A top adjustment mechanism for a helium leak detection pre-installed box feeding device

By designing the top adjustment mechanism and using a combination of threaded structure and aluminum profile reinforcements, the problem of beam deformation of the helium leak detection pre-loading box loading device is solved, automatic opening and rapid correction are achieved, and the reliability and stability of the device are improved. sex.

CN113074173BActive Publication Date: 2024-10-22CNNC JIANZHONG NUCLEAR FUEL
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010005100.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-01-03
Publication Date
2024-10-22
Estimated Expiration
2040-01-03

AI Technical Summary

Technical Problem

The beam of the existing helium leak detection pre-packed box loading device is too long, causing it to collapse and bend in the middle, which affects the reliability of the pre-packed box and cannot be opened effectively, causing damage to product quality.

Method used

Design an overhead adjustment mechanism that connects adjusting bolts, locking bolts, connecting plates and reinforcements through a threaded structure. It uses the torque principle to realize automatic adjustment of the beam to prevent deformation, and enhances bending resistance through the combined structure of aluminum profiles and rectangular steel. ability.

Benefits of technology

It realizes the automatic opening of the helium leak detection pre-installed box, avoids the deformation of the beam, ensures the rapid correction of the device and the stability in long-term use, and improves the reliability of the device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113074173B_ABST
    Figure CN113074173B_ABST
Patent Text Reader

Abstract

The present invention belongs to the field of mechanical and automation technology, and specifically relates to a top adjustment mechanism for a helium leak detection pre-installed box feeding device. The adjusting bolt is connected to the connecting plate through a threaded structure, and the bottom of the adjusting bolt is tightly attached to the connecting plate; the locking bolt is connected to the nut in the crossbeam through a threaded structure, and the connecting plate and the crossbeam are tightly attached and compacted; the connecting plate and the adjusting bolt are connected through a threaded structure, and the locking bolt is compacted on the connecting plate, and the connecting plate is tightly attached to the crossbeam and the reinforcement respectively; the nut in the crossbeam is connected to the locking bolt and the fastening bolt through a threaded structure, and the crossbeam is tightly attached to the connecting plate and the reinforcement respectively; the reinforcement is tightly attached to the adjusting bolt, the crossbeam, and the fastening bolt respectively; the fastening bolt is connected to the nut in the crossbeam by a threaded structure, and is tightly attached to the reinforcement. The device of the present invention can automatically open the pre-installed box; the crossbeam of the device of the present invention is not easy to deform; the crossbeam of the device of the present invention can be quickly corrected after deformation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of machinery and automation, and in particular relates to a top adjustment mechanism of a helium leak detection pre-installed box feeding device. Background Art

[0002] Fuel assemblies are the "core" of nuclear power plants, and their quality is directly related to whether nuclear power plants can operate safely and efficiently. At present, Tianwan Nuclear Power Plant uses high-burnup TVS-2M assemblies. Before the fuel rods are assembled into fuel assemblies, high-temperature helium leak tests are carried out to test the helium pressure inside the fuel rods to determine whether the sealing meets the requirements.

[0003] Before the high-temperature helium leak detection, the fuel rods need to be loaded into pre-loaded boxes according to the number of fuel rods. The pre-loading rod action is performed using a helium leak detection pre-loaded box loading device, which is an important auxiliary equipment of the high-temperature helium leak detection equipment.

[0004] Foreign countries including France, the United States, Germany, etc. all use room temperature to detect the sealing of fuel rods. Russia uses high-temperature helium leak detection for detection and has a special helium leak detection pre-installed box loading device. In my country, only the TVS-2M and fast reactor fuel rods produced for Tianwan use high-temperature helium leak detection for detection. The rest of the products use room temperature detection technology and equipment.

[0005] In recent years, Russia has also shown a trend of adopting normal temperature leak detection.

[0006] The original helium leak detection pre-installed box loading device was independently developed by relevant technicians based on Russian equipment and put into use in 2000.

[0007] As the device was used, its reliability began to decline, and product quality was sometimes damaged. Although Russia currently has some TVS-2M fuel rods that are tested at room temperature, the high-temperature helium detection process is a more mature process route.

[0008] The paddle on the original pre-loading box device is installed on a hollow beam about 4 meters in length. The purpose of the paddle is to open the pre-loading box (the pre-loading box is a rectangular box with 16 layers, each layer can store 0 to 21 fuel rods, and one side is open to enable the fuel rods to be loaded.

