Cable-stayed bridge cable tower end anchorage device and construction method
By adopting a simplified anchoring device at the cable-stayed bridge cable tower end, the stress capacity of steel components and steel-concrete combination is used to solve the problem of complex stress at the joint position of the anchor structure and concrete tower wall, and the structural durability and Improve construction efficiency.
Patent Information
- Application Number
- CN202110965772.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-08-23
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2041-08-23
AI Technical Summary
The anchoring method of cable-stayed bridge cable tower ends has complex stress on the joint position of the anchor structure and the concrete tower wall, which leads to the tower wall being prone to cracking, affecting the durability of the structure, and is difficult to construct, high cost, and high steel usage, which affects the construction and hoisting. ability.
A cable-stayed bridge cable tower end anchoring device is adopted, including the cable tower middle partition plate and anchor assembly. The anchor assembly is composed of stiffening plate, anchor pull plate and panel. The anchor strength is improved through full penetration welding and shear nails. The pull-end is equipped with fork ears, adjustable sleeves and anchor heads to simplify the structure, utilize the stress capacity of steel components and steel-concrete combinations to reduce material usage and construction costs.
The anchor structure has a reasonable stress, a cheap material usage, good economy, and convenient construction, avoiding tower wall cracks, improving structural durability and construction efficiency, and reducing steel usage and cost.
Smart Images

Figure CN113585069B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of cable-stayed cable tower end anchoring, and in particular to a cable-stayed bridge cable tower end anchoring device and a construction method. Background Art
[0002] At present, there are five main types of anchoring methods for the cable tower ends of cable-stayed bridges: steel anchor box anchoring, steel anchor beam anchoring, annular prestressed anchoring, cross anchoring and cable saddle anchoring.
[0003] However, the current anchoring method for the cable tower end of the cable-stayed bridge has problems such as complex stress at the junction of the anchoring structure and the concrete tower wall, and the concrete tower wall is prone to cracking, which affects the durability of the structure. In addition, during construction, the above-mentioned anchoring method has the problems of large amount of steel consumption, high cost, heavy installation crane, and certain requirements for construction lifting capacity. Summary of the invention
[0004] The present application provides a cable-stayed bridge cable tower end anchoring device and construction method, which can solve the problems in the prior art of complex force at the joint between the anchoring structure and the concrete tower wall, easy cracking of the concrete tower wall, affecting the durability of the structure, and great construction difficulty.
[0005] In a first aspect, the present invention provides a cable-stayed bridge cable tower end anchoring device, comprising:
[0006] A cable tower middle partition plate, configured to be connected to a cable tower middle column and extending in a vertical direction; and
[0007] An anchor assembly, which is arranged on the diaphragm in the cable tower and is used to connect the cables of the cable tower, and includes a stiffening plate and an anchor plate;
[0008] The stiffening plate is anchored at the center of the partition in the cable tower and extends along the transverse direction of the bridge; the anchor plate is anchored at the partition in the cable tower and connected to the stiffening plate, and the anchor plate has relative anchor ends in the longitudinal direction of the bridge, and the anchor ends correspond one by one to the cables on both sides of the cable tower in the longitudinal direction of the bridge, and the anchor ends pass through the sides of the partition in the cable tower to anchor the corresponding cables.
[0009] In the above implementation process, the middle partition of the cable tower is a concrete cast structure, and the middle partition of the cable tower is connected to the middle tower column of the cable tower. The stiffening plate and the anchor plate are both steel components. The stiffening plate is anchored in the center of the middle partition of the cable tower, and the anchor plate is anchored in the middle partition of the cable tower and connected to the stiffening plate. The two anchor ends of the anchor plate pass through the side wall of the middle partition of the cable tower and are anchored with the cable. The anchor plate is a complete plate to ensure the transmission of the force of the cable. The cables on both sides of the cable tower are anchored at the anchor ends of the anchor plate respectively. The balanced horizontal force of the cable is borne by the anchor plate, and the unbalanced horizontal force (including longitudinal and transverse unbalanced horizontal forces) is transmitted to the middle partition of the cable tower by the anchor plate and the stiffening plate, and is borne by the anchor plate, the stiffening plate and the middle partition of the cable tower. It should be noted that the overall structure of the anchor device at the end of the cable tower of the cable-stayed bridge is simple and reliable. The balanced horizontal force fully utilizes the tensile capacity of the steel component (anchor plate), and the unbalanced horizontal force fully utilizes the bearing capacity of the steel-concrete composite component. The longitudinal and lateral force transmission of the relevant components is simple and clear. Therefore, it has the advantages of reasonable force, low material consumption, good economy and convenient construction.
