 touches the bottom, it can ensure the precise position of the steel section 2 in the steel pipe, thereby ensuring the stability of the entire support system; the outer peripheral surface of the positioning base 51 is hingedly provided with a positioning rod 53, and this design allows the positioning rod 53 to rotate freely on the positioning base 51, thereby increasing the flexibility and adaptability of the system.

[0020] The branch pipe 52 is arranged at the bottom of the steel section 2 and slides with the upper end of the positioning base 51. This sliding structure allows the positioning assembly 5 to move synchronously when the steel section 2 moves in the steel pipe, ensuring the free movement and precise positioning of the steel section 2 in the steel pipe. A sliding rod 54 is hinged in the middle of the positioning rod 53, and the free end of the sliding rod 54 is hinged on the outer peripheral surface of the end of the branch pipe 52, so that the positioning rod 53 can flexibly adjust its position during the movement of the steel section 2 to adapt to different construction environments and requirements. The existence of the sliding rod 54 provides additional activity space for the positioning rod 53, making the positioning process more flexible and precise. The sliding sleeve 55 is arranged on the outer periphery of the branch pipe 52 by threaded rotation. This threaded connection method not only provides reliable connection strength, but also allows the sliding sleeve 55 to be fine-tuned when necessary to adapt to different construction conditions. This design of the sliding sleeve 55 increases the adjustability of the system, allowing construction personnel to make precise adjustments according to actual needs. The slide seat 56 is fixedly arranged on the upper end surface of the positioning base 51, and a plurality of slide slots are evenly spaced thereon. The positioning block 57 is slidably arranged in the slide slot. The above structural design enables the positioning block 57 to move freely in the slide slot, thereby realizing the precise positioning of the steel section 2. A limiting rod 58 is arranged on the positioning block 57, and a plurality of guide grooves 59 matching the limiting rod 58 are evenly spaced on the sliding sleeve disk 55. This structural design enables the positioning block 57 to be synchronously displaced under the drive of the sliding sleeve disk 55, thereby further improving the positioning accuracy.

[0021] It should be noted that the positioning assembly 5 includes a positioning base 51 and a branch pipe 52 arranged at the bottom of the steel section 2. The branch pipe 52 is slidably arranged with the upper end of the positioning base 51. The outer peripheral surface of the positioning base 51 is hinged with a positioning rod 53. The middle part of the positioning rod 53 is hinged with a sliding rod 54. The free end of the sliding rod 54 is hinged on the outer peripheral surface of the end of the branch pipe 52. During the movement of the steel section 2 in the steel pipe column, when the positioning base 51 does not touch the bottom, the positioning assembly 5 moves synchronously with the steel section 2. When the positioning base 51 touches the bottom, the branch pipe 52 slides on the positioning base 51 and moves the end of the positioning rod 53 toward the periphery until it abuts against the inner wall of the steel pipe pile 1 to complete the positioning. It should also be noted that, based on the above structure, this design of the positioning assembly 5 provides a simple and effective mechanism to ensure the precise positioning of the steel section 2 in the steel pipe, thereby improving the accuracy and efficiency of the construction. It not only reduces the adjustment work during the construction process and reduces the construction cost, but also helps to improve the stability and reliability of the entire support structure. By ensuring the correct positioning of the steel section 2, the system can better resist external forces such as soil pressure and groundwater flow, thereby providing a more stable and safe support for the construction site.

[0022] It should be noted that the positioning assembly 5 also includes a sliding sleeve disc 55, a sliding groove seat 56 and a plurality of positioning blocks 57. The sliding sleeve disc 55 is arranged on the outer periphery of the branch pipe 52 by threaded rotation. The sliding groove seat 56 is fixedly arranged on the upper end surface of the positioning base 51. The upper portion of the sliding groove seat 56 is evenly spaced with a plurality of sliding grooves, and the positioning block 57 is slidably arranged in the sliding grooves. A limiting rod 58 is also arranged on the positioning block 57. The sliding sleeve disc 55 is evenly spaced with a plurality of guide grooves 59 matching the limiting rod 58. When the positioning base 51 touches the bottom, the steel section 2 and the branch pipe 52 continue to fall, and the sliding sleeve disc 55 is driven to rotate by the thread. At the same time, the positioning block 57 is synchronously displaced on the sliding groove seat 56 through the guide grooves 59 and the limiting rod 58, so as to realize the positioning support of the steel pipe pile 1.

