A composite foundation for controlling post-construction settlement of highways in soft soil areas
By adopting step by step changing reinforced soil pile spacing and pile length design in soft soil area highway construction, the problems of inconsistency in settlement transition and high engineering costs are solved, and the smooth transition between bridges and general roadbed sections are achieved and driving safety improvements are improved. .
Patent Information
- Application Number
- CN202010920982.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-09-04
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2040-09-04
AI Technical Summary
In the soft soil area, the settlement transition is inconsistent, the vehicle feels strong when driving, and the engineering cost is high, and it fails to effectively connect the bridge and general roadbed sections.
Multiple rows of reinforced soil piles are used, and the pile spacing and pile length are gradually changed in three sections. The spacing between the first and third sections is gradually changed from S1 to S3, and the pile length is gradually changed from L1 to L3, meeting different load conditions and achieving settlement gradual Level control.
It has achieved a smooth transition between the bridge and the general roadbed section, reduced vehicle axes, improved driving safety, and reduced engineering costs through variable parameter design.
Smart Images

Figure CN111926643B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a composite foundation, in particular to a composite foundation for controlling post-construction settlement of a highway in a soft soil area. Background Art
[0002] Usually, the post-construction settlement control value of highway bridges is 0.5cm-1cm. According to the design specifications, the post-construction settlement value of the general highway subgrade section is 30cm. Therefore, it is necessary to set a road-bridge transition section between the bridge and the general subgrade to complete the settlement transition and make driving more stable and safe.
[0003] The existing settlement control technology in soft soil areas usually sets up a 20m-30m long road-bridge transition section. The foundation of the road-bridge transition section usually adopts composite foundation treatment such as cement mixing piles, cement mortar piles, high-pressure rotary jet piles, or prestressed pipe piles. The pile diameter, pile spacing and pile length are determined by calculation, and the post-construction settlement of the road-bridge transition section is controlled within 10cm according to the specifications. Usually, the pile diameter and pile plane layout form in a section of roadbed are fixed. The pile diameters of cement mixing piles, cement mortar piles, and high-pressure rotary jet piles are mostly 0.5m or 0.6m, and the pile diameters of prestressed pipe piles are mostly 0.3m, 0.4m or 0.5m, and the pile plane layout is mostly a regular quadrilateral or regular triangle.
[0004] When this technology is applied, the maximum settlement difference from the bridge to the road-bridge transition section is 10cm, which is relatively small and can basically meet the needs of the project. However, when the vehicle travels from the road-bridge transition section to the general roadbed section, the maximum settlement difference can reach more than 20cm, causing the road to be misaligned in the longitudinal section, and the settlement control is discontinuous. The settlement transition problem has not been completely solved, the vehicle has a strong sense of frustration when driving, there are safety hazards when driving at high speeds, and the bridge and the general roadbed section are not connected well.
[0005] In the cross-section direction of the roadbed, a single pile spacing and a single pile length were used for composite foundation treatment from slope to slope, and the design parameters were not adjusted according to the load size, resulting in a significant increase in project costs. Summary of the invention
[0006] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a composite foundation for controlling post-construction settlement of a highway in a soft soil area with a smoother transition and safer driving.
[0007] A composite foundation for controlling post-construction settlement of a highway in a soft soil area of the present invention comprises a plurality of rows of reinforced soil piles driven into the foundation of a road-bridge transition section, each row of reinforced soil piles comprises a plurality of reinforced soil piles arranged in parallel and spaced relation, and the central axes of the same row of reinforced soil piles are in the same vertical plane, and the central axes of the two adjacent rows of reinforced soil piles are arranged in parallel and spaced relation, and the plurality of rows of reinforced soil piles are divided into three sections along the longitudinal direction of the road-bridge transition section from the abutment to the roadbed, wherein the pile spacing between the two adjacent rows of reinforced soil piles in the first section is S1, and the front and rear spacing between the two adjacent rows of reinforced soil piles in each row of reinforced soil piles is S2. The spacing is S1; the spacing between the two adjacent rows of reinforced soil piles in the second section of reinforced soil piles gradually changes from S1 to S2 along the longitudinal direction, the front-to-back spacing between the two adjacent reinforced soil piles in the leftmost row of reinforced soil piles in the second section of reinforced soil piles is S1, and the front-to-back spacing between the two adjacent reinforced soil piles in the rightmost row of reinforced soil piles in the second section of reinforced soil piles is S2; the spacing between the two adjacent rows of reinforced soil piles in the third section of reinforced soil piles gradually changes from S2 to S3 along the longitudinal direction, the front-to-back spacing between the two adjacent reinforced soil piles in the rightmost row of reinforced soil piles in the third section of reinforced soil piles is S3, where S1 <S2<S3;
[0008] The pile lengths of the three sections of reinforced soil piles located in the roadbed width area within the transverse span of the roadbed are as follows: the pile length of each reinforced soil pile in the first section is L1, the pile length of each reinforced soil pile in the second section gradually changes from L1 to L2 along the longitudinal direction and the reinforced soil piles in the same row have the same length, the pile length of each reinforced soil pile in the third section gradually changes from L2 to L3 along the longitudinal direction and the reinforced soil piles in the same row have the same length, wherein L1>L2>L3; the pile length of the reinforced soil piles from the inside to the outside in each row of reinforced soil piles from the outer edge of the roadbed width area to the slope foot gradually shortens to the set length, wherein the pile length of each reinforced soil pile located at the outer edge of the roadbed width is consistent, and the pile length of each reinforced soil pile located near the slope angle is consistent.
