A geothermal energy pile construction device and a construction method thereof
By designing geothermal energy pile construction equipment, including traveling mechanisms, pile planting systems, lifting systems and heat transfer pipe layout devices, the problems in the existing technology of high construction difficulty and easy damage of heat transfer pipes are solved, and high efficiency of construction and heat transfer are achieved. Pipe safety protection.
Patent Information
- Application Number
- CN202110747835.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-07-02
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2041-07-02
AI Technical Summary
Among the existing geothermal energy pile construction technologies, the prefabricated pile implantation method has problems such as difficulty in construction, easy damage to the heat transfer pipe, and difficulty in installation. In particular, there is a lack of effective protection measures during the welding of prefabricated piles and subsequent earth excavation.
A geothermal energy pile construction equipment is designed, including a main equipment platform equipped with a traveling mechanism, a pile planting system for planting piles, a lifting system for lifting prefabricated piles, and a heat transfer pipe for winding and retracting heat transfer pipes. Arrange the device so that the heat transfer tubes can be deployed smoothly through the heat transfer tube passages, and use insulation materials and corrugated joints at the welded joints, combined with protective sleeves to protect the heat transfer tubes.
It achieves simplicity and high efficiency of construction, ensures the safe layout of heat transfer pipes, reduces the risk of damage to the heat transfer pipes, improves the reliability of construction, and protects the heat transfer pipes during the later earth excavation process.
Smart Images

Figure CN113373922B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of geothermal energy pile construction, in particular to geothermal energy pile construction equipment and a construction method thereof. Background Art
[0002] At present, the prefabricated pile implantation method is the development trend of pile foundation. It is a very effective means to arrange the heat transfer pipe of ground source heat pump by using the prefabricated pile implantation method. In the prior art, the invention patent with patent number CN 108570982 A discloses a static drill rooted pile energy pile and its construction method, which uses static drill rooted piles to bury the heat transfer pipe and arranges the heat transfer pipe inside the prefabricated pile. There are the disadvantages of great construction difficulty, easy damage to the joint and poor heat transfer effect. The invention patent with patent number CN 108709328A also discloses a static drill rooted geothermal energy pile and its heat transfer pipe burying method, which also uses static drill rooted piles to bury the heat transfer pipe. In this invention, all prefabricated piles are bamboo piles, which cannot give full play to the advantages of implanted piles, and also make the installation of heat transfer pipes difficult. No protective measures are taken for the heat transfer pipes at the welding joints of the prefabricated piles and the top of the piles, which is easy to cause damage to the heat transfer pipes during the welding of the prefabricated piles and the subsequent earthwork excavation project. During the precast pile sinking process, the heat transfer tube will be subject to strong resistance from the surrounding cement soil, which can easily cause damage to the heat transfer tube. The invention does not take effective measures, nor does it propose specific equipment and methods for sinking the heat transfer tube.
[0003] The present invention proposes equipment and method for laying heat transfer pipes of ground source heat pumps by embedding precast piles, and proposes effective protection measures for the precast pile welding joints, the heat transfer pipes on the top of the precast piles and the construction process, thereby solving the problems existing in the current precast pile implantation method for setting heat transfer pipes. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a geothermal energy pile construction device and a construction method thereof with simple construction method, high efficiency, reliable quality and capable of ensuring the safe layout of heat transfer pipes in view of the current status of the above-mentioned prior art.
[0005] The technical solution adopted by the present invention to solve the above technical problems is:
[0006] A geothermal energy pile construction device comprises an equipment main platform equipped with a walking mechanism, a pile planting system for planting piles is arranged in the center of the equipment main platform, a lifting system for lifting prefabricated piles is arranged near the front end of the equipment main platform, a heat transfer tube arrangement device for winding and releasing heat transfer tubes is arranged directly behind the pile planting system on the equipment main platform, and a heat transfer tube passage is opened on the equipment main platform at the rear end adjacent to the pile planting system, the heat transfer tube passage is a rectangular hole that enables the heat transfer tube wound on the heat transfer tube arrangement device to pass through the equipment main platform and be released downward; a pile planting opening is arranged in the center of the pile planting system, which enables the prefabricated pile to pass through the equipment main platform and be implanted into the pile hole.