[0023] It should also be noted that, based on the above structure, in the steel pipe pile 1 support system with embedded steel 2, the addition of the positioning assembly 5 significantly improves the accuracy and stability of the positioning of the steel 2 in the steel pipe. In addition to the aforementioned positioning base 51 and branch pipe 52, the positioning assembly 5 also innovatively introduces structures such as a sleeve disc 55, a slide groove seat 56 and a positioning block 57. The sleeve disc 55 is set on the outer periphery of the branch pipe 52 through thread rotation. When the positioning base 51 touches the bottom and the steel 2 and the branch pipe 52 continue to fall, the rotation of the thread drives the sleeve disc 55 to rotate accordingly. The rotation of the sleeve disc 55 cooperates with the limit rod 58 on the positioning block 57 through the evenly distributed guide grooves 59 thereon, thereby realizing the synchronous displacement of the positioning block 57 in the slide groove on the slide groove seat 56. This sophisticated thread transmission and guide groove 59-limit rod 58 cooperation mechanism ensures that the steel 2 can be accurately positioned in the steel pipe, and can adapt to different sinking depths, thereby improving the adaptability and reliability of the system.

[0024] More specifically, the slide seat 56 is fixed to the upper end surface of the positioning base 51, and is provided with a plurality of slide slots. The positioning block 57 slides in these slide slots, thereby increasing the flexibility of the positioning assembly 5. The limit rod 58 of the positioning block 57 interacts with the guide slot 59 on the sleeve plate 55, so that the positioning block 57 can move smoothly along the slide slot, thereby accurately controlling the position of the steel section 2. The above structural design not only improves the accuracy of positioning, but also reduces the risk of displacement of the steel section 2 due to construction errors, thereby ensuring the stability and bearing capacity of the steel pipe pile 1.

[0025] In this embodiment, it is more preferred that the length of the thread of the sleeve disc 55 and the branch pipe 52 is smaller than the maximum displacement length of the positioning block 57 in the slide slot. In this embodiment, it is more preferred that the positioning block 57 further includes: a moving rod 571 connected to the limit rod 58, a positioning ring 572 connected to the moving rod 571, the positioning ring 572 is a fan ring structure, and the moving rod 571 is slidably arranged in the slide slot. The length of the thread of the sleeve disc 55 and the branch pipe 52 is designed to be smaller than the maximum displacement length of the positioning block 57 in the slide slot, and the power provided by the thread is sufficient to achieve precise control within the entire stroke of the positioning block 57, without excessive rotation or insufficient power due to the excessive length of the thread.

[0026] Embodiment 2: As attached Figure 7 As shown, a rapid construction method for a steel pipe pile support system with embedded steel sections comprises the following steps: step 1, site leveling, wherein the compaction coefficient during the site leveling process is not less than 0.9; step 2, steel pipe pile 1 construction, wherein the construction process comprises in sequence: steel pipe production, measurement and layout, hole spacing positioning, in-situ drilling, steel pipe installation, steel section 2 installation, positioning calibration, hole cleaning, grouting machine installation, grouting pipe installation, cement mortar mixing, cement mortar injection and pressure grouting; step 3, crown beam construction, wherein the construction process comprises in sequence: determining the baseline, leveling the earthwork, cleaning the foundation trench and cushion construction, steel bar binding formwork installation, concrete pouring, formwork removal and maintenance; step 4, square layer excavation, before excavation, setting up a measurement control network to measure and control the control baseline, axis and horizontal reference point; step 5, steel plate wall construction, wherein the construction process comprises in sequence: cleaning the soil between piles, lowering the steel plate and welding; step 6, grouting, during the grouting process, the steel plate ensures that water is discharged through the drainage hole.

