A rolling line anchor bolt pre-embedded fixing device and method

The fixation device set up by angle steel and channel steel, combined with welded steel bars and concrete fixation, solves the problem of equipment fixation accuracy and stability in the steel rolling mill, achieves high-precision installation and improved stability, and supports subsequent dismantling and recycling.

CN113186971BActive Publication Date: 2024-10-18CHINA MCC5 GROUP CORP LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202110629976.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-06-07
Publication Date
2024-10-18
Estimated Expiration
2041-06-07

AI Technical Summary

Technical Problem

In steel rolling mills, the leveling requirements of equipment are different and the lines are long, resulting in a large number and complex types of embedded bolts in the equipment foundation, making installation difficult, and ground vibration may cause bolts to shift. It is difficult to ensure installation accuracy and stability with existing technology. sex.

Method used

Angle steel and channel steel are used to set up the fixing device, and fixed steel bars and horizontal steel bars are welded to form a strong rectangular structure. The position of the bolt holes can be adjusted as needed, and concrete is used to fix it to improve stability, and the device can be dismantled.

Benefits of technology

It achieves high-precision equipment fixation, improves installation stability and overall structural stability, and can be recycled after use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113186971B_ABST
    Figure CN113186971B_ABST
Patent Text Reader

Abstract

The present invention discloses a pre-embedded fixing device and method for anchor bolts of a rolling line, comprising a fixing mold for fixing on the ground along the rolling line direction, the fixing mold comprising a first fixing structure and a second fixing structure which are used to be arranged on the left and right sides of the center line of the rolling line and have the same structure; the first fixing structure comprises a vertical angle steel, a horizontal angle steel and an oblique support angle steel, one end of the vertical angle steel is used to be vertically fixed on the ground, and the other end is vertically fixed to the horizontal angle steel, and the oblique support angle steel is arranged on the diagonal of the rectangular structure; the fixing mold also comprises a fixed steel bar and a horizontal steel bar, the height of the horizontal steel bar is lower than the height of the horizontal angle steel, one end of the fixed steel bar is fixed to the horizontal steel bar, and the other end passes through the first support steel bar to be provided with an extended fixed end, the extended fixed ends of the first fixing structure and the second fixing structure are jointly fixed with a channel steel, and the channel steel is provided with bolt holes for fixing the rolling line equipment; the first fixing structure and the second fixing structure are arranged as a fixed integrated structure by pouring concrete.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of equipment fixation of a rolling mill plant, and in particular to a pre-embedded fixing device and method for anchor bolts of a rolling mill. Background Art

[0002] In the production process of steel mills, due to the different horizontal requirements of equipment and the long equipment lines in rolling mills, the number of pre-buried bolts in the equipment foundation is large, the models and specifications are complex and changeable, the geometric shapes of bolt distribution vary greatly, and there are many bolts on the side; the bolt elevation varies complexly; a large number of imported equipment cannot be cut or expanded after arrival, which greatly increases the difficulty of bolt embedding; ensuring the embedding accuracy of bolts is a difficulty of this project, which directly determines the quality and progress requirements of the project; currently, the equipment is mostly fixed on the factory floor with bolts directly, and the ground vibration may cause the bolts to shift, and the installation is difficult and the installation accuracy is low. Therefore, there is an urgent need for a pre-buried fixing device and method for rolling line anchor bolts with high installation accuracy and low installation difficulty. Summary of the invention

[0003] The present invention aims to provide a pre-embedded fixing device and method for anchor bolts of a rolling line. The fixing device is constructed using angle steel and channel steel. The fixed steel bars and horizontal steel bars are firmly welded to ensure the firmness and stability of the fixing device. The fixing device can be installed in accordance with actual conditions. If the position is offset, the position of the bolt hole of the channel steel can also be adjusted to ensure high installation accuracy. At the same time, concrete is poured after installation to improve the stability of the overall structure. The fixing device can be dismantled after use.