[0010] In an optional embodiment, the number of stiffening plates is two, and the two stiffening plates are located on both sides of the anchor plate upward along the transverse bridge, and are fully penetrated welded to the anchor plate respectively.
[0011] During the above implementation process, the anchor plate and the two stiffening plates are anchored to the middle partition of the cable tower. The stiffening plate is connected to the anchor plate by full penetration welding, which can effectively transfer the unbalanced horizontal force from the anchor plate and the stiffening plate to the middle partition of the cable tower, thereby improving the cable tower's ability to resist imbalance.
[0012] In an optional embodiment, the stiffening plate is provided with a plurality of first shear nails, and the plurality of first shear nails are anchored to the diaphragm in the cable tower;
[0013] The anchor plate is provided with a plurality of second shear nails, and the plurality of second shear nails are anchored to the partition plate in the cable tower.
[0014] In the above implementation process, the first shear nail and the second shear nail can improve the anchoring strength of the stiffening plate and the anchor plate to the diaphragm in the cable tower, and enhance the ability to transmit unbalanced horizontal force to the diaphragm in the cable tower.
[0015] In an optional embodiment, the anchor assembly further comprises a panel;
[0016] The panel is anchored to the side of the partition in the cable tower facing upward on the longitudinal bridge and is connected to the anchor plate. The panel is formed with a perforation for the anchor end of the anchor plate to pass through.
[0017] In the above implementation process, the panel protects the diaphragm in the cable tower, and when pouring the diaphragm in the cable tower, the panel can also be used as a side formwork for the construction of the diaphragm in the cable tower, thereby reducing the construction difficulty and construction cost.
[0018] In an optional embodiment, the panel is provided with a plurality of third shear nails, and the plurality of third shear nails are anchored to the partition plate in the cable tower.
[0019] In the above implementation process, the panel can be firmly fixed to the side of the diaphragm in the cable tower through a plurality of third shear nails. Since the panel is connected to the anchor plate, the unbalanced horizontal force exerted on the anchor plate can be effectively transmitted to the diaphragm in the cable tower through the panel.
[0020] In an optional embodiment, the anchor pull end is configured with a fork ear, an adjustment sleeve and an anchor head;
[0021] A pin hole is formed at the anchor pulling end, the fork ear is connected to the anchor pulling end through the cooperation of the pin shaft and the pin hole, the fork ear is connected to the anchor head through the adjusting sleeve, and the anchor head is used to fix the cable.
[0022] In the above implementation process, the anchor end can be conveniently connected to the cable through the fork ear, the adjusting sleeve and the anchor head. At the same time, the stress-free cable length of the inclined cable can be adjusted through the adjusting sleeve. When the cable is tensioned, the adjusting sleeve is adjusted while tensioning to ensure the force of the inclined cable.
[0023] In an optional embodiment, the cable-stayed bridge cable tower end anchoring device further includes a cable tower outer wall plate;
[0024] The outer wall plate of the cable tower is configured to be connected to the middle tower column of the cable tower, and a protective cavity is formed inside the outer wall plate of the cable tower, and the middle partition plate and the anchor assembly of the cable tower are located in the protective cavity;
[0025] The outer wall panels of the cable tower are provided with pre-buried sleeves for the cables to pass through.
[0026] In the above implementation process, the outer wall of the cable tower can be constructed of concrete structure or steel structure. The outer wall of the cable tower bears the overall force of the cable tower and does not bear the horizontal force of the inclined cable. At the same time, the middle partition of the cable tower is in the protective cavity of the outer wall of the cable tower, so it provides protection for the middle partition of the cable tower and the anchoring assembly, improving the durability of the structure.
[0027] In an optional embodiment, there are multiple anchor assemblies, and the multiple anchor assemblies are arranged on the partition plate in the cable tower along the vertical direction.
