A pile foundation steel cage anti-floating device and cast-in-place pile construction method
By arranging anti-floating devices of cross-shaped tracks, strip channel steel and threaded steel pipes at the lower end of the steel cage, and using movable steel drills to be inserted into the soil to fix the steel cage, the problem of floating steel cages during cast-in-place pile construction was solved, and construction efficiency and efficiency were improved. Piling quality, and the unit is easy to remove and reuse.
Patent Information
- Application Number
- CN202010860650.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-08-25
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2040-08-25
AI Technical Summary
In the construction of bridges and housing projects, the steel cages are prone to float due to excessive concrete return speed during cast-in-place pile construction, and the existing anti-floating devices may be damaged and unstable when removed.
Design an anti-floating device for pile foundation steel cages, including cross-shaped tracks, strip channel steel and threaded steel pipes, which are fixed at the lower end of the steel cage through connectors. The steel drills and threaded steel pipes are movablely connected to insert the steel drills into the soil and fix them. On strip channel steel, avoid floating and remove it after the concrete pouring is completed.
It effectively prevents the steel cage from floating, improves the quality of the pile foundation, simplifies the construction process, reduces labor costs, and the device is easy to take out, with high stability and multiple uses.
Smart Images

Figure CN111809614B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to an anti-floating device for a pile foundation steel cage and a cast-in-place pile construction method. Background Art
[0002] At present, bored pile construction is often required in the construction of bridges and building projects. After the holes are formed and cleaned, a steel cage needs to be lowered into the hole, and then concrete is poured to form piles. In the process of pouring concrete, when the concrete surface reaches the bottom of the steel cage, the buried depth of the conduit is shallow and the amount of concrete poured is relatively large, resulting in excessive concrete return speed, which generates a large upward force, thereby lifting the conduit and the steel cage; or in the process of lifting the conduit after pouring, it is easy to be caught by the conduit and lifted together, causing the steel cage to float. At this time, a simple and practical device is needed to suppress the floating of the steel cage.
[0003] In the prior art, most of them adopt the method of setting components on the steel cage, and controlling the steel cage to float up by counterweighting the components or setting telescopic parts to be inserted into the soil.
[0004] Problems and shortcomings of the prior art: (explain the reasons for these problems and shortcomings where possible). The prior art requires connecting parts to be made on the steel cage, which may damage the parent material, and is not convenient for removing the device after pouring is completed, and the effects of some methods are not stable enough. Summary of the invention
[0005] The technical problem to be solved by the present invention is to provide a pile foundation steel cage anti-floating device and a cast-in-place pile construction method, which solves the problem of steel cage floating during cast-in-place pile construction in the prior art.
[0006] The present invention adopts the following technical solutions to solve the above technical problems:
[0007] A pile foundation steel cage anti-floating device comprises a cross-shaped track and a strip channel steel. The cross-shaped track and the strip channel steel are connected to form a frame through a connecting piece. The frame is fixed at the lower end of the steel cage. The two ends of the strip channel steel pass through the wall of a steel casing. The cross-shaped track is located below the strip channel steel. A reserved hole is arranged at the center of the strip channel steel. A threaded steel pipe is inserted into the reserved hole. A circumferentially movable steel bar is arranged at the lower end of the threaded steel pipe. When the threaded steel pipe is pushed downward, the free end of the steel bar moves in the cross-shaped track. After the steel bar reaches the target position, the threaded steel pipe is fixed on the strip channel steel.
[0008] The connecting piece is two screw rods arranged on the same axis of the cross track. The upper ends of the two screw rods pass through the reserved holes on the strip channel steel and are fixed on the strip channel steel by bolts.
[0009] The cross-shaped track comprises four channel steels welded together, each channel steel is welded together by three steel plates, and the two screw rods are respectively welded to two channel steels on the same axis.
