High overload missile load comprehensive parameter test system
By adopting dual-core system and timing control technology in the gunfire weapon environment, the problems of high-dynamic process measurement and full ballistic data recording in the chamber are solved, multi-parameter measurement and data safe recycling are realized, and detailed dynamic characteristic analysis data is provided.
Patent Information
- Application Number
- CN202010748389.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-07-30
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2040-07-30
AI Technical Summary
The prior art cannot perform high-speed real-time acquisition of multi-channel data and dynamic data recording of test components in the gunfire weapon environment, especially in the high dynamic process in the chamber.
Using a dual-core system, timing control is introduced. After powering on, the system first runs in low-power mode. The high-G-value accelerometer signal is used as a trigger signal to complete the measurement of the high-dynamic process in the chamber, and the large-capacity data storage module is used to record the entire process. The dynamic data of the ballistic and the timing control module completes the power outage and self-protection before landing to ensure safe data recovery.
It realizes a complete record of multi-parameter measurement and full ballistic flight data during high-impact overload, provides detailed reference data for the study of the dynamic characteristics of weapons in the gunfire environment, and improves the system's reaction speed and data security.
Smart Images

Figure CN111780612B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of high-overload artillery projectiles, and in particular to a high-overload projectile comprehensive parameter testing system, which can measure important parameters in a high-impact overload process and record flight data of the entire trajectory. Background Art
[0002] The environment of artillery-launched weapons is characterized by high overload, high temperature, and high pressure, and is a complex and highly dynamic process. During the development of artillery-launched weapons, multiple rounds of live-fire shooting are required to verify the environmental adaptability of various components of the system. In order to better analyze the dynamic performance of various components of the weapon, the test data and ballistic characteristics of the weapon need to be recorded and analyzed during this process.
[0003] Existing technology and its shortcomings:
[0004] The invention patent "A missile-borne platform data acquisition and storage system and method" (CN 107168919 A) proposes a missile-borne platform data acquisition system and method. Different types of external signals are read into the low-power Soc chip through the data acquisition module, and the data is processed and stored in the Micro SD card. Finally, the data is read back and analyzed by the host computer through the USB interface. This patent focuses on the data recording of the external ballistic process and ignores the acquisition and recording of the high dynamic process in the chamber.
[0005] The invention patent "An Acceleration Recording Device for a Missile-Loaded Test System" (CN 106771352A) proposes an acceleration recording device for a missile-loaded test system. The acceleration signal is conditioned, and the voltage signal is converted into a digital signal for storage through the built-in A / D conversion of the STM32. At the same time, it can be transmitted to the host computer through the USB port for real-time processing. This invention focuses on the measurement of acceleration, only taking into account the overload process in the bore, and cannot complete the multi-channel parameter acquisition and recording and the data recording of the tested specimen.
[0006] The invention patent "Missile-borne data test system" (CN 102506617 A) invented a missile-borne data test system, which includes an acquisition module, a processing module, a communication module and a power module. The system has strong anti-interference, high and low temperature resistance, dustproof capabilities, reusability, low cost, high reliability, low power consumption and other advantages. The system uses a mechanical overload switch to power on, and due to the delay of the switch, the parameter measurement in the chamber will be missed. The system mainly completes the parameter measurement during the flight phase, mainly completing the analog-to-digital conversion of the sensor, and cannot take into account the dynamic data recording of the test piece.
[0007] The above patents are all single-core systems, with an external switch controlling the entire system to power on, and once powered on, all systems are powered on. It is impossible to perform timing control for the ballistic process and power on modules according to needs. It is impossible to solve the problem of high-speed real-time acquisition of multi-channel data in a missile-borne environment and data recording of the tested components. Summary of the invention
[0008] In view of the above-mentioned technical problems, the purpose of the present invention is to provide a high-overload missile-load comprehensive parameter testing system, which can measure important parameters in the high-impact overload process and record flight data of the entire trajectory. The present invention adopts a dual-core system and introduces timing control. After power-on, the system first runs in a low-power mode to detect the high-G value accelerometer signal as the trigger signal of the entire system. The system responds quickly and can fully test the high-dynamic process of the ms level in the chamber. The large-capacity data storage module can fully record the dynamic data of the tested specimen within the entire trajectory. Before landing, the timing control module can complete power-off self-protection to ensure the safe recovery of the main system data.