[0007] To optimize the above technical solutions, the specific measures taken also include:
[0008] The main platform of the equipment is rectangular in structure; the center of the pile system, the center of the heat transfer tube passage and the center of the heat transfer tube arrangement device are all located on the same center line of the main platform of the equipment, and the center line is parallel to the long side of the main platform of the equipment; the lifting system is set away from the center line.
[0009] The above-mentioned lifting system is installed on the main platform of the equipment at a position relatively close to the left front corner; the lifting system includes a rotating operating table installed on the main platform of the equipment and capable of rotating 360 degrees, and a boom hinged on the rotating operating table that can be retracted; a hook is installed on the boom through a wire rope.
[0010] The heat transfer tube arrangement device comprises a roller support fixed on the main platform of the equipment and a cylindrical roller rotatably mounted on the roller support; the heat transfer tubes are wound around the cylindrical roller in an orderly manner.
[0011] The present invention also provides a construction method of geothermal energy pile construction equipment, the method comprising the following steps:
[0012] 1) First, fix the upper end of the heat transfer tube of the ground source heat pump on the cylindrical drum of the heat transfer tube arrangement device, and then rotate the cylindrical drum clockwise so that the heat transfer tubes can be stacked and wound around the cylindrical drum in an orderly manner;
[0013] 2) Use the walking mechanism to move the main platform of the equipment to the pile hole where the pile needs to be planted, and make the center of the pile opening of the pile planting system coincide with the center of the pile hole where the pile needs to be planted; then use the lifting system to lift the first section of the prefabricated pile, and make the bottom of the prefabricated pile pass downward through the main platform of the equipment from the pile opening of the pile planting system;
[0014] 3) Rotate the cylindrical roller of the heat transfer tube arrangement device counterclockwise so that the lower end of the heat transfer tube is lowered from the cylindrical roller and passes through the main platform of the equipment through the heat transfer tube passage, and then use a binding belt or a clamp to fix the lower end of the heat transfer tube to the lower end of the first prefabricated pile;
[0015] 4) Use the cooperation of the lifting system and the pile planting system to plant the first section of the prefabricated pile into the pile hole. During the process of planting the pile, rotate the cylindrical roller counterclockwise so that the heat transfer pipe can be continuously lowered from the cylindrical roller under the drive of the first section of the prefabricated pile. After each pile is planted for a certain distance, use a binding belt or a clamp to fix the heat transfer pipe and the first section of the prefabricated pile. When the top of the first section of the prefabricated pile is 0.5 meters away from the platform surface of the main platform of the equipment, stop planting the pile.
[0016] 5) Use the pile planting system to temporarily fix the first section of the precast pile, and then use the lifting system to lift the second section of the precast pile, so that the bottom of the second section of the precast pile is aligned and tightly attached to the top of the first section of the precast pile, and then use welding to weld the second section of the precast pile to the first section of the precast pile;
[0017] 6) After welding is completed, the pile planting system loosens the first section of the prefabricated pile, and then continues to plant piles. During the same process of planting piles, the cylindrical roller is rotated counterclockwise so that the heat transfer tube can be continuously lowered from the cylindrical roller under the drive of the first section of the prefabricated pile. After each pile is planted for a certain distance, the heat transfer tube and the second section of the prefabricated pile are fixed with a binding belt or a clamp. When the top of the second section of the prefabricated pile is 0.5 meters away from the platform surface of the main platform of the equipment, the pile planting is stopped;
[0018] 7) Repeat steps 5) and 6) to plant the third and fourth precast piles. When planting the last precast pile, stop planting when the top of the last precast pile passes through the pile planting opening, and fix a protective sleeve for protecting the heat transfer pipe near the top of the precast pile. Then, after the upper end of the heat transfer pipe is accommodated and protected in the protective sleeve, continue planting to the designed elevation.
[0019] A corrugated joint with a certain elastic shrinkage function is added to the pipe section of the heat transfer pipe.
[0020] The heat transfer tube is provided with a thin steel wire rope for bearing the tension during pile planting. The thin steel wire rope is fixed to the heat transfer tube by a binding belt or a clamp.