[0010] The steel chisel is fixed to the lower end of the threaded steel pipe through a steel chisel connector, wherein the steel chisel connector includes two oppositely arranged perforated steel sheets, bolts passing through the perforated steel sheets and fixing nuts. One end of the steel chisel has a through hole, and a bolt is passed through the steel chisel through hole to fix it between the two perforated steel sheets.
[0011] The steel drill connection pieces include four pieces, which are uniformly welded to the lower end of the threaded steel pipe in the circumferential direction.
[0012] The steel chisel is a plain round steel bar, and its free end is arranged as a quadrangular pyramid end.
[0013] The upper end of the threaded steel pipe is provided with threads and fixed to the strip channel steel by nuts.
[0014] A cast-in-place pile construction method comprises the following steps:
[0015] Step 1: reserve two holes at both ends of any diameter of the steel casing for the passage of the strip channel steel in the pile foundation steel cage anti-floating device;
[0016] Step 2: bury the steel casing, and after the hole is formed and cleaned, lower the steel cage;
[0017] Step 3: After the steel cage is lowered, lower the components of the pile foundation steel cage anti-floating device except the strip channel steel into the hole, and keep the bottom of the device below the bottom of the steel casing;
[0018] Step 4: Pass the strip channel steel through the reserved hole of the steel casing;
[0019] Step 5: Pass the screws at both ends of the cross-shaped track in the device and the threaded steel pipe placed in the center of the cross-shaped track through the reserved holes on the strip channel steel, and fix the screws at both ends of the strip channel steel;
[0020] Step 6: Move the middle threaded steel pipe up and down to spread the four steel chisels until they are inserted into the hole wall soil. After the steel chisels are inserted into the hole wall, fix the threaded steel pipe on the strip channel steel;
[0021] Step 7: Pour the pile foundation concrete. After the concrete is poured to a certain height, remove the pile foundation steel cage anti-floating device.
[0022] In step 6, push the threaded steel pipe downward so that the four steel drills are spread out to the surroundings through the cross-shaped track and fully inserted into the hole wall, and then fix the threaded steel pipe to the strip channel steel with nuts.
[0023] In step 7, the concrete is poured until the steel cage is fixed and continues to pour until it stops floating, and then the pile foundation steel cage anti-floating device can be removed.
[0024] Compared with the prior art, the present invention has the following beneficial effects:
[0025] 1. The device cooperates with a steel casing with two reserved holes. A strip channel steel is inserted into the two reserved holes of the steel casing. The strip channel steel has three reserved holes, and the two reserved holes at both ends are used to connect with a cross channel steel through two threaded rods. The two threaded rods are welded to the cross channel steel at the ends and fixed to the upper strip channel steel through the upper and lower nuts of the two screws; a threaded steel pipe with four movable steel chisels is inserted into the reserved hole in the middle of the above-mentioned strip channel steel, and the four steel chisels are extended outward through the cross channel steel by adjusting the threaded steel pipe up and down, so that the four steel chisels can be inserted into the hole wall of the pile foundation, and finally the threaded steel pipe is fixed by the nut, so that the threaded steel pipe cannot move up and down, thereby achieving the purpose of fixing the steel cage, avoiding the phenomenon of the steel cage floating when pouring concrete, and improving the quality of pile foundation.
[0026] 2. The length of the exposed steel bar at the pile head is controlled, thereby improving construction efficiency and reducing labor costs. The device has a simple structure, is easy to manufacture, and is very practical.
[0027] 3. When the device is used for cast-in-place pile construction, the device is not connected to the steel cage and will not damage the parent material. The device is easy to take out, has high stability, can be reused many times, and is economical. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a front structural schematic diagram of the pile foundation steel cage anti-floating device of the present invention.
[0029] Figure 2 It is a top view of the pile foundation steel cage anti-floating device of the present invention.
[0030] Figure 3 It is the AA cross-sectional view of the pile foundation steel cage anti-floating device of the present invention.
