A decision-making method for site selection for new energy vehicle power battery recall

By constructing a reverse logistics network structure and a multi-objective dynamic location selection model for new energy vehicle power batteries, the problems of recall risk and resource utilization of new energy vehicle power batteries are solved, and safety, environmental protection and economic benefits are optimized.

CN112926862BActive Publication Date: 2024-10-01SHANGHAI SECOND POLYTECHNIC UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110240990.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-03-04
Publication Date
2024-10-01
Estimated Expiration
2041-03-04

AI Technical Summary

Technical Problem

The average scrapping time of new energy vehicle power batteries is short and domestic laws and regulations are imperfect, resulting in power battery recall risks that are not effectively managed and a lack of reverse logistics network design, which affects environmental protection and resource utilization.

Method used

Construct a reverse logistics network structure including service outlets, recall outlets, recall processing centers, recall transfer centers and echelon utilization centers, use the Fourier prediction model to predict the recall volume, and optimize the facility layout through a multi-objective dynamic site selection model, taking into account safety, Environmental protection and economic benefits, determine the optimal location for each target facility.

Benefits of technology

It reduces the safety risks of the reverse logistics network for new energy vehicle power batteries, reduces environmental impact, rationally considers multiple factors, optimizes the number and location of facilities, and improves resource utilization and economic benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112926862B_ABST
    Figure CN112926862B_ABST
Patent Text Reader

Abstract

The present invention provides a decision method for site selection for recall of power batteries of new energy vehicles, including: S1, constructing a reverse logistics network structure of power batteries of new energy vehicles with multiple target facilities considering the recall risk; S2, using a Fourier prediction model to predict the sales volume of new energy vehicles and the recall volume of power batteries in multiple cycles; S3, constructing a site selection model of multiple target facilities in the reverse logistics network structure of power batteries of new energy vehicles considering the recall risk; S4, based on steps S2 and S3, determining the proposed location of each target facility in the reverse logistics network structure of power batteries of new energy vehicles considering the recall risk; S5, constructing a nonlinear mixed integer programming model based on step S4, solving the global optimal solution, and the optimal solution is the site selection of multiple target facilities in the reverse logistics network structure of power batteries of new energy vehicles considering the recall risk. The present invention can realize the optimal site selection of each target facility in the logistics network of power batteries of new energy vehicles.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of site selection, and in particular to a decision-making method for site selection for recall of power batteries of new energy vehicles. Background Art

[0002] New energy vehicles refer to vehicles that use unconventional automotive fuels as their power source (or use conventional automotive fuels and adopt new on-board power devices), and integrate advanced technologies in vehicle power control and drive to form vehicles with advanced technical principles, new technologies, and new structures.

[0003] New energy vehicles generally use batteries as their power source. The power batteries of new energy vehicles have a certain lifespan. At the end of their lifespan, the power batteries need to be recycled, which can both improve resource utilization and avoid battery pollution of the environment.

[0004] Since new energy vehicles belong to an emerging industry, the average scrap time of power batteries is five years, and the domestic laws and regulations on the recall of new energy vehicle power batteries are still imperfect, so few people pay attention to the reverse logistics network design of new energy vehicle power batteries considering recall risks.

[0005] However, as the use and scope of new energy vehicles increase, it is necessary to study the site selection of new energy vehicle power battery logistics network in order to protect the environment and improve resource utilization. Summary of the invention

[0006] The purpose of the present invention is to provide a decision-making method for the site selection of the recall of power batteries for new energy vehicles. First, a reverse logistics network structure of power batteries for new energy vehicles including service outlets, recall outlets, recall processing centers, recall transfer centers and cascade utilization centers is constructed. Secondly, on the basis of using the Fourier model to predict the recall volume of power batteries for new energy vehicles in multiple cycles, the fixed cost, testing cost, packaging cost, operating cost, transportation cost, storage cost of each proposed facility in the reverse logistics network structure of power batteries for new energy vehicles, and the impact of the facility on safety and environmental protection during operation and transportation are considered. With the goal of minimizing safety and environmental protection risks and response time and maximizing economic benefits, a multi-period multi-objective dynamic site selection model is constructed to determine the number and site selection of each target facility in the network. This method reasonably considers multiple influencing factors and is more conducive to determining the optimal site selection of each target facility.

[0007] In order to achieve the above object, the present invention is implemented by the following technical solutions:

[0008] A decision-making method for selecting a recall site for a new energy vehicle power battery, the method comprising:

[0009] S1. Construct a multi-objective facility reverse logistics network structure for new energy vehicle power batteries considering recall risks;

[0010] S2. Use the Fourier prediction model to predict the sales volume of new energy vehicles and the recall volume of power batteries in multiple cycles;

[0011] S3. Construct a location selection model for multi-objective facilities in the reverse logistics network structure of new energy vehicle power batteries considering recall risks;

[0012] S4. Based on the steps S2 and S3, the proposed locations of the target facilities in the reverse logistics network structure of the new energy vehicle power battery considering the recall risk are set;

[0013] S5. Based on the step S4, a nonlinear mixed integer programming model is constructed to solve the global optimal solution, where the optimal solution is the location selection of multi-objective facilities in the reverse logistics network structure of new energy vehicle power batteries considering the recall risk.

