Organic solvent recovery system
By combining the circulation path, adsorption and desorption treatment and condensation recovery device in the organic solvent recovery system, and using the heating part and the cooling and melting part to process the frozen components, the problems of low condensation recovery efficiency and system complexity are solved, and efficient organic solvents are realized. Solvent recovery and system simplification.
Patent Information
- Application Number
- CN201980058727.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2018-09-11
- Filing Date
- 2019-09-06
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2039-09-06
AI Technical Summary
In the existing organic solvent recovery system, it is difficult to completely separate the organic solvent in the condensation recovery device, resulting in insufficient regeneration of the adsorbent material during the carrier gas cycle, limited purification capacity and recovery efficiency, and a complicated and large-scale system structure.
Adopt an adsorption and desorption treatment device and a condensation recovery device in the circulation path, combine the heating part and the cooling and melting part, and melt the frozen components by cooling them, reducing the condensation recovery efficiency, reducing the concentration of organic solvents in the carrier gas, and avoiding the second adsorption and desorption treatment device , simplifying the system structure.
It improves the condensation recovery efficiency of organic solvents, reduces the concentration of organic solvents in the carrier gas, improves the desorption efficiency of adsorption treatment, reduces operating costs, and achieves simplification and miniaturization of the system.
Smart Images

Figure HDA0002967121520000011 
Figure HDA0002967121520000012
Abstract
Description
Technical Field
[0001] The invention relates to an organic solvent recovery system, which separates the organic solvent from a treated gas containing the organic solvent and recovers the separated organic solvent by using a carrier gas. Background Art
[0002] In the past, there is known a gas treatment system containing an organic solvent, which uses an adsorbent material to adsorb and desorb the organic solvent from the treated gas containing the organic solvent, so that the organic solvent is moved from the treated gas to the carrier gas, thereby achieving the purification of the treated gas and the recovery of the organic solvent.
[0003] This type of organic solvent recovery system generally comprises: an adsorption-desorption treatment device, which allows the treated gas containing the organic solvent and the carrier gas in a high-temperature state to contact the adsorbent material alternately in time; and a condensation recovery device, which condenses and recovers the organic solvent by cooling the carrier gas discharged from the adsorption-desorption treatment device.
[0004] As one of such organic solvent recovery systems, Patent Document 1 discloses a gas treatment system containing an organic solvent using water vapor as a carrier gas.
[0005] In addition, recently, there is a desire for an organic solvent recovery system with a low discharge volume for the purpose of improving the quality of the recovered organic solvent and simplifying the discharge treatment process, and an organic solvent recovery system using an inert gas heated to a high temperature as a carrier gas is disclosed in Patent Document 2. In addition, Patent Document 3 discloses an organic solvent recovery system that uses an inert gas heated to a high temperature as a carrier gas and reduces the amount of inert gas used by circulating the inert gas in the organic solvent recovery system.
[0006] Prior art literature
[0007] Patent Literature
[0008] Patent Document 1: Japanese Utility Model Publication No. 3-32924
[0009] Patent Document 2: Japanese Patent Publication No. 7-68127
[0010] Patent Document 3: Japanese Patent Gazette "Patent No. 5482776"
[0011] In such an organic solvent recovery system, in order to improve the purification capability of the gas to be processed and the recovery efficiency of the organic solvent, it is necessary to fully perform the desorption of the organic solvent in the desorption process, that is, the regeneration of the adsorbent.
[0012] In order to reduce the running cost of the organic solvent recovery system, it is preferable to configure the used carrier gas to be circulated in the organic solvent recovery system and reused.
[0013] However, it is difficult to completely separate the organic solvent from the carrier gas in the condensation recovery device, so the carrier gas discharged from the condensation recovery device contains uncondensed organic solvent. Therefore, in the case of a structure in which the carrier gas is returned to the adsorption and desorption treatment device for circulation, the regeneration of the adsorbent material becomes insufficient, and there is a problem that the purification capacity of the treated gas and the improvement of the recovery efficiency of the organic solvent will naturally have a limit.
[0014] However, in Patent Document 3, a second adsorption-desorption element is provided, and the second adsorption-desorption element adsorbs and removes the organic solvent from the carrier gas containing the uncondensed organic solvent, and the organic solvent is discharged from the condensation recovery device, thereby improving the purification capacity of the treated gas and the recovery efficiency of the organic solvent. However, it is necessary to set a second adsorption-desorption treatment device filled with the second adsorption-desorption element on the circulation path of the carrier gas, and a component for making the carrier gas in a high-temperature state in order to desorb the organic solvent from the second adsorption-desorption element, etc., which has the problem of complicating the structure of the organic solvent recovery system and increasing the size. Summary of the invention
[0015] Therefore, the present invention is completed to solve the above-mentioned problems, and its purpose is to provide an organic solvent recovery system: it can suppress operating costs, and can improve the purification capacity of the treated gas and the recovery efficiency of the organic solvent, thereby simplifying and miniaturizing the system structure.
[0016] The inventors of the present invention have conducted intensive research and have found that the above-mentioned problems can be solved by the following means, thereby completing the present invention. That is, the present invention is constituted by the following structure.
