A unloading platform for attached lifting scaffolding

By installing cross beams on the unloading platform of the attached lifting scaffold and fixing them with locking devices, the problem of unstable rigidity of the unloading platform in the prior art is solved, and the stable connection and safety improvement of the platform and the main floor slab are achieved, ensuring that Safety and convenience during use.

CN113653340BActive Publication Date: 2024-11-08CHINA MCC5 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111041782.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-09-07
Publication Date
2024-11-08
Estimated Expiration
2041-09-07

AI Technical Summary

Technical Problem

The existing adhesive unloading platform cannot guarantee the overall stiffness stability during use and lifting, and there are safety hazards.

Method used

By installing cross beams on the main floor and fixing the cross beams with the platform with locking devices, ensuring a stable connection between the platform and the main floor and avoiding stress collapse. At the same time, the locking device can be removed during the lifting process to make the platform attached to the attached lifting scaffolding. promote.

Benefits of technology

The platform is stable and stress-bearing is avoided, and the safety is ensured. It is convenient to remove after use, and the connection is firm and reliable.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113653340B_ABST
    Figure CN113653340B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of unloading platforms, and specifically discloses an unloading platform for an attached lifting scaffold, comprising a platform connected to the attached scaffold, a fixing structure installed on a main body floor and connected to the platform; the fixing structure comprises a crossbeam connected to the platform and installed on the main body floor, and a locking device installed on the main body floor and used to lock the crossbeam. The present invention can effectively achieve connection with the main body floor, and the fixing is firm and reliable, and the installation and disassembly are convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of unloading platforms, and more particularly to an unloading platform for an attached lifting scaffold. Background Art

[0002] Unloading platforms are temporary operating platforms often set up at construction sites, generally used for material turnover. With the continuous emergence of high-rise buildings, the role of unloading platforms has become particularly prominent.

[0003] Attached lifting scaffolding refers to an external scaffolding that is erected at a certain height and attached to the engineering structure. It relies on its own lifting equipment and devices to climb or descend layer by layer with the engineering structure and has anti-overturning and anti-falling devices. The attached lifting scaffolding is mainly composed of the attached lifting scaffolding frame structure, attached supports, anti-overturning devices, anti-falling devices, lifting mechanisms and control devices. The attached lifting scaffolding equipment is a new type of scaffolding technology that has developed rapidly in the early 21st century. It has an important impact on the progress of construction technology in my country. It transforms high-altitude operations into low-altitude operations and suspended operations into operations inside the frame. It has significant low-carbon, high-tech content and is more economical, safer and more convenient.

[0004] The current attached unloading platform cannot guarantee the stability of the overall rigidity during use and lifting, and there are certain safety hazards. Summary of the invention

[0005] The technical problem to be solved by the present invention is to provide a discharging platform for an attached lifting scaffold, which can effectively realize the connection with the main floor slab, and has firm and reliable fixing and convenient installation and disassembly.

[0006] The solution adopted by the present invention to solve the technical problem is:

[0007] A material unloading platform for an attached lifting scaffold comprises a platform connected to the attached scaffold, and a fixing structure installed on a main floor and connected to the platform;

[0008] The fixing structure comprises a crossbeam connected to the platform and installed on the main body floor, and a locking device installed on the main body floor and used for locking the crossbeam.

[0009] The present invention connects the platform with the crossbeam, and fixes the platform connected with the crossbeam relative to the main floor slab by locking the crossbeam, so that after the materials are stacked on the platform, the platform can still be stably stressed and will not collapse under stress;

[0010] When the attached lifting scaffold is being lifted, the locking device is removed to separate the crossbeam from the platform, so that the platform can be effectively lifted along with the lifting of the attached lifting scaffold; the two do not interfere with each other, and the connection is stable and reliable.

[0011] In some possible implementations, in order to effectively fix the beams to the main floor slab;

[0012] The locking device comprises a base installed on the main body floor, a clamping part with one end connected to the base and forming a cavity between the base and the main body floor, and a locking piece used for locking the clamping part and the main body floor.