[0004] The embodiment of the present invention is achieved as follows:

[0005] A pre-embedded fixing device for anchor bolts of a rolling line, comprising a fixed mold for fixing on the ground along the rolling line direction, the fixed mold comprising a first fixed structure and a second fixed structure for being arranged on the left and right sides of the center line of the rolling line and having the same structure; the first fixed structure comprises a vertical angle steel, a horizontal angle steel and an oblique support angle steel, one end of the vertical angle steel is used to be vertically fixed on the ground, and the other end is vertically fixed to the horizontal angle steel, the number of the vertical angle steels is two, the vertical angle steel, the horizontal angle steel and the ground are enclosed to form a rectangular fixed structure, and the oblique support angle steel is arranged on the diagonal of the rectangular structure; the fixed mold also comprises a fixed steel bar and a horizontal steel bar, the height of the horizontal steel bar is lower than the height of the horizontal angle steel, one end of the fixed steel bar is fixed on the horizontal steel bar, and the other end passes through the first support steel bar to be provided with an extended fixed end, the extended fixed ends of the first fixed structure and the second fixed structure are jointly fixed with a channel steel, a connecting steel bar is arranged between the horizontal steel bars of the first fixed structure and the second fixed structure, and a bolt hole for fixing the rolling line equipment is arranged on the channel steel; the first fixed structure and the second fixed structure are arranged as a fixed integrated structure by pouring concrete. Angle steel and channel steel are used to set up the fixing device, and the fixing steel bars and horizontal steel bars are welded firmly to ensure the firmness and stability of the fixing device. The fixing device can be installed according to the actual situation. If the position is offset, the position of the bolt hole of the channel steel can also be adjusted to achieve high installation accuracy. At the same time, pouring concrete after installation is completed to improve the stability of the overall structure, and it can be dismantled after use.

[0006] Preferably, an embedded steel plate is arranged on the ground along the rolling line direction, and the vertical angle steel is detachably fixed to the embedded steel plate, so as to facilitate installation and removal.

[0007] Preferably, the number of the oblique support angle steels in the first fixed structure is two, and they are cross-arranged on the diagonal line of the rectangular fixed structure to improve the stability of the overall structure.

[0008] Preferably, the number of the fixed steel bars in the first fixed structure is two, and they are arranged parallel to each other.

[0009] Preferably, the channel steel is inverted on the transverse angle steels on both sides, and the extended fixed ends of the fixed steel bars are provided with threads for fixing the transverse angle steels through nuts.

[0010] Preferably, the transverse angle steels of the first fixing structure and the second fixing structure are also fixed by transverse supporting angle steels, and the ends of the transverse supporting angle steels are arranged at the intersection of the transverse angle steels and the vertical angle steels.

[0011] A method for pre-embedding and fixing anchor bolts of a rolling line is also provided, comprising the above-mentioned fixing device, and further comprising the following steps:

[0012] S1: fixing the vertical angle steel, the transverse angle steel and the diagonal support angle steel into a first fixed structure and a second fixed structure;

[0013] S2: Setting fixed steel bars, horizontal steel bars and connecting steel bars to fix the first fixed structure and the second fixed structure into one;

[0014] S3: pouring concrete to further fix the first fixed structure and the second fixed structure;

[0015] S4: Measure and mark the center line of the rolling line to determine the installation position of the equipment and the position of the corresponding bolt holes;

[0016] S5: pre-embedded steel plates are arranged at positions corresponding to the bolt holes to fix the first fixed structure and the second fixed structure to the ground;

[0017] S6: drilling bolt holes on the channel steel, and installing the channel steel on the first fixed structure and the second fixed structure;

[0018] S7: Install the wire rolling equipment on the channel steel, and dismantle the concrete structure, the first fixed structure, and the second fixed structure in sequence after use for recycling.

[0019] Preferably, in step S4, a rolling center line is released on the rolling platform, and wire racks are installed at both ends to pull steel wires, and then the center lines of each equipment foundation are separated from the rolling center line for positioning the embedded steel plates of the installation fixtures.

[0020] Preferably, in step S4, the bolt positions are marked in sections using a total station. First, the total station is used to place points at both ends in the longitudinal direction, and then an ink line is used to draw lines to determine the longitudinal positions of the embedded bolts in the same row; then the total station is used to perform transverse positioning of each embedded bolt, and the surveyor marks the measured position with a wipe-resistant oily marker, and uses a marker to strengthen the marking of the longitudinal position of the bolt; after positioning is completed, the bolt installation hole is made on the channel steel by gas cutting, and the hole center error cannot exceed 2mm. For ease of adjustment, the diameter of the hole is 2mm larger than the bolt.

