Method for controlling a material processing device and a material carrying vehicle

By calculating the current material level and expected processing rate of the material processing device, and adjusting the vehicle arrival time period and speed, the problem of waiting and waste in the construction site material carrier vehicle and device control system is solved, and production efficiency and utilization are improved.

CN113557486BActive Publication Date: 2024-10-29VOLVO CONSTRUCTION EQUIPMENT AB
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN201980093615.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-03-04
Publication Date
2024-10-29
Estimated Expiration
2039-03-04

AI Technical Summary

Technical Problem

Existing control systems for material handling vehicles and material processing devices at construction sites are difficult to effectively improve production efficiency and utilization, resulting in increased vehicle waiting time and fuel consumption, and material processing devices are easily exhausted or overloaded.

Method used

By determining the current material level and expected processing rate of the material processing device, the expected arrival time period of vehicle arrival is calculated, and the vehicle speed is adjusted to avoid waiting before allowing dumping and reduce fuel consumption, ensuring that materials are not wasted and equipment operates efficiently.

Benefits of technology

It improves the production efficiency and utilization rate of material processing equipment, reduces vehicle waiting time and fuel consumption, and avoids material waste and equipment overload.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113557486B_ABST
    Figure CN113557486B_ABST
Patent Text Reader

Abstract

A method for controlling a system including a processing device and a carrier vehicle, comprising: (S1) determining the total amount of unprocessed material that has been dumped into the processing device within a first time period between a first and a second time point; (S2) determining the total amount of unprocessed material that has been processed within the first time period; (S3) determining a reference level of the unprocessed material contained in the processing device at the first time point; (S4) determining the current level of the unprocessed material contained in the processing device based on the above steps; (S5) predicting at least one of an earlier time point and a later time point at which the level of the unprocessed material is expected to drop below a lower limit value or an upper limit value based on the current level of the unprocessed material contained in the processing device and an expected future processing rate; (S6) establishing an expected arrival time period for a first carrier vehicle to arrive at the processing device between a start point and an end point corresponding to the earlier time point and the later time point, respectively; and (S7) adjusting the speed of the first carrier vehicle to arrive at the processing device within the expected arrival time period.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a method for controlling a system comprising a material processing device and at least one material carrier vehicle configured to transport raw material to the material processing device and to dump the raw material directly or indirectly into the material processing device.

[0002] The invention is particularly applicable to construction sites where material-carrying vehicles such as transporters and dump trucks transport, for example, rock fragments to material processing means in the form of crushers. Background Art

[0003] Construction vehicles in the form of articulated haulers, wheel loaders, trucks and dump trucks are often used for loading and transporting material at construction sites etc. For example, a load-receiving container of a hauler or dump truck may be loaded with unprocessed material, such as rock fragments, for example at a loading location, transport the material to another location and dump the material into a material processing device, such as a buffer feeder of a crusher arranged to crush the rock fragments into smaller fragments.

[0004] Efficient production and utilization of equipment requires that material processing devices do not run out of unprocessed material and that vehicles do not have to wait in line when loading or unloading. WO2015 / 065251 addresses this problem and proposes calculating the estimated arrival time of vehicles to a certain target destination, transmitting information between vehicles about the estimated arrival time of various vehicles, and adjusting the speed of the vehicles to avoid waiting time or crusher emptying and save energy / fuel (when reducing speed).

[0005] Although the method disclosed in WO2015 / 065251 appears useful and may solve some of the problems associated with the control of construction site vehicles and equipment, there is still a need for improvement. Summary of the invention

[0006] The object of the present invention is to provide a method and system for controlling a material processing device and a material carrying vehicle configured to transport and dump unprocessed material to the processing device, which method / system has the potential to further improve the production efficiency and utilization of the equipment.

[0007] According to a first aspect of the invention, the object is achieved by a method as described below. According to a second aspect of the invention, the object is achieved by a system as described below. According to a further aspect of the invention, the object is solved by a computer-related item as described below.

[0008] A first aspect of the invention relates to a method for controlling a system comprising a material processing plant and at least one material carrier vehicle configured to transport material of unprocessed material to the material processing plant and to dump the unprocessed material directly or indirectly into the material processing plant.

[0009] The method is characterized by the following steps:

[0010] - determining the total amount of unprocessed material that has been dumped into the material processing device during a first time period between a first point in time and a second point in time;

[0011] - determining the total amount of unprocessed material that has been processed by the material processing device during the first time period;

[0012] - determining a reference level of unprocessed material contained in said material processing device at a first point in time;

[0013] - determining a current level of unprocessed material contained in the material processing device based on i) the total amount of unprocessed material that has been dumped into the material processing device during the first time period, ii) the total amount of unprocessed material that has been processed by the material processing device during the first time period, and iii) a reference level of unprocessed material contained in said material processing device at the first point in time;

[0014] - based on a current level of unprocessed material contained in the material processing device and an expected future processing rate of the material processing device, predicting at least one of the following:

[0015] a third time point at which the level of the unprocessed material is expected to drop below an upper limit value (at which the additional unprocessed material is not allowed to be dumped into the material processing device), thereby allowing the dumping of the unprocessed material, and

[0016] a fourth time point at which the material level of the unprocessed material is expected to drop below a lower limit value, the lower limit value indicating that the material processing device has run out of or is about to run out of unprocessed material;

[0017] - establishing an expected arrival time period for the first material carrier vehicle to arrive at the material processing device, wherein the expected arrival time period extends between a start point and an end point, and wherein at least one of the start point and the end point is set such that the start point is at a third time point at the earliest and / or such that the end point is at a fourth time point at the latest; and

[0018] - adjusting the speed of the first material carrying vehicle so as to arrive at the material processing device within said desired arrival time period.

[0019] In short, the method calculates the current material level in the processing device based on the dumping rate, the processing rate and the reference level value, then predicts the start and / or end of the expected arrival time period based on the current material level of the material processing device and the expected future processing rate, and then adjusts the speed of the vehicle so that it arrives at the processing device within the expected time period before the processing device runs out of material (for example, before the feeder of the crusher becomes empty) and / or after the processing device is too full, so that the vehicle can avoid waiting before being allowed to dump.

