A method for supporting formwork of super-high-rise frame beams

Through the simplified structure of the bottom formwork frame and the beam side scaffolding structure, the upper beam formwork is supported by the bearing capacity of the lower-layer forming beam, which solves the problems of complex structure, high material cost and safety hazards in super high-rise buildings, and realizes the support system Improve safety and reliability and construction efficiency.

CN112878673BActive Publication Date: 2024-11-26CHINA CONSTR FIFTH ENG DIV CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110268756.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-03-12
Publication Date
2024-11-26
Estimated Expiration
2041-03-12

AI Technical Summary

Technical Problem

Among the existing framework beam formwork support methods for super high-rise buildings, the scaffolding structure is complex, the material cost is high, the labor cost is large, the construction cycle is long, and there are safety hazards. This method is even more unsuitable in super high-rise buildings.

Method used

A simplified supporting formwork system is adopted, including the bottom supporting formwork frame and the side scaffolding of the beam, which is connected by vertical support rods and horizontal support rods. The lower forming beam is used as the supporting formwork frame bearing structure of the upper beam, and the second layer begins with Vertical struts are arranged inclined to support the upper beam formwork and transfer the weight of the poured concrete to the lower molded beam, reducing the number of structural parts and on-site workload.

Benefits of technology

The safety and reliability of the supporting mold system are achieved, the material and manpower consumption is reduced, the construction cycle is shortened, the transportation and rectification difficulty is reduced, and the construction safety is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112878673B_ABST
    Figure CN112878673B_ABST
Patent Text Reader

Abstract

The invention discloses a method for supporting formwork of frame beams of a super-high-rise frame layer, comprising the following steps: fixing a plurality of rows of vertical struts at evenly spaced intervals along the length direction of the beams at the positions of the beams corresponding to the roof surface of the building, the width of each row of vertical struts being greater than the width of the beams, and the rows of vertical struts being connected as a whole by longitudinal horizontal tie rods; setting up scaffolds on both sides / one side of the corresponding beam positions as operating frames for workers, the scaffolds on both sides being connected as a whole by transverse horizontal tie rods, and connecting and fixing the scaffolds to the vertical struts; fixing transverse horizontal struts at the upper ends of each row of vertical struts; installing a first layer of beam formwork above the transverse horizontal struts; casting and curing the first layer of beams; fixing a second layer of vertical struts on the top surface of the first layer of beams by raising the scaffolding, and the vertical struts on both sides being arranged obliquely; connecting and fixing the second layer of vertical struts to the scaffolds; installing a second layer of beam formwork; casting and curing the second layer of beams; and so on and so forth until the installation of the last layer of beam formwork is completed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of super high-rise buildings, and in particular relates to a super high frame layer frame beam formwork method for a super high-rise building. Background Art

[0002] Buildings with more than 40 floors and a height of more than 100 meters are called super high-rise buildings. They are generally large-scale projects with landmark significance. Most of the super high-rise buildings have two frame layers on the top. The frame beams of the frame layer are cast after supporting the formwork by setting up a full-height scaffolding.

[0003] Full-floor scaffolding is a construction process that involves laying down the full-floor scaffolding horizontally. Full-floor scaffolding is a high-density scaffolding, including a large number of vertical poles, horizontal poles, sweeping poles, middle poles, beam bottom poles, vertical scissors braces, horizontal scissors braces, wall connectors, and a large number of fasteners, pads, and top supports. It has a complex structure and requires high material costs. The workload of on-site erection and disassembly of the frame is large, requiring a large amount of manpower costs and a long construction period. Even leasing requires relatively high transportation costs. In addition, due to the complex structure of full-floor scaffolding and the large workload of erection, it is easy to lower the erection standards in order to speed up the erection progress, such as not installing the scissors braces at the same time, not tightening the bowl buckles, etc., which makes subsequent rectification difficult. Once the rectification is not in place, it may even cause safety hazards during the construction process.

[0004] In addition, the pouring of the frame beams of the frame layer is carried out after the lower floors are built. It is very difficult to transport the huge amount of materials to the roof, and the on-site workers are working at super-high altitudes, with a large workload and greater safety hazards. Obviously, for super-high frame layers with a height of more than three floors, it is even more inappropriate to use full-floor scaffolding formwork. Summary of the invention

[0005] The purpose of the present invention is to provide a method for supporting formwork for frame beams of a frame layer, which has a simple formwork system structure and is safe and reliable.