[0009] The technical solution of the present invention is:
[0010] A high overload missile comprehensive parameter testing system comprises a sensor module fixed on a missile body, the sensor module comprises an acceleration sensor, the acceleration sensor signal is used as a system trigger signal to connect a timing management chip, the timing management chip is connected to the sensor module and a tested piece through a power control switch, the tested piece is connected to a main control chip, the sensor module is connected to the main control chip after passing through a signal conditioning module, the main control chip is connected to a storage chip, the main control chip is also connected to a timing management chip, and the power supply is respectively connected to the timing management chip and the power control switch through a voltage conversion chip.
[0011] In a preferred technical solution, the sensor module further includes a temperature sensor and a pressure sensor. The temperature sensing head of the temperature sensor is exposed in the bottom device through the temperature measuring cavity, and the pressure measuring surface of the pressure sensor is connected to the bottom air chamber through a pressure measuring hole.
[0012] In a preferred technical solution, when the timing of the timing management chip reaches a preset in-bore time threshold, the sensor module is controlled to be powered off.
[0013] In a preferred technical solution, when the timing of the timing management chip reaches a preset full-ballistic flight time threshold, the entire control system is powered off.
[0014] In the preferred technical solution, the main control chip receives the test data of the tested component through the RS422 serial port, and stores the test data in a large-capacity Flash.
[0015] In the preferred technical solution, after the projectile is recovered, the control system is powered on, and the main control chip detects the write status of the storage chip and reads the stored time and voltage values in segments according to the input read operation instructions and transmits them to the host computer; the test data in the large-capacity Flash is read through the read instructions.
[0016] In the preferred technical solution, the main control chip scans and reads the data collected by acceleration to determine whether the set trigger threshold is reached. When the trigger threshold is not reached, the collected data is cyclically stored in the cache; otherwise, a trigger signal is sent to the timing management chip to control the switch according to the power-on time period set for each part to complete the timing control.
[0017] Compared with the prior art, the advantages of the present invention are:
[0018] 1. The present invention measures and stores the high-dynamic projectile characteristics and environmental parameters during projectile launch and exterior ballistic flight through temperature, pressure and acceleration sensors, and stores and records the output of the tested specimen during the entire flight process, providing a reference for the study of the dynamic characteristics of weapons in a cannon firing environment.
[0019] 2. The present invention adopts a dual-core system and introduces timing control. After power-on, the system first runs in low-power mode and detects high-G value accelerometer signals as the trigger signal of the entire system. The system reacts quickly and can fully test the high dynamic process of the ms level in the chamber. The large-capacity data storage module can fully record the dynamic data of the tested specimen within the full ballistic range. Before landing, the timing control module can complete power-off self-protection to ensure the safe recovery of the main system data. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The present invention will be further described below in conjunction with the accompanying drawings and embodiments:
[0021] Figure 1 This is the block diagram of the high overload missile load comprehensive parameter test system;
[0022] Figure 2 It is the internal software execution flow chart of the high overload missile comprehensive parameter test system. DETAILED DESCRIPTION
[0023] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is further described in detail below in conjunction with specific embodiments and with reference to the accompanying drawings. It should be understood that these descriptions are only exemplary and are not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concept of the present invention.
[0024] like Figure 1As shown in the figure, the system hardware design of the high overload missile load comprehensive parameter test system is divided into two modules: power supply and timing management module, signal conditioning and storage module. The power supply and timing management module is used to provide various power supplies for the system and control the power-on timing of each module according to the usage requirements. The signal conditioning and storage module is the core of the system, which is used to condition the signals of each sensor, control the timing logic through the main control chip, and receive multiple data and store them in the built-in Flash.
