Installation structure of roof truss and curved multi-layered horseway and construction method of horseway
Through the installation structure and construction methods of roof trusses and arc-shaped multi-layer horse lane, bolt connection and division unit construction are used to solve the problems of slow installation progress and high cost in the existing technology, and efficient and safe horse lane installation is achieved, reducing the number of constructions of the horse lane. Welding operations and safety risks.
Patent Information
- Application Number
- CN202010858556.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-08-24
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2040-08-24
AI Technical Summary
In the prior art, the installation progress of roof trusses and arc-shaped multi-layer horse lanes is slow, the safety risks are high, and the construction cost is high, so it is impossible to effectively use external equipment for lifting, resulting in complex high-altitude assembly operations of the horse lanes.
The installation structure of roof trusses and arc-shaped multi-layer horse paths is adopted. The parallelogram frame is formed through components such as hanging rods, walkway cross beams and connecting parts. The welding operation is reduced by bolt connections, and the horse paths are divided into hoisting units and loose parts units. The factory prefabricated semi-finished products and cross-external assembly methods are used to construct using the hoisted units as the operating platform.
It improves construction efficiency, reduces construction costs, reduces welding operations, achieves green and environmental protection, and makes full use of constrained space through a scientific construction management model to ensure the progress of the project.
Smart Images

Figure CN111852041B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building steel structure construction, and in particular relates to an installation structure of a roof truss and an arc-shaped multi-layered horseway and a construction method of the horseway. Background Art
[0002] With the ever-increasing spiritual and cultural needs of human beings, cultural tourism complex projects centered on theme parks continue to emerge. Their architectural shapes are unique and have unique regional characteristics, especially single buildings represented by large-scale special performance venues (gymnasiums, theaters, etc.).
[0003] Performance venues are mostly made of steel-concrete structures or structures with steel as the main structure. A large number of stage machinery facilities, pipelines, controllers, lighting equipment, etc. need to be suspended above the performance venues. In order to facilitate the staff to install, debug and repair these equipment, curved multi-layered horseways are often hung under the roof trusses to provide a bearing platform for the staff. The so-called arc is the high-altitude plane layout of the horseway, which is actually composed of multiple broken lines.
[0004] At present, the main method of installing the horseway is to install the horseway after the installation of the roof structure trusses is completed, and include the installation of the horseway in the interior decoration project of the performance hall. In this way, not only the installation progress is slow, but also, due to the capping of the roof, it is impossible to use external equipment to lift the segmented horseway through the gap in the roof truss. If a small crane is used to enter the venue to lift the segmented horseway, at this time, due to the limited lifting capacity, the horseway will have many high-altitude assembly operations, great safety risks, or a large number of measure brackets will need to be set up in the venue, which is costly. Summary of the invention
[0005] In view of the above-mentioned deficiencies in the prior art, the purpose of the present invention is to provide an installation structure of a roof truss and a curved multi-layered horseway and a construction method of the horseway, which can improve work efficiency and reduce construction costs.
[0006] The installation structure of the roof truss and the curved multi-layered horseway, the horseway spans across several roof trusses and is suspended on the lower chord of the roof trusses, a horseway unit is formed between two adjacent roof trusses, the plane projection of each horseway unit is a parallelogram, each horseway unit includes four hangers, each hanger is vertically arranged and located at the four vertices of the parallelogram, the lower ends of the four hangers are connected by two parallel walkway longitudinal beams arranged along the longitudinal direction of the horseway and two parallel walkway cross beams arranged along the transverse direction of the horseway to form a parallelogram frame, a walkway board is arranged in the parallelogram frame, and the whole horseway is formed by connecting several horseway units in series; the lower end of each hanger has a ring A first connecting piece of a shape, the first connecting piece is sleeved on the hanger and fixed to the hanger, a plurality of first stiffening plates are evenly distributed on the outer circumference of the first connecting piece, each first stiffening plate is provided with a plurality of first bolt holes, and a plurality of second bolt holes and third bolt holes corresponding to the first bolt holes are respectively provided at both ends of the walkway longitudinal beam and the walkway cross beam, the first bolt passes through the second bolt hole and the corresponding first bolt hole in sequence to fix the walkway longitudinal beam and the first connecting piece, thereby fixing the walkway longitudinal beam and the hanger; the second bolt passes through the third bolt hole and the corresponding first bolt hole in sequence to fix the walkway cross beam and the first connecting piece, thereby fixing the walkway cross beam and the hanger.