[0028] In a second aspect, the present invention provides a construction method for a cable-stayed bridge cable tower end anchoring device, the construction method is used to construct the cable-stayed bridge cable tower end anchoring device of the aforementioned embodiment, the method comprising the following steps:
[0029] Provide anchoring components, assemble stiffening plates and anchor plates;
[0030] Construct the middle partition of the cable tower, tie the steel bars, cast the middle partition of the cable tower and anchor the stiffening plates and anchor plates at the same time.
[0031] In an optional embodiment, the anchor pull end is configured with a fork ear, an adjustment sleeve and an anchor head; the anchor pull end is formed with a pin hole, the fork ear is connected to the anchor pull end through the cooperation of the pin shaft and the pin hole, the fork ear is connected to the anchor head through the adjustment sleeve, and the anchor head is used to fix the cable;
[0032] The method further comprises the following steps:
[0033] The traction cable is connected to the anchor end through the fork ear, the adjustment sleeve and the anchor head;
[0034] Tension the cable, tension the cable through the tensioning device, and adjust the adjusting sleeve at the same time. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0036] Figure 1 Schematic diagram of the anchoring device at the end of the cable tower of the cable-stayed bridge in this embodiment;
[0037] Figure 2 It is a cross-sectional view of the anchoring device at the end of the cable tower of the cable-stayed bridge in this embodiment;
[0038] Figure 3 is a schematic diagram of the anchoring assembly in this embodiment;
[0039] Figure 4 Schematic diagram of the anchor plate in this embodiment;
[0040] Figure 5 Schematic diagram of the anchor plate and two stiffening plates in this embodiment;
[0041] Figure 6 is a schematic diagram of a panel in this embodiment;
[0042] Figure 7 This is a working schematic diagram of the first tensioning device in this embodiment;
[0043] Figure 8 This is a schematic diagram of the operation of the second tensioning device in this embodiment.
[0044] Icons: 10-central partition of cable tower; 11-external wall of cable tower; 110-embedded casing; 12-transition section of cable tower;
[0045] 20-anchor assembly; 21-stiffening plate; 210-first shear nail; 22-anchor plate; 220-anchor end; 23-panel; 230-third shear nail; 231-panel splicing plate;
[0046] 30-fork ear; 31-adjusting sleeve; 32-anchor head; 33-stay cable;
[0047] 40-tensioning screw; 41-pin end distribution beam; 42-anchor head end distribution beam; 43-jack; 44-nut; 45-tensioning end distribution beam; 46-reaction support sleeve. DETAILED DESCRIPTION
[0048] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations.
[0049] Therefore, the following detailed description of the embodiments of the present application provided in the accompanying drawings is not intended to limit the scope of the present application for which protection is sought, but merely represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.
[0050] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0051] In the description of the embodiments of the present application, it should be understood that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, or are the orientations or positional relationships in which the products of the application are conventionally placed when in use, or are the orientations or positional relationships conventionally understood by those skilled in the art. They are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0052] In the description of the embodiments of the present application, it should also be noted that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0053] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application may be combined with each other.
[0054] The technical solution in this application will be described below in conjunction with the accompanying drawings.
[0055] This embodiment provides an anchoring device for the cable tower end of a cable-stayed bridge, which can solve the problems in the prior art of complex force at the joint between the anchoring structure and the concrete tower wall, easy cracking of the concrete tower wall, affecting the durability of the structure, and great construction difficulty.
[0056] See also Figure 1-Figure 3 , Figure 1 Schematic diagram of the anchoring device at the end of the cable tower of the cable-stayed bridge in this embodiment. Figure 2 This is a cross-sectional view of the anchoring device at the end of the cable tower of the cable-stayed bridge in this embodiment. Figure 3 Schematic diagram of the anchor assembly 20 in this embodiment.
[0057] The tower middle partition 10 is configured to be connected to the tower column in the tower and extend in the vertical direction.
[0058] The anchor assembly 20 is disposed on the partition plate 10 in the cable tower and is used to connect the cables of the cable tower. The anchor assembly 20 includes a stiffening plate 21 and an anchor plate 22 .
