Steel beam beam-carrying crane suspension assembly equipment and construction method
By designing a beam-load crane suspension equipment for hanging and moving steel beams, the problems of high installation cost and poor applicability of steel beams in crossing rivers and other areas are solved, and low-cost and rapid steel beam installation is achieved, reducing the number of steel beams Construction costs and improve construction efficiency.
Patent Information
- Application Number
- CN202011462937.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-12-14
- Publication Date
- 2025-02-07
- Estimated Expiration
- 2040-12-14
AI Technical Summary
The existing steel beam installation method is relatively costly and has poor applicability in areas such as crossing rivers and other areas that do not meet the lifting conditions. Although the suspension assembly method has high economic benefits, it is limited by the site and beam height, and there are many restrictions.
A steel beam and beam load crane suspension equipment was designed, including main beam, walking system, support system and lifting system, using components such as car crane, Beret beam, distribution beam, hydraulic jack, tooth plate, slide beam, etc. , through the cooperation of hydraulic jack and tooth plate, the suspension and movement of steel beams are achieved.
实现了在地面空间不足的情况下低成本、快速安装钢梁,降低了临时设施工程量,减少了施工成本,提高了施工效率和适用性。
Smart Images

Figure CN112376437B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to steel beam crane suspension assembly equipment and a construction method, belonging to the technical field of bridge construction. Background Art
[0002] China is still in the period of vigorously developing transportation infrastructure. There are three main ways to install steel beams: top-pushing, cantilever assembly, and bracket installation. At present, large-scale lifting equipment is still used in foreign countries to install steel beams. The main beam is hoisted to the designed position as a whole by a large-tonnage crane, and then the auxiliary structure is installed. This construction process has the advantages of rapid construction and high overall controllability. At the same time, it is limited by the site and beam height. Large floating cranes are still required in river-crossing areas, and the applicability is poor. In China, if the site meets the requirements and the existing lifting equipment meets the lifting conditions, cantilever assembly is used. In cases where there is no lifting equipment such as crossing the river, top-pushing is mainly used. The temporary facility project is large, so the cost is high.
[0003] In summary, the economic benefits of suspended assembly are higher, but there are more restrictions. Summary of the invention
[0004] In order to solve the problems raised in the above background technology, the present invention provides a steel beam beam-carrying crane suspension assembly device and a construction method.
[0005] In order to achieve the above object, the present invention is implemented through the following technical solutions:
[0006] A steel beam beam-carrying crane suspension assembly device, comprising a main beam, a traveling system, a supporting system and a lifting system;
[0007] The lifting system is a truck crane with outriggers at the bottom;
[0008] The support system includes a Bailey beam and a distribution beam, and the distribution beam is placed on the upper part of the Bailey beam;
[0009] The walking system includes a hydraulic jack, a tooth plate, a tooth block, a slide beam and a slide plate. One end of the hydraulic jack is connected to the tooth block, and the other end of the hydraulic jack is connected to the slide beam. The slide beam is arranged under the Bailey beam. The slide plate is detachably connected under the slide beam. The slide plate is in contact with the tooth plate below. The tooth plate is arranged on the main beam and a plurality of tooth grooves are arranged at intervals on the surface. The tooth block can be inserted into the tooth groove.
[0010] The preferred solution for the steel beam crane suspension assembly equipment is that an ear plate connected to the jack is arranged at the front end of the slideway beam, stiffening plates are arranged on both sides of the slideway beam in the width direction, and a plurality of limit blocks are arranged at equal intervals along the length direction of the slideway beam.
[0011] The preferred solution for the steel beam-carrying crane suspension assembly equipment also includes a car crane leg pad beam arranged between the car crane leg and the Bailey beam, the car crane leg pad beam is formed by splicing I-beams, the I-beams are welded with connecting steel plates on the upper and lower parts, and the I-beams are welded with reinforcing plates.
[0012] In the preferred embodiment of the steel beam crane suspension assembly equipment, a Bailey beam is provided with a plurality of Bailey beam limiters, and the Bailey beam limiters are two symmetrically arranged limit plates with triangular cross-sections, and the limit plates are connected in series as a whole.
[0013] A method for steel beam suspension assembly construction using a steel beam crane suspension assembly device comprises the following steps:
[0014] S1. Calculate the weight of the rod according to the cantilever construction, and select the appropriate truck crane according to the weight of the rod;
[0015] S2. Design the mobile platform of the beam crane according to the model of the truck crane and the weight of the rod;
[0016] S3. Assemble the upper steel beams of the temporary piers of the bridge, and use a crane to assemble the steel beams on the upper part of the temporary piers on the ground, which serves as a construction platform for the beam-carrying crane;
[0017] S4. Install the tooth plate, slideway beam with slide plate, hydraulic jack, tooth block, Bailey beam, distribution beam on the assembled main beam in sequence. After the installation of the outrigger pad beam of the truck crane is completed, install the truck crane in place;
[0018] S5. After the outriggers are completed, the crane hoists the rods to be assembled from bottom to top to assemble the steel beam of the next segment, release the platform limit, start the hydraulic jack, push it out to the next tooth groove of the tooth plate, buckle the tooth block into the tooth groove, and push it back with the hydraulic jack. The platform moves forward to the assembled steel beam of the previous segment, and then the crane rotates 180° to install the bridge deck of the next segment;
[0019] S6. After the bridge deck is installed, the crane rotates 180° and repeats step S5 until the steel beam is assembled;
[0020] S7. After the cantilever assembly construction is completed, the truck crane, truck crane leg pad beam, distribution beam, Bailey beam and slideway beam shall be dismantled in sequence.