[0006] The super-high-rise frame beam formwork method provided by the present invention comprises the following steps:

[0007] (1) Multiple rows of vertical braces are fixed at the corresponding beam positions on the roof surface at evenly spaced intervals along the length of the beam. The width of each row of vertical braces is greater than the width of the beam, and each row of vertical braces is connected as a whole by longitudinal horizontal tie rods;

[0008] (2) Scaffolds are set up on both sides / one side of the corresponding beam position as workers' operating frames. The scaffolds on both sides are connected into a whole through horizontal tie rods, and the scaffolds are connected and fixed to the vertical support rods;

[0009] (3) fixing the horizontal braces to the upper ends of each row of vertical braces fixed in step (1);

[0010] (4) Install the first layer of beam formwork above the horizontal braces;

[0011] (5) Casting and curing of the first layer of beams;

[0012] (6) While raising the scaffold, fix the second layer of vertical braces on the top surface of the first layer of beams according to step (1), but the vertical braces on both sides are arranged obliquely;

[0013] (7) Referring to step (2), connect and fix the second layer of vertical braces to the scaffolding;

[0014] (8) Repeat step (4) to install the second layer of beam formwork;

[0015] (9) Casting and curing of the second layer beams;

[0016] (10) Repeat steps (6)-(8) in sequence until the last layer of vertical struts is erected and connected and fixed to the scaffolding, and the last layer of beam formwork is installed.

[0017] In one implementation of the above method, at least two vertical braces are arranged in the middle of the bottom of each row of vertical braces.

[0018] In one implementation of the above method, the spacing between each row of vertical support rods in each layer is 600-900 mm.

[0019] In one implementation of the above method, each vertical support rod has a pad at its lower end, and the pad has a fastener mounting hole.

[0020] In one implementation of the above method, the lower outer edges of the two side braces of the second layer of vertical braces are 30 to 50 mm away from the beam edge, and after the top is connected to the transverse horizontal brace, the connection point is 100 to 200 mm away from the beam edge.

[0021] In one implementation of the above method, the inner uprights of the scaffolding on both sides of the frame beam are 200 to 350 mm away from the beam edge.

[0022] In one implementation of the above method, a metal wall tie is provided between the scaffold and the frame beam, and the metal wall tie is vertically pre-embedded on the center plane of the frame beam in the width direction.

[0023] In one implementation of the above method, the vertical spacing between the metal wall ties is no greater than the floor height of the frame layer, and the horizontal spacing is no greater than two spans.

[0024] In one implementation of the above method, two horizontal bars are arranged at the intersection corners of each side beam scaffolding, inner frame beam scaffolding, and core tube peripheral scaffolding to connect the scaffoldings on both sides of the corner.

[0025] The formwork system of the present invention only includes a beam bottom formwork frame and a beam side scaffolding. The beam bottom formwork frame includes vertical struts, transverse horizontal struts and longitudinal horizontal pull rods. The scaffolding serves as a worker operating frame, so it is only necessary to respectively set two rows of vertical rods on both sides of the longitudinal direction of the inner frame beam and two rows of vertical rods on the inner side of the side beam, and to set up the scaffolding structure according to the conventional structure. That is, the present invention cleverly uses the lower-layer forming beam as the load-bearing structure of the upper-layer beam formwork frame, and supports the side struts of the vertical struts starting from the second layer on the forming beam in an oblique manner, so that the vertical struts can safely and reliably support the upper-layer beam formwork and transfer the weight of the poured concrete to the lower-layer forming beam. The upper end can meet the support requirement that the width of the beam formwork is greater than the beam width. At the same time, the scaffolding on the beam side is fixed to the anchor bars embedded in the forming beam, thereby improving the overall stability of the formwork frame and the scaffolding. Therefore, while ensuring the safety and reliability of the formwork frame, the present invention has a much simpler structure than the formwork method of the full-floor scaffolding, and the number of structural parts is much less, so the on-site workload is much less, saving manpower and material resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 The figure is a schematic diagram of the plan layout of an embodiment of the present invention.

[0027] Figure 2 Schematic diagram of the formwork system at the inner frame beam in this embodiment.

[0028] Figure 3 for Figure 2 Schematic side view (only one layer of the formwork system is shown). DETAILED DESCRIPTION

[0029] like Figure 1 As shown, the main idea of ​​the formwork method for the super-high frame layer frame beam of the super-high-rise disclosed by the present invention is to set up formwork frames at the bottom of each beam, and set up scaffolds C on both sides of the inner frame beam A and the inner side of the side beam B as operating frames for workers to install beam templates, which meets the safety of formwork and requires less scaffolding materials. That is, the formwork system of this method only includes the beam bottom formwork frame and the beam side scaffold, and the formwork steps are as follows:

[0030] (1) Multiple rows of vertical braces are fixed at the corresponding beam positions on the roof surface at evenly spaced intervals along the length of the beam. The width of each row of vertical braces is greater than the width of the beam, and each row of vertical braces is connected as a whole by longitudinal horizontal tie rods;