[0007] Furthermore, a first connecting plate is provided at the upper end of each hanger, and a plurality of fourth bolt holes are provided on the first connecting plate and pass through the two side surfaces of the first connecting plate. A second connecting plate is provided on the lower chord of the roof truss, and a plurality of fifth bolt holes corresponding to the fourth bolt holes are provided on the second connecting plate. The third bolt passes through the fourth bolt hole and the fifth bolt hole in sequence to connect the first connecting plate and the second connecting plate, thereby fixing the horseway to the lower chord of the roof truss.
[0008] Furthermore, several layers of connecting rods are provided along the height direction of the hangers, and the connecting rods are arranged between two adjacent hangers and are evenly distributed up and down to divide the horseway unit into several layers, wherein the connecting rods arranged along the longitudinal direction of the horseway are connecting longitudinal rods, and the connecting rods arranged along the transverse direction of the horseway are connecting cross rods, and the two adjacent connecting cross rods in the upper and lower layers and the corresponding two hangers form a quadrilateral, and a first diagonal brace is distributed along the diagonal of the quadrilateral.
[0009] Furthermore, the connecting rod is fixedly connected to the suspension rod through an annular second connecting piece, the second connecting piece is sleeved on the suspension rod and fixed to the suspension rod, a plurality of second stiffening plates are provided on the outer circumference of the second connecting piece, and a plurality of sixth bolt holes are provided on the second stiffening plates, a plurality of seventh bolt holes corresponding to the sixth bolt holes are provided at both ends of the connecting rod, and the fourth bolt passes through the seventh bolt hole and the corresponding sixth bolt hole in sequence to fix the connecting rod and the suspension rod.
[0010] Furthermore, a third connecting plate is provided on both end surfaces of the second connecting member, a plurality of eighth bolt holes are provided on the third connecting plate, a ninth bolt hole corresponding to the eighth bolt hole is provided on the first diagonal brace rod, and the fifth bolt passes through the ninth bolt hole and the eighth bolt hole in sequence to fix the first diagonal brace rod and the third connecting plate.
[0011] Furthermore, a second diagonal brace is provided along the diagonal of the quadrilateral formed by the topmost connecting cross bar, the lower chord of the roof truss and the corresponding two hangers. One end of the second diagonal brace is fixedly connected to the third connecting plate by a sixth bolt, and the other end is fixedly connected to the second connecting plate by a seventh bolt.
[0012] Furthermore, guardrails are respectively fixed on the two walkway longitudinal beams.
[0013] The construction method of the curved multi-layered bridleway is to construct the curved multi-layered bridleway according to the aforementioned installation structure of the roof truss and the curved multi-layered bridleway, and specifically comprises the following steps:
[0014] (1) Making roof trusses: According to the BIM model of the venue, cut materials to make roof trusses, and at the same time obtain the spatial coordinates of all connection points between the lower chord of the roof truss and the entire curved walkway. When making the roof trusses, make the second connecting plate at the corresponding position of the lower chord of the roof truss according to the spatial coordinates of the connection points;
[0015] (2) Fabrication of the components of the bridleway: Based on the BIM model of the venue, the entire curved bridleway is divided into a number of hoisting units and loose component units according to the spacing between two adjacent roof trusses. Each loose component unit is located between two corresponding hoisting units. At the same time, the components of the bridleway are cut and fabricated, and the corresponding first connecting plate is fabricated at the top of each suspender.