[0017] 1. An organic solvent recovery system for separating and recovering an organic solvent from a treated gas containing an organic solvent, the organic solvent recovery system comprising: a circulation path for circulating a carrier gas; an adsorption-desorption treatment device, the adsorption-desorption treatment device being arranged on the circulation path, having an adsorption-desorption element, and alternately performing adsorption of the organic solvent by introducing the treated gas and desorption of the organic solvent by introducing the carrier gas; a condensation recovery device, the condensation recovery device being arranged on the downstream side of the adsorption-desorption treatment device on the circulation path, having a cooling section for cooling the carrier gas discharged from the adsorption-desorption treatment device, and condensing the organic solvent in the carrier gas by the cooling and recovering it as a condensate; and a heating section, the heating section being arranged on the upstream side of the adsorption-desorption treatment device on the circulation path, heating the carrier gas in a low-temperature state discharged from the condensation recovery device, the condensation recovery device having a melting section, the melting section temporarily heating a component frozen by the cooling to melt the component.
[0018] According to the above structure, the components frozen by cooling are temporarily heated by the melting section to melt them, so that the problem of gas flow caused by the adhesion of the frozen components can be eliminated. Therefore, the carrier gas can be cooled at a lower temperature than the previous system, so the condensation recovery efficiency of the organic solvent can be improved. In addition, the concentration of the organic solvent in the carrier gas discharged from the condensation recovery device can be reduced, and the desorption efficiency of the carrier gas in the adsorption treatment device is improved, so there is no need to set up a second adsorption desorption treatment device on the downstream side of the condensation recovery device. As a result, the operating cost can be reduced, and the purification capacity of the gas to be treated and the recovery efficiency of the organic solvent can be improved, thereby achieving simplification and miniaturization of the system structure.
[0019] 2. An organic solvent recovery system as described in 1 above, wherein the condensation recovery device has a refrigerant-heat medium supply section that selectively supplies refrigerant and heat medium, and the cooling section and the melting section are constructed as the same component as a cooling and melting section, and the cooling and melting section is supplied with refrigerant from the refrigerant-heat medium supply section and functions as the cooling section, and is supplied with heat medium from the refrigerant-heat medium supply section and functions as the melting section.
[0020] According to the above configuration, since the heat medium can be temporarily supplied to the cooling and melting section serving as the cooling source to efficiently heat the frozen component, the frozen component can be melted in a short time.
[0021] 3. An organic solvent recovery system as described in 2 above, wherein the system is provided with a static pressure difference measuring unit, which measures the static pressure difference between the inlet side and the outlet side of the carrier gas in the condensation recovery device, and when the static pressure difference measured by the static pressure measuring unit exceeds a specified value, the refrigerant heat medium supply unit selects the supply of the heat medium.
[0022] According to the above configuration, a problem in the gas flow due to the adhesion of frozen components can be detected based on the measurement result of the static pressure difference measuring unit, and the frozen components can be automatically heated and melted by switching to the supply of the heat medium.
[0023] 4. An organic solvent recovery system as described in any one of items 1 to 3 above, wherein the organic solvent recovery system comprises a vapor pressure measuring unit, which measures the vapor pressure of the organic solvent contained in the carrier gas discharged from the condensation recovery device, and the organic solvent recovery system comprises a temperature regulating unit, which regulates the temperature of the cooling unit so that the vapor pressure of the organic solvent measured by the vapor pressure measuring unit becomes below a specified value.
[0024] According to the above configuration, by adjusting the temperature of the cooling unit, the concentration of the organic solvent in the exhausted carrier gas can be kept below a certain level, and the organic solvent adsorbed to the adsorption-desorption element can be efficiently desorbed.
[0025] 5. The organic solvent recovery system according to any one of 1 to 4 above, wherein a carrier gas is not supplied to the condensation recovery device during the melting in the melting section.
[0026] According to the above configuration, it is possible to prevent the concentration of the organic solvent in the carrier gas discharged from the condensation recovery device from becoming higher than a certain level, and thus the organic solvent adsorbed to the adsorption and desorption element can be efficiently desorbed.
[0027] 6. The organic solvent recovery system as described in any one of 1 to 5 above, wherein the adsorption-desorption treatment device performs a purge treatment on the adsorption-desorption element after the adsorption and before the desorption, and the melting section performs the melting during the purge treatment.
[0028] According to the above configuration, the melting is performed during the purge process, and the melting is performed without temporarily stopping the adsorption and desorption processes, so that the system can be operated efficiently.
[0029] Effects of the Invention
[0030] According to the present invention, a melting section is provided in the organic solvent recovery system, thereby temporarily heating the components frozen by cooling to melt them, thereby being able to eliminate the problem of gas flow caused by the adhesion of the frozen components. Therefore, the carrier gas can be cooled at a lower temperature than in the previous system, so that the condensation recovery efficiency of the organic solvent can be improved. In addition, thereby, the concentration of the organic solvent in the carrier gas discharged from the condensation recovery device can be reduced, and the desorption efficiency of the carrier gas in the adsorption treatment device is improved, so there is no need to set up a second adsorption desorption treatment device on the downstream side of the condensation recovery device. As a result, the operating cost can be reduced, and the purification capacity of the gas to be treated and the recovery efficiency of the organic solvent can be improved, thereby achieving simplification and miniaturization of the system structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a diagram showing the structure of the organic solvent recovery system in the embodiment.