[0020] The method gives a span of vehicle speeds to be used so that a suitable speed is selected that saves fuel / energy. By setting only the end point of the expected arrival time period, it is avoided that the processing device runs out of material to be processed. By setting only the starting point of the expected arrival time period (taking into account that the crusher may be full), the method reduces or eliminates the risk of driving the vehicle at an unnecessary high speed (driving the vehicle at an unnecessary high speed will result in a waiting time at the processing device before the vehicle is allowed to dump its material). Although it may be sufficient to explicitly set only one of the starting point and the end point, in many cases it is useful to set both the starting point (if the processing device is not full, the starting point can be the current time point) and the end point of the expected arrival time period.

[0021] Regardless of the specific details used to implement the method, the method can be used to adjust the speed of the first material carrier vehicle to avoid the processing device running out of material (which would reduce the overall productivity / processing rate), and / or to avoid the vehicle having to wait at the processing device, in which case it is better to have the vehicle travel at a lower speed to reduce fuel consumption and arrive at the processing device later so that the unprocessed material can be dumped immediately upon arrival.

[0022] The second point in time may be set as the current point in time, so that the material level determined at the second point in time becomes the current level of the unprocessed material contained in the material processing device.

[0023] In short, the total amount of unprocessed material that has been dumped into the material processing device during the first time period can be obtained by having each vehicle send information to all other vehicles or some central control system about the weight of material that it has dumped or is about to dump at the processing device. All materials in the first time period are added together to obtain the total weight. The average dumping rate (tons / hour) can also be obtained.

[0024] In short, the total amount of unprocessed material that has been processed by the material processing device during a first time period can be obtained from some preset standard processing rate or average processing rate of the processing device and / or from measurement (for example, by a scale arranged to weigh the processed material), and this information is transmitted.

[0025] The reference level of the unprocessed material contained in the material processing device at the first point in time may be, for example, an empty processing device (feeder thereof), i.e., the level is zero, or when the level is at or above an upper limit value (at which no additional unprocessed material is allowed to be poured into the processing device), i.e., the level is 100% or >100% of the nominal level. Such a reference level may be determined manually or by using a coarse level sensor.

[0026] The third and fourth time points at which the level of unprocessed material is predicted to drop below an upper or lower limit value relate to expected dumping and processing rates, and may include, for example, unprocessed material dumped by a second material carrier vehicle in front of the first material carrier vehicle, and a given preset average processing rate of the material processing device.

[0027] Establishing an expected arrival time period for the first material carrier vehicle to arrive at the material processing device means setting a time period between a start point and an end point (i.e., between the earliest expected arrival time point and the latest expected arrival time point) during which time period it is expected that the first vehicle will arrive at the processing device and dump its material. By setting the end point at (or possibly slightly before) a predicted fourth time point (at which the material level of unprocessed material in the material processing device is expected to drop below a lower limit value), it is ensured that the processing device will not become empty. The start point of the expected arrival time period may be set by default to the current time point or to some arbitrary point before the end point, unless the processing device is full or likely to be full because one or more other vehicles will dump their material before the first vehicle.

[0028] Adjusting the speed of the first vehicle so as to reach the processing device within the desired arrival time period may be accomplished by calculating a speed interval based on the distance between the vehicle and the processing device and corresponding to the start and end of the desired time period, and then selecting a suitable speed from the calculated interval. This may also be accomplished in another way by starting with a generally suitable speed and checking whether this speed will bring the vehicle to the processing device within the desired time period, and if not, selecting another (reasonable) higher or lower speed. In any case, the selected speed may be displayed to indicate to the driver of the vehicle a recommended speed or the vehicle speed may be set directly by a control unit capable of controlling the operation of the vehicle.

[0029] The method can be used in situations where the material processing device does not have any level sensor. The method can also be used as a backup when the processing device is provided with a level sensor capable of transmitting sensor data, because it may be difficult to connect to the sensor and the connection may be lost. The method can also be used in situations where the processing device is only provided with a "simple" level sensor, which can only determine whether the level is above or below the above-mentioned upper limit value, i.e. a "full" device where the vehicle must be weighed in preparation for loading.

[0030] The expression "receiving a signal" as sometimes used in this disclosure generally refers to a signal being received by some appropriate receiving device. Typically, this means that an electromagnetic signal is automatically sent wirelessly, for example from a vehicle, a processing device or a central control system, and the signal is received by a receiver that is configured to receive signals of the type described and is arranged to be connected to, for example, a control unit of a vehicle or a central control system, wherein the control unit / control system is configured to process (via a processor, a memory, etc.) the information contained in the signal and to perform various calculations and determination steps. However, "receiving a signal" may also refer to, for example, receiving a signal sent to the control unit / control system via wires from a keyboard or the like. An example of a signal that may be received in the latter manner is a signal indicating some form of preset value that does not need to be updated frequently, such as an average processing rate of a material processing device (which can be used to estimate the total amount of unprocessed material that has been or will be processed by the processing device during a specific time period).

[0031] In a preferred variant of the invention, each material handling vehicle involved is provided with a transmitter and a receiver for sending and receiving signals by wireless communication (direct radio, vehicle-to-vehicle communication), and a control unit connected to the transmitter and the receiver and, for example, a GPS positioning unit, wherein the control unit comprises a memory, a processor, etc., for storing and processing data, for example, data received by the receiver and data to be sent by the transmitter. The same control unit (or another control unit that may be connected to the first control unit) is also configured to control the operation of the vehicle (for example, speed and dumping). All of this is well known. Each vehicle also has information on the material weight of the unprocessed material that has been dumped or is about to be dumped into the material processing device. Therefore, each vehicle is configured to be able to send information about the amount of unprocessed material that has been dumped or is about to be dumped into the processing device to all other vehicles. Therefore, each vehicle is also configured to receive such signals.

[0032] In one embodiment, the method comprises the step of determining whether a current level of unprocessed material in the material processing device is above an upper limit value that does not allow additional unprocessed material to be dumped into the material processing device.

[0033] If the first material carrier vehicle will arrive before the third time point of the predicted high material level, it will have to wait at the processing device until the material level has dropped below the upper limit. Therefore, it is better to drive at a slower speed and avoid waiting. On the contrary, if it is determined that the current material level is below the upper limit, the starting point of the expected time period can be set to the current time point or another arbitrary time point, or not set at all. In practice, this will mean that the first material carrier vehicle can drive at any suitable speed as long as it arrives before the end of the expected arrival time period.