[0016] (3) Factory prefabricated semi-finished products: The hangers, walkway beams, connecting crossbars, first diagonal braces and second diagonal braces of all the hoisting units are pre-assembled into semi-finished products in the factory, so that each hoisting unit has two semi-finished products;
[0017] (4) Assembling the hoisting unit outside the span: Harden the ground outside the span at the construction site, and then assemble the hoisting unit. During assembly, first weld and fix the walkway plate to the two walkway longitudinal beams, and then hoist the two semi-finished products to the two ends of the two walkway longitudinal beams in turn. Use the first bolt to connect the walkway longitudinal beam and the first connecting piece and initially tighten the first bolt. Then assemble the connecting longitudinal rods from bottom to top in turn, and initially tighten the fourth bolt. Then use a total station to measure the coordinates of the positioning points of the first connecting plate and the first connecting piece to ensure that the error between the measured coordinates and the theoretical value is less than 15 mm. Then, finally tighten the first bolt and the fourth bolt. Follow this step to complete the assembly of all hoisting units.
[0018] (5) Hoisting the hoisting unit outside the span: The hoisting frequency of the hoisting unit is consistent with the installation speed of the roof truss. After each roof truss is installed, the total station is used to re-measure the positioning coordinates of the second connecting plate set on the lower chord of the roof truss. After every two roof trusses are installed, 2 to 4 connecting steel beams are installed between the two roof trusses. Then, a large-scale hoisting equipment outside the span is used to hoist the hoisting unit to the corresponding position between the two roof trusses. The first connecting plate and the second connecting plate are connected by the third bolt and the third bolt is initially tightened. The second diagonal brace and the second connecting plate are connected by the seventh bolt and the seventh bolt is initially tightened. At this time, the crane is not unhooked. The total station is used to measure the positioning point coordinates of the first connecting plate and the first connecting member to ensure that the error between the measured coordinates and the theoretical value is less than 15 mm. Then the third bolt and the seventh bolt are finally tightened. The crane is unhooked to complete the installation of the hoisting unit.
[0019] (6) Assembling the scattered units within the span: Use the two hoisting units that have been hoisted as the operating platform to assemble the scattered units located between the two hoisting units. Use the fall chain and winch auxiliary pulley to hoist the walkway longitudinal beams, walkway boards and connecting longitudinal rods of the scattered units to the operating platform, and then install them in order from bottom to top, so as to complete the installation of all scattered units in this step;
[0020] (7) Assembling guardrails: hoist the guardrails onto the walkway board, and then weld the guardrails on the walkway longitudinal beams in turn. After the guardrails are assembled, the construction of the curved multi-layer walkway is completed.
[0021] Compared with the prior art, the present invention has the following beneficial effects:
[0022] 1. The components of the arc-shaped multi-layered horseway of the present invention are mostly connected by bolts, and the arc-shaped multi-layered horseway and the roof truss are connected by bolts, which reduces welding operations and is green and environmentally friendly.
[0023] 2. The present invention divides the entire curved multi-story horseway into hoisting units and loose parts units, and adopts factory-prefabricated semi-finished products, hoisting units assembled outside the span, hoisting units hoisted outside the span, and loose parts units assembled inside the span to complete the construction of the curved multi-story horseway, and uses the hoisting units that have been hoisted as operating platforms, saving construction costs; and in this way, the installation processes of the roof trusses, hoisting units, and loose parts units can be carried out simultaneously, which not only ensures the progress of the project but also makes full use of the limited working surface of the restricted space within the span, reflecting the advanced construction process layout and scientific construction management organization model. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 - Plan projection of the roof trusses and the curved multi-storey walkway.
[0025] Figure 2 -Schematic diagram of the horse track unit structure.