[0059] It is understandable that there are multiple anchoring assemblies 20, and multiple anchoring assemblies 20 are arranged on the diaphragm 10 in the tower along the vertical direction. Figure 1 It is only exemplarily shown that four anchor assemblies 20 are connected in sequence in the vertical direction, which does not mean that the number of anchor assemblies 20 in the cable tower end anchor device of the cable-stayed bridge provided in this embodiment is four. The number of anchor assemblies 20 may exceed four, for example, five, six or seven, etc. At the same time, it should be noted that, in other embodiments, the number of anchor assemblies 20 in the cable tower end anchor device of the cable-stayed bridge is not limited, and it can be one, two or three, etc.
[0060] It should be noted that the “transverse bridge direction” and “longitudinal bridge direction” described below are Figure 2 Indicated by arrows.
[0061] The stiffening plate 21 is anchored at the center of the diaphragm 10 of the cable tower and extends in the transverse direction. The anchor plate 22 is anchored at the diaphragm 10 of the cable tower and connected to the stiffening plate 21. The anchor plate 22 has relative anchor ends 220 in the longitudinal direction. The anchor ends 220 correspond to the cables 33 on both sides of the cable tower in the longitudinal direction. The anchor ends 220 pass through the side of the diaphragm 10 of the cable tower to anchor the corresponding cables 33.
[0062] See also Figure 4 , Figure 4 It is a schematic diagram of the anchor plate 22 in this embodiment. The anchor plate 22 is a complete plate to ensure the transmission of the force of the cable 33. The cables 33 on both sides are respectively connected to the anchor ends 220 on both sides of the anchor plate 22. The balanced horizontal force of the cable 33 is borne by the anchor plate 22, and the unbalanced horizontal force is transmitted to the middle partition 10 of the cable tower by the anchor plate 22 and the stiffening plate 21. It can be understood that in actual use, when the side and mid-span cables are coplanar, the anchor plate 22 is a flat steel plate; when the side and mid-span cables are not coplanar, the anchor plate 22 is bent through a large radius curve to adapt to the plane of the side and mid-span cables.
[0063] In the above implementation process, the cable tower partition 10 is a concrete casting structure, and the cable tower partition 10 is connected to the cable tower column. The stiffening plate 21 and the anchor plate 22 are both steel components. The stiffening plate 21 is anchored at the center of the cable tower partition 10, and the anchor plate 22 is anchored in the cable tower partition 10 and connected to the stiffening plate 21. The two anchor ends 220 of the anchor plate 22 pass through the side wall of the cable tower partition 10 and are anchored to the cable 33. The anchor plate 22 is a complete plate to ensure the transmission of the force of the cable 33. The cables 33 on both sides of the cable tower are anchored to the anchor ends 220 of the anchor plates 22 respectively. The balanced horizontal force of the cables 33 is borne by the anchor plates 22, and the unbalanced horizontal force (including longitudinal and transverse unbalanced horizontal forces) is transmitted to the cable tower partition 10 by the anchor plates 22 and the stiffening plates 21, and is borne jointly by the anchor plates 22, the stiffening plates 21 and the cable tower partition 10. It should be noted that the overall structure of the anchoring device at the end of the cable tower of the cable-stayed bridge is simple and reliable, the balanced horizontal force fully utilizes the tensile capacity of the steel component (anchor plate 22), the unbalanced horizontal force fully utilizes the bearing capacity of the steel-concrete composite component, and the longitudinal and transverse force transmission of the relevant components is simple and clear, so it has the advantages of reasonable force, low material consumption, good economy and convenient construction.
[0064] In some embodiments of the present application, the number of stiffening plates 21 is two, and the two stiffening plates 21 are located on both sides of the anchor plate 22 along the transverse bridge upward, and are fully penetrated and welded to the anchor plate 22 respectively. Figure 2 and Figure 5 , Figure 5 Schematic diagram of the anchor plate 22 and two stiffening plates 21 in this embodiment.
[0065] During the above-mentioned implementation process, the anchor plate 22 and the two stiffening plates 21 are all anchored to the middle partition plate 10 of the cable tower. The stiffening plate 21 is connected to the anchor plate 22 by full penetration welding, which can effectively transfer the unbalanced horizontal force from the anchor plate 22 and the stiffening plate 21 to the middle partition plate 10 of the cable tower, thereby improving the cable tower's ability to resist imbalance.
