A safety early warning system for coal mine mining
By setting up multiple sets of pressure monitoring anchors and related devices on the outside of the coal mine tunnel, monitoring the internal pressure changes of rocks and conducting zoning warnings, the problem that the existing technology cannot be warning in advance is solved, and effective monitoring of the internal deformation of rocks outside the coal mine tunnel is achieved and Early warning reduces the risk of accidents.
Patent Information
- Application Number
- CN202111095937.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-09-11
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2041-09-11
AI Technical Summary
The existing coal mine mining safety warning devices mainly monitor the deformation pressure of the rock layer on the surface of the tunnel, and cannot warning the deformation of the rock layer inside the rock outside the coal mine tunnel in advance, resulting in timely response measures, resulting in casualties and equipment losses.
Multiple sets of pressure monitoring anchors are used to comprehensively monitor the pressure changes in the rocks inside the rocks outside the coal mine tunnel, and the zoned warning is carried out through pressure sensors and data processors to warn construction personnel in advance, including pressure monitoring anchors, square troughs, anchor grid pressure plates, The main device consisting of fastening nuts, lower protective caps, fixed card sleeves, limit slots, elastic rubber sheets, rotating blocks and threading holes, combined with signal converters, data processors and controllers to achieve changes in rock pressure Real-time monitoring and early warning.
It can be used to early warning time, so that construction workers have sufficient time to take countermeasures, effectively reduce casualties and equipment losses, and has a simple and practical structure.
Smart Images

Figure CN113685212B_ABST
Abstract
Description
Technical Field
[0001] The invention discloses a safety warning system for coal mining, which relates to a safety warning system used in coal mining and belongs to the technical field of coal mining. In particular, it relates to a safety warning system that comprehensively monitors the pressure changes of the internal rock formations outside the coal mine tunnel by setting multiple groups of pressure monitoring anchor rods, and performs zoned warnings according to the pressure changes of the internal rock formations, which can advance the warning time, so that construction personnel have sufficient time to take appropriate countermeasures, and effectively reduce casualties and equipment losses. Background Art
[0002] Before coal mining, coal and rock masses are generally affected by gravity, and the forces in all aspects are balanced, and there is no pressure phenomenon. However, as the tunnel excavation work proceeds, a certain space is formed, causing the roof rock to be exposed, thereby destroying the original balanced and stable state of the stratum, and the rock begins to move and deform. The force generated by this rock activity is called mine pressure. During coal mining, in order to prevent the mine pressure from damaging the coal mine tunnels, the coal mine tunnels need to be supported. The most common coal mine tunnel support method is anchor support. However, when the mine pressure is greater than the maximum tensile shear strength that the anchor can withstand, the anchor will break, making it difficult to support the coal mine tunnel, which may lead to roof collapse accidents in the coal mine tunnels. If coal miners are not reminded in time, they will be in danger before a safety incident occurs. Therefore, if the workers do not react quickly, serious casualties may occur. Since the movement and deformation of the rock layer outside the coal mine tunnel is not instantaneous, safety warnings can be given to coal miners before a safety accident occurs. The existing coal mine mining safety warning devices mainly perform safety warnings by monitoring the deformation pressure of the rock layer on the surface of the coal mine tunnel. However, generally speaking, the internal rock layer of the rock outside the coal mine tunnel will move and deform earlier than the rock layer on the surface of the coal mine tunnel. If the deformation pressure of the rock layer on the surface of the coal mine tunnel is monitored, safety warnings cannot be given in advance. When the deformation pressure of the rock layer on the surface of the coal mine tunnel is detected to exceed the threshold, it may be too late to implement response measures to the safety accident, which may also result in casualties and equipment damage.
[0003] Announcement No. CN112033276A discloses a tunnel deformation monitoring device consisting of a main device and an early warning device. The main device consists of a support frame, a base, a control box, a cross bar and a warning light. The early warning device consists of a connecting plate, a fixed rod, a slide seat, a copper core, a conductive rod, a conductive plate, a spring, a slider, a fixed groove, a slide groove and a conductive groove. The device monitors the deformation of the rock strata on the surface of the tunnel by utilizing changes in current intensity. Usually, the internal rock strata of the rock outside the coal mine tunnel will move and deform earlier than the surface rock strata of the coal mine tunnel. When the monitored current value is less than the early warning threshold, it may be too late to implement response measures for the safety accident, which may also cause casualties and damage to equipment.