[0026] Figure 3 - Schematic diagram of the division of curved multi-story runway hoisting units and loose parts units.
[0027] Among them: 01-roof truss; 02-arc multi-layer horseway; 1-hanging rod; 2-walkway longitudinal beam; 3-walkway cross beam; 4-walkway board; 5-first connecting piece; 6-guardrail; 7-connecting longitudinal rod; 8-connecting cross rod; 9-first diagonal brace; 10-second diagonal brace; 11-first connecting plate; 12-second connecting piece; 13-third connecting plate; A-horseway unit; a-hoisting unit; b-loose parts unit. DETAILED DESCRIPTION
[0028] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0029] See also Figure 1 and Figure 2 , the installation structure of the roof truss and the curved multi-layered horseway, the curved multi-layered horseway 02 spans across a plurality of roof trusses 01 and is suspended on the lower chord of the roof trusses 01, a horseway unit A is formed between two adjacent roof trusses 01, the plane projection of each horseway unit is a parallelogram, each horseway unit includes four hangers 1, each hanger 1 is vertically arranged and located at the four vertices of the parallelogram, the lower ends of the four hangers 1 are connected by two parallel walkway longitudinal beams 2 arranged along the longitudinal direction of the horseway and two parallel walkway cross beams 3 arranged along the transverse direction of the horseway to form a parallelogram frame, a walkway board 4 is arranged in the parallelogram frame, and the whole horseway is formed by connecting a plurality of horseway units A in series; each hanger 1 The lower end is provided with an annular first connecting member 5, which is sleeved on the hanger and fixed to the hanger 1, and a plurality of first stiffening plates are evenly distributed on the outer circumference of the first connecting member 5, and each first stiffening plate is provided with a plurality of first bolt holes, and a plurality of second bolt holes and third bolt holes corresponding to the first bolt holes are respectively provided at both ends of the walkway longitudinal beam 2 and the walkway cross beam 3, and the first bolt passes through the second bolt hole and the corresponding first bolt hole in sequence to fix the walkway longitudinal beam and the first connecting member 5 to fix the walkway longitudinal beam 2 and the hanger 1; the second bolt passes through the third bolt hole and the corresponding first bolt hole in sequence to fix the walkway cross beam 3 and the first connecting member 5 to fix the walkway cross beam 3 and the hanger 1.
[0030] Here, the entire horseway is formed by connecting several horseway units in series. During the series connection process, two adjacent horseway units share some connecting components, namely, two hangers and aisle beams at the connection between the two horseway units. The two hangers and aisle beams are shared by the two horseway units.
[0031] During specific implementation, a first connecting plate 11 is provided at the upper end of each hanger 1, and a plurality of fourth bolt holes penetrating the two side surfaces of the first connecting plate 11 are provided on the first connecting plate 11; a second connecting plate is provided on the lower chord of the roof truss, and a plurality of fifth bolt holes corresponding to the fourth bolt holes are provided on the second connecting plate; the third bolt passes through the fourth bolt hole and the fifth bolt hole in sequence to connect the first connecting plate and the second connecting plate, thereby fixing the horseway to the lower chord of the roof truss.
[0032] During specific implementation, several layers of connecting rods are provided along the height direction of the hanger 1. The connecting rods are arranged between two adjacent hangers and are evenly distributed up and down to divide the horseway unit into several layers. The connecting rods arranged along the longitudinal direction of the horseway are connecting longitudinal rods 7, and the connecting rods arranged along the transverse direction of the horseway are connecting cross rods 8. The two adjacent connecting cross rods 8 in the upper and lower layers and the corresponding two hangers 1 form a quadrilateral, and the first diagonal bracing rods 9 are distributed along the diagonal lines of the quadrilateral.