[0034] In one embodiment, the method includes: determining whether at least a second material carrier vehicle will arrive at the material processing device before the first material carrier vehicle; and when so, predicting the amount of unprocessed material to be dumped into the material processing device by the second material carrier vehicle; wherein the step of predicting a third time point and / or a fourth time point at which the material level of the unprocessed material is expected to drop below an upper limit value or a lower limit value is also based on the predicted amount of unprocessed material to be dumped by the second material carrier vehicle.

[0035] If one or more other vehicles (i.e., at least the second vehicle) are ahead of the first vehicle and will dump material at the processing device before the first vehicle, it will take longer before the processing device runs out of material, so the first vehicle can slow down to save energy / fuel. It is also possible that the material dumped by the second vehicle can be expected to increase the material level above the upper limit value, so the first vehicle should reduce its speed to avoid waiting time at the processing device.

[0036] In one embodiment, the method includes the following steps: providing information about the current geographical location of the first material carrier vehicle; determining the distance between the first material carrier vehicle and the material processing device based on the current geographical location of the first material carrier vehicle and the information about the available routes and the geographical location of the material processing device; determining an adjusted minimum average speed based on the distance between the first material carrier vehicle and the material processing device and the end point of the expected arrival time period, so that: if the first material carrier vehicle moves at the minimum average speed, the first material carrier vehicle will arrive at the material processing device at the end point of the expected arrival time period; and / or determining an adjusted maximum average speed based on the distance between the first material carrier vehicle and the material processing device and the start point of the expected arrival time period, so that: if the first material carrier vehicle moves at the maximum average speed, the first material carrier vehicle will arrive at the material processing device at the start point of the expected arrival time period.

[0037] Therefore, a speed above the minimum average speed will bring the vehicle to the processing device before the end of the desired time period, and a speed below the maximum average speed will result in an arrival after the starting point of the desired time period. In some cases, it is impossible to reach the minimum speed for practical reasons. If so, the processing device may run out of material within a period of time. It makes the most sense to calculate the maximum average speed when the starting point of the desired time period is within a reasonable time interval, so that the maximum average speed becomes reasonable. For example, if the current material level of the unprocessed material is below the upper limit value and the starting point is set to the current time point, the maximum average speed will be infinite, which is unreasonable. Therefore, if the starting point of the desired time period is not within a reasonable time interval, there is no specific point to calculate the maximum average speed. Instead, the maximum average speed can then be set according to the actual requirements (maximum expected power, safety, etc.).

[0038] In one embodiment, the start point of the expected arrival time period is set to be somewhere between the current time point and a future time point before the end point of the expected arrival time period.

[0039] In one embodiment, the total amount of unprocessed material dumped into the material processing device during the first time period is obtained at least in part by receiving information about the weight of all material dumped into the material processing device during the first time period, or, when the materials have substantially the same weight, by receiving information about the number of times the material was dumped during the first time period.

[0040] In one embodiment, the total amount of unprocessed material processed by the material processing device during the first time period is obtained from information on a standard processing rate or an average processing rate of the material processing device and / or by receiving information from a weighing measurement of the total amount of processed material.

[0041] The material that has been processed / crushed by, for example, a crusher device can be weighed by a scale arranged at (below) the conveyor belt at the outlet of the crusher device, or the amount of processed material can be calculated based on the set standard processing rate (tons / hour) multiplied by the total production / processing time during the first time period.

[0042] A standard or average processing rate for a material processing device may be used for past processing and predicted future processing.

[0043] In one embodiment, the reference level of unprocessed material contained in the material processing device at the first time point is a lower limit value indicating that the material processing device has run out of or is about to run out of unprocessed material. That is, the material processing device is substantially empty at the first time point.

[0044] In one embodiment, at the first point in time, a reference material level of the unprocessed material contained in the material processing device is at or above an upper limit value that does not allow additional unprocessed material to be dumped into the material processing device.

[0045] In one embodiment, the reference material level of the unprocessed material contained in the material processing device at the first point in time is when the material level decreases and crosses an upper limit value.

[0046] The reference filling level may be determined by a coarse sensor which is able to detect whether the filling level is above or below an upper limit value and / or whether the processing device is (substantially) empty. Alternatively, the reference filling level may be determined manually.

[0047] By providing a processing plant with a level sensor and a transmitter connected to the sensor, a reference level (and possibly the actual level) can be communicated to all material handling vehicles involved (if receivers are provided).

[0048] If the current material level is above the upper limit value, it is known that the actual material level used as the reference material level is at least at the upper limit value. When the material level crosses the upper limit value (at the same time, the material level decreases in certain types of feeders during operation of the processing device), a more accurate estimate of the reference material level can be obtained by setting the reference material level. This material level (i.e., the upper limit value crossed during operation) can also be used to provide a wait-and-go-signal to a vehicle that has arrived at the processing device to prepare to dump unprocessed material and to switch between the wait-and-go signal (e.g., to provide a red light or a green light for the driver of the vehicle, and to provide other signals for an autonomous vehicle).

[0049] In one embodiment, the second time point is the current time point. This is not required, but will usually simplify calculations.

[0050] In one embodiment, the material processing device is a material crusher. Other possibilities are, for example, mixing equipment or load pockets, which can also be considered to be "processing" the material.

[0051] In one embodiment, at least the first material carrier vehicle is provided with a receiver for receiving signals transmitted by wireless communication and a control unit arranged to be in communication connection with the receiver, wherein the method comprises the following steps: receiving, by the receiver, a signal indicating the total amount of unprocessed material that has been dumped into the material processing device during a first time period between a first point in time and a second point in time; receiving, by the receiver, a signal indicating the total amount of unprocessed material that has been processed by the material processing device during the first time period, or obtaining information indicating the total amount of unprocessed material that has been processed by the material processing device during the first time period, such as a standard processing rate or an average processing rate of the material processing device, if such information is already available on the first material carrier vehicle; receiving, by the receiver, a signal indicating the amount of unprocessed material contained in the material processing device at the first point in time a signal of a reference level of a processed material; calculating, by the control unit, a current level of an unprocessed material contained in a material processing device based on the received or obtained information; predicting, by the control unit and based on the current level of the unprocessed material contained in the material processing device and an expected future processing rate of the material processing device, at least one of a third time point and a fourth time point; establishing, by the control unit, an expected arrival time period for a first material carrier vehicle to arrive at the material processing device, wherein the expected arrival time period extends between a starting point and an end point, and wherein at least one of the starting point and the end point is set so that the starting point is at the earliest at the third time point and / or so that the end point is at the latest at the fourth time point; and setting or indicating, by the control unit, a speed of the first material carrier vehicle so as to arrive at the material processing device within the expected arrival time period.