[0021] Preferably, the bolts are passed through the channel steel according to the positioning holes, the nuts are put on, the positions are adjusted according to the center lines of the bolts, and then the nuts are spot welded to the channel steel fixing frames; after the bolts of the entire equipment foundation are installed, the surveying personnel re-measure whether the bolt installation accuracy meets the requirements; after the re-measurement, the installation accuracy that does not meet the requirements is adjusted; until all bolts fully meet the requirements.

[0022] Due to the adoption of the above technical scheme, the beneficial effects of the present invention include: a pre-embedded fixing device for anchor bolts of a rolling line of the present invention includes a fixing mold for fixing on the ground along the rolling line direction, the fixing mold includes a first fixing structure and a second fixing structure for being arranged on the left and right sides of the center line of the rolling line and having the same structure; the first fixing structure includes a vertical angle steel, a horizontal angle steel and an oblique support angle steel, one end of the vertical angle steel is used to be vertically fixed on the ground, and the other end is vertically fixed to the horizontal angle steel, the number of vertical angle steels is two, the vertical angle steel, the horizontal angle steel and the ground are enclosed to form a rectangular fixed structure, and the oblique support angle steel is arranged on the diagonal of the rectangular structure; the fixing mold also includes a fixed steel bar and a horizontal steel bar, the height of the horizontal steel bar is lower than the height of the horizontal angle steel, one end of the fixed steel bar is fixed on the horizontal steel bar, and the other end passes through the first support steel bar to be provided with an extended fixed end, the extended fixed ends of the first fixed structure and the second fixed structure are jointly fixed with a channel steel, a connecting steel bar is arranged between the horizontal steel bars of the first fixed structure and the second fixed structure, and a bolt hole for fixing the rolling line equipment is arranged on the channel steel; the first fixed structure and the second fixed structure are arranged as a fixed integrated structure by pouring concrete. Angle steel and channel steel are used to set up the fixing device, and the fixing steel bars and horizontal steel bars are welded firmly to ensure the firmness and stability of the fixing device. The fixing device can be installed according to the actual situation. If the position is offset, the position of the bolt hole of the channel steel can also be adjusted to achieve high installation accuracy. At the same time, pouring concrete after installation is completed to improve the stability of the overall structure, and it can be dismantled after use. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0024] Figure 1 It is a side view structural schematic diagram of the present invention;

[0025] Figure 2 It is a schematic diagram of the top structure of the present invention.

[0026] Specific element symbol description: 1 concrete; 2 vertical angle steel; 3 horizontal angle steel; 4 channel steel; 5 inclined support angle steel; 6 fixed steel bars; 7 horizontal steel bars; 8 connecting steel bars; 9 first fixed structure; 10 second fixed structure; 41 bolt hole. DETAILED DESCRIPTION

[0027] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0028] The following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0029] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0030] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the product of the invention is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0031] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0032] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0033] Example 1: Please refer to Figure 1 and Figure 2The present embodiment is a rolling line anchor bolt embedded fixing device, including a mold for fixing on the ground along the rolling line direction. The mold includes a first fixing structure 9 and a second fixing structure 10 which are arranged on the left and right sides of the rolling line centerline and have the same structure; the first fixing structure 9 includes a vertical angle steel 2, a horizontal angle steel 3 and an oblique support angle steel 5, one end of the vertical angle steel 2 is used to be vertically fixed on the ground, and the other end is vertically fixed to the horizontal angle steel 3, and the vertical angle steel 2 The number is two, the vertical angle steel 2, the horizontal angle steel 3 and the ground are enclosed to form a rectangular fixed structure, and the oblique support angle steel 5 is arranged on the diagonal of the rectangular structure; the fixed mold also includes fixed steel bars 6 and horizontal steel bars 7, the height of the horizontal steel bar 7 is lower than the height of the horizontal angle steel 3, one end of the fixed steel bar 6 is fixed on the horizontal steel bar 7, and the other end passes through the first support steel bar to be provided with an extended fixed end, the first fixed structure 9 and the second fixed structure 10 are jointly fixed with the extended fixed end of the channel steel 4, and the horizontal steel bars 7 of the first fixed structure 9 and the second fixed structure 10 are provided with connecting steel bars 8, and the channel steel 4 is provided with bolt holes 41 for fixing the rolling equipment; the first fixed structure 9 and the second fixed structure 10 are set as a fixed integrated structure by pouring concrete 1. The fixing device is set up using angle steel and channel steel 4, and the fixed steel bars 6 and the horizontal steel bars 7 are welded firmly to ensure the firmness and stability of the fixing device. The fixing device can be installed according to the actual situation. If the position is offset, the position of the bolt hole 41 of the channel steel 4 can also be adjusted to achieve high installation accuracy. At the same time, after the installation is completed, concrete 1 is poured to improve the stability of the overall structure, and it can be dismantled after use.