[0013] In some possible implementations, in order to effectively prevent the beam from moving on the main floor;

[0014] The clamping part includes two rectangular tubes with one end vertically connected to the base and parallel to each other, a fixing plate 1 installed on the side of the rectangular tube away from the base and connected to the main floor, and a fixing plate 2 located in the chamber and connected to the side of the two rectangular tubes close to the main floor; a locking groove for locking the crossbeam is formed on the side where the fixing plate 1 and the fixing plate 2 are close to each other.

[0015] In some possible implementations, in order to effectively realize the connection between the rectangular tube and the main floor slab, it can effectively fix the crossbeam;

[0016] A long slot for installing a locking member is formed between the two rectangular tubes; the locking member comprises a locking bolt with one end passing through the main floor slab and a pad located on a side of the long slot away from the main floor slab.

[0017] In some possible implementations, in order to effectively achieve the connection between the platform and the fixed component;

[0018] The platform comprises two main beams connected to the fixed components, a secondary beam located between the two main beams, a bottom plate installed on the main beams and the secondary beams, and a guardrail structure installed on the bottom plate.

[0019] In some possible implementations, the fixing members are in two groups, and the cross beams in the two groups of fixing members are respectively arranged in one-to-one correspondence with the two main beams and are slidably connected.

[0020] In some possible implementations, a slide groove is provided on the top surface of the cross beam along its long direction, and a slide rail cooperating with the slide groove is provided on the main beam along its long direction.

[0021] In some possible implementations, the slide groove is a dovetail groove, and the slide rail is a dovetail slide rail.

[0022] In some possible implementations, there are at least two groups of locking devices on each group of the fixed structures.

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] The present invention effectively locks the crossbeam through the locking device. Since the crossbeam is connected to the platform, the platform and the main floor slab can be effectively connected, so that the device is stable in force during use.

[0025] The present invention effectively restricts the movement of the beam on the main floor slab by setting the fixing plate 1 and the fixing plate 2;

[0026] The present invention provides a slide groove on the crossbeam to achieve sliding cooperation with the slide rail provided on the main beam. When connection is required, the crossbeam is moved closer to one side of the main beam so that the slide rail is inserted into the slide rail, and then connected by bolts. When use is finished, the bolts are removed and the crossbeam is directly pulled to move to the side away from the main beam, so that the crossbeam and the main beam are separated.

[0027] The present invention further prevents the two from being separated during use by providing a dovetail groove on the slide groove and a dovetail slide rail on the slide rail; the installation and disassembly are convenient, and the connection is firm and reliable;

[0028] The invention has simple structure and strong practicability. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a schematic diagram of the top view of the structure of the present invention;

[0030] Figure 2 For the present invention Figure 1 The enlarged schematic diagram of point A in the middle;

[0031] Figure 3 It is a side view of the connection between the main floor plate, the beam and the locking device in the present invention;

[0032] Figure 4 It is a schematic diagram of the connection structure between the main beam and the cross beam in the present invention;

[0033] Among them: 1. Platform; 11. Main beam; 2. Fixed structure; 20. Cross beam; 21. Base; 22. Rectangular tube; 23. Fixed plate 1; 24. Fixed plate 2; 25. Locking bolt; 26. Pad; 3. Main floor slab; 10. Attached scaffolding. DETAILED DESCRIPTION

[0034] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral body; it can be directly connected, or indirectly connected through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. The "first", "second" and similar words mentioned in this application do not indicate any order, quantity or importance, but are only used to distinguish different components. Similarly, "one" or "one" and other similar words do not indicate a quantity restriction, but indicate the existence of at least one. In the implementation of this application, "and / or" describes the association relationship of the associated objects, indicating that there can be three relationships, for example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In the description of the embodiments of the present application, unless otherwise specified, the meaning of "multiple" refers to two or more. For example, multiple positioning columns refer to two or more positioning columns. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0035] The present invention is described in detail below.