[0032] Figure 2 1 is a diagram showing a timing chart showing the temporal switching of the adsorption process and the desorption process using a pair of adsorption and desorption elements in the organic solvent recovery system according to the embodiment. DETAILED DESCRIPTION
[0033] Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the embodiments described below, the same or common parts are denoted by the same reference numerals in the drawings, and their description will not be repeated.
[0034] like Figure 1 As shown, the organic solvent recovery system 100A in this embodiment includes a circulation path L1 for circulating a carrier gas, an adsorption and desorption treatment device 10 and a condensation recovery device 20 arranged on the circulation path L1. The circulation path L1 is also provided with a circulation blower 40 and a treated gas blower 50. As the carrier gas, various gases such as water vapor, heated air, and an inert gas heated to a high temperature can be used. In particular, if an inert gas that is a gas that does not contain water is used, the organic solvent recovery system 100A can be constructed more simply.
[0035] The circulation path L1 includes the piping lines L4 to L7 shown in the figure. The circulation blower 40 is a blower for circulating the carrier gas so that the carrier gas circulates in the circulation path L1. The treated gas blower 50 is a blower for supplying the treated gas from the piping line L2 to the adsorption and desorption treatment device 10.
[0036] The adsorption desorption treatment device 10 is provided with an adsorption desorption tank A11 and an adsorption desorption tank B12. The adsorption desorption tank A11 is filled with an adsorption desorption element A13 for adsorbing and desorbing an organic solvent, and the adsorption desorption tank B12 is filled with an adsorption desorption element B14 for adsorbing and desorbing an organic solvent. In the present embodiment, there are two adsorption desorption tanks, but there may be one or more than three. Moreover, the adsorption desorption treatment device 10 is also provided with a heater (heating unit) 30.
[0037] The heater 30 heats the carrier gas supplied to the adsorption desorption tank A11 or the adsorption desorption tank B12. More specifically, the heater 30 sets the carrier gas discharged from the condensation recovery device 20 and passed through the circulating blower 40 to a high temperature state and supplies it to the adsorption desorption tank A11 or the adsorption desorption tank B12. Here, the heater 30 adjusts the temperature of the carrier gas introduced into the adsorption desorption tank A11 and the adsorption desorption tank B12 so that the adsorption desorption element A13 and the adsorption desorption element B14 are maintained at a specified desorption temperature. In addition, the heater 30 can also be arranged outside the adsorption desorption treatment device 10.
[0038] The adsorption-desorption element A13 and the adsorption-desorption element B14 adsorb the organic solvent contained in the treated gas by contacting with the treated gas introduced from the piping line L2. The treated gas sometimes contains moisture, which is also adsorbed. Therefore, in the adsorption-desorption treatment device 10, when the treated gas is supplied to the adsorption-desorption tank A11 or the adsorption-desorption tank B12, the organic solvent and moisture are adsorbed by the adsorption-desorption element A13 or the adsorption-desorption element B14, thereby removing the organic solvent from the treated gas, and the treated gas is cleaned and discharged from the adsorption-desorption tank A11 or the adsorption-desorption tank B12 as a clean gas.
[0039] In addition, the adsorption desorption element A13 and the adsorption desorption element B14 contact with the carrier gas in a high temperature state to desorb the adsorbed organic solvent and moisture. Therefore, in the adsorption desorption treatment device 10, when the carrier gas in a high temperature state is supplied to the adsorption desorption tank A11 or the adsorption desorption tank B12, the organic solvent and moisture are desorbed from the adsorption desorption element A13 or the adsorption desorption element B14, and the carrier gas containing the organic solvent and moisture is discharged from the adsorption desorption tank A11 or the adsorption desorption tank B12.
[0040] The adsorption-desorption element A13 and the adsorption-desorption element B14 are composed of an adsorbent material including any one of granular activated carbon, activated carbon fiber, zeolite, silica gel, porous polymer and metal organic structure. It is preferred to use granular, powdered, honeycomb activated carbon and zeolite, and more preferably to use activated carbon fiber. Activated carbon fiber has a fibrous structure with micropores on the surface, so it has high contact efficiency with gas and achieves higher adsorption efficiency than other adsorbent materials.
[0041] In addition, activated carbon fibers have a higher adsorption selectivity for organic solvents than granular, powdered, honeycomb, and other activated carbons, and therefore hardly adsorb the moisture contained in the treated gas. Therefore, the amount of moisture contained in the carrier gas discharged from the adsorption desorption tank A11 or the adsorption desorption tank B12 of the adsorption desorption treatment device 10 is extremely small, and the organic solvent recovery system can be constructed more simply, and the organic solvent recovery system can be miniaturized. When an adsorption desorption element with low adsorption selectivity for organic solvents is used, a large amount of moisture contained in the treated gas will be adsorbed. Therefore, the amount of moisture contained in the carrier gas discharged from the adsorption desorption tank A11 and the adsorption desorption tank B12 of the adsorption desorption treatment device 10 is also large, and wastewater containing organic solvents is discharged from the organic solvent recovery system 100A, so separate wastewater treatment is required.
