A pollution-free cleaning method for removing titanium sponge after production
By taking the method of clean and honesty, the problems of impurities scattering and secondary pollution during the cleaning and removal process of titanium sponge are solved, and pollution-free clean removal is achieved, improving product quality and safety.
Patent Information
- Application Number
- CN202110673321.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-06-17
- Publication Date
- 2025-03-04
- Estimated Expiration
- 2041-06-17
AI Technical Summary
The existing pollution-free cleaning and removal method after the production of titanium sponge is likely to cause the scattering of low-priced titanium particles of black powder during the cleaning process, which may cause secondary pollution and increase impurities, affecting product quality.
The method of removing the magnesium chloride on the surface of the titanium lump is used to reverse the reaction kettle pot, and the head and hanging ears are used to quickly remove the large cover, fill the argon to clean up impurities, and clean the magnesium chloride crystals on the surface of the titanium lump in the upside down state, and finally the titanium and titanium lumps are taken in the clean state.
It effectively prevents secondary pollution of black powder and low-priced items, reduces the risk of impurities entering titanium lumps, improves the yield and appearance quality of sponge titanium, and ensures the safety of the production process.
Smart Images

Figure CN113215417B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of titanium sponge production, and in particular to a method for removing titanium sponge cleanly after production without pollution. Background Art
[0002] In the current production method of sponge titanium, sponge titanium undergoes a chemical reaction in a closed container, using liquid magnesium to reduce liquid titanium tetrachloride to generate sponge titanium. This process is a disproportionation reaction. During the reaction process, the existence of a cold zone in the reactor; the reaction between steam and steam between the raw materials; especially in the later stage when the amount of magnesium is insufficient and the replacement reaction is not thorough, low-priced substances, commonly known as "black powder", will be generated. Although sponge titanium has a secondary reaction during the formation process, some black powder low-priced titanium particles that objectively do not undergo a secondary reaction will be scattered in the gaps between the container connections, such as the upper surface of the reactor flange; the gap between the large cover and the reactor wall. Another part is scattered on the climbing titanium and titanium lumps. This part of black powder and low-priced substances are flammable and easy to absorb moisture. When taking out the titanium lumps, if these substances exist, there will be a direct risk of danger and pollution of the titanium lumps. In addition, the climbing titanium formed near the pot mouth of the reactor often contains high levels of oxygen and nitrogen impurities. If this part of the material is not cleaned up in advance, once small particles fall into the pores of the titanium lump when taking this part of the material, it will be difficult to clean and select, which will invisibly increase the impurity content of the titanium lump and affect product quality.
[0003] In the existing method for removing titanium sponge from the production process without pollution or incomplete cleaning, some black powder and low-price titanium particles that have not undergone secondary reaction are easily scattered on the wall-climbing titanium and titanium lumps during the cleaning process or when the cleaning is not thorough. This may cause secondary pollution of the titanium lumps. Therefore, it is necessary to design a method for removing titanium sponge from the production process without pollution or incomplete cleaning to address the above problem. Summary of the invention
[0004] The purpose of the present invention is to provide a method for cleaning and removing sponge titanium without pollution after production, so as to solve the problem of the existing method for cleaning and removing sponge titanium after production proposed in the above-mentioned background technology. During the cleaning process or incomplete cleaning, some black powder and low-cost titanium particles that objectively do not undergo secondary reaction are easily scattered on the climbing titanium and titanium lumps, which may cause secondary pollution of the titanium lumps.
[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a method for pollution-free and clean removal of sponge titanium after production, comprising a reactor pot, a reactor pot flange and a head hanging ear, a reactor large cover is installed above the reactor pot, and a feeding system is arranged on the upper outer side of the reactor large cover, the finished products produced on the upper inner wall of the reactor pot include wall-climbing titanium, and the finished products produced at the lower part of the reactor pot include titanium lumps, a large cover bottom is fixed on the lower side of the reactor large cover, the reactor pot flange is fixed to the upper outer ring of the reactor pot, and a sealing rubber gasket is arranged between the reactor pot flange and the reactor large cover, the outer edge of the reactor pot flange is penetrated by fastening bolts, the head hanging ear is welded to the lower sides of the reactor pot, and a sieve plate is fixed at the middle and lower part of the reactor pot.