[0014] Furthermore, the multi-target facilities include: recall outlets, recall processing centers, recall transfer centers and tiered utilization centers.

[0015] Furthermore, the Fourier prediction model is expressed as:

[0016] f(x)=a0+a1*cos(x*w)+b1*sin(x*w)+a2*cos(2x*w)+b2*

[0017] sin(2x*w), where x represents the year, f(x) represents the sales volume of new energy vehicles or the recall volume of power batteries, a0, a1, a2, b1, b2 are model parameters, and w is the fundamental frequency.

[0018] Furthermore, in step S3, when constructing a site selection model for a multi-objective facility, the objective function max F=(SR-SET)+EB is constructed with the goal of minimizing safety and environmental risks and response time and maximizing economic benefits, where SR represents social responsibility impact, SET represents safety and environmental risks and response time, and EB represents economic benefits.

[0019] Furthermore, the safety, environmental protection and response time SET of each cycle of the reverse logistics network of new energy vehicle power batteries considering recall risk includes the distances between the recall outlets, recall processing centers, and recall transfer centers in each cycle, as well as the size of the cascade utilization center, and is calculated using the following formula:

[0020]

[0021] Among them, dt st represents the distance from the recall processing center s to the recall transfer center t, dtte represents the distance from the recall transfer center t to the cascade utilization center e, dt rs represents the distance from the recall outlet r to the recall processing center s; if the recall transit center t is established during the pth operation period, then otherwise If the recall processing center s is established during the pth operation period, then otherwise If the secondary utilization center e is established during the pth operation period, then otherwise

[0022] Furthermore, the impact SR of each cycle of the reverse logistics network of new energy vehicle power batteries considering recall risks on social responsibility includes the number of jobs created by recall outlets, recall processing centers, recall transfer centers and cascade utilization centers in each cycle, and is calculated using the following formula:

[0023]

[0024] in, represents the number of jobs created by recall processing center s during its operation period p, represents the number of jobs created by the recall transfer center t during the operation period p, represents the number of jobs created by the cascade utilization center e during the operation period p. If the recall transfer center t is established during the pth operation period, then otherwise If the recall processing center s is established during the pth operation period, then otherwise If the secondary utilization center e is established during the pth operation period, then otherwise

[0025] Furthermore, the impact EB of each cycle of the reverse logistics network of new energy vehicle power batteries considering recall risk on economic benefits includes the value generated after the new energy vehicle power batteries recalled in each cycle are processed by the cascade utilization center, and is calculated using the following formula:

[0026]

[0027] EC=C1+C2+C3+C4+C5+C6+C7,

[0028] in, Represents the economic income of the enterprise, represents the inventory of the recycling center e in the operation cycle o, Pr represents the value generated by the recycling of power batteries after deducting the cost, β is the recycling rate of the recycling center e, 0≤β≤1, EC represents the economic cost of the enterprise, C1 represents the sum of the construction costs of the recall processing center and the recall transfer center in each cycle, C2 represents the sum of the transportation costs between various facilities in each cycle, C3 represents the sum of the testing costs of new energy vehicle power batteries in each cycle, C4 represents the sum of the packaging costs of new energy vehicle power batteries in each cycle, C5 represents the sum of the warehousing costs of the recall processing center, recall transfer center, and recycling center in each cycle, C6 represents the sum of the labor costs of the recall processing center, recall transfer center, and recycling center in each cycle, and C7 represents the sum of the operating costs of the recall processing center, the recall transfer center, and the recycling center in each cycle.

[0029] Furthermore, in the location selection model of the multi-objective facility, the constraints are set as follows:

[0030] The pth cycle ensures that each recall outlet has a corresponding processing center;

[0031] The pth cycle ensures that each selected recall processing center has a corresponding recall transfer center;

[0032] The pth cycle ensures that each selected recall transfer center has a corresponding cascade utilization center;

[0033] The number of power batteries shipped from the recall outlets to the recall processing center in the pth cycle is equal to the number of batteries recovered by the recall outlets;

[0034] The number of new energy vehicle power batteries transported from the recall outlets to the recall processing center in the pth cycle is equal to the number of new energy vehicle power batteries transported from the recall processing center to the recall transfer center;

[0035] The number of new energy vehicle power batteries transported from the recall processing center to the recall transfer center in the pth cycle is equal to the number of new energy vehicle power batteries transported from the recall transfer center to the cascade utilization center;

[0036] The number of new energy vehicle power batteries shipped from the recall outlets to the recall processing center in the pth cycle is equal to the inventory of the recall processing center;

[0037] The number of new energy vehicle power batteries shipped from the recall processing center to the recall transfer center in the pth cycle is equal to the inventory of the recall transfer center;

[0038] The number of new energy vehicle power batteries transported from the recall transfer center to the cascade utilization center in the pth cycle is equal to the inventory of the cascade utilization center;

[0039] The number of new energy vehicle power batteries delivered from the recall outlets to the recall processing center in the pth cycle does not exceed the maximum processing capacity of the recall processing center;