[0027] Step 2 specifically includes: Step 2.1, steel pipe production: cut the material according to the depth required by the design drawings, and weld the steel pipe joints; Step 2.2, measurement and layout: measure and lay out according to the spacing, row spacing and elevation required by the design; Step 2.3, hole spacing positioning: use a locator to drive into the ground for positioning according to the set hole diameter, spacing and row spacing, and use an auger to locate the hole position; Step 2.4, drilling in place: place the drilling rig and ensure that it is level, start the drilling rig to Drilling is carried out, and the drill rod is connected every 3m until the designed depth is reached, and the verticality of the drill rod is checked; Step 2.5, installation of steel pipe: Use a crane to lower the steel pipe, and then use a gravity static press to lower the steel pipe to the designed elevation position, and check the verticality of the steel pipe pile 1; Step 2.6, installation of steel 2: Scan the QR code of the built-in steel 2 to determine the number of the steel pipe pile 1 to be placed, and use a crane to lift the built-in steel 2 into the steel pipe pile 1; Step 2.7, positioning calibration: Use the positioning cross bar 4 1 and the fixing nut 42 and the positioning nut 43 are used together to position the steel section 2 at the center of the steel pipe and control the installation height; Step 2.8, hole cleaning: before injecting cement slurry, use a high-pressure air compressor to clean the pile hole to ensure that the thickness of the sediment in the hole is not more than 50mm, and use a spray device to control dust; Step 2.9, grouting machine installation: after fixing the grouting machine, connect the power supply; Step 2.10, grouting pipe installation: after lowering the steel pipe, the grouting pipe is directly connected to the grouting machine. On the steel pipe in the hole, the interface is sealed and connected, and the grouting pipe is transported by a rubber tube; step 2.11, mix cement mortar: the water-cement ratio is controlled between 0.45 and 0.5; step 2.12, inject cement mortar: the first grouting pressure is 0.5Mpa, and the pipe is not pulled out after grouting until the cement mortar flows out of the pipe, the grouting pipe is pulled out, and pressurization is applied until the cement mortar flows out of the steel pipe again; step 2.13, secondary pressurized grouting: secondary gap grouting is carried out until the pipe mouth turns over.

[0028] Step 3 specifically includes: Step 3.1, determine the baseline, according to the design requirements of the drawings, backfill the earth to the bottom elevation of the crown beam to determine the baseline; Step 3.2, level the earth so that the base size of the top beam is 100mm to 200mm larger than the structure; Step 3.3, clean the foundation pit and construct the cushion layer: pour the cushion layer concrete after the foundation pit is cleaned and accepted; Step 3.4, install the steel bar binding formwork: prepare and bind the steel bars according to the material reinforcement of the design drawings; Step 3.5, use concrete to cast the crown beam; Step 3.6, remove the formwork and carry out maintenance.

[0029] In general, the steel pipe pile 1 support system with embedded steel 2 and its rapid construction method in this embodiment realizes efficient, safe and reliable construction of the support system in the field of building construction through innovative structural design and construction steps. The core is that steel 2 is arranged in the steel pipe pile 1, and a perforation 3 is arranged on the steel 2. Through the coordinated use of the support component 4 (including the positioning cross bar 41, the fixing nut 42 and the positioning nut 43) and the positioning component 5, the steel 2 is accurately positioned and fixed in the steel pipe.

[0030] During the construction process, the site is first leveled to ensure that the compaction coefficient is not less than 0.9, laying a solid foundation for subsequent construction. Next, the steel pipe pile 1 is constructed, including steel pipe production, measurement and layout, hole spacing positioning, in-place drilling, and steel pipe installation. These steps ensure the accurate installation and positioning of the steel pipe pile 1. In the steel section 2 installation step, the number of the steel pipe pile 1 to be placed is determined by scanning the QR code of the built-in steel section 2, and the built-in steel section 2 is hoisted into the steel pipe pile 1 by a crane. This innovative method improves construction efficiency and accuracy.

[0031] In the positioning and calibration step, the steel section 2 is positioned at the center of the steel pipe by using the positioning cross bar 41, the fixing nut 42 and the positioning nut 43, and the installation height is controlled to ensure the precise positioning of the steel section 2. In the hole cleaning step, a high-pressure air compressor is used to clean the pile hole to ensure that the thickness of the sediment in the hole is no more than 50 mm, thereby improving the grouting quality. In the grouting step, cement mortar is injected into the steel pipe through a grouting machine and a grouting pipe. The first grouting pressure is 0.5 MPa. The pipe is not pulled out after grouting until the cement mortar flows out of the pipe, thereby ensuring the dense filling of cement mortar in the steel pipe.