[0042] The adsorption and desorption treatment device 10 is respectively connected to piping lines L2 and L3. The piping line L2 is a piping line for supplying the treated gas containing organic solvent and moisture to the adsorption and desorption tank A11 or the adsorption and desorption tank B12 via the treated gas blower 50. The piping line L2 switches the connection / disconnection state to the adsorption and desorption tank A11 through the valve V1, and switches the connection / disconnection state to the adsorption and desorption tank B12 through the valve V3. The piping line L3 is a piping line for discharging the clean gas from the adsorption and desorption tank A11 or the adsorption and desorption tank B12. The piping line L3 switches the connection / disconnection state to the adsorption and desorption tank A11 through the valve V2, and switches the connection / disconnection state to the adsorption and desorption tank B12 through the valve V4.
[0043] Moreover, piping lines L5 and L6 are also connected to the adsorption desorption treatment device 10, respectively. The piping line L5 is a piping line for supplying the carrier gas to the adsorption desorption tank A11 or the adsorption desorption tank B12 via the heater 30. The piping line L5 switches the connection / disconnection state to the adsorption desorption tank A11 through the valve V5, and switches the connection / disconnection state to the adsorption desorption tank B12 through the valve V7. The piping line L6 is a piping line for discharging the carrier gas from the adsorption desorption tank A11 or the adsorption desorption tank B12. The piping line L6 switches the connection / disconnection state to the adsorption desorption tank A11 through the valve V6, and switches the connection / disconnection state to the adsorption desorption tank B12 through the valve V8.
[0044] By operating the opening and closing of the above-mentioned valves V1 to V8, the treated gas and the carrier gas in a high-temperature state are respectively supplied alternately in time to the adsorption desorption tank A11 and the adsorption desorption tank B12. As a result, the adsorption desorption tank A11 and the adsorption desorption tank B12 function alternately as an adsorption tank and a desorption tank in time, and with this, the organic solvent and moisture move from the treated gas to the carrier gas in a high-temperature state. In addition, specifically, during the period when the adsorption desorption tank A11 functions as an adsorption tank, the adsorption desorption tank B12 functions as a desorption tank, and during the period when the adsorption desorption tank A11 functions as a desorption tank, the adsorption desorption tank B12 functions as an adsorption tank.
[0045] The condensation recovery device 20 includes a condenser (condenser) 21, a recovery tank 22, and a refrigerant / heat medium supply unit 23. The condenser 21 adjusts the temperature of the carrier gas in a high-temperature state discharged from the adsorption desorption tank A11 or the adsorption desorption tank B12 to a low-temperature state, thereby condensing the organic solvent and trace water contained in the carrier gas. Specifically, the condenser 21 liquefies the organic solvent and water by indirectly cooling the carrier gas using a refrigerant. The recovery tank 22 stores the organic solvent and water liquefied by the condenser 21 as a condensate. In addition, the recovery tank 22 and the refrigerant / heat medium supply unit 23 can also be arranged outside the condensation recovery device 20.
[0046] The refrigerant / heat medium supply unit 23 supplies refrigerant or heat medium to the condenser 21 alternately in time. The condensation recovery device 20 performs a condensation process (refrigerant supply), that is, supplies refrigerant from the refrigerant / heat medium supply unit 23, and uses the condenser 21 to indirectly cool the carrier gas containing organic solvent and water discharged from the adsorption and desorption treatment device 10, and adjusts the temperature of the carrier gas to a low temperature state to condense the organic solvent and water. In addition, the condensation recovery device 20 performs a melting process (heat medium supply), that is, supplies heat medium from the refrigerant / heat medium supply unit 23, and indirectly heats and melts the water and organic solvent (frozen components) frozen in the condenser 21 and its periphery. Through the melting process, the heat medium can be temporarily supplied to the condenser serving as a cooling source to efficiently heat the frozen components, so that the frozen components can be melted in a short time.
[0047] Here, as the refrigerant and the heat medium, any one of water, ethanol, ethylene glycol, propylene glycol, chlorofluorocarbons, hydrochlorofluorocarbons, hydrofluorocarbons, or a mixture thereof can be used, but there is no particular limitation. In addition, the heat medium refers to a medium at a higher temperature than the refrigerant.
[0048] Pipe lines L6 and L7 are connected to the condensation recovery device 20. The pipe line L6 is a pipe line for supplying the carrier gas discharged from the adsorption and desorption treatment device 10 to the condenser 21. The pipe line L7 is a pipe line for discharging the carrier gas from the condenser 21.
[0049] Furthermore, a piping line L9 is connected to the condenser 21 . The piping line L9 is a piping line for introducing the organic solvent and a trace amount of water condensed by the condenser 21 into the recovery tank 22 .