[0021] The advantages of the present invention are:
[0022] 1. The present invention has low manufacturing cost, convenient and quick installation and disassembly, novel and reasonable design, and is easy to promote and use.
[0023] 2. The invention effectively solves the problem of insufficient ground space during construction, reduces the impact on the surrounding environment, and is environmentally friendly.
[0024] 3. During the use of the present invention, one machine can be used for multiple purposes, with high conversion efficiency and fast construction speed, which can shorten the construction period. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.
[0026] Figure 1 It is an overall front view of the present invention.
[0027] Figure 2 It is an overall side view of the present invention.
[0028] Figure 3 It is a schematic diagram of the jack and the gear plate of the present invention.
[0029] Figure 4 It is a schematic diagram of the Bailey beam limit of the present invention.
[0030] Figure 5 The present invention is a slideway beam.
[0031] Figure 6 It is a schematic diagram of the connection of the slideway beam of the present invention.
[0032] Figure 7 This is a structural diagram of the car crane leg pad beam of the present invention.
[0033] 1-main beam; 2-tooth plate; 3-hydraulic jack; 3-1-pin shaft; 3-2-ear plate; 3-3-tooth block; 4-slide plate; 5-slideway beam; 5-1-limit block; 5-2-stiffening plate; 5-3-high-strength bolt; 6-Bailey beam limit; 6-1-limit plate; 7-Bailey beam; 8-distribution beam; 9-truck crane leg pad beam; 9-1-steel plate; 9-2-I-beam; 9-3-connecting plate; 10-truck crane. DETAILED DESCRIPTION
[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0035] In the description of the present invention, it should be noted that the terms "vertical", "up", "down", "horizontal", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0036] refer to Figure 1 and Figure 2A steel beam crane suspension assembly device comprises a main beam 1, a walking system, a supporting system and a lifting system; the lifting system is a car crane 10, and a support leg is provided at the bottom; the supporting system comprises a Bailey beam 7 and a distribution beam 8, and the distribution beam 8 is placed on the upper part of the Bailey beam 7; the walking system comprises a hydraulic jack 3, a tooth plate 2, a tooth block 3-3, a slideway beam 5 and a slide plate 4, one end of the hydraulic jack 3 is connected to the tooth block 3-3 through a pin shaft 3-1, and the other end of the hydraulic jack 3 is connected to the slideway beam 5 through a pin shaft 3-1, the slideway beam 5 is arranged below the Bailey beam 7, and the slide plate 4 is detachably connected to the slide plate 4 through a high-strength bolt 5-3 below the slide beam 5, and the slide plate 4 is in contact with the tooth plate 2 below, the tooth plate 2 is arranged on the main beam 1 and a plurality of tooth grooves are arranged on the surface at intervals, and the tooth block 3-3 can be inserted into the tooth groove.
[0037] refer to Figure 3 , the front end of the slideway beam 5 is provided with an ear plate 3-2 connected to the jack 3, refer to Figure 5 and Figure 6 Stiffening plates 5 - 2 are provided on both sides of the slideway beam 5 in the width direction, and a plurality of limit blocks 5 - 1 are arranged at equal intervals along the length direction of the slideway beam 5 .
[0038] refer to Figure 7 It also includes a car crane leg pad beam 9 set between the car crane 10 legs and the Bailey beam 7. The car crane leg pad beam 9 is spliced by I-beams 9-2. The I-beams 9-2 are welded with connecting steel plates 9-1 on the upper and lower parts, and the I-beams 9-2 are welded with reinforcing plates 9-3.
[0039] refer to Figure 4 The Bailey beam 7 is provided with a plurality of Bailey beam limiters 6, and the Bailey beam limiters 6 are two symmetrically arranged limit plates 6-1 with triangular cross sections, and the limit plates 6-1 are connected in series as a whole.