[0006] Preferably, the reactor cover and the reactor bottom are integrated, and the symmetry centers of the reactor cover and the reactor bottom coincide with the symmetry center of the reactor pot, and the reactor pot is barrel-shaped.
[0007] Preferably, the feeding system includes a feed port, a connecting flange and a feeding pipe. The feed port is arranged in the middle of the interior of the reactor cover and the bottom of the cover, and a connecting flange is installed above the feed port. The feeding pipe is connected above the connecting flange.
[0008] Preferably, the feeding pipe forms an integrated structure with the feeding port through a connecting flange, and the feeding port is communicated with the interior of the reaction kettle.
[0009] Preferably, the reactor pot flange is fixedly connected to the reactor pot, and the reactor pot flange is bolted to the reactor large cover through fastening bolts.
[0010] Preferably, two head lifting ears are provided, and the head lifting ears are symmetrical with respect to the vertical center line of the reaction kettle pot.
[0011] Preferably, the sieve plate is a circular structure, and the symmetry center of the sieve plate coincides with the symmetry center of the reaction kettle.
[0012] Preferably, the method for removing the titanium sponge from the production process without any pollution and cleanliness comprises the following steps:
[0013] S1: Invert the reactor, place the reactor mouth downward on a flat surface, and remove the fastening bolts and sealing gaskets;
[0014] S2 is dismantled upside down, and the head lifting lug is used to quickly lift the reactor pot and the reactor cover, and the reactor pot is turned upside down on another dry and clean surface;
[0015] S3 After pouring out and waiting for a certain period of time, the reactor is placed horizontally to clean the black powder, edge skin and oxygen-rich and nitrogen-rich sponge climbing titanium on the pot mouth. After cleaning to the standard, the reactor is hung upside down and the wall is knocked with a sledgehammer to clean some magnesium chloride crystals previously scattered on the upper surface of the titanium lump;
[0016] S4 is to take it upright, and then use a crane to turn the reactor pot over again, so that the mouth of the reactor pot is facing upwards and placed upright in the cover, so that the wall-climbing titanium and the titanium lump can be cleanly removed. This method is called the inverted dismantling and cleaning upright method.
[0017] Preferably, during the inversion step S1 and the inversion dismantling step S2, the reactor pot is inverted by using a crane to lift it upside down, and the tail end cover of the reactor pot is lifted by a crane chain, so that the reactor pot can be quickly separated from the reactor cover and lifted open.
[0018] Preferably, during the disassembly process of step S2, a certain amount of argon gas may be appropriately filled into the interior of the reaction kettle.
[0019] The present invention provides a pollution-free and clean method for removing titanium sponge after production, which has the following beneficial effects:
[0020] The pollution-free cleaning removal method for sponge titanium after production adopts the inverted dismantling, cleaning and straight removal method. This method is more scientific and practical, and can be operated by personnel. It reduces the uncertainty of influencing factors when taking sponge titanium lumps, and can prevent sponge titanium from being flammable and easy to absorb moisture, thereby improving safety, and effectively preventing impurities such as low-priced materials and distilled magnesium from contaminating the titanium lumps and causing secondary pollution. At the same time, it eliminates the risk of foreign matter such as distilled magnesium entering into sponge titanium, thereby effectively improving the yield and appearance quality of sponge titanium.