[0036] like Figure 1-Figure 4 As shown:

[0037] A material unloading platform 1 for an attached lifting scaffold, comprising a platform 1 connected to an attached scaffold 10, and a fixing structure 2 installed on a main floor slab 3 and connected to the platform 1;

[0038] The fixing structure 2 includes a crossbeam 20 connected to the platform 1 and installed on the main floor slab 3 , and a locking device installed on the main floor slab 3 and used to lock the crossbeam 20 .

[0039] The present invention is connected to the platform 1 through the cross beam 20, and the platform 1 connected to the cross beam 20 is fixed relative to the main floor 3 by locking the cross beam 20, so that after the materials are stacked on the platform 1, the platform 1 can still be stably stressed and will not collapse under stress;

[0040] When the attached lifting scaffold is being lifted, the locking device is removed to separate the cross beam 20 from the platform 1, so that the platform 1 can be effectively lifted along with the lifting of the attached lifting scaffold; the two do not interfere with each other, and the connection is stable and reliable.

[0041] In some possible implementations, in order to effectively fix the cross beam 20 on the main floor slab 3;

[0042] The locking device includes a base 21 installed on the main floor 3, a clamping part with one end connected to the base 21 and forming a cavity between the base 21 and the main floor 3, and a locking member for locking the clamping part and the main floor 3.

[0043] Preferably, Figure 1 , Figure 3 As shown, the base 21 is an angle steel, and a reinforcing plate is welded at the 90° angle formed by the base 21; the use of angle steel for the base 21 will effectively increase the contact area between the locking device and the main floor slab 3, thereby making the crossbeam 20 more stable in force;

[0044] The clamping part is mainly used to clamp the cross beam 20 in the cavity formed by the cross beam 20 and the main floor slab 3; the cross beam 20 is fixedly connected to the main floor slab 3 through the locking member; and the cross beam 20 is prevented from moving upward under force after being connected to the platform 1;

[0045] In some possible implementations, in order to effectively prevent the cross beam 20 from moving on the main floor slab 3;

[0046] The clamping part includes two rectangular tubes 22 which are vertically connected to the base 21 at one end and are parallel to each other, a fixing plate 1 23 which is installed on the side of the rectangular tube 22 away from the base 21 and abuts against the main floor 3, and a fixing plate 24 which is located in the chamber and one end of which is connected to the side of the two rectangular tubes 22 close to the main floor 3; a locking groove for locking the cross beam 20 is formed on the side where the fixing plate 1 23 and the fixing plate 2 24 are close to each other.

[0047] The cross beam 20 is fixed on both sides along its length direction by the cooperation between the fixing plate 1 23 and the fixing plate 2 24 to prevent it from moving along its width direction, and the rectangular tube 22 prevents it from moving upward, making the fixation of the cross beam 20 more effective.

[0048] In some possible implementations, in order to effectively realize the connection between the rectangular tube 22 and the main floor slab 3, it can be effectively fixed to the crossbeam 20;

[0049] A long slot for installing a locking member is formed between the two rectangular tubes 22 ; the locking member includes a locking bolt 25 with one end passing through the main floor slab 3 , and a pad 26 located on a side of the long slot away from the main floor slab 3 .

[0050] The two rectangular tubes 22 are arranged in parallel and vertically connected to the base 21, forming a chamber between the two rectangular tubes and the main floor slab 3; at the same time, a long groove for installing a locking piece is formed between the two rectangular tubes; the locking piece passes through the long groove and is connected to the main floor slab 3, thereby realizing the connection between the rectangular tube 22 and the main floor slab 3.

[0051] The rectangular tubes 22 are arranged in parallel to form long grooves, so that the locking member can find the best fixing point in the locking groove; the best fixing point mentioned here refers to the position of the plate reinforcement in the main floor slab 3 that is staggered.

[0052] The best fixing point can be obtained by using a steel bar detection device, and then a hole can be punched here for the locking bolt 25 to pass through, effectively avoiding the drilling of holes on the plate reinforcement to affect the structure of the main floor slab 3.

[0053] One end of the locking bolt 25 passes through the main floor slab 3 and is locked with a locking nut; the other end is covered with a backing plate 26 and then locked with a locking nut.