[0032] The steps of crown beam construction include determining the baseline, leveling the earthwork, cleaning the foundation trench and constructing the cushion layer, tying the steel bars and installing the formwork, pouring concrete, removing the formwork and maintaining the structure. These steps ensure the quality and stability of the crown beam. In the step of layered earth excavation, a measurement control network is set up to measure and control the baseline, axis and horizontal reference points to ensure the accuracy and safety of the excavation. The steps of steel plate wall construction include cleaning the soil between piles, lowering the steel plate and welding. These steps improve the construction quality and efficiency of the steel plate wall. In the final grouting step, water is discharged through the drainage holes to improve the grouting quality.

[0033] In terms of beneficial effects, the present invention greatly improves the bending resistance, tensile resistance and other properties of the steel pipe pile 1 by embedding the steel section 2 in the steel pipe pile 1. Filling cement mortar inside the steel pipe significantly enhances the connection effect between the steel pipe pile 1 and the embedded steel section 2, and improves the overall bending resistance. When drilling holes in the steel pipe pile 1 and filling the steel pipe pile 1 with cement mortar, the gap between the steel pipe pile 1 and the backfill soil layer is filled and compacted at the same time, thereby enhancing the support effect of the steel pipe pile 1. The upper end of the H-shaped steel 2 and the steel pipe top pipe are connected to the crown beam steel cage, and the whole is cast into a concrete crown beam, which significantly improves the overall stability between the steel pipe piles 1.

[0034] In addition, for the positioning assembly 5 in the positioning and calibration process, during use, the positioning base 51 is first placed in a predetermined position, and its function is to provide a stable support base for the entire positioning assembly 5. The outer peripheral surface of the positioning base 51 is hinged with positioning rods 53, and these positioning rods 53 can rotate freely on the base to adapt to different construction conditions. The middle part of the positioning rod 53 is hinged with a slide rod 54, and the free end of the slide rod 54 is hinged on the outer peripheral surface of the end of the branch pipe 52. This design enables the positioning assembly 5 to move synchronously when the steel section 2 moves in the steel pipe, ensuring that the steel section 2 can slide freely in the steel pipe until it reaches the predetermined position.

[0035] When the positioning base 51 touches the bottom, that is, reaches the bottom of the steel pipe column, the branch pipe 52 will slide on the positioning base 51, pushing the end of the positioning rod 53 to move toward the periphery until it abuts against the inner wall of the steel pipe column, completing the initial positioning. At this time, the sliding sleeve 55 is set on the periphery of the branch pipe 52 by thread rotation, and the rotation of the sliding sleeve 55 drives the positioning block 57 on the slide groove seat 56 to move along the slide groove. The thread length of the sliding sleeve 55 and the branch pipe 52 is designed to be smaller than the maximum displacement length of the positioning block 57 in the slide groove. Such a design not only ensures sufficient power transmission, but also avoids excessive rotation caused by excessive thread length.

[0036] A limiting rod 58 is provided on the positioning block 57, and a plurality of guide grooves 59 matching the limiting rod 58 are evenly spaced on the sliding sleeve disc 55. When the positioning base 51 touches the bottom, the steel section 2 and the branch pipe 52 continue to fall, the threaded rotation of the sliding sleeve disc 55 drives the sliding sleeve disc 55 to rotate, and the guide groove 59 interacts with the limiting rod 58 to achieve synchronous displacement of the positioning block 57 on the sliding groove seat 56. This synchronous displacement ensures that the steel section 2 can be accurately positioned in the steel pipe and can adapt to different sinking depths.