[0034] Embodiment 2: In this embodiment, embedded steel plates are provided on the ground along the rolling line direction, and the vertical angle steels 2 are detachably fixed to the embedded steels. It is convenient for installation and removal. The number of the inclined support angle steels 5 in the first fixed structure 9 of this embodiment is two, and they are cross-arranged on the diagonal of the rectangular fixed structure. The stability of the overall structure is improved. The number of the fixed steel bars 6 in the first fixed structure 9 of this embodiment is two, and they are arranged parallel to each other. The channel steel 4 of this embodiment is inverted on the transverse angle steels 3 on both sides, and the extended fixed ends of the fixed steel bars 6 are provided with threads to fix the transverse angle steels 3 through nuts. The transverse angle steels 3 of the first fixed structure 9 and the second fixed structure 10 of this embodiment are also fixed by transverse support angle steels, and the ends of the transverse support angle steels are arranged at the intersection of the transverse angle steels 3 and the vertical angle steels 2.

[0035] Embodiment 3: This embodiment also provides a method for pre-embedded fixing of anchor bolts for a rolling line, including the above-mentioned fixing device, and also including the following steps: S1: fix the vertical angle steel 2, the horizontal angle steel 3 and the inclined support angle steel 5 into a first fixed structure 9 and a second fixed structure 10; S2: set fixing steel bars 6, horizontal steel bars 7 and connecting steel bars 8 to fix the first fixed structure 9 and the second fixed structure 10 as a whole; S3: pour concrete 1 to further fix the first fixed structure 9 and the second fixed structure 10; S4: measure and mark the center line of the rolling line, determine the installation position of the equipment and the position of the corresponding bolt hole 41; S5: set embedded steel plates corresponding to the positions of the bolt holes 41, and fix the first fixed structure 9 and the second fixed structure 10 to the ground; S6: open bolt holes 41 on the channel steel 4, and install the channel steel 4 to the first fixed structure 9 and the second fixed structure 10; S7: install the rolling line equipment on the channel steel 4, and dismantle the concrete 1 structure, the first fixed structure 9 and the second fixed structure 10 in turn after use for recycling.

[0036] Embodiment 4: In step S4 of this embodiment, the rolling center line is released on the rolling platform, and the wire racks are installed at both ends to pull the steel wire, and then the center line of each equipment foundation is separated from the rolling center line to locate the embedded steel plate for installing the fixing device. In step S4 of this embodiment, the bolt positions are marked in sections using a total station, and points are first placed at both ends of the longitudinal direction using a total station, and then the longitudinal position of the embedded bolts in the same row is determined by using an ink line to draw lines; then the total station is used to perform the transverse positioning of each embedded bolt, and the surveyor marks the measured position with a wipe-resistant oily marker pen, and uses a marker pen to strengthen the marking of the longitudinal position of the bolt; after the positioning is completed, the bolt installation hole is made on the channel steel 4 by gas cutting, and the hole center error cannot exceed 2mm. For the convenience of adjustment, the diameter of the hole is 2mm larger than the bolt. In this embodiment, the bolts are passed through the channel steel 4 according to the positioning holes, the nuts are put on, and the positions are adjusted according to the center lines of the bolts before the nuts are spot welded to the fixing frames of the channel steel 4. After the bolts of the entire equipment foundation are installed, the surveying personnel re-measure whether the bolt installation accuracy meets the requirements. After the re-measurement, the installation accuracy that does not meet the requirements is adjusted until all the bolts fully meet the requirements.