[0052] This provides a distributed system where the dump truck or hauler or similar material handling vehicle receives the required signals and information and makes its own determinations, calculations etc. That is, this embodiment does not require a central control system.

[0053] The system involves a material processing facility and at least one material handling vehicle configured to transport a load of unprocessed material to the material processing facility and to dump the unprocessed material directly or indirectly into the material processing facility.

[0054] The system is characterized in that it is configured to:

[0055] - determining the total amount of unprocessed material that has been dumped into the material processing device during a first time period between a first point in time and a second point in time;

[0056] - determining the total amount of unprocessed material that has been processed by the material processing device during the first time period;

[0057] - determining a reference level of unprocessed material contained in said material processing device at a first point in time;

[0058] - determining a current level of unprocessed material contained in the material processing device based on i) the total amount of unprocessed material that has been dumped into the material processing device during the first time period, ii) the total amount of unprocessed material that has been processed by the material processing device during the first time period, and iii) a reference level of unprocessed material contained in said material processing device at the first point in time;

[0059] - based at least on a current level of unprocessed material contained in the material processing device and an expected future processing rate of the material processing device, predict at least one of the following:

[0060] a third time point at which the level of the unprocessed material is expected to drop below an upper limit value, thereby allowing the pouring of the unprocessed material, at which upper limit value the pouring of additional unprocessed material into the material processing device is not allowed, and

[0061] a fourth time point at which the material level of the unprocessed material is expected to drop below a lower limit value, the lower limit value indicating that the material processing device has run out of or is about to run out of unprocessed material;

[0062] - establishing an expected arrival time period for the first material carrier vehicle to arrive at the material processing device, wherein the expected arrival time period extends between a start point and an end point, and wherein at least one of the start point and the end point is set such that the start point is at the earliest at a third time point and / or such that the end point is at the latest at a fourth time point; and

[0063] - adjusting the speed of the first material carrying vehicle so as to arrive at the material processing device within said desired arrival time period.

[0064] In one embodiment, at least the first material carrier vehicle is provided with a receiver for receiving a signal sent via wireless communication and a control unit arranged to be in communication connection with the receiver, wherein the control unit is configured to: calculate a current material level of unprocessed material contained in the material processing device, predict a third time point and / or a fourth time point at which the material level of the unprocessed material in the material processing device is expected to drop below an upper limit value or a lower limit value, and set or at least indicate a speed of the first material carrier vehicle so as to arrive at the material processing device within the expected arrival time period.

[0065] In one embodiment, the system comprises at least a first material handling vehicle and a second material handling vehicle, wherein each of the vehicles comprises a receiver and a control unit as described above, and wherein each of the vehicles further comprises a transmitter for wirelessly transmitting a signal at least indicating a material amount of unprocessed material to be dumped or already dumped into a material processing device.

[0066] Preferably, each vehicle is also configured to send and receive signals representing other useful vehicle information, such as geographic location, speed, target destination, etc.

[0067] In one embodiment, the material processing device is provided with a level sensor configured to at least determine whether the level of the unprocessed material is above or below an upper limit value that does not allow additional unprocessed material to be dumped into the material processing device.

[0068] In one embodiment, the material processing device is provided with a production rate sensor configured to determine an amount of material processed by the material processing device.

[0069] In one embodiment, the material processing device is provided with a transmitter for transmitting a signal representing a level of unprocessed material and / or a signal representing an amount of processed material by wireless communication.

[0070] In one embodiment, the material processing device is a material crusher.

[0071] In one embodiment, the material handling vehicle is a transport vehicle or a truck provided with a material receiving bucket adapted to receive material in the form of rock fragments, gravel, sand or the like.

[0072] Further aspects of the invention relate to:

[0073] A computer program product comprises program code components for executing the steps of the above method when the program is run on a computer.

[0074] A computer readable medium carries a computer program including program code components for executing the steps of the above method when the program product is run on a computer.

[0075] A control unit for controlling the above system, the control unit being configured to perform the steps of the above method. Preferably, the control unit is arranged on the first material carrier vehicle. Preferably, the control unit is configured to also control the operation of the first material carrier vehicle.

[0076] Further advantages and advantageous features of the invention are disclosed in the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0077] With reference to the accompanying drawings, below follows a more detailed description of embodiments of the invention cited as examples.

[0078] In these figures:

[0079] Figure 1 An example of a material handling vehicle in the form of an articulated hauler is shown.

[0080] Figure 2 A schematic diagram of an embodiment of a system according to the invention is shown.

[0081] Figure 3 A general flow chart of the method according to the invention is shown. DETAILED DESCRIPTION

[0082] Figure 1 An example of a material-carrying vehicle 1 , 2 in the form of an articulated hauler is shown. Figure 1 The vehicles shown are representative of Figure 2 The vehicles 1 and 2 are shown. Figure 1 As shown, the transport vehicles 1, 2 have a material receiving container 14, 24, which is suitable for receiving material in the form of rock fragments, gravel, sand or the like. Figure 1 It is further shown that each transport vehicle 1, 2 is provided with a receiver 11 and a transmitter 21 and a control unit 12, 22. The receiver 11 and the transmitter 21 are arranged to receive and send signals by wireless communication (e.g. direct radio, vehicle-to-vehicle communication, 5g). The control unit 12, 22 is arranged to be in communication connection with the corresponding receiver 11 and transmitter 21. As will be further described below, the control unit 12, 22 is configured, for example, to calculate the level of the unprocessed material 5 contained in the material processing device 3 and the expected arrival time period Td of the transport vehicle 1, 2 to arrive at the material processing device 3 based in part on the signals received by the corresponding transmitter 11, 21.