[0021] The present invention adopts a crane to cooperate with the head lifting ear of the reactor pot during the inverted dismantling, which fully considers the operability of personnel and can avoid secondary pollution of sponge titanium caused by improper method of removing titanium lumps during the normal dismantling; then some argon gas is appropriately filled into the pot, so that more or less black powder and low-priced particles formed in the process of sponge titanium reduction, especially the black powder and low-priced particles on the surface of the reactor pot mouth flange, can be directly scattered on the inner surface of the large cover through the inverted dismantling method; then the inverted cleaning method is adopted to effectively clean up the black powder, edge skin and oxygen-rich and nitrogen-rich sponge wall titanium at the pot mouth, and then continue to remove the reactor. The kettle should be hung upside down to facilitate the cleaning of some magnesium chloride crystals previously scattered on the surface of the titanium lump, which completely avoids the possibility of impurities falling into the pot when disassembling and removing the titanium lump, causing secondary pollution of the titanium lump, thereby improving the yield of finished products. Finally, the finished product is taken out by the positive removal method, and it is disassembled upside down to clean first and then taken out positively, which avoids the possibility of some black powder, low-priced particles and other impurities falling on the titanium lump during the cleaning process or incomplete cleaning during positive disassembly. Moreover, once these impurities fall on the surface of the titanium lump, it is difficult to clean them up, and it is also difficult to pick out small impurity particles, thereby ensuring that the impurities in the titanium lump do not increase and effectively ensuring the quality of sponge titanium products. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the external structure of a method for removing titanium sponge after production without pollution and cleaning according to the present invention;
[0023] Figure 2 It is a schematic diagram of the internal structure of a method for removing titanium sponge after production without pollution and cleaning according to the present invention;
[0024] Figure 3 The present invention is a method for removing titanium sponge from the production process without pollution and cleaning Figure 2 The enlarged structural diagram at A in the middle;
[0025] Figure 4 A schematic diagram of the three-dimensional structure of a large cover bottom of a method for removing titanium sponge after production without pollution and cleaning according to the present invention;
[0026] Figure 5 This is a schematic diagram of the material distribution structure inside a reactor pot of a method for pollution-free clean removal of titanium sponge after production according to the present invention.
[0027] In the figure: 1. Reactor pot; 2. Reactor cover; 3. Feeding system; 301. Feed inlet; 302. Connecting flange; 303. Feeding pipe; 4. Climbing titanium; 5. Titanium lump; 6. Cover bottom; 7. Reactor pot flange; 8. Sealing gasket; 9. Fastening bolts; 10. Head lifting ear; 11. Screen plate. DETAILED DESCRIPTION
[0028] like Figure 1-5As shown, the present invention provides a technical solution: a method for cleaning and removing titanium sponge after production without pollution, comprising a reactor pot 1, a reactor pot flange 7 and a head hanging ear 10, a reactor large cover 2 is installed above the reactor pot 1, and a feeding system 3 is arranged on the upper outer side of the reactor large cover 2, the finished products produced on the upper inner wall of the reactor pot 1 include climbing wall titanium 4, and the finished products produced at the lower part of the reactor pot 1 include titanium lump 5, a large cover bottom 6 is fixed on the lower side of the reactor large cover 2, the reactor pot flange 7 is fixed to the upper outer ring of the reactor pot 1, and a sealing rubber gasket 8 is arranged between the reactor pot flange 7 and the reactor large cover 2, the outer edge of the reactor pot flange 7 is penetrated by fastening bolts 9, the head hanging ear 10 is welded to the lower sides of the reactor pot 1, and a sieve plate 11 is fixed at the middle and lower part of the reactor pot 1;
[0029] The specific operation is as follows: after the reaction, first remove the reactor cover 2 of the reactor pot 1 upside down, and then clean the impurities inside the reactor pot 1, that is, clean up the black powder, edge skin and oxygen-rich and nitrogen-rich sponge climbing titanium at the pot mouth, including some magnesium chloride crystals previously scattered on the upper surface of the titanium lump 5, and finally put it upright to take out the climbing titanium 4 and take out the titanium lump 5.
[0030] like Figure 2 As shown, the reactor cover 2 and the cover bottom 6 are integrated structures, and the symmetry centers of the reactor cover 2 and the cover bottom 6 coincide with the symmetry center of the reactor pot 1, and the reactor pot 1 is barrel-shaped;
[0031] The reactor pot 1 is barrel-shaped and is used for the reaction of materials. The reactor pot 1 can be sealed from above by a large reactor cover 2 and a large cover bottom 6 .
[0032] like Figure 1 As shown, the feeding system 3 includes a feeding port 301, a connecting flange 302 and a feeding pipe 303. The feeding port 301 is arranged in the middle of the reactor cover 2 and the bottom 6 of the reactor cover, and a connecting flange 302 is installed above the feeding port 301, and a feeding pipe 303 is connected above the connecting flange 302; the feeding pipe 303 forms an integrated structure with the feeding port 301 through the connecting flange 302, and the feeding port 301 is connected to the inside of the reactor pot 1;
[0033] The specific operation is as follows: the setting of the feed port 301 is convenient for adding reaction materials into the reactor pot 1, and the disassembly between the feed pipe 303 and the feed port 301 is facilitated by the connecting flange 302, so that it is convenient to remove the external feeding system 3 components when disassembling, which is convenient to use.