[0066] It is understandable that, in some embodiments, the stiffening plate 21 is provided with a plurality of first shear nails 210, and the plurality of first shear nails 210 are anchored to the cable tower diaphragm 10. The anchor plate 22 is provided with a plurality of second shear nails (not shown in the figure), and the plurality of second shear nails are anchored to the cable tower diaphragm 10.
[0067] In the above implementation process, the first shear nail 210 and the second shear nail can improve the anchoring strength between the stiffening plate 21 and the anchor plate 22 and the diaphragm 10 in the cable tower, and enhance the ability to transmit unbalanced horizontal force to the diaphragm 10 in the cable tower.
[0068] In some embodiments of this application, please combine Figure 6 , Figure 6 FIG. 2 is a schematic diagram of the panel 23 in this embodiment.
[0069] The anchor assembly 20 further includes a panel 23. The panel 23 is anchored to the side of the diaphragm 10 in the tower facing upward on the longitudinal bridge and connected to the anchor plate 22. The panel 23 is formed with a perforation through which the anchor end 220 of the anchor plate 22 passes.
[0070] In the above implementation process, the panel 23 protects the cable tower partition 10, and when the cable tower partition 10 is cast, the panel 23 can also be used as a side formwork for the construction of the cable tower partition 10, thereby reducing the construction difficulty and construction cost.
[0071] It can be understood that, in some embodiments, the panel 23 is provided with a plurality of third shear nails 230, and the plurality of third shear nails 230 are anchored to the cable tower diaphragm 10. The panel 23 can be firmly fixed to the side of the cable tower diaphragm 10 through the plurality of third shear nails 230, and since the panel 23 is connected to the anchor plate 22, the unbalanced horizontal force received by the anchor plate 22 can be effectively transmitted to the cable tower diaphragm 10 through the panel 23.
[0072] It can be understood that in an embodiment where there are multiple anchor assemblies 20, the panels 23 of two adjacent anchor assemblies 20 can be welded together so that the two adjacent anchor assemblies 20 are connected to each other; or the panel 23 can be configured with a panel splicing plate 231, and the panel splicing plate 231 can be used in conjunction with bolts to connect the panels 23 of two adjacent anchor assemblies 20.
[0073] Please see again Figure 2 and Figure 3In some embodiments of the present application, the anchor end 220 is configured with a fork ear 30, an adjustment sleeve 31 and an anchor head 32. The anchor end 220 is formed with a pin hole, the fork ear 30 is connected to the anchor end 220 through the cooperation of the pin shaft and the pin hole, the fork ear 30 is connected to the anchor head 32 through the adjustment sleeve 31, and the anchor head 32 is used to fix the cable 33.
[0074] In the above-mentioned implementation process, the anchor end 220 can be conveniently connected to the cable 33 through the fork ear 30, the adjusting sleeve 31 and the anchor head 32. At the same time, the stress-free cable length of the cable 33 can be adjusted through the adjusting sleeve 31. When the cable 33 is tensioned, the adjusting sleeve 31 is adjusted while tensioning to ensure that the inclined cable 33 is stressed.
[0075] In some embodiments of the present application, the cable-stayed bridge cable tower end anchoring device further includes a cable tower outer wall plate 11. The cable tower outer wall plate 11 is configured to be connected to the cable tower middle tower column, and a protective cavity is formed inside the cable tower outer wall plate 11, and the cable tower middle partition plate 10 and the anchor assembly 20 are located in the protective cavity. The cable tower outer wall plate 11 is configured with an embedded sleeve 110, and the embedded sleeve 110 is for the cable 33 to pass through.
[0076] In the above implementation process, the cable tower outer wall plate 11 can be constructed of a concrete structure or a steel structure. The cable tower outer wall plate 11 bears the overall force of the cable tower, and does not bear the horizontal force of the inclined cable 33. At the same time, the cable tower partition plate 10 is in the protection cavity of the cable tower outer wall plate 11, so the cable tower partition plate 10 and the anchor assembly 20 are protected, and the structural durability is improved.