[0025] The present invention adopts a dual-core system and introduces timing control. After power-on, the system first runs in a low-power mode and detects the high-G value accelerometer signal as the trigger signal of the entire system. The system reacts quickly and can fully test the high dynamic process of the ms level in the chamber. The large-capacity data storage module can fully record the dynamic data of the tested specimen within the full ballistic range. Before landing, the timing control module can complete power-off self-protection to ensure the safe recovery of the main system data.
[0026] The sensor includes a large-range high-overload resistant temperature sensor, a pressure sensor and a high-G value acceleration sensor. The large-range high-overload resistant temperature sensor is fixed on the projectile through a mounting seat, and the sensor temperature sensing head is exposed to the bottom device through the temperature measuring cavity. When the gunpowder in the chamber starts to work, the gas enters the temperature measuring cavity, and the temperature sensor temperature sensing head immediately senses the gas temperature and measures the bottom temperature during the full ballistic flight process; the pressure sensor is fixed on the projectile through a bow-shaped pressure measuring cavity mounting seat, and the sensor pressure measuring surface is connected to the bottom air chamber through the pressure measuring hole to measure the combustion gas pressure when moving in the bore of the gun; the high-G value acceleration sensor, the sensor is fixed on the projectile through a mounting seat, and measures the acceleration value of the three-axis direction when the projectile moves in the bore. Of course, other types of sensors can also be set, and this embodiment only takes three types of sensors as examples for explanation.
[0027] The acceleration sensor signal is connected to the timing management chip as a system trigger signal. The timing management chip is connected to the sensor module and the tested piece through the power control switch (switches 1-4 in the figure). The tested piece is connected to the main control chip. The sensor module is connected to the main control chip after passing through the signal conditioning module. The main control chip is connected to the storage chip. The main control chip is also connected to the timing management chip. The power supply is connected to the timing management chip and the power control switch respectively through the voltage conversion chip.
[0028] Before the projectile is loaded into the chamber, the battery lead of the reserved projectile-borne test system is connected to the system power lead, and the power supply is supplied to the timing management chip and each sensor through the power conversion chip 1 and the power conversion chip 2 respectively. When the projectile is launched, the timing management chip detects the trigger signal provided by the high-G accelerometer, starts the system timing, and turns on the power control switch of each sensor and the acquisition and storage system, and supplies power to the tested test piece, temperature sensor, pressure sensor and acquisition and storage chip at the same time. During the power supply period of the sensor and the acquisition and storage system, the temperature, pressure, acceleration sensor and its corresponding signal conditioning circuit convert the state quantity measured by the sensor into the corresponding voltage signal and input it into the I / O port of the main control chip. The main control chip transmits the data to the external storage chip at high speed for storage when the valid signal is correctly identified.
[0029] When the timing management chip reaches the preset in-bore time threshold, such as 1s (which can be modified according to actual shooting conditions), the temperature, pressure sensors and high-G accelerometer are powered off. The system receives the data of the tested piece during the entire flight process through the RS422 serial port and stores the data in a large-capacity Flash.
[0030] When the power timing management chip reaches the preset full-ballistic flight time threshold, such as 100s (which can be modified according to actual shooting conditions), the entire system is powered off, allowing the system to experience the landing impact process under power-off, thereby increasing system safety and reliability.
[0031] After the projectile is recovered, the system is powered on again. After the main control chip detects the write status of the storage chip, it reads the stored time and voltage values in segments according to the input read operation instructions and transmits them to the host computer. According to the circuit design and measured parameters, the voltage value is converted into the correct sensor measurement value, which serves as the reference data for the projectile characteristic analysis. The test data in the large-capacity Flash is read through the read instruction to analyze the working characteristics of the tested test piece in the full trajectory, providing a basis for subsequent design improvements.