[0040] The number of new energy vehicle power batteries transported from the recall processing center to the recall transfer center in the pth cycle does not exceed the maximum processing capacity of the recall transfer center;

[0041] The number of new energy vehicle power batteries transported from the recall transfer center to the cascade utilization center in the pth cycle does not exceed the maximum processing capacity of the cascade utilization center;

[0042] The number of new energy vehicle power batteries in the recall processing center in the pth cycle does not exceed the maximum inventory of the recall processing center;

[0043] The number of new energy vehicle power batteries in the recall transfer center in the pth cycle does not exceed the maximum inventory of the recall transfer center;

[0044] The number of new energy vehicle power batteries in the p-th cycle cascade utilization center shall not exceed the maximum inventory of the cascade utilization center;

[0045] The number of recall processing centers built in the pth cycle is less than the maximum number that can be built;

[0046] The number of recall transfer centers built in the pth cycle is less than the maximum number that can be built;

[0047] The number of cascade utilization centers built in the pth period is less than the maximum number that can be built.

[0048] Compared with the prior art, the present invention has the following beneficial effects:

[0049] (1) A decision-making method for recall site selection of new energy vehicle power batteries of the present invention first constructs a reverse logistics network structure of new energy vehicle power batteries that takes into account recall risks, including service outlets, recall outlets, recall processing centers, recall transfer centers, and cascade utilization centers. Secondly, based on the prediction of the recall volume of new energy vehicle power batteries in multiple cycles, the fixed cost, testing cost, packaging cost, operating cost, transportation cost, warehousing cost of each proposed facility in the reverse logistics network structure of new energy vehicle power batteries, as well as the safety and environmental impact of the facility during operation and transportation are considered. With the goal of minimizing safety and environmental risks and response time and maximizing economic benefits, a multi-period multi-objective dynamic site selection model is constructed to determine the number, site selection, and flow distribution between target facilities in the reverse logistics network structure of new energy vehicle power batteries. This method reasonably considers multiple influencing factors and is more conducive to determining the optimal site selection of each target facility.

[0050] (2) A decision-making method for recalling power batteries for new energy vehicles of the present invention establishes a model with the goal of minimizing safety and environmental protection risks and response time and maximizing economic benefits, thereby reducing the safety risks of the reverse logistics network structure of power batteries for new energy vehicles and reducing the impact on the environment;

[0051] (3) The decision method for site selection for recall of new energy vehicle power batteries of the present invention conducts a sensitivity analysis on the site selection decision of the reverse logistics network structure of new energy vehicle power batteries based on safety and environmental protection factors, social responsibility factors, and economic factors. It combines the Fourier prediction model with the nonlinear mixed integer programming model to optimize the number, site selection, flow distribution and inventory of recall outlets, recall processing centers, recall transfer centers and cascade utilization centers of the reverse logistics network structure of new energy vehicle power batteries in each cycle. BRIEF DESCRIPTION OF THE DRAWINGS

[0052] In order to more clearly illustrate the technical solution of the present invention, the following briefly introduces the drawings required for the description. Obviously, the drawings described below are an embodiment of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative work:

[0053] Figure 1 A schematic diagram of a process flow of a decision-making method for selecting a recall site for a power battery of a new energy vehicle provided by an embodiment of the present invention;

[0054] Figure 2 It is a schematic diagram of multi-target facilities in the reverse logistics network structure of new energy vehicle power batteries of the present invention;

[0055] Figure 3 It is the influence diagram of the change of parameters λ and μ on the optimal value of the objective function;

[0056] Figure 4 For parameters and The effect of the change of on the optimal value of the objective function. DETAILED DESCRIPTION

[0057] The technical solution proposed in the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods. According to the following description, the advantages and features of the present invention will be clearer. It should be noted that the accompanying drawings are in a very simplified form and use non-precise proportions, which are only used to conveniently and clearly assist in explaining the purpose of the implementation method of the present invention. In order to make the purpose, features and advantages of the present invention more obvious and easy to understand, please refer to the accompanying drawings. It should be noted that the structure, proportion, size, etc. illustrated in the accompanying drawings of this specification are only used to match the content disclosed in the specification, so that people familiar with this technology can understand and read, and are not used to limit the limiting conditions for the implementation of the present invention, so they have no technical substantive significance. Any modification of the structure, change in the proportional relationship or adjustment of the size, without affecting the effect that the present invention can produce and the purpose that can be achieved, should still fall within the scope of the technical content disclosed by the present invention.

[0058] like Figure 1 As shown, the present invention provides a decision method for selecting a recall site for a new energy vehicle power battery, the method specifically comprising:

[0059] S1. Construct a multi-objective facility new energy vehicle power battery reverse logistics network structure considering recall risks. In this embodiment, Figure 2 As shown in Figure 1, the multi-target facilities in the reverse logistics network structure of new energy vehicle power batteries considering recall risks include: recall outlets, recall processing centers, recall transfer centers and cascade utilization centers. After a problem occurs with a power battery, the service outlets announced by the Ministry of Industry and Information Technology (the specific addresses of relevant online stores are announced on the official website of the Ministry of Industry and Information Technology) will recall it. After the service outlets collect the problematic power batteries, they will be transported to the recall outlets, which will be aggregated and sent to the recall processing center. After a simple packaging test at the recall processing center, the recall processing center will send them to the recall transfer center, and finally the recall transfer center will send them to the cascade utilization center for final processing.