[0050] Furthermore, the condenser 21 is connected to piping lines L10 and L11, respectively. The piping line L10 is a piping line for supplying refrigerant or heat medium from the refrigerant / heat medium supply unit 23 to the condenser 21. The piping line L11 is a piping line for discharging the refrigerant or heat medium from the condenser 21 to the outside. In the present embodiment, the piping line L11 is connected to the refrigerant / heat medium supply unit 23 so that the refrigerant or heat medium is circulated. By circulating the refrigerant or heat medium, heat recovery can be performed, and the condensation recovery device 20 can be operated in an energy-saving manner.
[0051] Figure 2 It means in Figure 1 The organic solvent recovery system 100A shown in FIG. 1 is a timing chart showing the time switching of the adsorption process and the desorption process using the adsorption and desorption element A13 and the adsorption element B14. Figure 2 The details of the treatment of the gas to be treated using the organic solvent recovery system 100A according to the present embodiment will be described by taking the case where an inert gas is used as a carrier gas as an example.
[0052] Organic solvent recovery system 100A will Figure 2 The one cycle shown is repeated as a unit period, so that the gas to be processed can be processed continuously.
[0053] In the first half of the above cycle ( Figure 2 At the same time, a purge process (Japanese: パージ) is performed in the adsorption desorption tank A11 of the adsorption desorption treatment device 10 filled with the adsorption desorption element A13 between the time t0 and t2 shown in FIG. 1 . At the same time, a purge process (Japanese: パージ) is performed in the adsorption desorption tank B12 of the adsorption desorption treatment device 10 filled with the adsorption desorption element B14 to replace the adsorption desorption tank B12 with an inert gas. Figure 2 ) and then perform desorption treatment ( Figure 2Between the moments t1 and t2 shown in ). The inert gas and the carrier gas used in the purge treatment are the same. It is preferred to perform piping in the following manner: the downstream of the adsorption desorption tank B12 in the purge treatment is connected to the upstream side of the treated gas blower 50, and the treated gas (the gas remaining in the adsorption desorption tank B12) replaced by the inert gas and discharged is supplied to the adsorption desorption tank A11 undergoing adsorption treatment together with the treated gas. This is because the recovery concentration of the organic solvent can be increased by supplying it to the adsorption treatment again. In the present embodiment, it is configured as described above: the downstream of the adsorption desorption tank in the purge treatment becomes connected to the upstream side of the treated gas blower 40 and becomes disconnected from the condenser 21 side (not shown). Switching to this connected / disconnected state is also performed by a valve.
[0054] In addition, in the second half of the above cycle ( Figure 2 In the adsorption desorption treatment device 10 filled with the adsorption desorption element B14, an adsorption treatment is carried out in the adsorption desorption tank B12. At the same time, in the adsorption desorption tank A11 of the adsorption desorption treatment device 10 filled with the adsorption desorption element A13, a purge treatment is carried out to replace the adsorption desorption tank A11 with an inert gas ( Figure 2 ) and then perform desorption treatment ( Figure 2 between time t3 and t4 shown in FIG.
[0055] The condensation treatment is carried out in the condensation recovery device 20 ( Figure 2 ), that is, refrigerant is supplied from the refrigerant / heat medium supply unit 23, and the carrier gas containing the organic solvent and trace amounts of water discharged from the adsorption-desorption treatment device 10 is indirectly cooled by the condenser 21, thereby adjusting the temperature of the carrier gas to a low temperature state to condense the organic solvent, and the organic solvent and trace amounts of water are recovered.
[0056] The condensation recovery device 20 may also include a vapor pressure measuring unit (not shown) for measuring the vapor pressure of the organic solvent contained in the carrier gas discharged from the condenser 21, and may also include a temperature regulating unit (not shown) for regulating the temperature of the condenser 21 so that the vapor pressure of the organic solvent measured by the vapor pressure measuring unit becomes less than a predetermined value. By regulating the temperature of the condenser, the concentration of the organic solvent in the discharged carrier gas can be kept below a certain value, and the organic solvent adsorbed on the adsorption and desorption element can be efficiently desorbed.
[0057] For example, when the organic solvent is ethyl acetate as in the embodiment described later, in the condensation process, it is preferred to adjust the temperature of the carrier gas so that the vapor pressure of the organic solvent contained in the carrier gas discharged from the condenser 21 is 11.4 mmHg or less, and it is more preferred to further adjust the temperature of the carrier gas so that the vapor pressure of the organic solvent is 6.1 mmHg or less. When the vapor pressure of the organic solvent contained in the carrier gas discharged from the condenser 21 is 11.4 mmHg or less, the vapor pressure of the organic solvent contained in the carrier gas that contacts the adsorption and desorption element A13 and the adsorption and desorption element B14 through circulation is also sufficiently reduced, thereby effectively promoting the regeneration of the adsorption and desorption element A13 and the adsorption and desorption element B14. On the other hand, when the vapor pressure of the organic solvent contained in the carrier gas discharged from the condenser 21 exceeds 11.4 mmHg, the vapor pressure of the organic solvent contained in the carrier gas that contacts the adsorption-desorption element A13 and the adsorption-desorption element B14 by circulation is also high, so it is difficult to fully regenerate the adsorption-desorption element A13 and the adsorption-desorption element B14, and the performance of the system is reduced. The values of 11.4 mmHg and 6.1 mmHg are values derived from the experimental results in the examples described later.