[0031] (2) Scaffolds are set up on both sides / one side of the corresponding beam position as workers' operating frames. The scaffolds on both sides are connected into a whole through horizontal tie rods, and the scaffolds are connected and fixed to the vertical support rods;

[0032] (3) fixing the horizontal braces to the upper ends of each row of vertical braces fixed in step (1);

[0033] (4) Install the first layer of beam formwork above the horizontal braces;

[0034] (5) Casting and curing of the first layer of beams;

[0035] (6) While raising the scaffold, fix the second layer of vertical braces on the top surface of the first layer of beams according to step (1), but the vertical braces on both sides are arranged obliquely;

[0036] (7) Referring to step (2), connect and fix the second layer of vertical braces to the scaffolding;

[0037] (8) Repeat step (4) to install the second layer of beam formwork;

[0038] (9) Casting and curing of the second layer beams;

[0039] (10) Repeat steps (6)-(8) in sequence until the last layer of vertical struts is erected and connected and fixed to the scaffolding, and the last layer of beam formwork is installed.

[0040] In this embodiment, the inner frame beam A of the frame layer has a width of 600 mm and a height of 700 mm, the side beam B has a width of 400 mm and a height of 700 (900) mm, the frame layer has 9 layers, the total height is 38100 mm, and the scaffolding erection height is 35900 mm.

[0041] The formwork construction steps of the present embodiment are as follows:

[0042] 1. Erection of the first layer of formwork and scaffolding

[0043] (1) Multiple rows of vertical braces are evenly spaced along the length of the beam at the positions of the inner frame beams and side beams on the roof surface. The width of each row of vertical braces is greater than the width of the beam. Each row of vertical braces is connected into a whole through longitudinal horizontal tie rods and fasteners at the bottom.

[0044] Figure 2 , Figure 3 A schematic structural diagram of the formwork and scaffolding at the inner frame beam in this embodiment is shown.

[0045] The inner frame beam is arranged in a row with four vertical braces, two of which are beam bottom braces 1 and the other two are side braces 2, all arranged vertically. The center distance between the beam bottom braces is 200mm, and they are arranged symmetrically about the beam width center plane. The center distance between the two side braces and the beam bottom brace is about 300mm.

[0046] The lower end of each support rod is provided with a pad, which is connected and fixed to the embedded parts in the roof structure of the building through fasteners.

[0047] The spacing between adjacent rows of vertical braces is 900.

[0048] Only bottom support rods are set at the side beams, and the layout is the same as that of the inner frame beams, so no schematic diagram is given.

[0049] (2) Scaffolding is set up on both sides of the corresponding inner frame beam and the inner side of the side beam as a worker operating frame, and the scaffolding is connected and fixed to the vertical support rod. The erection of the scaffolding shall be carried out in accordance with relevant standards.

[0050] from Figure 2 , Figure 3 It can be seen that the uprights 3 of the scaffolding on both sides of the inner frame beam are connected into a whole through the transverse horizontal tie rods 4 and the scissors braces 5 to enhance the stability of the formwork system.

[0051] The scaffolding on the inner side of the side beam is connected to the formwork at the bottom of the beam as a whole. The specific operation refers to the treatment at the inner frame beam.

[0052] (3) Workers stand on the scaffolding, connect and fix each row of vertical struts fixed in step (1) through the middle and top longitudinal horizontal tie rods, fix the transverse horizontal tie rods near the top support of the top of each row of vertical struts through fasteners and other accessories, and install the transverse horizontal struts 6 at the top support.

[0053] (4) Install the first layer of beam formwork above the horizontal support rods.

[0054] (5) The first layer of beams is cast and cured.

[0055] 2. Second layer formwork and scaffolding erection

[0056] While raising the scaffold, fix the second layer of vertical braces on the top surface of the first layer of beams according to step (1), but the vertical braces on both sides are arranged at an angle.

[0057] from Figure 2 It can be seen that the arrangement of the bottom support rod 1 of the second layer of vertical support rods is the same as that of the first layer, with the upper end connected to the top support, and the upper end of the side support rod 2 extending out of the upper end of the bottom support rod 1. The middle part of the transverse horizontal support rod 6 is installed through the top support, and the two ends are connected and fixed to the side support rod 2 through fasteners and other accessories, so that the vertical support rods are arranged into an open screen surface that is narrow at the bottom and wide at the top.

[0058] In this embodiment, the distance between the outer edge of the lower end of the second layer side support rod and the edge of the beam should be about 50 mm, and the connection position between the upper end and the fastener should be about 200 mm away from the edge of the beam.

[0059] Other operations of this layer are performed in accordance with the operations of the first layer. That is, the structural difference between the second layer formwork and the first layer formwork is that the side braces of each row of vertical braces are arranged obliquely, in order to ensure the force transmission performance of the vertical brace rows.