[0060] S2. Use the Fourier prediction model to predict the sales volume of new energy vehicles and the recall volume of power batteries in multiple periods.

[0061] Wherein, the Fourier prediction model is expressed as:

[0062] f(x)=a0+a1*cos(x*w)+b1*sin(x*w)+a2*cos(2x*w)+b2*sin(2x*w) (1)

[0063] Among them, x represents the year, f(x) represents the sales volume of new energy vehicles or the recall volume of power batteries, a0, a1, a2, b1, b2 are model parameters, and w is the base frequency.

[0064] Since the predicted automobile sales volume and power battery recall volume are related to the year, x represents the year, and f(x) obtained by formula (1) is the sales volume or recall volume.

[0065] The model parameters a0, a1, a2, b1, and b2 are determined in the following way: by substituting the year and sales volume into the Fourier prediction model for fitting, the relevant model parameters of the sales volume can be obtained, or by substituting the year and recall volume into the Fourier prediction model for fitting, the relevant model parameters of the recall volume can be obtained.

[0066] S3. Construct a location selection model for multi-objective facilities in the reverse logistics network structure of new energy vehicle power batteries considering recall risks.

[0067] In this embodiment, when constructing a multi-objective facility site selection model, the goal is to minimize safety and environmental risks and response time and maximize economic benefits, and construct an objective function maxF=(SR-SET)+EB(2), where SR represents social responsibility impact, SET represents safety and environmental risks and response time, and EB represents economic benefits.

[0068] The reverse logistics network structure of the new energy vehicle power battery recall includes P cycles, R recall outlets, S recall processing centers, T recall transfer centers, and E cascade utilization centers. The set of cycles is P = {1, 2, ..., P}, the set of recall outlets is R = {1, 2, ..., R}, the set of recall processing centers is S = {1, 2, ..., S}, the set of recall transfer centers is T = {1, 2, ..., T}, and the set of cascade utilization centers is E = {1, 2, ..., E}, r∈R, s∈S, t∈t, e∈E, p∈P, that is, p represents the pth cycle, r represents the rth recall outlet, s represents the sth recall processing center, t represents the tth recall transfer center, and e represents the ethth cascade utilization center.

[0069] Preferably, the safety, environmental protection and response time SET of each cycle of the reverse logistics network for new energy vehicle power batteries considering recall risks include: the distances between the recall outlets, recall processing centers, and recall transfer centers in each cycle, and the size of the cascade utilization center.

[0070]

[0071] Preferably, the social responsibility impact SR of each cycle of the reverse logistics network for new energy vehicle power batteries considering recall risks includes: the number of jobs created by recall outlets, recall processing centers, recall transfer centers and cascade utilization centers in each cycle.

[0072]

[0073] Preferably, the economic benefit impact EB of each cycle of the reverse logistics network of new energy vehicle power batteries considering recall risks includes: the value generated after the new energy vehicle power batteries recalled in each cycle are processed by the recycling center.

[0074]

[0075] EC=C1+C2+C3+C4+C5+C6+C7 (6)

[0076] represents the economic income of the enterprise, and EC represents the economic cost of the enterprise.

[0077] The sum of the construction costs of the recall processing center and the recall transfer center in each cycle

[0078] The sum of transportation costs between facilities in each cycle

[0079] The sum of the testing costs of new energy vehicle power batteries in each cycle

[0080] The sum of the packaging costs of new energy vehicle power batteries in each cycle

[0081] The sum of the storage costs of the recall processing center, recall transfer center, and tiered utilization center in each cycle

[0082] The sum of the labor costs of the recall processing center, the recall transfer center, and the tiered utilization center in each cycle

[0083] The sum of the operating expenses of the recall processing center, recall transfer center, and cascade utilization center in each cycle

[0084] In addition, in the location selection model of the multi-objective facility, the constraints are set as follows:

[0085] The pth cycle ensures that each recall outlet has a corresponding processing center, expressed as:

[0086]

[0087] The pth cycle ensures that each selected recall processing center has a corresponding recall transfer center, expressed as:

[0088]

[0089] The pth cycle ensures that each selected recall transfer center has a corresponding cascade utilization center, expressed as:

[0090]

[0091] The number of power batteries shipped from the recall outlets to the recall processing center in the pth cycle is equal to the number of batteries recovered by the recall outlets, expressed as:

[0092]

[0093] The number of new energy vehicle power batteries transported from the recall outlets to the recall processing center in the pth cycle is equal to the number of new energy vehicle power batteries transported from the recall processing center to the recall transfer center, expressed as:

[0094]

[0095] The number of new energy vehicle power batteries transported from the recall processing center to the recall transfer center in the pth cycle is equal to the number of new energy vehicle power batteries transported from the recall transfer center to the cascade utilization center, expressed as:

[0096]