[0058] The temperature adjustment of the carrier gas can be controlled by the amount of the refrigerant or the temperature of the refrigerant from the refrigerant / heat medium supply unit 23. Specifically, the relationship between the temperature and the vapor pressure is maintained as data, and the temperature of the carrier gas is adjusted by the refrigerant so as to achieve the desired vapor pressure. In addition, the relationship between the temperature and the vapor pressure varies depending on the type of organic solvent, but can be confirmed by literature, etc. The vapor pressure of the organic solvent can be measured by a VOC concentration meter, gas chromatography, etc.
[0059] In addition, if the condensation recovery device 20 regulates the temperature of the carrier gas so that the vapor pressure of the organic solvent contained in the carrier gas discharged from the condenser 21 is below a specified value, there is no need to provide an adsorption desorption element for adsorbing and removing the organic solvent in the carrier gas between the condenser 21 and the adsorption desorption treatment device 10, and the organic solvent recovery system 100A can be made into a simple structure and miniaturized.
[0060] In addition, when the condensation recovery device 20 adjusts the temperature of the carrier gas so that the vapor pressure of the organic solvent contained in the carrier gas discharged from the condenser 21 is below a specified value, it is necessary to adjust the temperature of the carrier gas to below 0°C depending on the type of organic solvent. Therefore, the organic solvent and water contained in the carrier gas are frozen in the condenser 21, the flow path of the carrier gas is blocked, the ventilation resistance of the condenser 21 increases, and the carrier gas cannot circulate. Therefore, the supply of the refrigerant is switched to the supply of the heat medium in the refrigerant / heat medium supply unit 23, thereby performing a melting process to indirectly heat the frozen organic solvent and trace water to melt them so as to prevent the flow path in the condenser 21 from being blocked ( Figure 2 The melted organic solvent and a small amount of water are discharged to the recovery tank 22 through the pipe line L9.
[0061] In addition, during the melting treatment, it is preferred not to supply a carrier gas to the condenser 21. If a carrier gas is supplied to the condenser 21 during the melting treatment, the melted organic solvent and water will be vaporized and contained in the carrier gas, and will be discharged to the circulation path L1 through the piping line L7, and it is impossible to efficiently perform liquefaction recovery. Therefore, it is best to perform the melting treatment without supplying a carrier gas to the condenser 21 during the purge treatment in which the adsorption-desorption element A13 or the adsorption-desorption element B14 is not performing the desorption treatment. In the present embodiment, as described above, the adsorption-desorption tank B12 in the purge treatment is in a state of being disconnected from the condenser 21, and instead, is in a state of being connected to the upstream of the treated gas blower 50, so that the treated gas (the gas remaining in the adsorption-desorption tank B12) that is replaced by the inert gas and discharged during the purge treatment will not be supplied to the condenser 21.
[0062] In addition, in the condensation recovery device 20, the condensation process continues until the organic solvent and trace water in the condenser 21 are almost melted. When the melting of the organic solvent and trace water is completed, the refrigerant / heat medium supply unit 23 switches from supplying the heat medium to supplying the refrigerant. As a result, the condenser 21 performs the condensation process again ( Figure 2 ), that is, indirectly cooling the carrier gas, adjusting the carrier gas temperature to a low temperature state to condense the organic solvent and a trace amount of water.
[0063] Here, in Figure 2 As an example, the melting process is shown as being performed between time t2 and t3, but it is not necessary to perform the melting process of the condenser 21 in each of all cycles. It can be performed periodically or irregularly. Figure 2 As shown in FIG. 1 , the operation is limited to being performed during the purge process of the adsorption / desorption element A13 , but may also be performed during the purge process of the adsorption / desorption element B14 .
[0064] In addition, when the melting process cannot be completed during the purge process of the adsorption / desorption element A13 or the adsorption / desorption element B14, a structure may be set as follows: a plurality of condensers are provided, and while the melting process is continued by one condenser, the condensation process is performed by another condenser. In addition, in this case, a structure such as switching between the condenser for performing the melting process and the condenser for performing the condensation process by valve operation may be considered, but it is not particularly limited.
[0065] Here, a static pressure difference measuring unit (not shown) is provided for measuring the difference between the static pressure at the inlet of the condenser 21 of the carrier gas and the static pressure at the outlet of the condenser 21. If the condensation process is switched to the melting process at the time when the static pressure difference reaches a predetermined value or more, the ventilation resistance of the condenser 21 can be always prevented from increasing. According to the measurement result of the static pressure difference measuring unit, the problem of gas flow caused by the adhesion of frozen components can be detected, and the frozen components can be automatically heated and melted by switching to the melting process (heat medium supply). Here, the "predetermined value" is determined by the pressure loss (differential pressure) of the condenser 21 to the extent that the discharge pressure of the circulation blower 40 does not decrease as a limit value. The discharge pressure of the circulation blower 40 is determined by the motor capacity of the circulation blower 40. As the static pressure difference measuring unit, a pressure gauge is used. When the positive pressure measuring port of the pressure gauge is connected to the inlet (L6 side) of the condenser 21 and the negative pressure measuring port is connected to the outlet (L7 side) of the condenser 21, the static pressure difference can be measured.