[0033] Generally, a venue has multiple curved bridleways on its roof trusses. These curved bridleways may be single-layer structures, or multi-layer structures such as two-layer and three-layer structures, or may include curved bridleways of multiple multi-layer structures, such as Figure 2 The arc-shaped horseway shown is a four-layer structure, and connecting ladders are provided between the arc-shaped horseways to connect all the arc-shaped horseways for the convenience of staff to pass.
[0034] During specific implementation, the connecting rod is fixedly connected to the suspension rod 1 through an annular second connecting member 12, the second connecting member 12 is sleeved on the suspension rod 1 and fixed to the suspension rod, a plurality of second stiffening plates are provided on the outer circumference of the second connecting member, and a plurality of sixth bolt holes are provided on the second stiffening plates, a plurality of seventh bolt holes corresponding to the sixth bolt holes are provided at both ends of the connecting rod, and the fourth bolt passes through the seventh bolt hole and the corresponding sixth bolt hole in sequence to fix the connecting rod and the suspension rod 1.
[0035] In specific implementation, a third connecting plate 13 is provided on both end surfaces of the second connecting member 12, a plurality of eighth bolt holes are provided on the third connecting plate 13, a ninth bolt hole corresponding to the eighth bolt hole is provided on the first diagonal brace rod 9, and the fifth bolt passes through the ninth bolt hole and the eighth bolt hole in sequence to fix the first diagonal brace rod 9 and the third connecting plate 13.
[0036] During specific implementation, a second diagonal brace 10 is provided along the diagonal line of the quadrilateral formed by the top connecting cross bar, the lower chord of the roof truss and the corresponding two hangers. One end of the second diagonal brace 10 is fixedly connected to the third connecting plate 13 by a sixth bolt, and the other end is fixedly connected to the second connecting plate by a seventh bolt.
[0037] During specific implementation, guardrails 6 are respectively fixed on the two walkway longitudinal beams 2 .
[0038] The components of the curved multi-story walkway are mostly connected by bolts, which reduces welding work and is environmentally friendly.
[0039] The construction method of the curved multi-layered bridleway is to construct the curved multi-layered bridleway according to the aforementioned installation structure of the roof truss and the curved multi-layered bridleway, and specifically comprises the following steps:
[0040] (1) Making roof trusses: According to the BIM model of the venue, cut materials to make roof trusses, and at the same time obtain the spatial coordinates of all connection points between the lower chord of the roof truss and the entire curved walkway. When making the roof trusses, make the second connecting plate at the corresponding position of the lower chord of the roof truss according to the spatial coordinates of the connection points;
[0041] Before making the roof trusses, BIM technology will pre-arch the roof trusses based on the problem of downward winding after the roof trusses are installed. In this way, the arch coordinates of the roof trusses can be obtained according to BIM, and then the roof trusses can be built accordingly.
[0042] (2) Make the components of the horse track: see Figure 3 According to the BIM model of the venue, the entire curved bridle 02 is divided into several hoisting units a and loose parts units b according to the spacing between two adjacent roof trusses, and each loose parts unit b is located between two corresponding hoisting units a; at the same time, the components of the bridle are cut and manufactured, and the corresponding first connecting plate is manufactured at the top of each suspender;
[0043] In this way, the walkway unit serves as a lifting unit, and the loose parts unit is equivalent to a connecting unit connecting two lifting units. The loose parts unit only includes a walkway longitudinal beam, a walkway plate and a connecting longitudinal rod, and shares two lifting rods, a walkway crossbeam, a connecting cross rod and the corresponding first diagonal brace rod and second diagonal brace rod with two adjacent lifting units.
[0044] (3) Factory prefabricated semi-finished products: The hangers, walkway beams, connecting crossbars, first diagonal braces and second diagonal braces of all the hoisting units are pre-assembled into semi-finished products in the factory, so that each hoisting unit has two semi-finished products;
[0045] Pre-assembly in the factory workshop can effectively ensure the assembly accuracy and help speed up the progress of on-site construction.