[0021] On the heat transfer pipe, a heat insulating material having a heat insulating function is pasted at the welding point between the two prefabricated piles.
[0022] The protective sleeve is composed of a non-closed circular sleeve with a strip opening in the axial direction and an upper end cover mounted on the upper end of the non-closed circular sleeve; the non-closed circular sleeve is provided with flanges on both wings of the strip opening for convenient fixed connection with the prefabricated pile.
[0023] The protective sleeve is fixedly installed on the prefabricated pile by welding or bolt connection.
[0024] Compared with the reference document, the present invention is equipped with a heat transfer tube arrangement device for winding and releasing the heat transfer tube on the movable main platform of the equipment, so that the heat transfer tube can be placed in an orderly manner on the heat transfer tube arrangement device during construction. In order to ensure the smoothness of the placement of the heat transfer tube, the present invention also has a heat transfer tube passage on the main platform of the equipment that can provide a guide for the placement of the heat transfer tube, and the heat transfer tube can pass downward through the main platform of the equipment through the heat transfer tube passage. The construction method of the geothermal energy pile construction equipment of the present invention is simple and efficient. The provided steel wire rope and corrugated joint can ensure that the heat transfer tube is not pulled during the layout, and the provided protective sleeve can prevent the heat transfer tube from being damaged during the later earth excavation process. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a structural schematic diagram of the construction equipment of the present invention;
[0026] Figure 2 yes Figure 1 A top view of
[0027] Figure 3 It is one of the construction state diagrams of the present invention;
[0028] Figure 4 This is the second construction state diagram of the present invention;
[0029] Figure 5 It is a schematic diagram of the structure of the pile-pile connection of the present invention;
[0030] Figure 6 yes Figure 5 A local enlarged schematic diagram of the middle A;
[0031] Figure 7 yes Figure 5 A partial enlarged schematic diagram of point B in the middle;
[0032] Figure 8 It is a schematic diagram of pasting insulation materials;
[0033] Fig. 9 It is one of the three-dimensional structural schematic diagrams of the protective cover of the present invention;
[0034] Fig.10 This is the second schematic diagram of the three-dimensional structure of the protective cover of the present invention. DETAILED DESCRIPTION
[0035] The embodiments of the present invention are further described in detail below with reference to the accompanying drawings.
[0036] Figures 1 to 10 It is a schematic diagram of the structure of the present invention and its construction status.
[0037] The accompanying drawings are marked as follows: insulation material R, prefabricated piles Z, main platform 1, heat transfer pipe passage 1a, walking mechanism 2, pile system 3, pile opening 3a, lifting system 4, rotating operating table 41, lifting arm 42, hook 43, heat transfer pipe arrangement device 5, roller bracket 51, cylindrical roller 52, heat transfer pipe 6, corrugated joint 61, binding belt 7, protective sleeve 8, non-closed circular sleeve 81, strip opening 81a, flange 811, upper end cover 82, thin steel wire rope 9.