[0097] The number of new energy vehicle power batteries shipped from the recall outlets to the recall processing center in the pth cycle is equal to the inventory of the recall processing center, expressed as:

[0098]

[0099] The number of new energy vehicle power batteries shipped from the recall processing center to the recall transfer center in the pth cycle is equal to the inventory of the recall transfer center, expressed as:

[0100]

[0101] The number of new energy vehicle power batteries transported from the recall transfer center to the cascade utilization center in the pth cycle is equal to the inventory of the cascade utilization center, expressed as:

[0102]

[0103] The number of new energy vehicle power batteries transported from the recall outlets to the recall processing center in the pth cycle does not exceed the maximum processing capacity of the recall processing center, expressed as:

[0104]

[0105] The number of new energy vehicle power batteries transported from the recall processing center to the recall transfer center in the pth cycle does not exceed the maximum processing capacity of the recall transfer center, expressed as:

[0106]

[0107] The number of new energy vehicle power batteries transported from the recall transfer center to the cascade utilization center in the pth cycle does not exceed the maximum processing capacity of the cascade utilization center, expressed as:

[0108]

[0109] The number of new energy vehicle power batteries in the recall processing center in the pth cycle does not exceed the maximum inventory of the recall processing center, expressed as:

[0110]

[0111] The number of new energy vehicle power batteries in the recall transfer center in the pth cycle does not exceed the maximum inventory of the recall transfer center, expressed as:

[0112]

[0113] The number of new energy vehicle power batteries in the p-th cycle cascade utilization center does not exceed the maximum inventory of the cascade utilization center, expressed as:

[0114]

[0115] The number of recall processing centers built in the pth cycle is less than the maximum number that can be built, expressed as:

[0116]

[0117] The number of recall transfer centers built in the pth period is less than the maximum number that can be built, expressed as:

[0118]

[0119] The number of construction of cascade utilization centers in the pth period is less than the maximum number that can be built, expressed as:

[0120]

[0121] in,

[0122]

[0123] Subscript Description:

[0124] (1) r: the serial number of the candidate recall outlet, r∈R, where R represents the set of all recall outlets;

[0125] (2) s: the serial number of the candidate recall processing center, s∈S, s represents the set of all candidate recall processing centers;

[0126] (3) t: the serial number of the candidate recall transfer center, t∈T, T represents the set of all candidate recall transfer centers;

[0127] (4) e: alternative cascade utilization center, e∈E, E represents the set of all alternative cascade utilization centers;

[0128] (5) p: the serial number of the operation cycle, p∈P, where P represents the set of operation cycle numbers in the location selection problem of recall outlets, recall processing centers, recall transfer centers, and cascade utilization centers. For example, P={1,2,3} is a location selection problem that considers three cycles, and the operation time of each cycle is expressed in days.

[0129] Parameter Description:

[0130] (1) d: number of operating days per operating cycle;

[0131] (2) Fixed Input of recall processing center s during operation period p;

[0132] (3) The fixed investment of the recall transfer center t during the operation period p;

[0133] (4) Fixed investment of cascade utilization center e during operation period p;

[0134] (5) The number of jobs created by recall processing center s during operating period p (Job Creation);

[0135] (6) The number of jobs created by recall transfer center t during its operating period p;

[0136] (7) The number of jobs created by the secondary utilization center e during its operation period p;

[0137] (8) sc: Shipping cost per unit distance of each recalled power battery;

[0138] (9) pkc: Packing Cost of each recalled power battery;

[0139] (10) dc: Detection cost of each recalled power battery (Detect Cost);

[0140] (11) wc s : The daily storage cost per unit of the recall processing center s (Warehouse Cost);

[0141] (12) wc t : The daily storage cost per unit of the recall transshipment center t;

[0142] (13) wc e : The daily storage cost per unit of the cascade utilization center e;

[0143] (14)oc s : Unit operating cost of recall processing center s (Operating Cost);

[0144] (15)oc t : Unit operating cost of recall transfer center t;

[0145] (16)oc e : Unit operating cost of cascade utilization center e;

[0146] (17)lc s : The daily cost of each employee in the recall processing center (Labor Cost);

[0147] (18)lc t : The cost per employee per day for recalling the transfer center;

[0148] (19)lc e : Cost per employee per day for the tiered utilization center e;

[0149] (20)dt rs : The distance from the recall outlet r to the recall processing center s;

[0150] (21)dt st : The distance from the recall processing center s to the recall transfer center t;

[0151] (22)dt te : The distance from the recall transfer center t to the cascade utilization center e;

[0152] (23)N s : The maximum processing capacity of the recall processing center s;

[0153] (24)M t : The maximum processing capacity of the recall transfer center t;

[0154] (25)M e : The maximum processing capacity of center e is utilized in stages;

[0155] (26) The inventory of recall processing center s during the operation period p;

[0156] (27) The inventory of recall transshipment center t during the operation period p;

[0157] (28) The inventory of the cascade utilization center e during the operation period p;

[0158] (29)L s : The maximum number of recall processing centers s to be built;

[0159] (30)L t : The maximum number of constructions of recall transfer center t;