[0004] Announcement No. CN110821541A discloses a graded early warning and protective anchor device in a coal mine, including an anchor, which is inserted into a coal seam roof, and one end of the anchor extends out of the coal seam roof to form an extension, on which an external thread is provided. The extension is sequentially sleeved with a stress sensor, a tray and a clamping nut from top to bottom, the clamping nut is threadedly connected to the extension and presses the tray and the stress sensor upward against the coal seam roof, and a buzzer and an alarm light are provided on the tray. The device performs light and sound alarms in advance according to changes in the stress on the anchor, but the device only monitors the stress changes of deformation of the rock strata on the surface of the tunnel through the stress sensor, and cannot monitor the stress changes of deformation of the internal rock strata of the rock outside the coal mine tunnel. Summary of the invention
[0005] In order to improve the above situation, the present invention provides a safety warning system for coal mine development, which provides a safety warning system that comprehensively monitors the pressure changes of the internal rock strata outside the coal mine tunnel through the arrangement of multiple groups of pressure monitoring anchor rods, and performs zoned warning according to the pressure changes of the internal rock strata. The warning time can be advanced, so that the construction personnel have sufficient time to take appropriate response measures, thereby effectively reducing casualties and equipment losses.
[0006] A safety warning system for coal mine mining of the present invention is implemented as follows: A safety warning system for coal mine mining of the present invention is composed of a main device and a pressure monitoring device, the main device is composed of a pressure monitoring anchor rod, a square through groove, an anchor net pressure plate, a fastening nut, a lower protective cap, a fixed sleeve, a limit slot, an elastic rubber sheet, a rotating block and a threading hole, the pressure monitoring anchor rod is hollow inside, and a plurality of square through grooves are equidistantly opened on the pressure monitoring anchor rod along the circumferential direction, the plurality of square through grooves are close to one end of the pressure monitoring anchor rod, an elastic rubber sheet is placed on the square through groove, a fixed sleeve is built-in at one end of the pressure monitoring anchor rod, two limit slots are opened on the inner wall of the fixed sleeve, the two limit slots are symmetrical about the center line of the fixed sleeve, and the limit slot is a lower opening structure The other end of the pressure monitoring anchor rod is an open structure, and a thread is formed on the outer surface of the pressure monitoring anchor rod, and the thread extends from the other end of the pressure monitoring anchor rod to one-third of the pressure monitoring anchor rod. A thread is formed on the inner wall of the lower protective cap, and the other end of the pressure monitoring anchor rod passes through the anchor net pressure plate and is screwed to the lower protective cap. A sealing gasket is placed between the other end of the pressure monitoring anchor rod and the lower protective cap, and the rotating block is placed in the lower protective cap. A through hole is formed in the rotating block, and the through hole is divided into an upper and lower section. The diameter of the upper section of the through hole is smaller than the diameter of the lower section, and the length of the upper section of the through hole is greater than the length of the lower section. A threading hole is formed below the lower protective cap, and the threading hole is connected to the pressure monitoring anchor rod. A detachable sealing ring sleeve is built into the threading hole, and a fastening nut It is screwed together with the pressure monitoring anchor rod, and the fastening nut is located under the anchor net pressure plate. The pressure monitoring device is composed of a fixed clip, an insertion rod, an adjusting rod, an electric telescopic rod, an arc-shaped support plate, a pressure sensor, a fixed block, a warning light and a control box. A fixed block is arranged at one end of the insertion rod, and the fixed block is rotatably arranged in the lower through hole in the rotating block. The other end of the insertion rod passes through the upper through hole in the rotating block and extends upward into the fixed clip sleeve. Two fixed clips are arranged at the other end of the insertion rod, and the two fixed clips are inserted into two limit slots one by one. A plurality of adjusting rods are arranged equidistantly along the circumference of the insertion rod, and a plurality of arc-shaped support plates correspond to a plurality of adjusting rods one by one. One end of the adjusting rod is hinged to the insertion rod through a hinged ear, and the other end is hinged to the corresponding arc-shaped support through a hinged ear. The plates are hinged at one-third of each other, the