[0009] The beneficial effects of the present invention are:
[0010] 1. In the existing structure, the post-construction settlement of the road-bridge transition section is 10cm, and the post-construction settlement of the general roadbed section is 30cm. The maximum settlement difference between the road-bridge transition section and the general roadbed section can reach more than 20cm, and the transition effect is not ideal. The present invention divides the road-bridge transition section into two levels, and the settlement is controlled step by step, so that the transition between the bridge and the general roadbed is smoother and driving is safer.
[0011] 2. The foundation settlement of the existing road-bridge transition section is mostly a step-shaped transition. This structure adopts a variable parameter design to make the settlement transition smoother and the driving comfort better.
[0012] 3. The foundation structure of the existing road-bridge transition only considers the most unfavorable situation, with a conservative design and single parameters; the local foundation treatment structure adopts a variable pile spacing structure in the plane and a variable pile length structure in the longitudinal and cross-sectional directions, and the design is more in line with the actual project.
[0013] 4. The horizontal, vertical and horizontal roadbed adopts variable parameter structure, so that the number and length of piles can be adjusted according to the needs of the project, making the project more economical and reasonable. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a plan layout of a composite foundation for controlling post-construction settlement of a highway in a soft soil area according to the present invention;
[0015] Figure 2 yes Figure 1 AA section layout of the composite foundation shown;
[0016] Figure 3 yes Figure 1 BB section layout of the composite foundation shown. DETAILED DESCRIPTION
[0017] The present invention is described in detail below in conjunction with the accompanying drawings and embodiments:
[0018] The principle of the present invention is as follows: according to different post-construction settlement control standards, the roadbed type is divided into a general roadbed section and a road-bridge transition section. The post-construction settlement of the general roadbed section should not be greater than 30cm; the road-bridge transition section adopts a two-level transition section, the post-construction settlement of the first-level transition section is not greater than 10cm, and the post-construction settlement of the second-level transition section is 10cm-30cm.
[0019] A calculation model is established based on the fill load of the first-level transition section, vehicle load, design reference period (pavement design reference period), stratum mechanics parameters, etc. By adjusting parameters such as pile diameter, pile plane layout, pile spacing, and pile length, the composite foundation can meet the requirements of foundation bearing capacity, settlement, and stability.
[0020] As shown in the attached drawings, a composite foundation for controlling post-construction settlement of a highway in a soft soil area of the present invention comprises a plurality of rows of reinforced soil piles 1 driven into the foundation of a road-bridge transition section, each row of reinforced soil piles comprises a plurality of reinforced soil piles arranged in parallel and spaced relation, and the central axes of the same row of reinforced soil piles are in the same vertical plane, and the central axes of the two adjacent rows of reinforced soil piles are arranged in parallel and spaced relation, and the plurality of rows of reinforced soil piles are divided into three sections along the longitudinal direction of the road-bridge transition section from the abutment to the roadbed, wherein the pile spacing between the two adjacent rows of reinforced soil piles in the first section is S1, and the spacing between the two adjacent rows of reinforced soil piles in each row of reinforced soil piles is S2. The front-to-back spacing is S1; the pile spacing between the two adjacent rows of reinforced soil piles in the second section of reinforced soil piles gradually changes from S1 to S2 along the longitudinal direction, the front-to-back spacing between the two adjacent reinforced soil piles in the leftmost row of reinforced soil piles in the second section of reinforced soil piles is S1, and the front-to-back spacing between the two adjacent reinforced soil piles in the rightmost row of reinforced soil piles in the second section of reinforced soil piles is S2; the pile spacing between the two adjacent rows of reinforced soil piles in the third section of reinforced soil piles gradually changes from S2 to S3 along the longitudinal direction, the front-to-back spacing between the two adjacent reinforced soil piles in the rightmost row of reinforced soil piles in the third section of reinforced soil piles is S3, where S1 <S2<S3。
[0021] The lengths of the three sections of reinforced soil piles located in the roadbed width area within the transverse span of the roadbed are as follows: the length of each reinforced soil pile in the first section is L1, the length of each reinforced soil pile in the second section gradually changes from L1 to L2 along the longitudinal direction and the lengths of the reinforced soil piles in the same row are the same, the length of each reinforced soil pile in the third section gradually changes from L2 to L3 along the longitudinal direction and the lengths of the reinforced soil piles in the same row are the same, wherein L1>L2>L3; the length of the reinforced soil piles from the inside to the outside of each row of reinforced soil piles from the outer edge of the roadbed width area to the slope foot is gradually shortened to a set length, such as being shortened to 5m, wherein the length of each reinforced soil pile located at the outer edge of the roadbed width is consistent, and the length of each reinforced soil pile located near the slope angle is consistent.