[0083] Examples of information that vehicles 1 and 2 can transmit directly to each other wirelessly are the amount of raw material 5 to be dumped or already dumped into the crusher 3 (which may be the weight of the material currently being transported or recently dumped), the current speed, the geographic location, the estimated arrival time at the crusher 3, etc.

[0084] The control unit 12, 22 may include a microprocessor, a microcontroller, a programmable digital signal processor, or another programmable device. The control unit may also include or alternatively include an application specific integrated circuit, a programmable gate array or programmable array logic, a programmable logic device, or a digital signal processor. In the case where the control unit includes a programmable device (such as the above-mentioned microprocessor, microcontroller, or programmable digital signal processor), the processor may also include computer executable code that controls the operation of the programmable device.

[0085] Figure 2 A schematic diagram of an embodiment of a system 10 according to the invention is shown. The illustrated system 10 comprises a material processing device 3 in the form of a crusher and a first material carrier vehicle 1 and a second material carrier vehicle 2 which are configured to transport raw material 5 (in this case rock fragments) from a loading location 9 to the crusher 3 and dump the raw material 5 into a feeder 32 of the crusher 3. The crusher 3 produces processed / crushed material 6 which is fed by the crusher at its output side (at Figure 2 The crusher 3 is fed away by the conveyor belt 33 on the right side of the crusher 3. A preset average crusher processing rate (in tons / hour) has been established for the crusher 3.

[0086] The first material-carrying vehicle 1 and the second material-carrying vehicle 2 are in this case identical and are Figure 1 The second vehicle 2 is in front of the first vehicle 1 and will reach the crusher 3 and dump its material before the first vehicle 1. The vehicles 1, 2 may be of conventional type with a human driver, or they may be configured for autonomous operation.

[0087] Figure 2 Also shown are a wheel loader 8 loading the vehicles at the loading site 9 and another material carrier vehicle 20 which has dumped its load of unprocessed material 5 into the feeder 32 of the crusher 3 .

[0088] In this case, the crusher 3 is provided with a "simple" level sensor 31, which is configured to determine only whether the level of unprocessed material 5 in the crusher feeder 32 is above or below an upper limit value that does not allow further unprocessed material 5 to be dumped into the crusher 3. The crusher 3 is also provided with a production sensor in the form of a scale integrated in the conveyor belt 33 in order to determine (weigh) the amount of material that has been processed / crushed by the material processing device / crusher 3 (as a supplement to the preset crusher processing rate). It can be noted that during the processing described here, no material is lost or gained (except for some lost dust, etc.), so that a certain weight of processed material 6 corresponds to the same weight of unprocessed material 5.

[0089] The crusher is also provided with a transmitter (indicated by reference numeral 31, i.e. the same as the level sensor) for transmitting, by wireless communication, a signal representing the level of the unprocessed material 5 and a signal representing the amount of processed material. These signals can be received by the first vehicle 1 and the second vehicle 2. It should be noted that for the present invention, the crusher 3 does not have to be provided with any transmitter such as Figure 2 Sensors or transmitters 31 , 33 are shown.

[0090] like Figure 3 As shown, the system 10 may be controlled by the following exemplary general method steps (including some explanatory comments at the end of each step):

[0091] S1- Determine the total amount of unprocessed material 5 (in this case the total weight of rock fragments) that has been dumped into the crusher 3 during a first time period T1 between a first time point t1 and a second time point t2, and wherein, typically, t2 is the current time point, the dumping during T1 having been completed by Figure 2 other vehicles not shown, which have sent the weight of the material they dumped);

[0092] S2-determine the total amount of unprocessed material 5 that has been processed by the crusher 3 during the first time period T1 (also the total weight of rock fragments, obtained according to the preset crusher processing rate multiplied by the duration of T1 and / or obtained from the data measured by the scale of the conveyor belt 33);

[0093] S3 - determining a reference level of the unprocessed material 5 contained in the material processing device 3 at a first point in time t1 (when the level exceeds an upper limit value obtained from the “simple” level sensor 31);

[0094] S4 - determining the current level of the unprocessed material 5 contained in the crusher 3 based on the information obtained in steps S1 - S3 (the difference compared to the reference level depends on the amount of material dumped and processed during T1 );

[0095] S5 - predicting, based on the current level of the unprocessed material 5 contained in the crusher 3 and the expected future processing rate of the crusher 3, a fourth time point t4 at which the level of the unprocessed material 5 is expected to drop below a lower limit value, which indicates that the crusher 3 has run out of or is about to run out of unprocessed material 5 (based on said preset crusher processing rate and, if the prediction is related to the first vehicle 1, also includes the material to be dumped by the second vehicle 2);

[0096] S6-establishing an expected arrival time period Td for the first material carrier vehicle 1 to arrive at the crusher 3, wherein the expected arrival time period Td extends between a start point and an end point, and wherein the end point is set at the latest to a predicted fourth time point t4, at which the material level of the unprocessed material 5 in the crusher 3 is expected to drop below a lower limit value (i.e., calculating the latest arrival time point of the first vehicle 1 to the crusher 3 to avoid the crusher 3 becoming empty); and

[0097] S7 - Adjusting the speed of the first material carrying vehicle 1 so as to reach the crusher 3 within said desired arrival time period Td (ie before a fourth time point t4 when the crusher becomes empty).

[0098] At least steps S1 - S3 do not necessarily have to be performed in the order shown.

[0099] The methods S1-S7 can be performed more or less continuously for each material-carrying vehicle 1 included in the system 10. This means that the method can also be performed for a second vehicle 2 which does not have any material-carrying vehicle in front of it that will dump material before the second vehicle 2 (if it is taken into account that the other vehicle 20 has already dumped its material). Another way of saying the same thing in principle is to say that the second vehicle 2 (and the other vehicle 20) are optional, in which case there is no vehicle in front of the first material-carrying vehicle 1 that will dump any material before the first vehicle.

[0100] One key point of the above method is that a suitable arrival time point or arrival time period can be obtained without using a level sensor that provides an input of the current level of material in the feeder 32; instead, the current level is determined / calculated based on the amount of material dumped into the crusher 3 and the amount of material processed by the crusher 3 between t1 and t2, and a reference value of the level at t1. This reference level can be provided manually or by the "simple" level sensor 31 described above.