[0037] The positioning block 57 also includes a moving rod 571 connected to the limiting rod 58, and a positioning ring 572 connected to the moving rod 571. The positioning ring 572 is a fan ring structure, and the moving rod 571 slides in the slide groove. This design allows the positioning block 57 to move flexibly in the slide groove to achieve precise positioning. The fan ring structure design of the positioning ring 572 enables it to rotate flexibly within a certain angle range to adapt to forces in different directions, thereby increasing the adaptability and stability of the positioning assembly 5. Through the above-mentioned complex mechanical linkage, the positioning assembly 5 can ensure the precise positioning of the steel section 2 in the steel pipe.

[0038] The above specific implementation methods further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above are only specific implementation methods of the present invention and are not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A steel pipe pile support system with embedded steel, comprising a steel pipe pile (1), characterized in that: A steel section (2) is arranged inside the steel pipe pile (1), and a through hole (3) is arranged on the steel section (2). The support system further comprises a support assembly (4) arranged at the upper and lower ends of the steel pipe pile (1), and the support assembly (4) comprises: a positioning cross bar (41), a fixing nut (42) and a positioning nut (43). The positioning cross bar (41) passes through the through hole (3), and the positioning nut (43) is arranged on the positioning cross bar (41) and is placed at both ends of the through hole (3). The fixing nut (42) is arranged on the positioning cross bar (41) and is placed at both ends of the through hole (3) and abuts against the inner wall of the steel pipe pile (1) during positioning. The support system further comprises a positioning assembly (5) arranged at the bottom of the steel section (2), wherein the positioning assembly (5) completes a positioning process as the steel section (2) moves within the steel pipe column.

2. The steel pipe pile support system with embedded steel according to claim 1, characterized in that: The positioning assembly (5) comprises a positioning base (51) and a branch pipe (52) arranged at the bottom of the steel section (2); the branch pipe (52) and the upper end of the positioning base (51) are slidably arranged; a positioning rod (53) is hingedly arranged on the outer peripheral surface of the positioning base (51); a sliding rod (54) is hingedly arranged in the middle of the positioning rod (53); the free end of the sliding rod (54) is hingedly arranged on the outer peripheral surface of the end of the branch pipe (52); when the steel section (2) moves in the steel pipe column, when the positioning base (51) does not touch the bottom, the positioning assembly (5) moves synchronously with the steel section (2); when the positioning base (51) touches the bottom, the branch pipe (52) slides on the positioning base (51) and causes the end of the positioning rod (53) to move toward the outer periphery until it abuts against the inner wall of the steel pipe pile (1) to complete the positioning.

3. The steel pipe pile support system with embedded steel according to claim 2, characterized in that: The positioning assembly (5) further comprises a sleeve disc (55), a slide groove seat (56) and a plurality of positioning blocks (57); the sleeve disc (55) is rotatably arranged on the outer periphery of the branch pipe (52) by means of a thread; the slide groove seat (56) is fixedly arranged on the upper end surface of the positioning base (51); a plurality of slide grooves are evenly spaced on the upper portion of the slide groove seat (56); and the positioning block (57) is slidably arranged in the slide grooves; a limiting rod (58) is also arranged on the positioning block (57); a plurality of guide grooves (59) matching the limiting rod (58) are evenly spaced on the sleeve disc (55); when the positioning base (51) touches the bottom, the steel section (2) and the branch pipe (52) continue to fall, and the sleeve disc (55) is driven to rotate by means of the thread; at the same time, the positioning block (57) is synchronously displaced on the slide groove seat (56) by means of the guide grooves (59) and the limiting rod (58), so as to realize the positioning support of the steel pipe pile (1).

4. The steel pipe pile support system with embedded steel according to claim 3, characterized in that: The length of the thread of the sliding sleeve disc (55) and the branch pipe (52) is smaller than the maximum displacement length of the positioning block (57) in the sliding groove.

5. The steel pipe pile support system with embedded steel according to claim 3, characterized in that: The positioning block (57) further comprises: a moving rod (571) connected to the limiting rod (58), and a positioning ring (572) connected to the moving rod (571); the positioning ring (572) is a fan ring structure; and the moving rod (571) is slidably disposed in a sliding groove.