[0160] (31)L e : The maximum number of construction of cascade utilization center e;

[0161] (32)Q f : Predicted recall volume of power batteries;

[0162] (33) Pr: the value generated by the secondary utilization of power batteries (after deducting costs);

[0163] (34)β is the cascade utilization rate of cascade utilization center e, 0≤β≤1;

[0164] (35)δ1,δ2: the cut-off points of transportation scale discount;

[0165] (36)γ1,γ2: the cutoff points of transport distance penalty;

[0166] (37)f(T r0 ,dt r0 ) = sc·δγ (= freight rate function), δ is the discount rate, which depends on the transportation volume T between the recall network r and the recall processing center s rs ; γ is the penalty rate, which means that the power battery to be recalled must be returned to the recall network r within a certain period of time. Here, the time is represented by the distance, which depends on the distance dt between the recall network r and the recall processing center s. rs .

[0167] (38)

[0168] (39)

[0169] Description of decision variables:

[0170] (1) It represents the period of recalling outlet t within the pth operating cycle, and the operating cycle is expressed in days.

[0171] (2) It indicates the number of power batteries sent from recall outlet r to recall processing center s during the pth operation cycle, otherwise it is 0;

[0172] (3) It represents the number of power batteries sent from recall processing center s to recall transfer center t in the pth operation cycle, otherwise it is 0;

[0173] (4) It indicates the number of power batteries sent from recall transfer center t to cascade utilization center e during the pth operation cycle, otherwise it is 0;

[0174] (5)

[0175] (6)

[0176] (7)

[0177] (8)

[0178] (9)

[0179] (10)

[0180] S4. Based on step S2 and step S3, determine the proposed locations of each target facility in the reverse logistics network structure of new energy vehicle power batteries considering the recall risk.

[0181] For example, as shown in Tables 1-4, the proposed location coordinates of the service outlets, recall outlets, recall processing centers, recall transfer centers, and tiered utilization centers set in this embodiment are shown.

[0182] Table 1 Recall outlet locations

[0183]

[0184]

[0185] Table 2 Alternative locations for recall processing centers

[0186]

[0187] Table 3 Alternative locations for recall transfer centers

[0188]

[0189] Table 4 Alternative points for cascade utilization centers

[0190]

[0191] As shown in Table 1-4, in the reverse logistics network structure of new energy vehicle power batteries under recall, there are 6 recall processing center candidate points, 4 recall transfer center candidate points, and 2 cascade utilization center candidate points. The optimization model can determine the optimal solution of 3 recall processing centers, 2 recall transfer centers, and 1 cascade utilization center, that is, at most 3 recall processing centers, 2 recall transfer centers, and 1 cascade utilization center can be constructed. Taking Shanghai as an example, the recall volume of each power battery is obtained according to the predicted data, and the relevant coordinates are set by the simulation data.

[0192] S5. Based on the step S4, a nonlinear mixed integer programming model is constructed to solve the global optimal solution, which is the location of multi-objective facilities in the reverse logistics network structure of new energy vehicle power batteries considering the recall risk. In this embodiment, a mixed integer nonlinear programming model containing 822 variables and 247 constraints is constructed, and the global optimal solution is solved by Lingo 18.0 using DELLXPS 13.

[0193] The case shows that the minimum cost of building and operating the Shanghai new energy vehicle power battery reverse logistics network within three cycles is 433,126,300 yuan, and the maximum profit is 433,126,300 yuan. The site selection plan of the reverse logistics network is shown in the following table.

[0194] Table 5 Site selection plan

[0195]

[0196] The following is a sensitivity analysis of the decision-making method of the present invention.

[0197] The present invention proposes a decision-making method for selecting a recall site for new energy vehicle power batteries, which fully weighs safety, environmental protection, and economic benefits. The model part is divided into two important contents, namely, the safety and environmental protection social responsibility level (SR-SET) and the economic benefit level (EB). The safety and environmental protection responsibility level includes minimizing social security risks and environmental pollution risks (SET) and maximizing social responsibility (SR); the economic benefit level means that enterprises should maintain a certain income or control losses within a certain range under the condition of ensuring safety and environmental protection.

[0198] The parameter that affects the safety and environmental protection responsibility level (SR-SET) is λ, the parameter that affects the economic benefit EB is μ, and the parameter that affects the social responsibility SR is The parameters that affect the safety and environmental protection response time SET are: Right now

[0199]

[0200] The increase or decrease of these parameter values ​​will have an important impact on the reverse logistics network of power battery recalls. Sensitivity analysis will help enterprise managers make reasonable recall decisions and will also help relevant government departments to formulate guidance or regulatory policies that are in line with reality. The present invention conducts a sensitivity experiment to expand or reduce each parameter value to test the impact of parameter changes on the overall goal. For each parameter, there are three different rates of change, namely 0.5, 1, and 1.5, as shown in the third column of Table 6 and the third column of Table 7. The parameter changes corresponding to each parameter in the experimental group are 0.5 times, 1 times, and 1.5 times, respectively, and the remaining four parameters are set to unit value 1.