[0101] The signal comprising the information related to steps S1-S3 may be received by the receiver 11 of the first vehicle 1 and the calculations and determinations etc. in steps S4-S6 may be performed by the control unit 12. Furthermore, the speed adjustment of the first vehicle 1 in step S7 may be performed by the control unit 12 (possibly indirectly by the control unit 12 if the control unit 12 is not arranged to control the operation of the first vehicle 1 but may send control commands to such an operating control unit). Adjusting the speed may for example mean: displaying a recommended speed for the driver of the first vehicle 1 or, for an autonomous vehicle, directly controlling its speed. The step of adjusting the speed comprises determining the position of the first vehicle 1 and the crusher 3 and determining the distance to be travelled by the first vehicle 1, as is well known.

[0102] In step S1, the total amount of unprocessed material 5 dumped into the feeder 32 of the crusher 3 during the first time period T1 can be obtained by receiving the transmitted information about the weight of all materials dumped into the material processing device 3 during the first time period T1, or, when the materials have substantially the same weight, by receiving information about the number of times the materials were dumped during the first time period T1. For example, the first vehicle 1 and the second vehicle 2 can send information about the weight of its materials at what point in time it has dumped or plans to dump its materials into the crusher 3 to all other vehicles involved (and the previous vehicle has sent this information to the first vehicle 1 and the second vehicle 2).

[0103] The following steps can be added to the above steps S1-S7:

[0104] - determining whether the current level of the unprocessed material 5 in the crusher 3 is above an upper limit value that does not allow additional unprocessed material 5 to be dumped into the crusher 3;

[0105] - predicting, based on the current level of the unprocessed material 5 contained in the crusher 3 and the expected future processing rate of the crusher 3, a third point in time t3 at which the level of the unprocessed material 5 is expected to drop below an upper limit value (which does not allow the dumping of additional unprocessed material 5 into the material processing device 3) so that the dumping of the unprocessed material 5 becomes permitted; and

[0106] - setting the starting point of the expected arrival time period Td to be at the earliest at the predicted third time point t3 at which the level of the unprocessed material 5 in the crusher 3 is expected to drop below the upper limit value.

[0107] Therefore, the expected arrival time period Td may be set to extend between t3 and t4 (or from slightly after t3 to slightly before t4).

[0108] If the current material level is not higher than the upper limit value, the starting point of the expected arrival time period Td may be set to the current time point.

[0109] The step of predicting the third time point t3 and the fourth time point t4 at which the material level of the unprocessed material 5 is expected to drop below the upper limit value or the lower limit value may include the following steps:

[0110] - determining whether another material-carrying vehicle (the second material-carrying vehicle 2) will reach the crusher 3 before the first material-carrying vehicle 1, for example based on the geographical location of the second vehicle 2 sent from the second vehicle 2 to the first vehicle 1; and, when so,

[0111] - predicting the amount of unprocessed material 5 to be dumped by the further material carrier vehicle (the second material carrier vehicle) into the crusher 3 and including this amount when predicting t3 and t4.

[0112] Step S7 may include the following steps:

[0113] - providing information about the current geographical location of the first material handling vehicle 1 (obtained from a global positioning device arranged on board the first vehicle 1);

[0114] - determining the distance between the first material carrier vehicle 1 and the crusher 3 based on the current geographical location of the first material carrier vehicle 1 and information about available routes and the geographical location of the crusher 3 (which may be stored in a memory accessible to the control unit 12);

[0115] - based on the distance between the first material carrier vehicle 1 and the crusher 3 and the end point of the desired arrival time period Td, determining the adjusted minimum average speed so that: if the first material carrier vehicle 1 moves at the minimum average speed, the first material carrier vehicle 1 will reach the crusher 3 at the end point of the desired arrival time period Td; and / or

[0116] - Based on the distance between the first material carrier vehicle 1 and the crusher 3 and the starting point of the desired arrival time period Td, an adjusted maximum average speed is determined so that: if the first material carrier vehicle 1 moves at this maximum average speed, the first material carrier vehicle 1 will reach the crusher 3 at the starting point of the desired arrival time period Td.

[0117] In one embodiment of steps S1-S7, the method includes the following steps (eg Figure 3 shown):

[0118] S100 - receiving, via the receiver 11, a plurality of signals representing the total amount of unprocessed material 5 that has been dumped into the crusher 3 during a first time period T1 between a first time point t1 and a second time point t2, wherein the signals include information about the weight of the dumped material and these weights have been sent from other material transport vehicles.

[0119] S200—receiving, by means of the receiver 11, from a transmitter connected to a productivity sensor integrated in the conveyor belt 33 of the crusher 3, a signal representative of the total amount of unprocessed material 5 that has been processed by the crusher 3 during the first time period T1, and, in addition, obtaining information representative of the total amount of unprocessed material 5 that has been processed by the crusher 3 during the first time period T1 in the form of a preset average processing rate of the crusher 3 accessible to the control unit 12 on board the first material carrier vehicle 1;

[0120] S300 - receiving, by means of the receiver 11, from a transmitter of a level sensor 31 connected to the crusher 3, a signal representing a reference level of the unprocessed material 5 contained in said crusher 3 at a first point in time t1;

[0121] S400 - calculating, by the control unit 12 , the current level of the unprocessed material 5 contained in the crusher 3 based on the received and / or obtained information;

[0122] S500—predicting, by the control unit 12 and based on the current level of the unprocessed material 5 contained in the crusher 3 and the expected future processing rate of the crusher 3, a fourth time point t4 at which the level of the unprocessed material 5 is expected to drop below a lower limit value, which indicates that the crusher 3 has run out of or is about to run out of unprocessed material 5 (in addition or alternatively, the third time point t3 may be predicted as explained above);

[0123] S600 - establishing, by means of the control unit 12, an expected arrival time period Td for the first material carrier vehicle 1 to reach the crusher 3, wherein the expected arrival time period Td extends between a start point and an end point, wherein the end point is set at the latest to a predicted fourth time point t4, at which the material level of the unprocessed material 5 in the crusher 3 is expected to drop below a lower limit value (in addition or alternatively, the third time point t3 may be used to set the starting point); and S700 - setting or indicating, by means of the control unit 12, a speed of the first material carrier vehicle 1 so as to reach the crusher 3 within the expected arrival time period Td.