multiple arc-shaped support plates correspond to the multiple square through grooves one by one, the thickness of the arc-shaped support plates gradually decreases from bottom to top, the pressure sensor is placed on the outer side of the arc-shaped support plate, an electric telescopic rod is placed between the adjusting rod and the plug rod, one end of the electric telescopic rod is hinged to the plug rod through a hinge ear, and the other end is hinged to the corresponding adjusting rod through a hinge ear, the hinge of the plug rod and the electric telescopic rod is higher than the hinge of the corresponding adjusting rod and the electric telescopic rod, the warning light is placed on the control box, the control box is respectively provided with a signal converter, a data processor, a controller and a sound alarm, the pressure sensor, the signal converter, the data processor, the controller, the sound alarm and the warning light are connected through a power cord;
[0007] The signal converter is capable of receiving the pressure signal of the pressure sensor and performing signal conversion;
[0008] The data processor and the signal converter perform information exchange, and a computer program is stored in the data processor, and the following steps are implemented when the program is executed:
[0009] Receive the pressure signal transmitted by the signal converter, and perform data processing to obtain the pressure value of the rock formation inside the rock outside the current tunnel, and compare the processed pressure value with the preset value in the data processor;
[0010] The controller and the data processor exchange information and execute instructions issued by the data processor, so as to control the start and stop of the sound alarm and the color change of the warning light.
[0011] Beneficial Effects
[0012] 1. It can comprehensively monitor the pressure changes of the rock formations outside the coal mine tunnels and provide zoned early warnings based on the pressure changes of the internal rock formations.
[0013] 2. A safety warning system that can provide early warning so that construction personnel have sufficient time to take appropriate countermeasures and effectively reduce casualties and equipment losses.
[0014] 3. Simple structure, convenient and practical. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is a structural schematic diagram of a safety early warning system for coal mine development according to the present invention;
[0016] Figure 2 This is a structural schematic diagram of a pressure monitoring anchor rod of a safety early warning system for coal mining according to the present invention;
[0017] Figure 3 This is a schematic diagram of the structure of a pressure monitoring anchor rod of a safety early warning system for coal mining according to the present invention, which only shows the internal connection of the upper part of the anchor rod;
[0018] Figure 4 A schematic diagram of a pressure monitoring structure of a safety early warning system for coal mining according to the present invention;
[0019] Figure 5 A three-dimensional structural diagram of a pressure monitoring structure of a safety early warning system for coal mining according to the present invention;
[0020] Figure 6 This is a schematic diagram of the structure of a pressure monitoring anchor rod of a safety early warning system for coal mining according to the present invention, which only shows the internal connection of the lower part of the anchor rod.
[0021] In the attached figure
[0022] The components include: a pressure monitoring anchor rod (1), a common anchor rod (2), a warning light (3), a control box (4), a square through slot (5), an anchor net pressure plate (6), a fastening nut (7), a lower protective cap (8), a fixing sleeve (9), a fixing clip strip (10), an insert rod (11), an elastic rubber sheet (12), a limit slot (13), an adjustment rod (14), an electric telescopic rod (15), an arc-shaped support plate (16), a pressure sensor (17), a threading hole (18), a fixing block (19), and a rotating block (20). DETAILED DESCRIPTION
[0023] The invention discloses a safety early warning system for coal mine exploitation, which is realized in this way. The system is composed of a main device and a pressure monitoring device. The main device is composed of a pressure monitoring anchor rod (1), a square through groove (5), an anchor net pressure plate (6), a fastening nut (7), a lower protective cap (8), a fixed clamping sleeve (9), a limit slot (13), an elastic rubber sheet (12), a rotating block (20) and a threading hole (18). The pressure monitoring anchor rod (1) is hollow inside, and a plurality of square through grooves (5) are equidistantly formed on the pressure monitoring anchor rod (1) along the circumferential direction. The plurality of square through grooves (5) are close to one end of the pressure monitoring anchor rod (1), and an elastic rubber sheet (12) is placed on the square through groove (5). A fixed clamping sleeve (9) is built into one end of the pressure monitoring anchor rod (1). The fixed clamping sleeve (9) The inner wall is provided with two limit slots (13), the two limit slots (13) are symmetrical about the center line of the fixed sleeve (9), the limit slots (13) are of a downward opening structure, the other end of the pressure monitoring anchor rod (1) is of an open structure, the outer surface of the pressure monitoring anchor rod (1) is provided with a thread, the thread extends from the other end of the pressure monitoring anchor rod (1) to one third of the pressure monitoring anchor rod (1), the inner wall of the lower protective cap (8) is provided with a thread, the other end of the pressure monitoring anchor rod (1) passes through the anchor net pressure plate (6) and is screwed to the lower protective cap (8), a sealing gasket is placed between the other end of the pressure monitoring anchor rod (1) and the lower protective cap (8), the rotating block (20) is placed in the lower protective cap (8), the rotating block (2 0) is provided with a through hole, the through hole is divided into two sections, the diameter of the upper section of the through hole is smaller than the diameter of the lower section, the length of the upper section of the through hole is greater than the length of the lower section, a threading hole (18) is provided below the lower protective cap (8), the threading hole (18) is connected to the pressure monitoring anchor rod (1), a detachable sealing ring sleeve is built in the threading hole (18), a fastening nut (7) and the pressure monitoring anchor rod (1) are screwed together, the fastening nut (7) is located below the anchor net pressure plate (6), the pressure monitoring device is composed of a fixed clamping strip (10), an insertion rod (11), an adjustment rod (14), an electric telescopic rod (15), an arc support plate (16), a pressure sensor (17), a fixing block (19), a warning light (3) and a control box (4), the insertion rod ( A fixing block (19) is arranged at one end of the rod (11), and the fixing block (19) is rotatably arranged in a lower through hole in a rotating block (20). The other end of the insertion rod (11) passes through an upper through hole in the rotating block (20) and extends upward to a fixing sleeve (9). Two fixing clips (10) are arranged at the other end of the insertion rod (11), and the two fixing clips (10) are inserted into two limiting slots (13) in a one-to-one manner. A plurality of adjusting rods (14) are arranged equidistantly along the circumference of the insertion rod (11), and a plurality of arc-shaped support plates (16) and a plurality of adjusting rods (14) are in one-to-one correspondence. One end of the adjusting rod (14) is hinged to the insertion rod (11) through a hinged ear, and the other end is hinged to a third of the corresponding arc-shaped support plate (16) through a hinged ear.The plurality of arc-shaped support plates (16) correspond to the plurality of square through grooves (5) one by one, the thickness of the arc-shaped support plates (16) gradually decreases from bottom to top, the pressure sensor (17) is arranged on the outer surface of the arc-shaped support plate (16), an electric telescopic rod (15) is arranged between the adjustment rod (14) and the insertion rod (11), one end of the electric telescopic rod (15) is hinged to the insertion rod (11) through a hinge ear, and the other end is hinged to the corresponding adjustment rod (14) through a hinge ear, the hinge point of the insertion rod (11) and the electric telescopic rod (15) is higher than the hinge point of the corresponding adjustment rod (14) and the electric telescopic rod (15), the warning light (3) is arranged on the control box (4), the control box (4) is respectively provided with a signal converter, a data processor, a controller and a sound alarm, and the pressure sensor (17), the signal converter, the data processor, the controller, the sound alarm and the warning light (3) are connected through a power line;,
[0024] The signal converter is capable of receiving a pressure signal from a pressure sensor (17) and performing signal conversion;
[0025] The data processor and the signal converter perform information exchange, and a computer program is stored in the data processor, and the following steps are implemented when the program is executed:
[0026] Receive the pressure signal transmitted by the signal converter, and perform data processing to obtain the pressure value of the rock formation inside the rock outside the current tunnel, and compare the processed pressure value with the preset value in the data processor;
[0027] The controller and the data processor exchange information and execute instructions issued by the data processor, thereby controlling the start and stop of the sound alarm and the color change of the warning light (3);