[0038] like Figure 1 and Figure 2 As shown, the present invention discloses a geothermal energy pile construction equipment, which includes an equipment main platform 1 equipped with a walking mechanism 2. The equipment main platform 1 is a rectangular structure, and the walking mechanism 2 can carry the equipment main platform 1 and all components installed on the equipment main platform 1 to move forward, backward, left and right. A pile planting system 3 for pile planting is provided at the center of the equipment main platform 1. The pile planting system 3 includes a hydraulic actuator, through which the prefabricated pile can be clamped so as to pause the pile planting and facilitate the connection of two pile sections. A pile planting opening 3a that passes through the equipment main platform 1 is provided at the center of the pile planting system 3. The pile planting opening 3a is a cylindrical hole, and the diameter of the hole is larger than the diameter of the prefabricated pile Z, so that the prefabricated pile can be implanted into the pile hole through the equipment main platform 1 through the pile planting opening 3a. A lifting system 4 is installed on the equipment main platform 1 near the front end, and the lifting system 4 includes a rotating operating table 41 fixedly installed on the equipment main platform 1 and a lifting arm 42 that can be extended and retracted on the rotating operating table 41. A hook 43 is installed on the lifting arm 42 through a steel wire rope. The rotating operating table 41 is equipped with a rotating disk, so it can drive the boom 42 to rotate 360 degrees. A winch is also installed on the rotating operating table 41. The hook 43 can be controlled by the winch to retract and release the wire rope. The main function of the lifting system 4 is to lift and position the prefabricated piles and perform other lifting operations. The greatest contribution of the present invention is that a heat transfer tube arrangement device 5 is installed on the main platform 1 of the equipment. The heat transfer tube arrangement device 5 can make the heat transfer tubes 6 stacked and orderly wound on the heat transfer tube arrangement device 5, so that the heat transfer tubes 6 can be laid out during subsequent construction. The heat transfer tube arrangement device 5 is arranged directly behind the pile planting system 3, which can ensure that the heat transfer tubes 6 are laid out more smoothly. A heat transfer pipe passage 1a is provided on the main platform 1 of the equipment close to the rear end of the pile system 3. The heat transfer pipe passage 1a is a rectangular hole penetrating downward through the main platform 1 of the equipment, so that the heat transfer pipe 6 wound on the heat transfer pipe arrangement device 5 can be laid downward through the main platform 1 of the equipment via the heat transfer pipe passage 1a.
[0039] In order to ensure that the heat transfer tube 6 will not be scratched by the heat transfer tube passage 1a when being placed, a guide wheel is provided in the heat transfer tube passage 1a to provide guidance for the heat transfer tube 6. The heat transfer tube 6 passes through the heat transfer tube passage 1a in contact with the guide wheel by rolling friction.
[0040] In the embodiment, from Figure 2 It can be seen that the center of the pile system 3, the center of the heat transfer tube passage 1a and the center of the heat transfer tube arrangement device 5 of the present invention are all located on the same midline of the equipment main platform 1, and the midline is parallel to the long side of the equipment main platform 1. The lifting system 4 is installed on the equipment main platform 1 at a position relatively close to the left front corner, so the lifting system 4 is set away from the midline of the equipment main platform 1.
[0041] In the embodiment, the heat transfer tube arrangement device 5 of the present invention is composed of a roller support 51 fixed on the main platform 1 of the equipment and a cylindrical roller 52 rotatably mounted on the roller support 51. The heat transfer tube 6 is orderly wound on the cylindrical roller 52. When winding, the upper end of the heat transfer tube 6 can be first fixed on the cylindrical roller 52, and then the cylindrical roller 52 is rotated, so that the heat transfer tube 6 is wound on the cylindrical roller 52 layer by layer from the inside to the outside until the lower end of the heat transfer tube 6 is also wound on the cylindrical roller 52.
[0042] The present invention also provides a construction method of geothermal energy pile construction equipment, the method comprising the following steps:
[0043] 1) First, fix the upper end of the heat transfer tube 6 of the ground source heat pump on the cylindrical drum 52 of the heat transfer tube arrangement device 5, and then rotate the cylindrical drum 52 clockwise so that the heat transfer tube 6 can be stacked and orderly wound around the cylindrical drum 52. Considering that the heat transfer tube 8 will be subjected to a large tensile force during the pile planting process, it is easy to break or damage the heat transfer tube 8 if you are not careful. Therefore, the heat transfer tube 6 of the present invention is equipped with a full-length thin steel wire rope 9, and the thin steel wire rope 9 is fixed to the heat transfer tube 6 through a binding belt 7 or a clamp. In other words, first fix the upper end of the heat transfer tube 6 of the ground source heat pump tied with the thin steel wire rope 9 on the cylindrical drum 52 of the heat transfer tube arrangement device 5. The thin steel wire rope 9 is used to bear the tension during pile planting, so that the tension of pile planting is mainly borne by the thin steel wire rope 9. The present invention also adds a corrugated joint 61 (such as a corrugated joint 61) with a certain elastic contraction function in the pipe section of the heat transfer tube 6. Figure 6 The corrugated joint 61 can ensure that the internal structure of the heat transfer tube 6 is not affected by a certain elastic deformation under the action of external force.