[0124] It should be understood that the present invention is not limited to the embodiments described above and shown in the drawings; rather, those skilled in the art will recognize that many modifications and variations are possible within the scope of the present invention.

Claims

1. A method for controlling a system (10) comprising a material processing device (3) and at least one material carrier vehicle (1, 2), the at least one material carrier vehicle (1, 2) being configured to transport material of unprocessed material (5) to the material processing device (3) and to dump the unprocessed material (5) directly or indirectly into the material processing device (3), The method is characterized by the following steps: (S1) determining the total amount of unprocessed material (5) that has been poured into the material processing device (3) during a first time period (T1) between a first time point (t1) and a second time point (t2); (S2) determining the total amount of unprocessed material (5) that has been processed by the material processing device (3) during the first time period (T1); (S3) determining a reference material level of the unprocessed material (5) contained in the material processing device (3) at the first time point (t1); (S4) determining a current level of the unprocessed material (5) contained in the material processing device (3) based on i) the total amount of unprocessed material (5) that has been poured into the material processing device (3) during the first time period (T1), ii) the total amount of unprocessed material (5) that has been processed by the material processing device (3) during the first time period (T1), and iii) the reference level of the unprocessed material (5) contained in the material processing device (3) at the first time point (t1); (S5) predicting at least one of the following based on at least a current material level of the unprocessed material (5) contained in the material processing device (3) and an expected future processing rate of the material processing device (3): a third time point (t3), at which the material level of the unprocessed material (5) is expected to drop below an upper limit value, thereby allowing the pouring of the unprocessed material (5), at which the pouring of additional unprocessed material (5) into the material processing device (3) is not allowed, and a fourth time point (t4), at which the material level of the unprocessed material (5) is expected to drop below a lower limit value, the lower limit value indicating that the material processing device (3) has run out of or is about to run out of unprocessed material (5); (S6) establishing an expected arrival time period (Td) for the first material transport vehicle (1) to arrive at the material processing device (3), wherein: The expected arrival time period (Td) extends between a start point and an end point, and wherein at least one of the start point and the end point is set so that the start point is at the third time point (t3) at the earliest and / or so that the end point is at the fourth time point (t4) at the latest; and (S7) adjusting the speed of the first material transport vehicle (1) so as to reach the material processing device (3) within the expected arrival time period (Td).

2. The method according to claim 1, wherein: The method comprises the following steps: - determining whether the current level of the unprocessed material (5) in the material processing device (3) is above the upper limit value which does not allow additional unprocessed material (5) to be dumped into the material processing device (3).

3. The method according to claim 1 or 2, wherein: The method comprises: - determining whether at least a second material handling vehicle (2) will arrive at the material handling device (3) before the first material handling vehicle (1); and, if so, - predicting the amount of unprocessed material (5) to be dumped by the second material carrier vehicle (2) into the material processing device (3); The step of predicting the third time point (t3) and / or the fourth time point (t4) at which the material level of the unprocessed material (5) is expected to drop below the upper limit value or the lower limit value is also based on the predicted amount of unprocessed material (5) to be dumped by the second material transport vehicle (2).

4. The method according to claim 1 or 2, wherein: The method comprises the following steps: - providing information about the current geographical location of the first material handling vehicle (1); - determining the distance between the first material handling vehicle (1) and the material processing installation (3) based on the current geographical location of the first material handling vehicle (1) and information about available routes and the geographical location of the material processing installation (3); - determining an adjusted minimum average speed based on the distance between the first material handling vehicle (1) and the material processing device (3) and the end point of the expected arrival time period (Td), so that: if the first material handling vehicle (1) moves at the minimum average speed, the first material handling vehicle (1) will reach the material processing device (3) at the end point of the expected arrival time period (Td); and / or - Based on the distance between the first material transporting vehicle (1) and the material processing device (3) and the starting point of the expected arrival time period (Td), the adjusted maximum average speed is determined so that: if the first material transporting vehicle (1) moves at the maximum average speed, the first material transporting vehicle (1) will reach the material processing device (3) at the starting point of the expected arrival time period (Td).

5. The method according to claim 1 or 2, wherein: The start point of the expected arrival time period (Td) is set to be somewhere between the current time point and a future time point before the end point of the expected arrival time period (Td).

6. The method according to claim 1 or 2, wherein: The total amount of unprocessed material (5) dumped into the material processing device (3) during the first time period (T1) is at least partially obtained by receiving information about the weight of all materials dumped into the material processing device (3) during the first time period (T1), or, when the materials have substantially the same weight, by receiving information about the number of times the materials were dumped during the first time period (T1).

7. The method according to claim 1 or 2, wherein: The total amount of unprocessed material (5) processed by the material processing device (3) during the first time period (T1) is obtained from information on a standard processing rate or an average processing rate of the material processing device (3), and / or is obtained by receiving information from a weighing measurement of the total amount of processed material (6).

8. The method according to claim 1 or 2, wherein: The reference level of the unprocessed material (5) contained in the material processing device (3) at the first time point (t1) is a lower limit value indicating that the material processing device (3) has run out of or is about to run out of unprocessed material (5).

9. The method according to claim 1 or 2, wherein: At the first time point (t1), the reference material level of the unprocessed material (5) contained in the material processing device (3) is at or above an upper limit value that does not allow additional unprocessed material (5) to be poured into the material processing device (3).

10. The method according to claim 9, wherein: The reference material level of the unprocessed material (5) contained in the material processing device (3) at the first time point (t1) is when the material level decreases and exceeds the upper limit value.