[0201] Table 6 Sensitivity analysis of λ and μ

[0202]

[0203] Table 7 and Sensitivity analysis of

[0204]

[0205] From Table 6 and Figure 3 It can be seen that the safety, environmental protection and social responsibility parameter λ has little effect on the function target result, while the economic benefit parameter μ has a greater impact. It can be seen that the parameter λ has no significant effect on the performance of the recall reverse logistics network, but the parameter μ has a significant impact on the performance of the recall reverse logistics network. This obvious interest gap makes some companies often drive out profit maximization when making recall decisions or designing recall reverse logistics networks, while ignoring safety issues and environmental pollution issues.

[0206] The parameter λ is given by and The common influence, so the parameters and parameters For separate analysis, see Table 7 and Figure 4 See the parameters and parameters The effect of changes on the function, parameters Positively correlated, parameters It plays a negative correlation role. That is, the greater the social responsibility, the more obvious the increase in the objective function; the higher the requirements for safety, environmental protection and recall response time, the lower the objective function. The recall of new energy vehicle power batteries is unique, such as the existence of certain safety risks, environmental pollution risks and huge economic benefits. Therefore, while encouraging the recycling or recall of power batteries, countries have also issued relevant laws, regulations or standards and formulated strict and safe recall processes. Although there are huge benefits for power batteries, safety and environmental protection cannot be abandoned and unlimited profit-seeking cannot be pursued. It is precisely because of the irreplaceability of safety and environmental protection and the weak economic nature of recall that policymakers and corporate managers should rely on standard operations and scientific management to obtain appropriate benefits and implement the extended producer responsibility system to actively assume social responsibilities while paying attention to safety and environmental protection. In short, when formulating recall-related policies or standards, we cannot rely solely on the single indicator of economic benefits. We must fully consider the social safety and environmental protection aspects of the recall to ensure that power batteries can be recalled and reused safely, quickly and greenly.

[0207] In summary, a decision-making method for selecting a site for recalling power batteries of new energy vehicles of the present invention first constructs a reverse logistics network structure of power batteries of new energy vehicles including service outlets, recall outlets, recall processing centers, recall transfer centers and cascade utilization centers. Secondly, on the basis of using Fourier model to predict the recall volume of power batteries of new energy vehicles in multiple cycles, the fixed cost, testing cost, packaging cost, operation cost, transportation cost, warehousing cost of each proposed facility in the reverse logistics network structure of power batteries of new energy vehicles, as well as the impact of facilities on safety and environmental protection during operation and transportation are considered, and the safety and environmental protection risks and response time are minimized, and the economic efficiency is minimized. With the goal of maximizing benefits, a multi-period and multi-objective dynamic site selection model is constructed to determine the number, site selection, flow distribution and inventory of each target facility in the reverse logistics network structure of new energy vehicle power batteries. At the same time, this method conducts a sensitivity analysis on the site selection decision of the reverse logistics network structure of new energy vehicle power batteries based on safety and environmental protection factors, social responsibility factors and economic factors. The Fourier prediction model and the nonlinear mixed integer programming model are combined to optimize the number, site selection, flow distribution and inventory of recall outlets, recall processing centers, recall transfer centers and cascade utilization centers in the reverse logistics network structure of new energy vehicle power batteries in each period.

[0208] Although the content of the present invention has been described in detail through the above preferred embodiments, it should be appreciated that the above description should not be considered as a limitation of the present invention. After reading the above content, it will be apparent to those skilled in the art that various modifications and substitutions of the present invention will occur. Therefore, the protection scope of the present invention should be limited by the appended claims.

Claims

1. A decision-making method for selecting a recall site for a new energy vehicle power battery, characterized in that: The method comprises: S1. Construct a multi-objective facility reverse logistics network structure for new energy vehicle power batteries that takes into account recall risks; the multi-objective facilities include: recall outlets, recall processing centers, recall transfer centers, and cascade utilization centers; S2. Use the Fourier prediction model to predict the sales volume of new energy vehicles and the recall volume of power batteries in multiple cycles; S3. Construct a location selection model for multi-objective facilities in the reverse logistics network structure of new energy vehicle power batteries considering recall risks; S4. Based on the steps S2 and S3, the proposed locations of the target facilities in the reverse logistics network structure of the new energy vehicle power battery considering the recall risk are set; S5. Based on the step S4, a nonlinear mixed integer programming model is constructed to solve a global optimal solution, wherein the optimal solution is the location selection of multi-objective facilities in the reverse logistics network structure of new energy vehicle power batteries considering the recall risk; In step S3, when constructing the site selection model of the multi-objective facility, the objective is to minimize the safety and environmental risk and response time and maximize the economic benefit, and construct the objective function maxF=(SR-SET)+EB, where SR represents social responsibility impact, SET represents safety and environmental risk and response time, and EB represents economic benefit; The safety, environmental protection and response time SET of each cycle of the reverse logistics network of new energy vehicle power batteries considering recall risks include the distances between the recall outlets, recall processing centers, and recall transfer centers in each cycle, as well as the size of the cascade utilization center, and are calculated using the following formula: Among them, dt st represents the distance from the recall processing center s to the recall transfer center t, dt te represents the distance from the recall transfer center t to the cascade utilization center e, dt rs represents the distance from the recall outlet r to the recall processing center s; if the recall transit center t is established during the pth operation period, then otherwise If the recall processing center s is established during the pth operation period, then otherwise If the secondary utilization center e is established during the pth operation period, then otherwise 2. The decision-making method for selecting a recall site for a new energy vehicle power battery according to claim 1, characterized in that: The Fourier prediction model is expressed as: f(x)=a0+a1*cos(x*w)+b1*sin(x*w)+a2*cos(2x*w)+b2* sin(2x*w), where x represents the year, f(x) represents the sales volume of new energy vehicles or the recall volume of power batteries, a0, a1, a2, b1, b2 are model parameters, and w is the fundamental frequency.