[0044] 2) Use the walking mechanism 2 to move the main platform 1 of the equipment to the pile hole where the pile needs to be planted, and make the center of the pile opening 3a of the pile system 3 coincide with the center of the pile hole where the pile needs to be planted; then use the lifting system 4 to lift the first section of the prefabricated pile Z, and make the pile bottom of the prefabricated pile Z pass downward through the main platform 1 of the equipment from the pile opening 3a of the pile system 3;
[0045] 3) Rotate the cylindrical roller 52 of the heat transfer tube arrangement device 5 counterclockwise, so that the lower end of the heat transfer tube 6 is lowered from the cylindrical roller 52 and passes through the main platform 1 of the equipment downward through the heat transfer tube passage 1a, and then use the binding belt 7 or the clamp to fix the lower end of the heat transfer tube 6 and the lower end of the first prefabricated pile Z together (see Figure 3 ); The first precast pile Z is a bamboo pile, and the remaining precast piles Z can be bamboo piles or other types of precast piles, such as pipe piles.
[0046] 4) Using the cooperation of the lifting system 4 and the pile-planting system 3, the first section of the prefabricated pile Z is planted into the pile hole. During the process of planting the pile, the cylindrical roller 52 is rotated counterclockwise so that the heat transfer pipe 6 can be continuously lowered from the cylindrical roller 52 under the drive of the first section of the prefabricated pile Z. After each pile is planted for a certain distance, the heat transfer pipe 6 is fixed to the first section of the prefabricated pile Z with a binding belt 7 or a clamp. When the distance between the top of the first section of the prefabricated pile Z and the platform surface of the equipment main platform 1 is 0.5 meters, the pile planting is stopped.
[0047] 5) Use the pile planting system 3 to temporarily fix the first section of the precast pile Z, and then use the lifting system 4 to lift the second section of the precast pile Z, so that the bottom of the second section of the precast pile Z is aligned and tightly attached to the top of the first section of the precast pile Z, and then use welding to weld the second section of the precast pile Z to the first section of the precast pile Z (see Figure 4 );
[0048] 6) After welding is completed, the piling system 3 releases the first prefabricated pile Z, and then continues to plant piles. During the same process of planting piles, the cylindrical roller 52 is rotated counterclockwise so that the heat transfer pipe 6 can be continuously lowered from the cylindrical roller 52 under the drive of the first prefabricated pile Z, and the heat transfer pipe 6 is fixed to the second prefabricated pile Z with a binding belt 7 or a clamp after each planting of a certain distance; when the top of the second prefabricated pile Z is 0.5 meters away from the platform surface of the equipment main platform 1, the planting of piles is stopped;
[0049] 7) Repeat steps 5) and 6) to plant the third and fourth precast piles. When planting the last precast pile, stop planting when the top of the last precast pile passes through the pile planting opening 3a, and fix a protective sleeve 8 for protecting the heat transfer pipe 6 at the position near the top of the precast pile Z. Then, after the upper end of the heat transfer pipe 6 is accommodated and protected in the protective sleeve 8, continue to plant the pile to the designed elevation. The protective sleeve 8 is used to protect the heat transfer pipe 6 and can prevent damage to the heat transfer pipe 6 during the subsequent earthwork excavation process.
[0050] like Fig. 9 and Fig.10As shown, the protective sleeve 8 of the present invention is composed of a non-closed circular sleeve 81 with a strip opening 81a in the axial direction and an upper end cover 82 covered on the upper end of the non-closed circular sleeve 81; the non-closed circular sleeve 81 is formed with flanges 811 on both wings of the strip opening 81a for facilitating fixed connection with the prefabricated pile Z.
[0051] The protective sleeve 8 is fixedly installed on the prefabricated pile Z by welding or bolting.
[0052] Since a large amount of heat is generated when the two sections of prefabricated piles are welded, and this heat cannot be dissipated in time when the piles are planted, the heat may damage the heat transfer tube 6 when it contacts the heat transfer tube. Therefore, in order to prevent this risk from occurring, the present invention uses a heat insulation material R at the welding interface of the two sections of the pile to protect the heat transfer tube 6. The heat insulation material R has the function of quick adhesion, such as Figure 7 and Figure 8 As shown, the heat insulating material R is pasted and coated on the heat transfer tube 6 at the welding point of the two prefabricated piles.