[0032] System software execution process, such as Figure 2As shown in the figure, after the system is powered on, some peripherals are initialized first. These peripherals are mainly used for communication with the host computer and the storage chip. After the initialization is completed, the flag bit is detected to determine whether a trigger acquisition has been completed. If there is data inside, wait for the serial port instruction. The serial port instructions are divided into three categories: read back the data collected by each sensor, read the ballistic data stored in the high-speed Flash, and convert it into the unit value of the required measurement class through calculation; read back the dynamic data of the tested test piece, which is stored in the large-capacity Flash; clear the data, set the system to the waiting trigger state, and prepare for the next test. After each type of instruction is completed, a specific completion flag is sent to the host computer. If the program is in the waiting trigger mode, the peripherals are further turned on. These peripherals are mainly used for communication with sensors and the tested test piece. The system scans and reads the data collected by the high G value acceleration to determine whether the set trigger threshold is reached. Before the trigger threshold is reached, this part of the data is stored in the cache in a loop and does not occupy the Flash storage space. After the system is triggered, a trigger signal is sent to the timing management module to control the switch according to the power-on time period set for each part to complete the timing control. After the trigger, the data acquisition phase begins, and the sensor values are converted to AD and stored in the Flash. The tested device and the main system complete data transmission through the serial port and DMA, completing the transmission and recording of large-capacity data. After the timing is reached, each switch is powered off, and the system implements power-off protection before landing.
[0033] It should be understood that the above specific embodiments of the present invention are only used to illustrate or explain the principles of the present invention, and do not constitute a limitation of the present invention. Therefore, any modifications, equivalent substitutions, improvements, etc. made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. In addition, the appended claims of the present invention are intended to cover all changes and modifications that fall within the scope and boundaries of the appended claims, or the equivalent forms of such scope and boundaries.
Claims
1. A high overload missile load comprehensive parameter testing system, characterized in that: The device comprises a sensor module fixed on the body, the sensor module comprises an acceleration sensor, the acceleration sensor signal is used as a system trigger signal to connect to a timing management chip, the timing management chip is connected to the sensor module and a test piece through a power control switch, the test piece is connected to a main control chip, the sensor module is connected to the main control chip after passing through a signal conditioning module, the main control chip is connected to a storage chip, the main control chip is also connected to a timing management chip, and the power supply is respectively connected to the timing management chip and the power control switch through a voltage conversion chip; When the timing management chip reaches a preset in-chamber time threshold, the sensor module is controlled to be powered off; When the timing of the timing management chip reaches a preset full trajectory flight time threshold, the control system is powered off as a whole.
2. The high overload missile load comprehensive parameter testing system according to claim 1 is characterized in that: The sensor module also includes a temperature sensor and a pressure sensor. The temperature sensing head of the temperature sensor is exposed in the bottom device through the temperature measuring cavity, and the pressure measuring surface of the pressure sensor is connected to the bottom air chamber through the pressure measuring hole.
3. The high overload missile load comprehensive parameter testing system according to claim 1 is characterized in that: The main control chip receives the test data of the tested component through the RS422 serial port, and stores the test data in a large-capacity Flash.
4. The high overload missile load comprehensive parameter testing system according to claim 3 is characterized in that: After the projectile is recovered, the control system is powered on. The main control chip detects the write status of the storage chip and reads the stored time and voltage values in segments according to the input read operation instructions and transmits them to the host computer; the test data in the large-capacity Flash is read through the read instructions.
5. The high overload missile load comprehensive parameter testing system according to claim 1 is characterized in that: The main control chip scans and reads the data collected by acceleration to determine whether the set trigger threshold is reached. When the trigger threshold is not reached, the collected data is cyclically stored in the cache; otherwise, a trigger signal is sent to the timing management chip to control the switch according to the power-on time period set for each part to complete the timing control.