[0066] Furthermore, if the concentration of the organic solvent and the amount of water contained in the gas to be processed can be known in advance, these data can be stored in advance and the condensation process and the melting process can be switched at a certain time interval in the refrigerant / heat medium supply unit 23 .
[0067] Here, if activated carbon fibers are used in the adsorption-desorption element A13 and the adsorption-desorption element B14, the moisture contained in the treated gas is hardly adsorbed, so the moisture contained in the carrier gas supplied to the condenser 21 is extremely small. Therefore, the amount of moisture frozen in the condenser 21 can be extremely small, the frequency of the thawing process of the condenser 21 is significantly reduced, the energy required for the thawing process can be reduced, and the organic solvent recovery system 100A can be made into a simpler structure.
[0068] The organic solvent recovery system 100A of this embodiment can reuse the carrier gas by constructing the circulation path L1, so it is also economically excellent. Therefore, when an inert gas represented by nitrogen is used as the carrier gas, the effect of being able to suppress running costs can be obtained.
[0069] In the organic solvent recovery system 100A of the present embodiment described above, the frozen components are temporarily heated and melted by supplying heat medium to the condenser 21, so that the problem of gas flow caused by the attachment of the frozen components can be eliminated. Therefore, the carrier gas can be cooled at a lower temperature than the previous system, so the condensation recovery efficiency of the organic solvent can be improved. In addition, the concentration of the organic solvent in the carrier gas discharged from the condensation recovery device 20 can be reduced, and the desorption efficiency of the carrier gas in the adsorption desorption treatment device 10 is improved, so there is no need to set up a second adsorption desorption treatment device on the downstream side of the condensation recovery device 20. Since the concentration of the organic solvent in the carrier gas can be reduced, it becomes a result of promoting the regeneration of the adsorption desorption element A13 and the adsorption desorption element B14 in the desorption treatment, and in the adsorption treatment performed later, the organic solvent can be more efficiently adsorbed and removed from the treated gas. Therefore, by using the organic solvent recovery system 100A, the running cost can be reduced, and the purification capacity of the treated gas and the recovery efficiency of the organic solvent can be improved, and the system structure can be simplified and miniaturized. As described above, according to the present embodiment, it is possible to provide an organic solvent recovery system having higher performance and a simpler structure than conventional systems.
[0070] (Example)
[0071] In the following examples, the gas to be processed was processed using the organic solvent recovery system 100A in the above-described embodiment of the present invention.
[0072] In the embodiment, a gas containing ethyl acetate as an organic solvent at a concentration of 3000 ppm and at a temperature of 40°C and a relative humidity of 60% RH was used as the treated gas. Nitrogen at 120°C was used as the carrier gas. In addition, as the adsorption and desorption elements A13 and B14, a gas having a BET specific surface area of 1500 mg / m 2 The activated carbon fibers were used as refrigerant and heat medium, and a 70 mass % ethylene glycol aqueous solution was used.
[0073] First, the treated gas blower 50 is used to blow the gas at a volume of 10 Nm 3 / min is supplied to one of the adsorption and desorption tank A11 and the adsorption and desorption tank B12 of the adsorption and desorption treatment device 10 for 10 minutes, thereby making the one adsorption and desorption tank function as an adsorption tank and performing adsorption treatment.
[0074] After the adsorption process is completed, the valve is switched to switch one of the adsorption and desorption tanks to the desorption tank, and the other adsorption and desorption tank is used as the adsorption tank. In the desorption tank, a purge process is performed to replace the desorption tank with nitrogen, and then the air volume is 1.5 Nm 3 / min nitrogen heated to 120°C by the heater 30 is introduced to perform desorption treatment of the adsorption desorption element. In the adsorption tank, the adsorption treatment is performed under the same conditions as above. Condensation treatment is performed in the condensation recovery device 20, that is, refrigerant is supplied from the refrigerant / heat medium supply unit 23 to the condenser 21, and the nitrogen containing ethyl acetate discharged from the desorption tank is cooled to -30°C.
[0075] The above-described one cycle was continuously repeated, and as a result, it was confirmed that the concentration of ethyl acetate contained in the clean gas discharged from the adsorption and desorption treatment device 10 was reduced to about 20 ppm. In other words, it was confirmed that ethyl acetate could be removed at a high removal rate of about 99% in the example.
[0076] In addition, it was confirmed that, in the above-mentioned desorption process, the vapor pressure of ethyl acetate contained in the nitrogen gas flowing through the piping line L6 for introducing gas into the condensation recovery device 20 increased to 15.2 mmHg on average, and the vapor pressure of ethyl acetate contained in the nitrogen gas flowing through the piping line L7 for discharging gas from the condensation recovery device 20 always decreased to 2.7 mmHg or less. In this embodiment, the temperature of the refrigerant is changed to adjust the temperature of the nitrogen gas so that the vapor pressure of ethyl acetate is always 2.7 mmHg or less.