[0053] The main advantages of the present invention are:
[0054] 1. Provides a construction equipment for heat transfer pipes, which changes the current situation of manually placing heat transfer pipes, greatly saves manpower and improves construction efficiency;
[0055] 2. Provide a corrugated joint for the heat transfer pipe, so that the heat transfer pipe is not damaged by external forces during construction. Combined with the corrugated pipe pile joint, the steel wire rope is used as the main force-bearing component, which reduces the force on the heat transfer pipe and effectively protects the heat transfer pipe from damage;
[0056] 3. A welding joint protection measure is proposed to prevent the heat of the welding joint from damaging the heat transfer tube. The construction is quick and effective;
[0057] 4. A new type of protective cover is proposed to effectively protect the heat transfer tube from being damaged during the later excavation period.
[0058] The best embodiment of the present invention has been described, and various changes or modifications made by those skilled in the art will not depart from the scope of the present invention.
Claims
1. A construction method for geothermal energy pile construction equipment, the geothermal energy pile construction equipment comprising an equipment main platform (1) equipped with a walking mechanism (2), a pile planting system (3) for planting piles is provided at the center of the equipment main platform (1), and a lifting system (4) for lifting prefabricated piles (Z) is installed near the front end of the equipment main platform (1), wherein: A heat transfer tube arrangement device (5) for winding and releasing the heat transfer tube (6) is installed on the main platform (1) of the equipment at the rear of the pile planting system (3), and a heat transfer tube passage (1a) is opened on the main platform (1) at the rear end adjacent to the pile planting system (3). The heat transfer tube passage (1a) is a rectangular hole that allows the heat transfer tube (6) wound on the heat transfer tube arrangement device (5) to pass through the main platform (1) and be released downward; a pile opening (3a) is provided at the center of the pile planting system (3) to allow the prefabricated pile (Z) to pass through the main platform (1) and be implanted into the pile hole; the main platform (1) of the equipment is provided with a heat transfer tube arrangement device (5) for winding and releasing the heat transfer tube (6) at the rear end of the pile planting system (3). The platform (1) is of rectangular structure; the center of the pile system (3), the center of the heat transfer tube passage (1a) and the center of the heat transfer tube arrangement device (5) are all located on the same midline of the main platform (1) of the equipment, and the midline is parallel to the long side of the main platform (1) of the equipment; the lifting system (4) is arranged to deviate from the midline; the heat transfer tube arrangement device (5) comprises a roller bracket (51) fixed on the main platform (1) of the equipment and a cylindrical roller (52) rotatably mounted on the roller bracket (51); the heat transfer tube (6) is wound on the cylindrical roller (52) in an orderly manner; It includes the following steps: 1) First, the upper end of the heat transfer tube (6) of the ground source heat pump is fixed on the cylindrical roller (52) of the heat transfer tube arrangement device (5), and then the cylindrical roller (52) is rotated clockwise so that the heat transfer tube (6) can be stacked and wound around the cylindrical roller (52) in an orderly manner; 2) Using the walking mechanism (2) to move the main platform (1) of the equipment to the pile hole where the pile needs to be planted, and making the center of the pile opening (3a) of the pile planting system (3) coincide with the center of the pile hole where the pile needs to be planted; then using the lifting system (4) to lift the first section of the prefabricated pile (Z), and making the pile bottom of the prefabricated pile (Z) pass downward through the main platform (1) of the equipment from the pile opening (3a) of the pile planting system (3); 3) Rotate the cylindrical roller (52) of the heat transfer tube arrangement device (5) counterclockwise so that the lower end of the heat transfer tube (6) is lowered from the cylindrical roller (52) and passes through the main platform (1) of the equipment downward through the heat transfer tube passage (1a), and then use a binding belt (7) or a clamp to fix the lower end of the heat transfer tube (6) and the lower end of the first prefabricated pile (Z) together; 4) Using the cooperation of the lifting system (4) and the pile planting system (3), the first section of the prefabricated pile (Z) is planted into the pile hole. During the process of planting the pile, the cylindrical roller (52) is rotated counterclockwise so that the heat transfer pipe (6) can be continuously lowered from the cylindrical roller (52) driven by the first section of the prefabricated pile (Z). After each pile is planted for a certain distance, the heat transfer pipe (6) and the first section of the prefabricated pile (Z) are fixed with a binding belt (7) or a clamp. When the distance between the top of the first section of the prefabricated pile (Z) and the platform surface of the equipment main platform (1) is 0.5 meters, the pile planting is stopped. 