[0022] Each of the reinforced soil piles can be a cement mixing pile, a cement mortar pile, a high-pressure jet spray pile or a prestressed pipe pile.
[0023] In this structure, the pile spacing and pile length are adjusted to meet the requirements of 10cm post-construction settlement, foundation bearing capacity and foundation stability, and the values of pile spacing S1 and pile length L1 are obtained.
[0024] In this structure, the secondary transition section refers to the design principle of the primary transition section, and the pile spacing S1, S2, S3 of the reinforced soil piles and the pile lengths L1, L2, L3 of the reinforced soil piles are calculated at the post-construction settlement of 10cm, 20cm, and 30cm respectively. Within the 10m range before the secondary transition section, the pile spacing of the reinforced soil piles on the plane gradually changes from S1 to S2, and the pile length of the reinforced soil piles on the longitudinal section gradually changes from L1 to L2; within the 10m range after the secondary transition section, the pile spacing S2 of the reinforced soil piles on the plane gradually changes to S3, and the pile length L2 of the reinforced soil piles on the longitudinal section gradually changes to L3.
[0025] In this structure, variable pile length design is adopted from the roadbed to the slope foot. The pile length of the roadbed width range is L1-L3, and from the roadbed to the slope foot, the pile length gradually changes from L1-L3 to 5m.
[0026] To facilitate design and construction in this structure, the spacing of the reinforced soil piles changes from S1 to S2 and from S2 to S3 in steps of an integer multiple of 0.1 m, and the length of the reinforced soil piles changes from L1 to L2 and from L2 to L3 in steps of an integer multiple of 0.5 m to 1.0 m.
[0027] The length of the reinforcement piles from the inside to the outside of each row of reinforcement piles from the outer edge of the roadbed width area to the slope foot is gradually shortened to a set length, and the gradual step length is an integer multiple of 0.5m-1.0m.
[0028] Figure 2 The H in represents the roadbed fill height.
Claims
1. A composite foundation for controlling post-construction settlement of a highway in a soft soil area, comprising a plurality of rows of reinforced soil piles driven into the foundation of a road-bridge transition section, wherein each row of reinforced soil piles comprises a plurality of reinforced soil piles arranged in parallel and spaced relation, and the central axes of the same row of reinforced soil piles are in the same vertical plane, and the central axes of two adjacent rows of reinforced soil piles are arranged in parallel and spaced relation on the left and right sides of the vertical plane, characterized in that: The multiple rows of reinforced soil piles are divided into three sections along the longitudinal direction of the road-bridge transition section from the abutment to the roadbed, wherein the pile spacing between two adjacent rows of reinforced soil piles on the left and right in the first section is S1, and the front-to-back spacing between two adjacent reinforced soil piles in each row is S1; the pile spacing between two adjacent rows of reinforced soil piles on the left and right in the second section gradually changes from S1 to S2 along the longitudinal direction, the front-to-back spacing between two adjacent reinforced soil piles in the leftmost row of reinforced soil piles in the second section is S1, and the front-to-back spacing between two adjacent reinforced soil piles in the rightmost row of reinforced soil piles in the second section is S2; the pile spacing between two adjacent rows of reinforced soil piles on the left and right in the third section gradually changes from S2 to S3 along the longitudinal direction, the front-to-back spacing between two adjacent reinforced soil piles in the rightmost row of reinforced soil piles in the third section is S3, wherein S1 <S2<S3; The pile lengths of the three sections of reinforced soil piles located in the roadbed width area within the transverse span of the roadbed are as follows: the pile length of each reinforced soil pile in the first section is L1, the pile length of each reinforced soil pile in the second section gradually changes from L1 to L2 along the longitudinal direction and the reinforced soil piles in the same row have the same length, the pile length of each reinforced soil pile in the third section gradually changes from L2 to L3 along the longitudinal direction and the reinforced soil piles in the same row have the same length, wherein L1>L2>L3; the pile length of the reinforced soil piles from the inside to the outside in each row of reinforced soil piles from the outer edge of the roadbed width area to the slope foot gradually shortens to the set length, wherein the pile length of each reinforced soil pile located at the outer edge of the roadbed width is consistent, and the pile length of each reinforced soil pile located near the slope angle is consistent.
2. The composite foundation for controlling post-construction settlement of highway in soft soil areas according to claim 1 is characterized by: The gradual change step length of the spacing of the reinforced soil piles from S1 to S2 and from S2 to S3 is an integer multiple of 0.1m, and the gradual change step length of the pile length of the reinforced soil piles from L1 to L2 and from L2 to L3 is an integer multiple of 0.5m-1.0m.
3. The composite foundation for controlling post-construction settlement of highway in soft soil areas according to claim 1, characterized in that: The length of the reinforcement piles from the inside to the outside of each row of reinforcement piles from the outer edge of the roadbed width area to the slope foot is gradually shortened to a set length, and the gradual step length is an integer multiple of 0.5m-1.0m.