[0046] (4) Assembling the hoisting unit outside the span: Harden the ground outside the span at the construction site, and then assemble the hoisting unit. During assembly, first weld and fix the walkway plate to the two walkway longitudinal beams, and then hoist the two semi-finished products to the two ends of the two walkway longitudinal beams in turn. Use the first bolt to connect the walkway longitudinal beam and the first connecting piece and initially tighten the first bolt. Then assemble the connecting longitudinal rods from bottom to top in turn, and initially tighten the fourth bolt. Then use a total station to measure the coordinates of the positioning points of the first connecting plate and the first connecting piece to ensure that the error between the measured coordinates and the theoretical value is less than 15 mm. Then, finally tighten the first bolt and the fourth bolt. Follow this step to complete the assembly of all hoisting units.
[0047] The on-site cross-over assembly requires the production of an operating platform, which is made of I18 I-beams. The assembly site is paved with stones, and the location where the operating platform is placed is hardened with C25 concrete to increase the base bearing capacity of the operating platform and prevent the operating platform from sinking. At the same time, the upper surface of the operating platform is located on the same horizontal plane. The dimensions of the two semi-finished products of the same hoisting unit prefabricated in the factory are re-measured with a tape measure to eliminate the errors of the parts before assembly.
[0048] (5) Hoisting the hoisting unit outside the span: The hoisting frequency of the hoisting unit is consistent with the installation speed of the roof truss. After each roof truss is installed, the total station is used to re-measure the positioning coordinates of the second connecting plate set on the lower chord of the roof truss. After every two roof trusses are installed, 2 to 4 connecting steel beams are installed between the two roof trusses. Then, a large-scale hoisting equipment outside the span is used to hoist the hoisting unit to the corresponding position between the two roof trusses. The first connecting plate and the second connecting plate are connected by the third bolt and the third bolt is initially tightened. The second diagonal brace and the second connecting plate are connected by the seventh bolt and the seventh bolt is initially tightened. At this time, the crane is not unhooked. The total station is used to measure the positioning point coordinates of the first connecting plate and the first connecting member to ensure that the error between the measured coordinates and the theoretical value is less than 15 mm. Then the third bolt and the seventh bolt are finally tightened. The crane is unhooked to complete the installation of the hoisting unit.
[0049] Connecting steel beams are installed between roof trusses to fix the spacing between roof trusses and prevent lateral instability of roof trusses. The installation position of this connecting steel beam should avoid the hook position within the lifting span of the lower-hanging horseway unit, in order to reduce the interference of the lifting of the lower-hanging horseway unit.
[0050] (6) Assembling the scattered units within the span: Use the two hoisting units that have been hoisted as the operating platform to assemble the scattered units located between the two hoisting units. Use the fall chain and winch auxiliary pulley to hoist the walkway longitudinal beams, walkway boards and connecting longitudinal rods of the scattered units to the operating platform, and then install them in order from bottom to top, so as to complete the installation of all scattered units in this step;
[0051] (7) Assembling guardrails: hoist the guardrails onto the walkway board, and then weld the guardrails on the walkway longitudinal beams in turn. After the guardrails are assembled, the construction of the curved multi-layer walkway is completed.
[0052] This construction method can ensure that the installation processes of the roof trusses, hoisting units and loose parts units are carried out simultaneously, which not only ensures the progress of the project but also makes full use of the limited working surface of the confined space within the span, reflecting the advanced construction process layout and scientific construction management organization model.
[0053] All bolts of the present invention are high-strength bolts. The use of BIM technology is mainly based on the consideration that the horseway is a special-shaped component, there are many irregular components, and there are a large number of scattered parts. BIM technology can solve the problems of cutting special-shaped parts, installation angle of connecting plates, spatial coordinate positioning, arch coordinate control of roof truss production, and drilling accuracy control of hanger connecting plates. At the same time, the BIM collaborative management platform can also be used to identify the QR code information of steel component products, which can realize the rapid search function. At the same time, the platform is used to realize the collaborative management of the construction parties of the project quality, safety and progress, shorten the problem handling time, and improve work efficiency.