5) temporarily fix the first prefabricated pile (Z) by using the pile planting system (3), and then hoist the second prefabricated pile (Z) by using the hoisting system (4), so that the bottom of the second prefabricated pile (Z) is aligned and closely attached to the top of the first prefabricated pile (Z), and then the second prefabricated pile (Z) is welded and connected to the first prefabricated pile (Z) by welding; 6) After the welding is completed, the piling system (3) loosens the first prefabricated pile (Z), and then continues to plant piles. During the same process of planting piles, the cylindrical roller (52) is rotated counterclockwise so that the heat transfer pipe (6) can be continuously lowered from the cylindrical roller (52) under the drive of the first prefabricated pile (Z), and after each pile is planted for a certain distance, the heat transfer pipe (6) is fixed to the second prefabricated pile (Z) with a binding belt (7) or a clamp; when the top of the second prefabricated pile (Z) is 0.5 meters away from the platform surface of the equipment main platform (1), the planting of piles is stopped; 7) Repeat steps 5) and 6) to plant the third and fourth prefabricated piles. When the last prefabricated pile is planted, the planting is stopped after the top of the last prefabricated pile passes through the pile planting opening (3a). A protective sleeve (8) for protecting the heat transfer pipe (6) is fixedly installed near the top of the prefabricated pile (Z). The upper end of the heat transfer pipe (6) is then accommodated and protected in the protective sleeve (8), and the pile planting is continued to the designed elevation.
2. The construction method of a geothermal energy pile construction equipment according to claim 1 is characterized by: The lifting system (4) is installed on the main platform (1) of the equipment at a position relatively close to the left front corner; the lifting system (4) comprises a rotating operating table (41) installed on the main platform (1) of the equipment and capable of rotating 360 degrees, and a lifting arm (42) hinged on the rotating operating table (41) and capable of being retracted; a lifting hook (43) is installed on the lifting arm (42) via a steel wire rope.
3. The construction method of a geothermal energy pile construction equipment according to claim 2 is characterized by: A corrugated joint (61) having a certain elastic contraction function is added to the pipe section of the heat transfer pipe (6).
4. The construction method of a geothermal energy pile construction equipment according to claim 3 is characterized by: The heat transfer tube (6) is provided with a thin steel wire rope (9) for bearing the tension during pile planting. The thin steel wire rope (9) is fixed to the heat transfer tube (6) by a binding belt (7) or a clamp.
5. The construction method of a geothermal energy pile construction equipment according to claim 4 is characterized by: A heat insulating material (R) having a heat insulating function is pasted on the heat transfer pipe (6) at the welding point between the two prefabricated piles.
6. The construction method of a geothermal energy pile construction equipment according to claim 5 is characterized by: The protective sleeve (8) is composed of a non-closed circular sleeve (81) with a strip opening (81a) in the axial direction and an upper end cover (82) mounted on the upper end of the non-closed circular sleeve (81); flanges (811) are formed on both wings of the strip opening (81a) on the non-closed circular sleeve (81) for facilitating fixed connection with the prefabricated pile (Z).
7. The construction method of a geothermal energy pile construction equipment according to claim 6 is characterized by: The protective sleeve (8) is fixedly installed on the prefabricated pile (Z) by welding or bolt connection.
Citation Information
Patent Citations
Static drill rooting energy pile and construction method thereof
CN108570982A
Static drilling rooting construction method geothermal energy resource pile and heat transmission tube burying method thereof
CN108709328A
Ground source heat pump tube embedment method based on piling process
CN103103985A
Ground-source heat pump pile buried pipe
CN202730750U
Geothermal energy pile construction equipment
CN215441885U