[0031] Figure 4 This is an elevation view of the connection between the steel chisel fixing plate and the threaded steel pipe of the pile foundation steel cage anti-floating device of the present invention.
[0032] Figure 5 This is a plan view of the connection between the steel chisel fixing plate and the threaded steel pipe of the pile foundation steel cage anti-floating device of the present invention.
[0033] Figure 6 This is a vertical view of the connection between the strip channel steel and the threaded steel pipe of the pile foundation reinforcement cage anti-floating device of the present invention.
[0034] Among them, the markings in the figure are: 1-cross track; 2-steel drill fixing plate; 3-steel drill; 4-threaded steel pipe; 5-strip channel steel; 6-screw; 7-nut. DETAILED DESCRIPTION
[0035] The structure and working process of the present invention will be further described below in conjunction with the accompanying drawings.
[0036] A pile foundation steel cage anti-floating device comprises a cross-shaped track and a strip channel steel. The cross-shaped track and the strip channel steel are connected to form a frame through a connecting piece. The frame is fixed at the lower end of the steel cage. The two ends of the strip channel steel pass through the wall of a steel casing. The cross-shaped track is located below the strip channel steel. A reserved hole is arranged at the center of the strip channel steel. A threaded steel pipe is inserted into the reserved hole. A circumferentially movable steel bar is arranged at the lower end of the threaded steel pipe. When the threaded steel pipe is pushed downward, the free end of the steel bar moves in the cross-shaped track. After the steel bar reaches the target position, the threaded steel pipe is fixed on the strip channel steel.
[0037] The connecting piece is two screw rods arranged on the same axis of the cross track. The upper ends of the two screw rods pass through the reserved holes on the strip channel steel and are fixed on the strip channel steel by bolts.
[0038] The cross-shaped track comprises four channel steels welded together, each channel steel is welded together by three steel plates, and the two screw rods are respectively welded to two channel steels on the same axis.
[0039] The steel chisel is fixed to the lower end of the threaded steel pipe through a steel chisel connector, wherein the steel chisel connector includes two oppositely arranged perforated steel sheets, bolts passing through the perforated steel sheets and fixing nuts. One end of the steel chisel has a through hole, and a bolt is passed through the steel chisel through hole to fix it between the two perforated steel sheets.
[0040] Specific embodiments, such as Figures 1 to 6 As shown,
[0041] The device comprises: a cross track 1, a steel drill fixing plate 2, a steel drill 3, a threaded steel pipe 4, a strip channel steel 5, a screw 6 and a nut 7; wherein the cross track 1 and the strip channel steel 5 are connected into a frame through a connecting piece, and the connecting piece is two screws 6 welded at both ends of the cross track 1, and the screws cooperate with the nuts to fix the strip channel steel 5; the frame is fixed at the lower end of the steel cage, and the two ends of the strip channel steel 5 pass through the wall of the steel casing, and the cross track 1 is located below the strip channel steel 5; wherein a reserved hole is arranged at the center of the strip channel steel 5, and the threaded steel pipe 4 is inserted into the reserved hole, and a movably connected steel drill 3 is circumferentially arranged at the lower end of the threaded steel pipe 4, and when the threaded steel pipe 4 is pushed downward, the free end of the steel drill 3 moves in the cross track, and after the steel drill reaches the target position, the nut 7 is used to fix the threaded steel pipe on the strip channel steel 5.
[0042] In this embodiment, four steel drills 3 are fixed to the lower end of the threaded steel pipe 4. The four steel drills 3 have holes at one end and quadrangular pyramid ends at the other end.
[0043] The strip channel steel 5 will pass through the steel casing with two reserved holes, and the strip channel steel 5 has three reserved holes for fixing the threaded steel pipe 4 with the movable steel chisel 3 and the two screws 6 welded to the cross channel steel 1, so that the whole device is connected as a whole.