[0077] It should be noted that the cable-stayed bridge cable tower end anchoring device provided above has the following advantages over the prior art:
[0078] The amount of steel used is reduced, the weight of the structure is reduced, and the economy of the structure is improved; the complexity of the force is greatly reduced, avoiding the occurrence of cracks that may occur at the connection between the anchor structure of other anchoring methods and the concrete cable tower; the anchor assembly 20 and the cable tower as a whole perform their respective functions, the structural force is clear, and the cable tower structure is further simplified. The outer tower wall components are simple, avoiding the increase in the complexity of the outer tower wall structure and the truncation of steel bars caused by other structures, and the concrete pouring is convenient, which improves the quality and durability of the structure; the partition 10 in the cable tower uses the panel 23 as a template, and the anchor assembly 20 is not provided with a horizontal steel plate, which is convenient for concrete pouring and has guaranteed quality; the anchor assembly 20 is located inside the cable tower and has good durability; it occupies a small space in the cable tower, and the size of the cable tower can be further optimized. At the same time, ladders and elevators can be set up in the tower for easy maintenance; the simplification of the anchoring device at the end of the cable-stayed bridge cable tower further improves the processing quality of the anchor assembly 20 and the concrete pouring quality, which is more guaranteed, and the subsequent maintenance is more convenient.
[0079] It should be noted that the present application also provides a construction method for a cable-stayed bridge cable tower end anchoring device, which is used to construct the cable-stayed bridge cable tower end anchoring device described above, and the method comprises the following steps:
[0080] Providing an anchor assembly 20, assembling a stiffening plate 21 and an anchor plate 22;
[0081] The diaphragm 10 in the cable tower is constructed, the steel bars are tied, the diaphragm 10 in the cable tower is cast and the stiffening plate 21 and the anchor plate 22 are anchored at the same time.
[0082] It should be noted that, in some embodiments of the present application, the construction method of the anchor device at the end of the cable tower of a cable-stayed bridge also includes the following steps: pulling the cable 33, stretching it to the anchor end 220 through the fork ear 30, the adjusting sleeve 31 and the anchor head 32; tensioning the cable 33, tensioning the cable 33 through the tensioning device, and adjusting the adjusting sleeve 31 at the same time.
[0083] In some embodiments of the present application, the cable-stayed bridge cable tower end anchoring device can be constructed according to the following steps:
[0084] Step 1: Casting the cable tower to the cable tower transition section 12;
[0085] Step 2: completing the prefabrication of the anchor plate 22, the panel 23 and the stiffening plate 21 in the factory;
[0086] Step 3: welding the anchor plate 22, the panel 23 and the stiffening plate 21 in the factory to complete the assembly of the anchor assembly 20;
[0087] Step 4: transport multiple anchoring assemblies 20 to the bridge location, and hoist them to the cable tower transition section 12 by a crane;
[0088] Step 5: Connect two adjacent anchoring assemblies 20 in the vertical direction by welding or by using a panel splicing plate 231;
[0089] Step 6: Tie the steel bars, cast the cable tower outer wall plate 11 and the cable tower middle partition plate 10, and embed the embedded casing 110;
[0090] Step 7: Produce the cable 33 in the factory, and install the fork ear 30, the anchor head 32 and the adjustment sleeve 31 on the cable 33;
[0091] Step 8: Pull the cable so that the cable 33 is connected to the anchor plate 22;
[0092] Step 9: tension the cable 33 through the tensioning device, and adjust the adjusting sleeve 31 synchronously.
[0093] It should be noted that the present application provides two tensioning devices, which will be described below:
[0094] When there is enough space on one side of the tower, the first tensioning device can be used to tension the cable 33 conveniently and quickly. Figure 7 , Figure 7 The diagram is a working diagram of the first tensioning device in this embodiment. The tensioning device includes a tensioning screw 40, a pin-end distribution beam 41, an anchor-end distribution beam 42, a jack 43 and a nut 44. The pin-end distribution beam 41 is arranged on the pin between the cable 33 and the anchor plate 22 and is connected to the tensioning screw 40. The anchor-end distribution beam 42 is fixed to the anchor head 32 and is connected to the tensioning screw 40. The jack 43 is arranged on the side of the anchor-end distribution beam 42 away from the pin-end distribution beam 41 and is connected to the tensioning screw 40. The tensioning screw 40, the pin-end distribution beam 41 and the anchor-end distribution beam 42 are fixed by a nut 44. When the jack 43 is tensioned, the structure composed of the three provides a reaction force for the tensioning of the cable 33.