[0009] Method: Insert the pick into the pre-installed box, open each layer of stainless steel sheet of the pre-installed box, and then load the fuel rods). Loading the fuel rods is the main function of the helium leak detection pre-installed box loading device.

[0010] Because the beam is too long and is supported only on both sides (if it is supported in the middle, it will cause mechanical interference with the fuel rods rolling into the pre-installed box, so there can only be supports at both ends of the beam), forming a simply supported beam. Under the influence of the deadweight of the beam and the paddle, and the frequent movement of the beam during use, the middle of the beam gradually collapses and bends over time, making the reliability of opening the pre-installed box poor, or even impossible to open the pre-installed box. Summary of the invention

[0011] The purpose of the present invention is to provide a top adjustment mechanism for a helium leak detection pre-installed box feeding device in view of the above defects in the prior art, so as to solve the problem that the pre-installed box cannot be opened and avoid deformation and bending of the crossbeam.

[0012] The technical solution of the present invention is as follows:

[0013] A top adjustment mechanism for a helium leak detection pre-installed box feeding device, wherein the adjusting bolt is connected to the connecting plate through a threaded structure, and the bottom of the adjusting bolt is tightly attached to the connecting plate;

[0014] The locking bolt is connected to the nut in the beam through a threaded structure, and the connecting plate and the beam are pressed tightly together;

[0015] The connecting plate is connected to the adjusting bolts through a threaded structure, the locking bolts are pressed against the connecting plate, and the connecting plate is respectively pressed against the crossbeam and the reinforcement;

[0016] The nuts in the crossbeam are respectively connected with the locking bolts and the fastening bolts through threaded structures, and the crossbeam is respectively tightly attached to the connecting plate and the reinforcement;

[0017] The reinforcement parts are respectively tightly attached to the adjusting bolts, the cross beams and the fastening bolts;

[0018] The fastening bolts and the nuts in the cross beam are connected by a threaded structure and are tightly attached to the reinforcement.

[0019] The adjusting bolt is used to adjust the beam. When the middle part of the beam collapses and bends, rotate the adjusting bolt. The adjusting bolt applies a downward force to the reinforcement. The reinforcement is connected to the beam through the fastening bolts, with the connecting plate as the reference plane. At this time, the beam will be subjected to an upward torque. When the adjusting bolt is rotated to a certain position, the middle of the beam is pushed up, thereby realizing manual recovery of the beam after deformation.

[0020] The adjusting bolt is used to adjust the beam, when the middle part of the beam collapses and bends;

[0021] The adjusting bolt is connected to the connecting plate through a threaded structure, and the bottom of the adjusting bolt is in direct contact with the reinforcement; the locking bolt is used to fasten the beam to the connecting plate, and the locking bolt is connected to the beam with a threaded structure, wherein the nut is in the beam groove so as to be connected and locked with the locking bolt.

[0022] The adjusting bolt and locking bolt must be parallel.

[0023] The connecting plate is the basic workpiece for realizing torque adjustment and provides a reference surface. The holes corresponding to the adjusting bolts in the connecting plate are threaded holes for locking and adjustment, while the holes corresponding to the locking bolts in the connecting plate are through holes for tightening the locking bolts and the nuts inside the beam so as to press the connecting plate and the beam tightly.

[0024] The crossbeam is made of aluminum profile structure, and there are mounting holes in four directions of the aluminum profile.

[0025] The crossbeam fixes the connecting plate and the reinforcement thereon by means of a bolt structure respectively; the reinforcement is mainly used to enhance the crossbeam's resistance to bending deformation. By tightening the bolts, when the crossbeam is deformed, the reinforcement will also tend to deform, thereby jointly resisting the bending deformation, thereby achieving the goal of strengthening the crossbeam 4's resistance to deformation.

[0026] There is a through hole in the middle of the reinforcement to ensure that after the fastening bolts and the nuts in the beam are connected, the beam and the reinforcement can be tightly pressed; the fastening bolts are mainly used to fix the reinforcement on the beam, and are connected to the nuts in the beam through a threaded structure so that the beam and the reinforcement can be tightly pressed.

[0027] The tightening bolts and adjusting bolts remain vertical.

[0028] The beneficial effects of the present invention are:

[0029] (1) The device of the present invention can automatically open the pre-installed box;

[0030] (2) The cross beam of the device of the present invention is not easily deformed;

[0031] (3) The cross beam of the device of the present invention can be quickly corrected after deformation. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 It is a schematic diagram of the structure of the top adjustment mechanism of the present invention.