[0060] 3. Erection of the Nth layer of formwork and scaffolding

[0061] The formwork and scaffolding for other layers can be set up in the same way as for the second layer.

[0062] In order to further improve the safety and stability of the formwork and scaffolding after erection, when pouring each beam, the anchor bars 7 extending upward are embedded as wall connecting parts. When the scaffolding is erected, the anchor bars are connected and fixed to the scaffolding through fasteners and other accessories, such as Figure 2 shown.

[0063] In this embodiment, anchor bars are arranged on each layer of beams, and the spacing between the anchor bars on the same layer is not greater than two spans.

[0064] Because the building is a ring structure, the scaffolding around the inner frame beam, side beam and core tube is connected to the concrete structure by means of wall connecting parts and holding columns, and two horizontal bars are set at the intersection of the side beam scaffolding, inner frame beam scaffolding and core tube scaffolding to connect the scaffolding on both sides of the corner. Figure 1 As shown, to ensure the overall stability of the whole layer of scaffolding.

[0065] Combination Figures 1 to 3 It can be seen that the formwork system of the present invention only includes the beam bottom formwork frame and the beam side scaffolding. The beam bottom formwork frame includes vertical support rods, transverse horizontal support rods and longitudinal horizontal pull rods. The scaffolding serves as a worker operating frame, so it is only necessary to set two rows of vertical rods on both sides of the longitudinal direction of the inner frame beam and two rows of vertical rods on the inner side of the side beam, and set up according to the conventional scaffolding structure. That is, the present invention cleverly uses the lower-layer forming beam as the load-bearing structure of the upper-layer beam formwork frame, and the side support rods of the vertical support rods starting from the second layer are supported in an oblique manner. The lower end can be supported on the forming beam, so that the vertical support rods can safely and reliably support the upper-layer beam formwork and transfer the weight of the poured concrete to the lower-layer forming beam. The upper end can meet the support requirement that the width of the beam formwork is greater than the beam width. At the same time, the scaffolding on the beam side is fixed to the anchor bars embedded in the forming beam, thereby improving the overall stability of the formwork frame and the scaffolding. Therefore, while ensuring the safety and reliability of the formwork frame, the present invention has a much simpler structure than the formwork method of the full-floor scaffolding, and the number of structural parts is much less, so the on-site workload is much less, saving manpower and material resources.

Claims

1. A method for supporting formwork of a super-high-rise frame beam layer, comprising the following steps: (1) Multiple rows of vertical braces are fixed at the corresponding beam positions on the roof surface at evenly spaced intervals along the length of the beam. The width of each row of vertical braces is greater than the width of the beam, and each row of vertical braces is connected into a whole by longitudinal horizontal tie rods; (2) Scaffolding is set up on both sides / one side of the corresponding beam position as a worker operating frame. The scaffolding on both sides is connected into a whole through horizontal tie rods, and the scaffolding is connected and fixed to the vertical support rods; (3) Fixing the horizontal braces to the upper ends of each row of vertical braces fixed in step (1); (4) Install the first layer of beam formwork above the horizontal braces; (5) Casting and curing of the first layer of beams; (6) While raising the scaffold, fix the second layer of vertical braces on the top surface of the first layer of beams according to step (1), but the vertical braces on both sides are arranged at an angle; (7) Refer to step (2) to connect and fix the second layer of vertical support rods to the scaffolding; (8) Repeat step (4) to install the second layer of beam formwork; (9) Casting and curing of the second-layer beams; (10) Repeat steps (6) to (8) until the last layer of vertical bracing is erected and connected to the scaffolding, and the last layer of beam formwork is installed.

2. The method according to claim 1, characterized in that: Each row of vertical braces is provided with at least two vertical braces in the middle of the bottom of the beam.

3. The method according to claim 1, characterized in that: The spacing between each row of vertical braces on each floor is 600-900mm.

4. The method according to claim 1, characterized in that: The lower end of each vertical support rod is provided with a pad, and the pad is provided with a fastener mounting hole.

5. The method according to claim 1, characterized in that: The outer edges of the lower ends of the two side braces of the second layer of vertical braces are 30-50mm away from the beam edge. After the top is connected to the transverse horizontal brace, the connection point is 100-200mm away from the beam edge.

6. The method according to claim 1, characterized in that: The inner uprights of the scaffolding on both sides of the frame beam are 200-350mm away from the edge of the beam.

7. The method according to claim 3, characterized in that: Metal wall ties are arranged between the scaffolding and the frame beams, and the metal wall ties are vertically pre-embedded on the center plane of the frame beam in the width direction.

8. The method according to claim 3, characterized in that: Two horizontal bars are set at the intersection corners of the side beam scaffolding, inner frame beam scaffolding and core tube peripheral scaffolding to connect the scaffolding on both sides of the corner.