[0095] When the first tensioning device is used to tension the cable 33, the tensioning process is as follows: installing the tensioning device, pre-tightening the tensioning jack 43; applying pressure from the jack 43, tightening the nut 44 synchronously, and adjusting the adjustment sleeve 31; and removing the tensioning device. It should be noted that in order to reduce the unbalanced horizontal force, the cables 33 on both sides can be tensioned synchronously by two tensioning devices.
[0096] When there is insufficient space on one side of the tower, the second tensioning device can be used, see Figure 8 , Figure 8 Schematic diagram of the working of the second tensioning device in this embodiment. The tensioning device includes a tensioning screw 40, a pin end distribution beam 41, an anchor end distribution beam 42, a jack 43, a nut 44, a tensioning end distribution beam 45 and a reaction support sleeve 46. The pin end distribution beam 41 is arranged on the pin between the cable 33 and the anchor plate 22 and is connected to the reaction support sleeve 46, the anchor end distribution beam 42 is fixed to the anchor head 32 and connected to the tensioning screw 40; the tensioning end distribution beam 45 is connected to the tensioning screw 40 and is located on the side away from the anchor end distribution beam 42; the reaction support sleeve 46 is located between the pin end distribution beam 41 and the tensioning end distribution beam 45, and is connected to the pin end distribution beam 41 and the tensioning end distribution beam 45, and is used to realize the tensioning of the cable 33 on the other side of the partition 10 in the cable tower.
[0097] The tensioning screw rod 40 and the anchor head end distribution beam 42 are connected by a nut 44 , and the tensioning screw rod 40 and the reaction force support sleeve 46 and the tensioning end distribution beam 45 are connected by a nut 44 .
[0098] When the jack 43 is tensioned, the structure composed of the reaction support sleeve 46 and the pin end distribution beam 41 provides a reaction force, thereby achieving the tensioning of the tensioning screw 40. The structure composed of the tensioning screw 40 and the anchor head end distribution beam 42 drives the tensioning of the cable 33.
[0099] When the second tensioning device is used to tension the cable 33, the tensioning process is as follows: installing the tensioning device, pre-tightening the tensioning jack 43; applying pressure by the jack 43, tightening the nut 44 synchronously, and adjusting the adjusting sleeve 31; and removing the tensioning device. It should be noted that in order to reduce the unbalanced horizontal force, the cables 33 on both sides can be tensioned synchronously by two tensioning devices.
[0100] The above are only preferred embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. An anchoring device for the cable tower end of a cable-stayed bridge, It is characterized in that include: The cable tower middle partition is configured to be connected to the cable tower middle column and extend in the vertical direction; as well as An anchor assembly, arranged in the diaphragm of the cable tower and used to connect the cables of the cable tower, the anchor assembly comprising a stiffening plate, a panel and an anchor plate; The stiffening plate is anchored at the center of the diaphragm in the cable tower and extends in the transverse direction of the bridge; the anchor plate is anchored at the diaphragm in the cable tower and connected to the stiffening plate, the anchor plate has relative anchor ends in the longitudinal direction of the bridge, the anchor ends correspond one to one with the cables on both sides of the cable tower in the longitudinal direction, the anchor ends pass through the side of the diaphragm in the cable tower to anchor the corresponding cables, the panel is anchored at the side of the diaphragm in the cable tower facing upward in the longitudinal direction and the panel is connected to the anchor plate, the panel is formed with a through hole, the through hole is for the anchor end of the anchor plate to pass through, the panel is provided with a plurality of third shear nails, the plurality of third shear nails are anchored to the diaphragm in the cable tower, the panel is used as a side formwork for the construction of the diaphragm in the cable tower, and the anchor assembly is not provided with a horizontal steel plate; The cable-stayed bridge cable tower end anchoring device also includes a cable tower outer wall plate; the cable tower outer wall plate is configured to be connected to the cable tower middle tower column, and a protective cavity is formed inside the cable tower outer wall plate, the cable tower middle partition plate and the anchoring assembly are located in the protective cavity; the cable tower outer wall plate is configured with an embedded sleeve, and the embedded sleeve is for the cable to pass through.
2. The cable-stayed bridge cable tower end anchoring device according to claim 1, It is characterized in that There are two stiffening plates, which are located on both sides of the anchor plate upward along the transverse bridge and are fully penetrated and welded to the anchor plate respectively.