[0044] In the embodiment of the present invention, the steel brazing connector is a steel plate 2 with four groups (eight pieces) of square steel plates 2 with holes welded around the lower end of the threaded steel pipe 4, and four bolts pass through the steel plates respectively and are screwed and fastened with four nuts.
[0045] In the embodiment of the present invention, the strip channel steel 5 has three reserved holes.
[0046] The following is a detailed description of several important components of the docking fine-tuning device:
[0047] Cross track 1: It is composed of 4 channel steels welded together. Each channel steel is welded into a cross shape using three 2mm thick steel plates. The height of each channel steel around is 3cm, the width of the bottom plate is 5cm, and the screws 6 are welded to two channel steels on the same axis.
[0048] Steel drill fixing plate 2: Four groups (eight pieces) of square steel plates with holes with a specification of 2cm*1cm, and four bolts with a specification of M3.0 pass through the steel plates respectively, and are screwed and tightened with four nuts.
[0049] Steel bar 3: It is made of smooth round steel bar with a diameter of 8mm and a length of 1m. A hole is punched at the connecting end of the steel bar, and bolts are passed through the steel bar fixing plate and fixed with nuts to achieve the purpose of connecting with the steel bar fixing plate.
[0050] Threaded steel pipe 4: The upper end is made with M30, coarse pitch 3.5mm thread, length 2m, diameter 28mm.
[0051] Strip channel steel 5: There are 1 in total. Each strip channel steel (rectangular) is formed by welding three 3mm thick steel plates. Its height is 3cm and the bottom plate width is 7cm. Three holes are reserved in the bottom plate. The hole diameters on both sides are 12mm and the middle hole diameter is 30mm.
[0052] Plain round steel bar screw 6: Use screw with specification of M12 and length of 1.8m.
[0053] Nut 7: The thread is M30 and the nut is an M30 hexagonal nut.
[0054] Specific embodiment 2:
[0055] A cast-in-place pile construction method comprises the following steps:
[0056] Step 1: reserve two holes at both ends of any diameter of the steel casing for the passage of the strip channel steel in the pile foundation steel cage anti-floating device;
[0057] Step 2: bury the steel casing, and after the hole is formed and cleaned, lower the steel cage;
[0058] Step 3: After the steel cage is lowered, lower the components of the pile foundation steel cage anti-floating device except the strip channel steel into the hole, and keep the bottom of the device below the bottom of the steel casing;
[0059] Step 4: Pass the strip channel steel through the reserved hole of the steel casing;
[0060] Step 5: Pass the screws at both ends of the cross-shaped track in the device and the threaded steel pipe placed in the center of the cross-shaped track through the reserved holes on the strip channel steel, and fix the screws at both ends of the strip channel steel;
[0061] Step 6: Move the middle threaded steel pipe up and down to spread the four steel chisels until they are inserted into the hole wall soil. After the steel chisels are inserted into the hole wall, fix the threaded steel pipe on the strip channel steel;
[0062] Step 7: Pour the pile foundation concrete. After the concrete is poured to a certain height, remove the pile foundation steel cage anti-floating device.
[0063] In step 6, push the threaded steel pipe downward so that the four steel drills are spread out to the surroundings through the cross-shaped track and fully inserted into the hole wall, and then fix the threaded steel pipe to the strip channel steel with nuts.
[0064] In step 7, the concrete is poured until the steel cage is fixed and continues to pour until it stops floating, and then the pile foundation steel cage anti-floating device can be removed.
[0065] Those skilled in the art should understand that those skilled in the art can implement variations by combining the prior art and the above embodiments, which will not be described in detail here. Such variations do not affect the essential content of the present invention, and will not be described in detail here.