[0054] Of course, the bottom of the main floor slab 3 can also be covered with a pad 26.

[0055] In some possible implementations, in order to effectively realize the connection between the platform 1 and the fixed component;

[0056] The platform 1 includes two main beams 11 connected to the fixed components, a secondary beam located between the two main beams 11, a bottom plate installed on the main beams 11 and the secondary beams, and a guardrail structure installed on the bottom plate.

[0057] In some possible implementations, the fixing members are in two groups, and the cross beams 20 in the two groups of fixing members are respectively arranged in one-to-one correspondence with the two main beams 11 and are slidably connected.

[0058] The two groups of fixing components are symmetrically arranged, which effectively fixes the platform 1 and makes the force on the platform 1 more uniform.

[0059] In some possible implementations, a slide groove is provided on the top surface of the cross beam 20 along its long direction, and a slide rail cooperating with the slide groove is provided on the main beam 11 along its long direction.

[0060] In some possible implementations, the slide groove is a dovetail groove, and the slide rail is a dovetail slide rail.

[0061] In some possible implementations, there are at least two groups of locking devices on each group of the fixing structures 2 .

[0062] At least two locking groups on a set of fixing structures 2 are arranged in parallel and evenly installed on the crossbeam 20 to effectively fix the crossbeam 20.

[0063] Preferably, Figure 4 As shown, the cross beam 20 is made of I-beam, and a slide groove is arranged on the top surface thereof; the main beam 11 is made of channel steel, and a slide rail matching the slide groove is arranged at the bottom of the groove in the channel steel.

[0064] Before connecting the main beam 11 and the cross beam 20, the cross beam 20 is not locked. The cross beam 20 is moved to one side of the main beam 11 according to the position of the main beam 11, so that the two are connected with the cooperation of the slide groove and the slide rail; then the connection between the two is further strengthened by bolts; after the main beam 11 and the cross beam 20 are relatively fixed, the fixing structure 2 is fixed on the cross beam 20, so that the cross beam 20 is connected with the main floor slab 3;

[0065] As the number of floors increases, the attached scaffolding 10 will be lifted. At this time, the fixed structure 2 is first removed, the connecting bolts between the cross beam 20 and the main beam 11 are removed, and the cross beam 20 is moved to a side away from the main beam 11 to separate the two.

[0066] The present invention is not limited to the above-mentioned specific embodiments, but extends to any new features or any new combination disclosed in this specification, as well as any new method or process steps or any new combination disclosed.

Claims

1. A material unloading platform for an attached lifting scaffold, characterized in that: It includes a platform connected to the attached scaffolding, and a fixed structure installed on the main floor and connected to the platform; the fixed structure includes a beam connected to the platform and installed on the main floor, and a locking device installed on the main floor and used to lock the beam; The locking device comprises a base installed on the main floor, a clamping part with one end connected to the base and forming a cavity between the base and the main floor, and a locking piece for locking the clamping part and the main floor; the clamping part comprises two rectangular tubes with one end connected to the base vertically and parallel to each other, a fixing plate 1 installed on the side of the rectangular tube away from the base and connected to the main floor, and a fixing plate 2 located in the cavity and connected to the side of the two rectangular tubes close to the main floor; a locking groove for locking the crossbeam is formed on the side of the fixing plate 1 and the fixing plate 2 close to each other; a long groove for installing the locking piece is formed between the two rectangular tubes; The locking member includes a locking bolt with one end passing through the main floor slab, and a pad located on the side of the long slot away from the main floor slab; the platform includes two main beams connected to the fixing member, a secondary beam located between the two main beams, a bottom plate installed on the main beam and the secondary beam, and a guardrail structure installed on the bottom plate; There are two groups of fixed components, and the cross beams in the two groups of fixed components are respectively arranged in one-to-one correspondence with the two main beams and are slidably connected; the top surface of the cross beam is provided with a slide groove along its long direction, and the main beam is provided with a slide rail matching the slide groove along its long direction; the slide groove is a dovetail groove, and the slide rail is a dovetail slide rail; there are at least two groups of locking devices on each group of the fixed structures.