3. The cable-stayed bridge cable tower end anchoring device according to claim 1, It is characterized in that The stiffening plate is provided with a plurality of first shear nails, and the plurality of first shear nails are anchored to the diaphragm in the cable tower; The anchor plate is provided with a plurality of second shear nails, and the plurality of second shear nails are anchored to the partition plate in the cable tower.
4. The cable-stayed bridge cable tower end anchoring device according to claim 1, It is characterized in that The anchor pull end is provided with a fork ear, an adjustment sleeve and an anchor head; The anchor end is formed with a pin hole, the fork ear is connected to the anchor end through the cooperation of the pin shaft and the pin hole, the fork ear is connected to the anchor head through the adjustment sleeve, and the anchor head is used to fix the cable.
5. The cable-stayed bridge cable tower end anchoring device according to any one of claims 1 to 4, It is characterized in that There are multiple anchoring assemblies, and the multiple anchoring assemblies are arranged on the partition plate in the cable tower along the vertical direction.
6. A construction method for an anchoring device at the end of a cable tower of a cable-stayed bridge. It is characterized in that The construction method is used to construct the cable tower end anchoring device of the cable-stayed bridge according to claim 1, and the method comprises the following steps: Providing an anchoring assembly to assemble the stiffening plate and the anchor plate; Constructing the diaphragm in the cable tower, tying the steel bars, casting the diaphragm in the cable tower and anchoring the stiffening plate and the anchor plate at the same time; The anchor end is provided with a fork ear, an adjustment sleeve and an anchor head; the anchor end is formed with a pin hole, the fork ear is connected to the anchor end through the cooperation of the pin shaft and the pin hole, the fork ear is connected to the anchor head through the adjustment sleeve, and the anchor head is used to fix the cable; The method further comprises the following steps: A traction cable is connected to the anchor end through the fork ear, the adjustment sleeve and the anchor head; Tensioning the cable, tensioning the cable through a tensioning device and adjusting the adjusting sleeve at the same time; Wherein, the step of tensioning the cable comprises: The tensioning device includes a tensioning screw, a pin-end distribution beam, an anchor-end distribution beam, a jack and a nut; the pin-end distribution beam is arranged on the pin between the cable and the anchor plate and is connected to the tensioning screw, and the anchor-end distribution beam is fixed to the anchor head and is connected to the tensioning screw; the jack is arranged on a side of the anchor-end distribution beam away from the pin-end distribution beam and is connected to the tensioning screw; the tensioning screw, the pin-end distribution beam and the anchor-end distribution beam are fixed by the nut, and when the jack is tensioned, the structure composed of the three provides a reaction force for the tensioning of the cable; the tensioning process is: installing the tensioning device, tensioning the jack for pre-tightening; the jack applies pressure, synchronously tightens the nut, and adjusts the adjusting sleeve; Alternatively, the tensioning device includes a tensioning screw, a pin shaft end distribution beam, an anchor head end distribution beam, a jack, a nut, a tensioning end distribution beam and a reaction force support sleeve, the pin shaft end distribution beam is arranged on the pin shaft between the cable and the anchor plate and is connected to the reaction force support sleeve, the anchor head end distribution beam is fixed to the anchor head and connected to the tensioning screw; the tensioning end distribution beam is connected to the tensioning screw and is located on a side away from the anchor head end distribution beam; the reaction force support sleeve is located between the pin shaft end distribution beam and the tensioning end distribution beam, and is connected to the pin shaft end distribution beam and the tensioning end distribution beam, so as to realize the tensioning in the cable tower. The other side of the partition is used to tension the cable, and the tensioning screw and the anchor head end distribution beam are connected through the nut, and the tensioning screw is connected to the reaction support sleeve and the tensioning end distribution beam through the nut. When the jack is tensioned, the structure composed of the reaction support sleeve and the pin shaft end distribution beam provides reaction force, thereby realizing the tensioning of the tensioning screw, and the structure composed of the tensioning screw and the anchor head end distribution beam drives the tensioning of the cable. The tensioning process is: installing the tensioning device, tensioning the jack for pre-tightening, applying pressure from the jack, synchronously tightening the nut, and adjusting the adjusting sleeve.