3. The decision-making method for selecting a recall site for a new energy vehicle power battery according to claim 1, characterized in that: The impact SR of each cycle of the reverse logistics network of new energy vehicle power batteries considering recall risks on social responsibility includes the number of jobs created by recall outlets, recall processing centers, recall transfer centers and cascade utilization centers in each cycle, and is calculated using the following formula: in, represents the number of jobs created by recall processing center s during its operation period p, represents the number of jobs created by the recall transfer center t during the operation period p, represents the number of jobs created by the cascade utilization center e during the operation period p. If the recall transfer center t is established during the pth operation period, then otherwise If the recall processing center s is established during the pth operation period, then otherwise If the secondary utilization center e is established during the pth operation period, then otherwise 4. The decision method for selecting a recall site for a new energy vehicle power battery according to claim 1, characterized in that: The impact of each cycle of the reverse logistics network of new energy vehicle power batteries considering recall risks on the economic benefits EB includes the value generated by the new energy vehicle power batteries recalled in each cycle after being processed by the cascade utilization center, and is calculated using the following formula: EC=C1+C2+C3+C4+C5+C6+C7, in, Represents the economic income of the enterprise, represents the inventory of the recycling center e in the operating cycle p, Pr represents the value generated by the recycling of power batteries after deducting the cost, β is the recycling rate of the recycling center e, 0≤β≤1, EC represents the economic cost of the enterprise, C1 represents the sum of the construction costs of the recall processing center and the recall transfer center in each cycle, C2 represents the sum of the transportation costs between various facilities in each cycle, C3 represents the sum of the testing costs of new energy vehicle power batteries in each cycle, C4 represents the sum of the packaging costs of new energy vehicle power batteries in each cycle, C5 represents the sum of the warehousing costs of the recall processing center, recall transfer center, and recycling center in each cycle, C6 represents the sum of the labor costs of the recall processing center, recall transfer center, and recycling center in each cycle, and C7 represents the sum of the operating costs of the recall processing center, the recall transfer center, and the recycling center in each cycle.

5. The decision-making method for selecting a recall site for a new energy vehicle power battery according to claim 1, characterized in that: In the multi-objective facility location model, the constraints are set as: The pth cycle ensures that each recall outlet has a corresponding processing center; The pth cycle ensures that each selected recall processing center has a corresponding recall transfer center; The pth cycle ensures that each selected recall transfer center has a corresponding cascade utilization center; The number of power batteries shipped from the recall outlets to the recall processing center in the pth cycle is equal to the number of batteries recovered by the recall outlets; The number of new energy vehicle power batteries transported from the recall outlets to the recall processing center in the pth cycle is equal to the number of new energy vehicle power batteries transported from the recall processing center to the recall transfer center; The number of new energy vehicle power batteries transported from the recall processing center to the recall transfer center in the pth cycle is equal to the number of new energy vehicle power batteries transported from the recall transfer center to the cascade utilization center; The number of new energy vehicle power batteries shipped from the recall outlets to the recall processing center in the pth cycle is equal to the inventory of the recall processing center; The number of new energy vehicle power batteries shipped from the recall processing center to the recall transfer center in the pth cycle is equal to the inventory of the recall transfer center; The number of new energy vehicle power batteries transported from the recall transfer center to the cascade utilization center in the pth cycle is equal to the inventory of the cascade utilization center; The number of new energy vehicle power batteries delivered from the recall outlets to the recall processing center in the pth cycle does not exceed the maximum processing capacity of the recall processing center; The number of new energy vehicle power batteries transported from the recall processing center to the recall transfer center in the pth cycle does not exceed the maximum processing capacity of the recall transfer center; The number of new energy vehicle power batteries transported from the recall transfer center to the cascade utilization center in the pth cycle does not exceed the maximum processing capacity of the cascade utilization center; The number of new energy vehicle power batteries in the recall processing center in the pth cycle does not exceed the maximum inventory of the recall processing center; The number of new energy vehicle power batteries in the recall transfer center in the pth cycle does not exceed the maximum inventory of the recall transfer center; The number of new energy vehicle power batteries in the p-th cycle cascade utilization center shall not exceed the maximum inventory of the cascade utilization center; The number of recall processing centers built in the pth cycle is less than the maximum number that can be built; The number of recall transfer centers built in the pth cycle is less than the maximum number that can be built; The number of cascade utilization centers built in the pth period is less than the maximum number that can be built.