[0054] Finally, it should be noted that the above embodiments of the present invention are only examples for illustrating the present invention, and are not intended to limit the implementation methods of the present invention. For those skilled in the art, other different forms of changes and modifications can be made based on the above description. It is impossible to list all implementation methods here. Any obvious changes or modifications derived from the technical solution of the present invention are still within the scope of protection of the present invention.
Claims
1. A method for constructing a curved multi-layered horseway, characterized in that: The invention relates to the installation of a roof truss and a curved multi-layered horsewalk, wherein the horsewalk spans across a plurality of roof trusses and is suspended on the lower chord of the roof trusses, a horsewalk unit is formed between two adjacent roof trusses, the plane projection of each horsewalk unit is a parallelogram, each horsewalk unit comprises four hangers, each hanger is vertically arranged and located at the four vertices of the parallelogram, the lower ends of the four hangers are connected by two parallel walkway longitudinal beams arranged along the longitudinal direction of the horsewalk and two parallel walkway transverse beams arranged along the transverse direction of the horsewalk to form a parallelogram frame, a walkway board is arranged in the parallelogram frame, and the whole horsewalk is formed by connecting a plurality of horsewalk units in series; the lower end of each hanger has An annular first connecting member, the first connecting member is sleeved on the suspension rod and fixed to the suspension rod, a plurality of first stiffening plates are evenly distributed on the outer circumference of the first connecting member, each of the first stiffening plates is provided with a plurality of first bolt holes, and a plurality of second bolt holes and third bolt holes corresponding to the first bolt holes are respectively provided at both ends of the walkway longitudinal beam and the walkway cross beam, the first bolt passes through the second bolt hole and the corresponding first bolt hole in sequence to fix the walkway longitudinal beam and the first connecting member, thereby fixing the walkway longitudinal beam and the suspension rod; the second bolt passes through the third bolt hole and the corresponding first bolt hole in sequence to fix the walkway cross beam and the first connecting member, thereby fixing the walkway cross beam and the suspension rod; A first connecting plate is provided at the upper end of each suspension rod, and a plurality of fourth bolt holes are provided on the first connecting plate and penetrate the two sides of the first connecting plate; a second connecting plate is provided on the lower chord of the roof truss, and a plurality of fifth bolt holes corresponding to the fourth bolt holes are provided on the second connecting plate; a third bolt passes through the fourth bolt hole and the fifth bolt hole in sequence to connect the first connecting plate and the second connecting plate, thereby fixing the bridleway to the lower chord of the roof truss; Several layers of connecting rods are arranged along the height direction of the suspension rods. The connecting rods are arranged between two adjacent suspension rods and are evenly distributed up and down to divide the horseway unit into several layers. The connecting rods arranged along the longitudinal direction of the horseway are connecting longitudinal rods, and the connecting rods arranged along the transverse direction of the horseway are connecting cross rods. The two adjacent connecting cross rods in the upper and lower layers and the corresponding two suspension rods form a quadrilateral, and the first diagonal bracing rods are distributed along the diagonal lines of the quadrilateral. The connecting rod is fixedly connected to the suspension rod through an annular second connecting piece, the second connecting piece is sleeved on the suspension rod and fixed to the suspension rod, a plurality of second stiffening plates are provided on the outer circumference of the second connecting piece, and a plurality of sixth bolt holes are provided on the second stiffening plates, a plurality of seventh bolt holes corresponding to the sixth bolt holes are provided at both ends of the connecting rod, and the fourth bolts pass through the seventh bolt holes and the corresponding sixth bolt holes in sequence to fix the connecting rod and the suspension rod; A third connecting plate is provided on both end surfaces of the second connecting member, a plurality of eighth bolt holes are provided on the third connecting plate, a ninth bolt hole corresponding to the eighth bolt hole is provided on the first diagonal