[0034] like Figure 3 As shown, the reactor pot flange 7 is fixedly connected to the reactor pot 1, and the reactor pot flange 7 is bolted to the reactor large cover 2 through the fastening bolts 9;
[0035] By tightening the bolts 9 and the reactor pot flange 7, the reactor large cover 2 and the reactor pot 1 can be easily disassembled, so that the disassembly step when taking out the titanium sponge after production can be realized.
[0036] like Figure 1 As shown, two end cap lifting ears 10 are provided, and the end cap lifting ears 10 are symmetrical with respect to the vertical center line of the reaction kettle pot 1;
[0037] The two symmetrically arranged head lifting ears 10 can bear the weight of the bottom of the reactor pot 1, and can conveniently use a crane chain to lift the tail head lifting ear 10 of the reactor pot 1 when dismantling, so as to facilitate the dismantling step.
[0038] like Figure 2 As shown, the sieve plate 11 is a circular structure, and the symmetry center of the sieve plate 11 coincides with the symmetry center of the reaction kettle pot 1;
[0039] The sieve plate 11 is installed at the lower part of the reaction kettle 1 , and the structures of the two are consistent. The arrangement of the sieve plate 11 is convenient for screening the internal materials.
[0040] The method for removing titanium sponge from the production process without pollution and cleaning comprises the following steps:
[0041] S1: Invert the reactor 1, place it upside down on a flat surface with the reactor mouth facing downwards, and remove the fastening bolts 9 and the sealing gasket 8 when it is inverted;
[0042] S2 is dismantled upside down, and the head lifting lug 10 is used to quickly lift the reactor pot 1 and the reactor large cover 2, and the reactor pot 1 is continued to be turned upside down on another dry and clean plane;
[0043] During the disassembly process of step S2, a certain amount of argon gas may be appropriately filled into the interior of the reaction kettle 1;
[0044] During the inversion of step S1 and the inversion dismantling of step S2, the reactor 1 is inverted by using a crane to lift it upside down, and the tail end cap lifting lug 10 of the reactor 1 is lifted by a crane chain, so that the reactor 1 can be quickly separated from the reactor cover 2 and lifted open;
[0045] S3: After pouring out and waiting for a certain period of time, the reactor pot 1 is placed horizontally to clean the black powder, edge skin and oxygen-rich nitrogen-rich sponge climbing titanium at the pot mouth. After cleaning to the standard, the reactor pot 1 is hung upside down, and the wall of the device is knocked with a sledgehammer to clean some magnesium chloride crystals previously scattered on the upper surface of the titanium lump 5;
[0046] S4 is taken upright, and then the reactor pot 1 is turned over by a crane so that the mouth of the reactor pot 1 is placed upright in the cover facing upwards, and the wall-climbing titanium 4 and the titanium lump 5 can be cleanly removed. This method is called the inverted dismantling and cleaning upright method.
[0047] In summary, the method for removing the titanium sponge from the reactor after production without pollution and cleaning can be used. When in use, the reactor 1 can be placed upside down on a plane with the reactor mouth facing downward by using a crane. In the upside-down state, the fastening bolts 9 and the sealing gasket 8 are removed. Then, the tail end ... of argon; after a certain period of stagnation, the reactor pot 1 is laid horizontally, the black powder, the edge skin and the oxygen-rich and nitrogen-rich sponge climbing titanium at the pot mouth are cleaned, and after the cleaning reaches the standard, the reactor pot 1 is hung upside down, and the wall of the device is knocked with a sledgehammer to clean some magnesium chloride crystals previously scattered on the upper surface of the titanium lump 5; finally, the reactor pot 1 is turned over by a crane, so that the pot mouth of the reactor pot 1 is facing up and placed in the cover, and the climbing titanium 4 and the titanium lump 5 can be cleanly knocked out, thus completing the use process of the pollution-free cleaning removal method after the entire sponge titanium production.