[0040] A method for steel beam suspension assembly construction using a steel beam crane suspension assembly device comprises the following steps:
[0041] S1. Calculate the weight of the rod according to the cantilever construction, and select the appropriate truck crane 10 by the weight of the rod;
[0042] S2. Design the mobile platform of the beam crane according to the model of the truck crane 10 and the weight of the rod;
[0043] S3. Assemble the upper steel beams of the temporary piers of the bridge, and use a crane to assemble the steel beams on the upper part of the temporary piers on the ground, which serves as a construction platform for the beam-carrying crane;
[0044] S4. Install the tooth plate 2, the slide beam 5 with the slide plate 4, the hydraulic jack 3, the tooth block 2, the Bailey beam 7, the distribution beam 8, and the car crane leg pad beam 9 on the assembled main beam 1, and then install the car crane 10 in place;
[0045] S5. After the outriggers of the truck crane 10 are completed, the rods to be assembled are lifted from bottom to top to assemble the steel beam of the next segment in sequence, the platform limit is released, the hydraulic jack 3 is started, and the platform is pushed out to the next tooth groove of the tooth plate 2, the tooth block 3-3 is buckled into the tooth groove, the hydraulic jack 3 is pushed back, and the platform moves forward to the assembled steel beam of the previous segment. After that, the truck crane 10 rotates 180 degrees and installs the bridge deck of the next segment;
[0046] S6. After the bridge deck is installed, the truck crane 10 rotates 180° and repeats step S5 until the assembly of the steel beam is completed;
[0047] S7. After the cantilever assembly construction is completed, the truck crane 10, the truck crane leg pad beam 9, the distribution beam 8, the Bailey beam 7 and the slideway beam 5 are dismantled in sequence.
[0048] It can be seen from the embodiments that in this embodiment, the equipment can be flexibly selected according to the weight of the steel beam, the components can be flexibly assembled, and the installation of the bridge deck can be taken into consideration.
[0049] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A steel beam crane suspension assembly device, characterized in that: It includes a main beam (1), a walking system, a supporting system and a lifting system; The lifting system is a truck crane (10) with outriggers at the bottom; The support system comprises a Bailey beam (7) and a distribution beam (8), wherein the distribution beam (8) is placed on the upper part of the Bailey beam (7); The walking system comprises a hydraulic jack (3), a tooth plate (2), a tooth block (3-3), a slideway beam (5) and a slide plate (4); one end of the hydraulic jack (3) is connected to the tooth block (3-3); the other end of the hydraulic jack (3) is connected to the slideway beam (5); the slideway beam (5) is arranged below the Bailey beam (7); the slide plate (4) is detachably connected below the slideway beam (5); the slide plate (4) is in contact with the tooth plate (2); the tooth plate (2) is arranged on the main beam (1) and has a plurality of tooth grooves arranged at intervals on the surface; the tooth block (3-3) can be buckled into the tooth grooves.
2. The steel beam crane suspension assembly equipment according to claim 1 is characterized in that: An ear plate (3-2) connected to the jack (3) is arranged at the front end of the slideway beam (5), stiffening plates (5-2) are arranged on both sides of the slideway beam (5) in the width direction, and a plurality of limit blocks (5-1) are arranged at equal intervals along the length direction of the slideway beam (5).
3. The steel beam crane suspension assembly equipment according to claim 1 is characterized in that: The invention comprises a car crane leg pad beam (9) arranged between the car crane (10) leg and the Bailey beam (7), the car crane leg pad beam (9) being formed by splicing I-beams (9-2), the I-beams (9-2) having welded connection steel plates (9-1) on the upper and lower parts, and the I-beams (9-2) being welded with reinforcement plates (9-3).
4. The steel beam crane suspension assembly equipment according to claim 1, characterized in that: The Bailey beam (7) is provided with a plurality of Bailey beam limiters (6), wherein the Bailey beam limiters (6) are two symmetrically arranged limiter plates (6-1) with triangular cross-sections, and the limiter plates (6-1) are connected in series as one body.
5. A method for steel beam suspension assembly construction using the steel beam crane suspension assembly equipment according to any one of claims 1 to 4, characterized in that: The steps include: S1. Calculate the weight of the rod according to the cantilever construction, and select an appropriate truck crane according to the weight of the rod (10); S2. Design the mobile platform of the crane on the beam according to the model and weight of the truck crane (10); S3. Assemble the upper steel beams of the temporary piers of the bridge, and use a crane to assemble the steel beams on the upper part of the temporary piers on the ground, which serves as a construction platform for the beam-carrying crane; S4. Install the tooth plate (2), the slideway beam (5) with the slide plate (4), the hydraulic jack (3), the tooth block (3-3), the Bailey beam (7), the distribution beam (8) on the assembled main beam (1), and after the installation of the car crane leg pad beam (9), install the car crane (10) in place; S5. After the outriggers of the truck crane (10) are completed, the rods to be assembled are lifted from bottom to top to assemble the steel beam of the next segment in sequence, the platform limit is released, the hydraulic jack (3) is started, and the platform is pushed out to the next tooth groove of the tooth plate (2), the tooth block (3-3) is buckled into the tooth groove, the hydraulic jack (3) is returned to the top, and the platform moves forward to the assembled steel beam of the previous segment. After that, the truck crane (10) rotates 180° to install the bridge deck of the next segment; S6. After the bridge deck is installed, the truck crane (10) rotates 180° and repeats step S5 until the assembly of the steel beam is completed; S7. After the cantilever assembly construction is completed, the truck crane (10), the truck crane leg pad beam (9), the distribution beam (8), the Bailey beam (7) and the slideway beam (5) are dismantled in sequence.
Citation Information
Patent Citations
Steel beam load crane suspended splicing equipment
CN214143330U