brace, and the fifth bolt passes through the ninth bolt hole and the eighth bolt hole in sequence to fix the first diagonal brace and the third connecting plate; A second diagonal brace is provided along the diagonal line of the quadrilateral formed by the topmost connecting crossbar, the lower chord of the roof truss and the corresponding two hangers. One end of the second diagonal brace is fixedly connected to the third connecting plate by the sixth bolt, and the other end is fixedly connected to the second connecting plate by the seventh bolt. Guardrails are respectively fixed to the two walkway longitudinal beams. The specific steps include: (1) Making roof trusses: According to the BIM model of the venue, cut materials to make roof trusses, and at the same time obtain the spatial coordinates of all connection points between the lower chord of the roof truss and the entire curved walkway. When making the roof trusses, make the second connecting plate at the corresponding position of the lower chord of the roof truss according to the spatial coordinates of the connection points; (2) Fabrication of the components of the bridleway: Based on the BIM model of the venue, the entire curved bridleway is divided into a number of hoisting units and loose component units according to the spacing between two adjacent roof trusses. Each loose component unit is located between two corresponding hoisting units. At the same time, the components of the bridleway are cut and fabricated, and the corresponding first connecting plate is fabricated at the top of each suspender. (3) Factory prefabricated semi-finished products: The hangers, walkway beams, connecting crossbars, first diagonal braces and second diagonal braces of all the hoisting units are pre-assembled into semi-finished products in the factory, so that each hoisting unit has two semi-finished products; (4) Assembling the hoisting unit outside the span: Harden the ground outside the span at the construction site, and then assemble the hoisting unit. During assembly, first weld and fix the walkway plate to the two walkway longitudinal beams, and then hoist the two semi-finished products to the two ends of the two walkway longitudinal beams in turn. Use the first bolt to connect the walkway longitudinal beam and the first connecting piece and initially tighten the first bolt. Then assemble the connecting longitudinal rods from bottom to top in turn, and initially tighten the fourth bolt. Then use a total station to measure the coordinates of the positioning points of the first connecting plate and the first connecting piece to ensure that the error between the measured coordinates and the theoretical value is less than 15 mm. Then, finally tighten the first bolt and the fourth bolt. Follow this step to complete the assembly of all hoisting units. (5) Hoisting the hoisting unit outside the span: The hoisting frequency of the hoisting unit is consistent with the installation speed of the roof truss. After each roof truss is installed, the total station is used to re-measure the positioning coordinates of the second connecting plate set on the lower chord of the roof truss. After every two roof trusses are installed, 2 to 4 connecting steel beams are installed between the two roof trusses. Then, a large-scale hoisting equipment outside the span is used to hoist the hoisting unit to the corresponding position between the two roof trusses. The first connecting plate and the second connecting plate are connected by the third bolt and the third bolt is initially tightened. The second diagonal brace and the second connecting plate are connected by the seventh bolt and the seventh bolt is initially tightened. At this time, the crane is not unhooked. The total station is used to measure the positioning point coordinates of the first connecting plate and the first connecting member to ensure that the error between the measured coordinates and the theoretical value is less than 15 mm. Then the third bolt and the seventh bolt are finally tightened. The crane is unhooked to complete the installation of the hoisting unit. (6) Assembling the scattered units within the span: Use the two hoisting units that have been hoisted as the operating platform to assemble the scattered units located between the two hoisting units. Use the fall chain and winch auxiliary pulley to hoist the walkway longitudinal beams, walkway boards and connecting longitudinal rods of the scattered units to the operating platform, and then install them in order from bottom to top, so as to complete the installation of all scattered units in this step; (7) Assembling guardrails: hoist the guardrails onto the walkway board, and then weld the guardrails on the walkway longitudinal beams in turn. After the guardrails are assembled, the construction of the curved multi-layer walkway is completed.