[0033] In the figure: 1—adjusting bolt; 2—locking bolt; 3—connecting plate; 4—crossbeam; 5—reinforcement; 6—fastening bolt. DETAILED DESCRIPTION

[0034] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0035] As shown in the attached drawings, a top adjustment mechanism of a helium leak detection pre-installed box feeding device is provided, wherein the adjusting bolt 1 is connected to the connecting plate 3 through a threaded structure, and the bottom of the adjusting bolt 1 is tightly attached to 6.

[0036] The locking bolt 2 is connected to the nut in the cross beam 4 through a threaded structure, and the connecting plate 3 and the cross beam 4 are pressed tightly together.

[0037] The connecting plate 3 is connected to the adjusting bolt 1 through a threaded structure, the locking bolt is pressed on the connecting plate 3, and the connecting plate 3 is tightly attached to the cross beam 4 and the reinforcement 5 respectively.

[0038] The nuts in the cross beam 4 are respectively connected to the locking bolt 2 and the fastening bolt 6 through a threaded structure, and the cross beam 4 is respectively in close contact with the connecting plate 3 and the reinforcement 5 .

[0039] The reinforcement member 5 is respectively tightly attached to the adjusting bolt 1 , the cross beam 4 , and the fastening bolt 6 .

[0040] The fastening bolt 6 is connected to the nut in the cross beam 4 by a threaded structure and is tightly attached to the reinforcement member 5 .

[0041] The adjusting bolt 1 is used to adjust the cross beam 4. When the middle part of the cross beam 4 collapses and bends, it can be restored in the following way: rotate the adjusting bolt 1, the adjusting bolt 1 applies a downward force to the reinforcement 5, the reinforcement 5 is connected to the cross beam 4 through the fastening bolt 6, and the connecting plate 3 is used as the reference surface. At this time, the cross beam 4 will be subjected to an upward torque. When the adjusting bolt 1 is rotated to a certain position, the middle part of the cross beam 4 is pushed up, thereby realizing manual restoration of the cross beam 4 after deformation;

[0042] The adjusting bolt 1 is connected to the connecting plate 3 through a threaded structure, and the bottom of the adjusting bolt 1 is in direct contact with the reinforcing member 5. The locking bolt 2 is used to fasten the crossbeam 4 to the connecting plate 3. Only after tightening to form a whole can the principle of torque be used for adjustment. The locking bolt 2 is connected to the crossbeam 4 with a threaded structure, and the nut is in the groove of the crossbeam 4 so as to be connected and locked with the locking bolt.

[0043] The adjusting bolt 1 and the locking bolt 2 must be parallel.

[0044] The connecting plate 3 is the basic workpiece for realizing torque adjustment and provides a reference surface. The hole corresponding to the adjusting bolt 1 at the connecting plate 3 is a threaded hole for locking and adjustment, and the hole corresponding to the locking bolt 2 at the connecting plate 3 is a through hole for tightening the locking bolt 2 and the nut located inside the crossbeam 4 so as to press the connecting plate 3 and the crossbeam 4 tightly. If the corresponding part of the locking bolt 2 is a threaded hole, the connecting plate 3 and the crossbeam 4 cannot be pressed tightly.

[0045] The crossbeam 4 adopts an aluminum profile structure, which is lighter than stainless steel or other metal materials and is conducive to weight reduction. In addition, the aluminum profile has mounting holes in four directions for installation. In addition, the aluminum profile is a universal part and does not require special processing. Therefore, this is also the reason why the aluminum profile is directly selected as the crossbeam.

[0046] As shown in the figure, the cross beam 4 fixes the connecting plate 3 and the reinforcement 5 thereon respectively through the bolt structure. The reinforcement 5 is mainly used to enhance the cross beam 4's ability to resist bending deformation. By tightening the bolts 6, when the cross beam 4 deforms, the reinforcement 5 will also have a tendency to deform, thereby jointly resisting bending deformation, thereby achieving the ability of the cross beam 4 to resist deformation.

[0047] The middle of the reinforcement member 5 is a through hole to ensure that after the fastening bolt 6 is connected with the nut in the cross beam 4, the cross beam 4 and the reinforcement member 5 can be tightly pressed. The fastening bolt 6 is mainly used to fix the reinforcement member 5 on the cross beam 4, and is connected with the nut in the cross beam 4 through a threaded structure, so as to tightly press the cross beam 4 and the reinforcement member 5. The fastening bolt 6 and the adjusting bolt 1 are kept vertical.