Claims
1. A method for removing titanium sponge from the production process without any pollution, characterized in that: The invention comprises a reactor pot (1), a reactor pot flange (7) and a head hanging ear (10), wherein a reactor pot cover (2) is installed above the reactor pot (1), and a feeding system (3) is arranged on the upper outer side of the reactor pot cover (2), the finished product produced on the upper inner wall of the reactor pot (1) comprises wall-climbing titanium (4), and the finished product produced at the lower part of the reactor pot (1) comprises titanium lumps (5), a large cover bottom (6) is fixed at the lower side of the reactor pot cover (2), the reactor pot flange (7) is fixed at the upper outer ring of the reactor pot (1), and a sealing rubber gasket (8) is arranged between the reactor pot flange (7) and the reactor pot cover (2), a fastening bolt (9) penetrates the outer edge of the reactor pot flange (7), the head hanging ear (10) is welded to the lower sides of the reactor pot (1), and a sieve plate (11) is fixed at the lower middle part of the reactor pot (1), and the method for removing titanium sponge after production without pollution comprises the following steps: S1: Invert the reactor pot (1) with the reactor pot opening facing downwards on a flat surface, and remove the fastening bolts (9) and the sealing gasket (8) that are fastened in the inverted state; S2 is dismantled upside down, and the head lifting lug (10) is used again to quickly lift the reaction kettle (1) and the reaction kettle cover (2) apart, and the reaction kettle (1) is then turned upside down on another dry and clean surface; S3 After pouring out the cleaning and waiting for a certain period of time, the reactor (1) is placed horizontally to clean the black powder, edge skin and oxygen-rich and nitrogen-rich sponge titanium on the pot mouth. After cleaning to the standard, the reactor (1) is hung upside down and the wall is knocked with a sledgehammer to clean some magnesium chloride crystals previously scattered on the upper surface of the titanium lump (5); S4: taking the reaction kettle (1) upright, and then using a crane to turn the reaction kettle (1) over again, so that the mouth of the reaction kettle (1) is facing upward and placed upright in the sleeve, and the wall-climbing titanium (4) and the titanium lump (5) are cleanly removed. This method is called the upside-down dismantling and cleaning upright method; During the inversion step S1 and the inversion dismantling step S2, the reactor pot (1) is inverted by using a crane to lift it upside down, and the tail end head lifting ear (10) of the reactor pot (1) is lifted by a crane chain, so as to quickly separate the reactor pot (1) from the reactor large cover (2) and lift it open; During the disassembly process of step S2, a certain amount of argon gas is appropriately filled into the interior of the reaction kettle (1).
2. The method for removing titanium sponge after production without pollution and cleaning according to claim 1, characterized in that: The reactor cover (2) and the cover bottom (6) are an integrated structure, and the symmetry centers of the reactor cover (2) and the cover bottom (6) coincide with the symmetry center of the reactor pot (1), and the reactor pot (1) is barrel-shaped.
3. The method for removing titanium sponge after production without pollution and cleaning according to claim 1, characterized in that: The feeding system (3) comprises a feeding port (301), a connecting flange (302) and a feeding pipe (303); the feeding port (301) is arranged in the middle of the reactor cover (2) and the cover bottom (6); a connecting flange (302) is installed above the feeding port (301); and a feeding pipe (303) is connected above the connecting flange (302).
4. The method for removing titanium sponge after production without pollution and cleaning according to claim 3, characterized in that: The feeding pipe (303) forms an integrated structure with the feeding port (301) through the connecting flange (302), and the feeding port (301) is connected to the interior of the reaction kettle (1).
5. The method for removing titanium sponge after production without pollution and cleaning according to claim 4, characterized in that: The reactor pot flange (7) is fixedly connected to the reactor pot (1), and the reactor pot flange (7) is bolted to the reactor large cover (2) via fastening bolts (9).
6. The method for removing titanium sponge after production without pollution and cleaning according to claim 1, characterized in that: Two end cap lifting ears (10) are provided, and the end cap lifting ears (10) are symmetrical with respect to the vertical center line of the reaction kettle pot (1).
7. The method for removing titanium sponge after production without pollution and cleaning according to claim 1, characterized in that: The sieve plate (11) has a circular structure, and the symmetry center of the sieve plate (11) coincides with the symmetry center of the reaction kettle (1).
Citation Information
Patent Citations
Reduction distillation device for producing sponge titanium
CN101629248A