[0077] In addition, it was confirmed that 5 hours after the start of the supply of the treated gas, a trace amount of water froze (solidified) in the condenser 21 of the condensation recovery device 20, and the static pressure difference between the inlet and outlet of the nitrogen gas increased from 150 mmH 2 O rises to 300 mmH 2 O, therefore, during the purge process of one of the adsorption / desorption element A13 or the adsorption / desorption element B14, the refrigerant / heat medium supply unit 23 is switched from the supply of refrigerant to the supply of heat medium, and the condenser 21 is switched from the condensation process to the melting process. The temperature of the heat medium supplied from the refrigerant / heat medium supply unit 23 is set to 30°C.
[0078] Since the frozen trace amount of water is rapidly melted by the melting process of the condenser 21 , the refrigerant / heat medium supply unit 23 is again switched from supplying the heat medium to supplying the refrigerant, and the condenser 21 is switched from the melting process to the condensing process.
[0079] In the melting process of the condenser 21 described above, the pressure difference between the static pressure at the inlet of the condenser 21 and the static pressure at the outlet of the condenser 21 is reduced from 150 mm H 2 O up to 300 mm H 2 More specifically, the melting process of the condenser 21 is performed every approximately 5 hours while the purging process of the adsorption / desorption element A13 or the adsorption / desorption element B14 is being performed.
[0080] It was confirmed that the concentration of ethyl acetate contained in the clean gas discharged from the adsorption and desorption treatment device 10 was also reduced to about 20 ppm immediately after the melting treatment of the condenser 21 described above. That is, it was confirmed that the melting treatment of the condenser can be performed without affecting the removal efficiency of ethyl acetate from the treated gas in this embodiment.
[0081] The embodiments and examples disclosed above are illustrative in all aspects and are not restrictive. The technical scope of the present invention is defined by the scope of the invention to be protected, and includes all changes within the meaning and scope equivalent to the description of the scope of the invention to be protected.
[0082] Industrial Applicability
[0083] The present invention can be effectively used in a system for treating a gas to be treated containing an organic solvent exhausted from, for example, a factory or a high-rise building.
[0084] Explanation of symbols
[0085] 10 adsorption and desorption treatment device, 11 adsorption and desorption tank A, 12 adsorption and desorption tank B, 13 adsorption and desorption element A, 14 adsorption and desorption element B, 20 condensation recovery device, 21 condenser (melting part, cooling part, cooling and melting part), 22 recovery tank, 23 refrigerant / heat medium supply part (refrigerant heat medium supply part), 30 heater (heating part), 40 circulation blower, 50 treated gas blower, 100A organic solvent recovery system, L1 circulation path, L2 to L11 piping lines, V1 to V8 valves
Claims
1. An organic solvent recovery system for separating and recovering an organic solvent from a treated gas containing an organic solvent, wherein the organic solvent recovery system comprises: a circulation path for circulating a carrier gas; an adsorption-desorption treatment device, which is disposed on the circulation path, has an adsorption-desorption element, and alternately performs adsorption of the organic solvent by introducing the gas to be treated and desorption of the organic solvent by introducing the carrier gas; a condensation recovery device, the condensation recovery device being provided on the circulation path at a downstream side of the adsorption and desorption treatment device, having a cooling portion for cooling the carrier gas discharged from the adsorption and desorption treatment device, and condensing the organic solvent in the carrier gas by the cooling and recovering it as a condensate; and a heating unit, which is provided on the circulation path at the upstream side of the adsorption and desorption treatment device, and heats the low-temperature carrier gas discharged from the condensation recovery device, The condensate recovery device includes a melting section that temporarily indirectly heats the frozen components frozen by the cooling to melt the frozen components. The low-temperature carrier gas discharged from the condensation recovery device is directly introduced into the heating part via a circulating blower. The adsorption-desorption treatment device performs a purge treatment on the adsorption-desorption element after the adsorption and before the desorption, and the melting unit performs the melting during the purge treatment. There is no adsorption-desorption device different from the adsorption-desorption treatment device on the downstream side of the condensation recovery device on the circulation path, The condensation recovery device has a refrigerant and heat medium supply unit for selectively supplying refrigerant and heat medium. The cooling unit and the melting unit are configured as the same member as a cooling and melting unit that functions as the cooling unit when a refrigerant is supplied from the refrigerant and heat medium supply unit and functions as the melting unit when a heat medium is supplied from the refrigerant and heat medium supply unit.
2. The organic solvent recovery system according to claim 1, characterized in that: A static pressure difference measuring unit is provided, the static pressure difference measuring unit measuring the static pressure difference between the inlet side and the outlet side of the carrier gas in the condensation recovery device, The refrigerant heat medium supply unit selects supply of the heat medium when the static pressure difference measured by the static pressure difference measurement unit exceeds a predetermined value.
3. The organic solvent recovery system according to claim 1 or 2, characterized in that: The organic solvent recovery system includes a vapor pressure measuring unit for measuring the vapor pressure of the organic solvent contained in the carrier gas discharged from the condensation recovery device. The organic solvent recovery system includes a temperature adjustment unit that adjusts the temperature of the cooling unit so that the vapor pressure of the organic solvent measured by the vapor pressure measurement unit becomes equal to or less than a predetermined value.
4. The organic solvent recovery system according to claim 1 or 2, characterized in that: During the melting by the melting unit, a carrier gas is not supplied to the condensate recovery device.