[0048] Before using the mechanism, it should be installed and adjusted. The installation is shown in the figure. Adjustment needs to ensure that the bottom of the adjusting bolt 1 is tightly against the reinforcement 5, the locking bolt 2 presses the connecting plate 3 tightly against the beam 4, and the tightening bolt 6 presses the reinforcement 5 tightly against the beam 4.

[0049] When the cross beam 4 is bent and deformed (collapses downward in the middle to become a U shape), the adjusting bolt 1 is rotated with the hexagon socket bolt. The basic principle of torque is used to apply downward force to the reinforcement 5 by the adjusting bolt 1. Since the locking bolt 2 presses the connecting plate 3 and the cross beam 4 together to form a whole, the reinforcement 5 cannot move downward and can only generate a counterclockwise torque. The torque is transmitted to the cross beam 4 through the fastening bolt, thereby realizing the anti-bending and adjustment of the cross beam 4.

[0050] (1) The crossbeam is made of aluminum profile, which has the advantages of light weight, multiple mounting holes, universal parts, and reduced processing. Most importantly, it is very light, which effectively reduces the bending deformation caused by the crossbeam being too long and too heavy.

[0051] (2) Rectangular steel is used as a reinforcement, and the reinforcement and the crossbeam are tightened by bolts to form a whole. In order for the crossbeam to deform, the reinforcement and the crossbeam must be overcome at the same time. In addition, the rectangular steel structure itself is a structure that resists bending deformation, which also enhances the anti-deformation ability. The main reason why it is not directly used for the crossbeam is to reduce weight.

[0052] (3) By utilizing the torque principle, the adjustment after deformation is achieved by rotating the adjusting bolt, avoiding disassembly and correction after deformation, and realizing quick manual adjustment.

Claims

1. A top adjustment mechanism for a helium leak detection pre-installed box feeding device, wherein the adjusting bolt is connected to the connecting plate through a threaded structure, and the bottom of the adjusting bolt is tightly attached to the top of the reinforcement member; The locking bolt is connected to the nut in the beam through a threaded structure, and the connecting plate and the beam are pressed tightly together; Features: The locking bolts are pressed firmly on the connecting plate, and the connecting plate is respectively pressed tightly against the cross beam and the reinforcement; The nuts in the crossbeam are respectively connected with the locking bolts and the fastening bolts through threaded structures, and the crossbeam is respectively tightly attached to the connecting plate and the reinforcement; The reinforcement parts are respectively tightly attached to the adjusting bolts, the cross beams and the fastening bolts; The adjusting bolt is used to adjust the beam. When the middle part of the beam collapses and bends, the adjusting bolt is rotated. The adjusting bolt applies a downward force to the reinforcement. The reinforcement is connected to the beam through the fastening bolts, and the connecting plate is used as the reference surface. At this time, the beam will be subjected to an upward torque. When the adjusting bolt is rotated to a certain position, the middle of the beam is pushed up, thereby realizing manual recovery of the beam after deformation. The adjusting bolt and locking bolt must be parallel; The connecting plate is the basic workpiece for realizing torque adjustment and provides a reference surface. The holes corresponding to the adjusting bolts on the connecting plate are threaded holes for locking and adjustment, while the holes corresponding to the locking bolts on the connecting plate are through holes for tightening the locking bolts and the nuts inside the crossbeam so as to compact and fit the connecting plate and the crossbeam tightly. The crossbeam fixes the connecting plate and the reinforcement on it through bolt structures respectively; the reinforcement is mainly used to enhance the crossbeam's ability to resist bending deformation. By fastening the bolts, when the crossbeam deforms, the reinforcement will also tend to deform, thereby jointly resisting bending deformation, thereby enhancing the crossbeam's ability to resist deformation; There is a through hole in the middle of the reinforcement to ensure that after the fastening bolts and the nuts in the beam are connected, the beam and the reinforcement can be pressed tightly together; The tightening bolts and adjusting bolts remain vertical.

2. The top adjustment mechanism of the helium leak detection pre-installed box feeding device according to claim 1, characterized in that: The nut is in the crossbeam groove so as to be connected and locked with the locking bolt.

3. The top adjustment mechanism of the helium leak detection pre-installed box feeding device according to claim 1, characterized in that: The crossbeam is made of aluminum profile structure, and there are mounting holes in four directions of the aluminum profile.