[0037] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A pre-embedded fixing device for a rolling line anchor bolt, characterized in that: The invention comprises a fixed mold for fixing on the ground along the rolling line direction, wherein the fixed mold comprises a first fixed structure and a second fixed structure which are used to be arranged on the left and right sides of the center line of the rolling line and have the same structure; the first fixed structure comprises a vertical angle steel, a horizontal angle steel and an oblique support angle steel, one end of the vertical angle steel is used to be vertically fixed on the ground, and the other end is vertically fixed to the horizontal angle steel, the number of the vertical angle steels is two, the vertical angle steel, the horizontal angle steel and the ground are enclosed to form a rectangular fixed structure, and the oblique support angle steel is arranged on the diagonal of the rectangular fixed structure; the fixed mold also comprises a fixed steel bar and a horizontal steel bar, the height of the horizontal steel bar is lower than the height of the horizontal angle steel, one end of the fixed steel bar is fixed on the horizontal steel bar, and the other end passes through the first support steel bar to be provided with an extended fixed end, the extended fixed ends of the first fixed structure and the second fixed structure are jointly fixed with a channel steel, a connecting steel bar is arranged between the horizontal steel bars of the first fixed structure and the second fixed structure, and a bolt hole for fixing the rolling line equipment is arranged on the channel steel; the first fixed structure and the second fixed structure are arranged as a fixed integrated structure by pouring concrete; An embedded steel plate is arranged on the ground along the rolling line direction, and the vertical angle steel is detachably fixed to the embedded steel plate; The number of the oblique support angle steels in the first fixed structure is two, and they are cross-arranged on the diagonal line of the rectangular fixed structure; The number of the fixed steel bars in the first fixed structure is two, and they are arranged parallel to each other; The channel steel is buckled on the transverse angle steels on both sides, and the extended fixed end of the fixed steel bar is provided with a thread to fix the transverse angle steel through a nut; The transverse angle steels of the first fixing structure and the second fixing structure are also fixed by transverse supporting angle steels, and the ends of the transverse supporting angle steels are arranged at the intersections of the transverse angle steels and the vertical angle steels.

2. A method for pre-embedding and fixing anchor bolts of a rolling line, characterized in that: The fixing device according to claim 1 further comprises the following steps: S1: fixing the vertical angle steel, the transverse angle steel and the diagonal support angle steel into a first fixed structure and a second fixed structure; S2: Setting fixed steel bars, horizontal steel bars and connecting steel bars to fix the first fixed structure and the second fixed structure into one; S3: pouring concrete to further fix the first fixed structure and the second fixed structure; S4: Measure and mark the center line of the rolling line to determine the installation position of the equipment and the position of the corresponding bolt holes; S5: pre-embedded steel plates are arranged at positions corresponding to the bolt holes to fix the first fixed structure and the second fixed structure to the ground; S6: drilling bolt holes on the channel steel, and installing the channel steel on the first fixed structure and the second fixed structure; S7: Install the wire rolling equipment on the channel steel, and dismantle the concrete structure, the first fixed structure, and the second fixed structure in sequence after use for recycling.

3. The method for pre-embedding and fixing the rolling line anchor bolts according to claim 2 is characterized in that: In step S4, the rolling center line is released on the rolling platform, and wire racks are installed at both ends to pull the steel wire, and then the center line of each equipment foundation is divided from the rolling center line to locate the embedded steel plate of the installation fixture.

4. The method for pre-embedding and fixing the rolling line anchor bolts according to claim 2, characterized in that: In step S4, the bolt positions are marked in sections using a total station. First, the total station is used to place points at both ends of the longitudinal direction, and then the ink line is used to draw lines to determine the longitudinal positions of the embedded bolts in the same row; then the total station is used to perform the transverse positioning of each embedded bolt, and the surveyor marks the measured position with a wipe-resistant oily marker, and uses a marker to strengthen the marking of the longitudinal position of the bolt; after the positioning is completed, the bolt installation hole is made on the channel steel by gas cutting, and the hole center error cannot exceed 2mm. For the convenience of adjustment, the diameter of the hole is 2mm larger than the bolt.

5. The method for pre-embedding and fixing the rolling line anchor bolts according to claim 2, characterized in that: Bolts are passed through the channel steel according to the positioning holes, nuts are put on, and the positions are adjusted according to the center lines of the bolts before spot welding the nuts on the channel steel fixing frames. After the bolts of the entire equipment foundation are installed, the surveyors will re-measure whether the bolt installation accuracy meets the requirements. After the re-measurement, adjustments will be made to the installation accuracy that does not meet the requirements until all bolts fully meet the requirements.

Citation Information

Patent Citations

  • Rolling line foundation bolt pre-embedding fixing device

    CN215801769U