6. A rapid construction method for a steel pipe pile support system with embedded steel, characterized in that: A steel pipe pile support system with embedded steel according to any one of claims 1 to 5, comprising the following steps: Step 1: site leveling, the compaction coefficient during site leveling shall not be less than 0.9; Step 2, steel pipe pile (1) construction, the construction process includes: steel pipe production, measurement and layout, hole spacing positioning, in-place drilling, steel pipe installation, steel (2) installation, positioning calibration, hole cleaning, grouting machine installation, grouting pipe installation, cement mortar mixing, cement mortar injection and pressure grouting; Step 3: crown beam construction. The construction process includes: determining the baseline, leveling the earthwork, cleaning the foundation trench and constructing the cushion layer, tying the steel bars and installing the formwork, pouring concrete, and removing the formwork for maintenance. Step 4: Before excavation, set up a measurement control network to measure and control the control baseline, axis and horizontal reference point; Step 5: Steel plate wall construction, the construction process includes: cleaning the soil between the piles, lowering the steel plate and welding; Step 6: grouting. During the grouting process, the steel plate ensures that water is discharged through the drainage holes.

7. The rapid construction method of a steel pipe pile support system with embedded steel according to claim 6 is characterized by: Step 2 specifically includes: Step 2.1, steel pipe production: cut the steel pipe according to the depth required by the design drawing and weld the steel pipe joints; Step 2.2, measurement and layout: measurement and layout are carried out according to the spacing and row spacing required by the design and the elevation provided by the design; Step 2.3, hole spacing positioning: Use a locator to drive into the ground for positioning according to the set hole diameter, spacing, and row spacing, and use an auger to locate the hole position; Step 2.4, drilling in place: After placing the drilling rig and ensuring it is level, start the drilling rig to drill, connect the drill rod every 3m until the designed depth is reached, and check the verticality of the drill rod; Step 2.5, installing the steel pipe: Use a crane to lower the steel pipe, and then use a gravity static press to lower the steel pipe to the designed elevation, and check the verticality of the steel pipe pile (1); Step 2.6, installation of the steel (2): Scan the QR code of the internal steel (2) to determine the number of the steel pipe pile (1) to be inserted, and use a crane to lift the internal steel (2) into the steel pipe pile (1); Step 2.7, positioning and calibration: by using the positioning cross bar (41) and the fixing nut (42) and the positioning nut (43) in coordination, the steel section (2) is positioned at the center of the steel pipe and the installation height is controlled; Step 2.8, hole cleaning: Before injecting cement slurry, use a high-pressure air compressor to clean the pile hole to ensure that the thickness of the sediment in the hole is no more than 50mm, and use a spray device to control dust; Step 2.9, grouting machine installation: After fixing the grouting machine, connect it to the power supply; Step 2.10, install the grouting pipe: after the steel pipe is lowered, the grouting pipe is directly connected to the steel pipe in the entry hole by the grouting machine, the interface is sealed and connected, and the grouting pipe is transported by a rubber tube; Step 2.11, mix cement mortar: the water-cement ratio is controlled between 0.45 and 0.5; Step 2.12, injecting cement mortar: the first grouting pressure is 0.5Mpa. After grouting, the pipe is not pulled out until the cement mortar flows out of the pipe. The grouting pipe is pulled out and pressurized until the cement mortar flows out of the steel pipe again. Step 2.13, secondary pressure grouting: perform secondary gap grouting until the pipe mouth overflows.

8. The rapid construction method of a steel pipe pile support system with embedded steel according to claim 6 is characterized by: Step 3 specifically includes: Step 3.1, determine the baseline. According to the design requirements of the drawings, backfill the earthwork to the bottom elevation of the crown beam to determine the baseline; Step 3.2, level the earthwork so that the base size of the top beam is 100mm to 200mm larger than the structure; Step 3.3, clean the foundation pit and construct the cushion layer: pour the cushion layer concrete after the foundation pit is cleaned and accepted; Step 3.4, installation of steel bar binding template: prepare and bind steel bars according to the material distribution in the design drawings; Step 3.5, pouring the crown beam with concrete; Step 3.6, remove the mold and carry out maintenance.

Citation Information

Patent Citations

  • Novel foundation pit supporting system and construction method

    CN113216209A

  • Construction method for secant piles in water-rich rock-filled layer-containing soft soil area

    CN115584722A

  • Large-diameter steel pipe column mounting and positioning device