11. The method according to claim 1 or 2, wherein: The second time point (t2) is the current time point.

12. The method according to claim 1 or 2, wherein: The material processing device (3) is a material crusher.

13. The method according to claim 1 or 2, wherein: At least the first material handling vehicle (1) is provided with a receiver (11) for receiving a signal transmitted via wireless communication and a control unit (12) arranged to be in communication connection with the receiver (11), wherein the method comprises the following steps: (S100) receiving, by the receiver (11), at least one signal representing the total amount of unprocessed material (5) that has been dumped into the material processing device (3) during the first time period (T1) between the first time point (t1) and the second time point (t2); (S200) receiving, by means of the receiver (11), at least one signal indicating the total amount of unprocessed material (5) that has been processed by the material processing device (3) during the first time period (T1), and / or obtaining information indicating the total amount of unprocessed material (5) that has been processed by the material processing device (3) during the first time period (T1); (S300) receiving, by means of the receiver (11), at least one signal representing the reference material level of the unprocessed material (5) contained in the material processing device (3) at the first time point (t1); (S400) calculating, by the control unit (12), a current material level of the unprocessed material (5) contained in the material processing device (3) based on the received or obtained information; (S500) predicting at least one of the third time point (t3) and the fourth time point (t4) by the control unit (12) and based at least on the current material level of the unprocessed material (5) contained in the material processing device (3) and the expected future processing rate of the material processing device (3); (S600) establishing, by means of the control unit (12), the expected arrival time period (Td) for the first material carrier vehicle (1) to arrive at the material processing device (3), wherein the expected arrival time period (Td) extends between the starting point and the end point, and wherein at least one of the starting point and the end point is set so that the starting point is at the earliest at the third time point (t3) and / or so that the end point is at the latest at the fourth time point (t4); and (S700) Setting or instructing the speed of the first material transport vehicle (1) by the control unit (12) so as to arrive at the material processing device (3) within the expected arrival time period (Td).

14. The method according to claim 13, wherein: The information on the total amount of unprocessed material (5) that has been processed by the material processing device (3) during the first time period (T1) comprises a standard processing rate or an average processing rate of the material processing device (3).

15. A system (10) comprising a material processing device (3) and at least one material carrier vehicle (1, 2), the at least one material carrier vehicle (1, 2) being configured to transport material of unprocessed material (5) to the material processing device (3) and to dump the unprocessed material (5) directly or indirectly into the material processing device (3), It is characterized in that The system is configured to: - determining the total amount of unprocessed material (5) which has been poured into the material processing device (3) during a first time period (T1) between a first time point (t1) and a second time point (t2); - determining the total amount of unprocessed material (5) that has been processed by said material processing device (3) during said first period of time (T1); - determining a reference level of the unprocessed material (5) contained in the material processing device (3) at the first point in time (t1); - determining a current level of the unprocessed material (5) contained in the material processing device (3) based on i) the total amount of unprocessed material (5) that has been poured into the material processing device (3) during the first time period (T1), ii) the total amount of unprocessed material (5) that has been processed by the material processing device (3) during the first time period (T1), and iii) the reference level of the unprocessed material (5) contained in the material processing device (3) at the first point in time (t1); - predicting at least one of the following based on at least a current level of unprocessed material (5) contained in the material processing device (3) and an expected future processing rate of the material processing device (3): a third time point (t3), at which the material level of the unprocessed material (5) is expected to drop below an upper limit value, thereby allowing the pouring of the unprocessed material (5), at which the pouring of additional unprocessed material (5) into the material processing device (3) is not allowed, and a fourth time point (t4), at which the material level of the unprocessed material (5) is expected to drop below a lower limit value, the lower limit value indicating that the material processing device (3) has run out of or is about to run out of unprocessed material (5); - establishing an expected arrival time period (Td) for the first material handling vehicle (1) to arrive at the material processing device (3), wherein the expected arrival time period (Td) extends between a start point and an end point, and wherein at least one of the start point and the end point is set such that the start point is at the earliest at the third time point (t3) and / or such that the end point is at the latest at the fourth time point (t4); and - adjusting the speed of the first material handling vehicle (1) so as to reach the material processing device (3) within the desired arrival time period (Td).

16. The system (10) of claim 15, wherein: At least the first material transport vehicle (1) is provided with a receiver (11) for receiving a signal transmitted by wireless communication and a control unit (12) arranged to be in communication connection with the receiver (11), wherein the control unit (12) is configured to: calculate a current material level of unprocessed material (5) contained in the material processing device (3), predict the third time point (t3) and / or the fourth time point (t4) at which the material level of the unprocessed material (5) in the material processing device (3) is expected to drop below the upper limit value or the lower limit value, and set or at least indicate the speed of the first material transport vehicle (1) so as to arrive at the material processing device (3) within the expected arrival time period (Td).

17. The system (10) of claim 16, wherein: The system comprises at least a first material handling vehicle (1) and a second material handling vehicle (2), wherein each of the vehicles comprises a receiver (11) and a control unit (12, 22) according to claim 16, and wherein each of the vehicles (1, 2) further comprises a transmitter (21) for wirelessly transmitting a signal representing at least the amount of unprocessed material (5) to be dumped or already dumped into the material processing device (3).

18. The system (10) according to any one of claims 15 to 17, wherein: The material processing device (3) is provided with a material level sensor (31), which is configured to at least determine whether the material level of the unprocessed material (5) is above or below an upper limit value that does not allow additional unprocessed material (5) to be poured into the material processing device (3).

19. The system (10) according to any one of claims 15 to 17, wherein: The material processing device (3) is provided with a production rate sensor (33) configured to determine the amount of material processed by the material processing device (3).

20. The system (10) of claim 18, wherein: The material processing device (3) is provided with a transmitter, and the transmitter of the material processing device (3) is used to transmit a signal indicating the material level of the unprocessed material (5) and / or a signal indicating the amount of processed material through wireless communication.

21. The system (10) according to any one of claims 15 to 17, wherein: The material processing device (3) is a material crusher.

22. The system (10) according to any one of claims 15 to 17, wherein: The material transport vehicle (1, 2) is a transport vehicle or a truck provided with a material receiving bucket (14, 24), wherein the material receiving bucket (14, 24) is suitable for receiving materials in the form of rock fragments, gravel, and sand.

23. A computer readable medium carrying a computer program comprising program code components for performing the steps of the method of any one of claims 1 to 14 when the computer program is run on a computer.

24. A control unit (12, 22) for controlling a system (10) according to any one of claims 15-22, the control unit being configured to perform the steps of the method according to any one of claims 1-14.

25. The control unit (12, 22) according to claim 24, wherein: The control unit is arranged on the material transport vehicle (1, 2).

26. A control unit (12, 22) according to claim 24 or 25, wherein: The control unit is configured to also control the operation of the material handling vehicles (1, 2).

Citation Information

Patent Citations

  • System for calculating desired estimated time of arrival

    WO2015065251A1

  • Vehicle travel route control system

    US6484078B1

  • Method and system for efficient processor usage

    US6529812B1