[0066] The preferred embodiments of the present invention are described above. It should be understood that the sizes of various parts of the above device should be flexibly changed according to different pile diameters, and the device of the above size is suitable for piles with a pile diameter of 1.6-1.8m. The present invention is not limited to the above-mentioned specific implementation mode, and the equipment and structure that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can make many possible changes and modifications to the technical solution of the present invention by using the methods and technical contents disclosed above without departing from the scope of the technical solution of the present invention, or modify it into an equivalent embodiment of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the scope of protection of the technical solution of the present invention.
Claims
1. A cast-in-place pile construction method based on a pile foundation steel cage anti-floating device, wherein the pile foundation steel cage anti-floating device comprises a cross-shaped track and a strip channel steel, wherein the cross-shaped track and the strip channel steel are connected to form a frame through a connecting piece, wherein the frame is fixed to the lower end of the steel cage, and both ends of the strip channel steel pass through the wall of the steel casing, and the cross-shaped track is located below the strip channel steel; in, A reserved hole is set in the center of the strip channel steel, and a threaded steel pipe is inserted into the reserved hole. A steel drill with a movable connection is set circumferentially at the lower end of the threaded steel pipe. When the threaded steel pipe is pushed downward, the free end of the steel drill moves in the cross-shaped track. After the steel drill reaches the target position, the threaded steel pipe is fixed on the strip channel steel. The connecting member is two screw rods set on the same axis of the cross-shaped track. The upper ends of the two screw rods pass through the reserved holes on the strip channel steel and are fixed to the strip channel steel by bolts. The cross-shaped track includes four channel steels welded together, each channel steel is welded by three steel plates, and the two screw rods are respectively welded to two channel steels on the same axis; it is characterized in that: the cast-in-place pile construction method includes the following steps: Step 1: reserve two holes at both ends of any diameter of the steel casing for the passage of the strip channel steel in the pile foundation steel cage anti-floating device; Step 2: bury the steel casing, and after the hole is formed and cleaned, lower the steel cage; Step 3: After the steel cage is lowered, lower the components of the pile foundation steel cage anti-floating device except the strip channel steel into the hole, and keep the bottom of the device below the bottom of the steel casing; Step 4: Pass the strip channel steel through the reserved hole of the steel casing; Step 5: Pass the screws at both ends of the cross-shaped track in the device and the threaded steel pipe placed in the center of the cross-shaped track through the reserved holes on the strip channel steel, and fix the screws at both ends of the strip channel steel; Step 6: Move the middle threaded steel pipe up and down to spread the four steel chisels until they are inserted into the hole wall soil. After the steel chisels are inserted into the hole wall, fix the threaded steel pipe on the strip channel steel; Step 7: Pour the pile foundation concrete until the steel cage is fixed and continue pouring until it reaches a height where it will not float up. Then you can remove the anti-floating device of the pile foundation steel cage.
2. The cast-in-place pile construction method according to claim 1, Features: The steel chisel is fixed to the lower end of the threaded steel pipe through a steel chisel connector, wherein the steel chisel connector includes two oppositely arranged perforated steel sheets, bolts passing through the perforated steel sheets and fixing nuts. One end of the steel chisel has a through hole, and a bolt is passed through the steel chisel through hole to fix it between the two perforated steel sheets.
3. The cast-in-place pile construction method according to claim 2, Features: The steel drill connection pieces include four pieces, which are uniformly welded to the lower end of the threaded steel pipe in the circumferential direction.
4. The cast-in-place pile construction method according to claim 1, Features: The steel chisel is a plain round steel bar, and its free end is arranged as a quadrangular pyramid end.
5. The cast-in-place pile construction method according to claim 1, Features: The upper end of the threaded steel pipe is provided with threads and fixed to the strip channel steel by nuts.
6. The cast-in-place pile construction method according to claim 1, Features: In step 6, push the threaded steel pipe downward so that the four steel drills are spread out to the surroundings through the cross-shaped track and fully inserted into the hole wall, and then fix the threaded steel pipe to the strip channel steel with nuts.
Citation Information
Patent Citations
Device for preventing steel reinforcement cage come -up
CN206538759U