[0028] When in use, firstly, anchor holes are drilled in the side walls and top plates of the tunnel, then anchoring agent is injected into the anchor holes, then the common anchor rods (2) and the pressure monitoring anchor rods (1) are cross-inserted into the anchor holes one by one, first the common anchor rods (2) are fixed, then the anchor net pressure plate (6) is passed through the pressure monitoring anchor rod (1) to fit the anchor net, then the fastening nut (7) is passed through the pressure monitoring anchor rod (1) and tightened so that the anchor net pressure plate (6) fits the anchor net tightly, then the insertion rod (11) is inserted into the pressure monitoring anchor rod (1), and the fixing clip (10) at one end of the insertion rod (11) is inserted into the limiting slot (13), and the limiting slot (13) limits the insertion rod (11) through the fixing clip (10) to prevent it from rotating in the pressure monitoring anchor rod (1), and then the other end of the pressure monitoring anchor rod (1) is screwed The lower protective cap (8) seals the pressure monitoring anchor rod (1) to prevent dust and water vapor in the tunnel from entering the pressure monitoring anchor rod (1). The rotating block (20) can prevent the plug rod (11) and the pressure monitoring anchor rod (1) from rotating relative to each other when the lower protective cap (8) and the pressure monitoring anchor rod (1) are screwed together. At the same time, the threading hole (18) below the lower protective cap (8) can allow the power lines of the pressure sensor (17) and the electric telescopic rod (15) to pass through. Then, the electric telescopic rod (15) is started and controlled to extend, driving the arc-shaped support plate (16) to extend outward, thereby driving the pressure sensor (17) to extend outward, so that the pressure sensor (17) presses against the elastic rubber sheet (12) to stretch the elastic rubber sheet (12) tightly against the anchoring agent.
[0029] The preset pressure value interval is set as interval A where the pressure is less than the tensile shear strength of the pressure monitoring anchor rod (1), interval B where the pressure is set so that the pressure monitoring anchor rod (1) is deformed but not broken, and interval C where the pressure is greater than the tensile shear strength of the pressure monitoring anchor rod (1). The data interval can be obtained through experimental testing.
[0030] The pressure sensor (17) transmits the monitored pressure signal of the rock formation inside the rock outside the tunnel to the signal converter, and the signal converter performs signal conversion and exchanges information with the data processor. The data processor stores a computer program, and when the program is executed, the following steps are implemented: receiving the pressure signal transmitted by the signal converter, and performing data processing to obtain the current pressure value of the rock formation inside the rock outside the tunnel, and comparing the processed pressure value with a preset value in the data processor;
[0031] When the pressure value is within the A range, the data processor sends a command to the controller, causing the controller to control the warning light (3) to light up green.
[0032] When the pressure value is in the B range, the data processor sends a command to the controller, causing the controller to control the warning light (3) to light up yellow, and the coal miners can reinforce the coal mine tunnel again;
[0033] When the pressure value is in the C range, the data processor sends a command to the controller, causing the controller to control the warning light (3) to light up red, and to control the sound alarm in the control box (4) to sound an alarm. At the same time, the data processor sends a danger signal to the background control center for alarm, and the background control center instructs the coal miners to implement countermeasures for safety accidents.
[0034] The threading hole (18) is provided with a detachable sealing sleeve, which can seal the threading hole (18) to prevent dust and water vapor in the tunnel from entering the pressure monitoring anchor rod (1) through the threading hole (18).
[0035] The design of the fixed block (19) being rotatably disposed in the lower through hole of the rotating block (20) can prevent the insertion rod (11) from rotating relative to the pressure monitoring anchor rod (1) when the lower protective cap (8) and the pressure monitoring anchor rod (1) are screwed together;
[0036] The outer surface of the pressure monitoring anchor rod (1) is provided with a thread, and the thread extends from the other end of the pressure monitoring anchor rod (1) to one third of the pressure monitoring anchor rod (1), so as to facilitate the lower thread cap to seal the pressure monitoring anchor rod (1), and at the same time, the pressure monitoring anchor rod (1) that penetrates into the rock formation outside the tunnel has a larger contact area with the rock formation;
[0037] The hinged joint of the insertion rod (11) and the electric telescopic rod (15) is designed to be higher than the hinged joint of the corresponding adjustment rod (14) and the electric telescopic rod (15), so that the electric telescopic rod (15) can save more effort when pushing the adjustment rod (14);
[0038] The design of the arc-shaped support plate (16) gradually decreasing in thickness from bottom to top enables the pressure sensor (17) to fit the rock formation more closely during the process of the arc-shaped support plate (16) expanding outwards;
[0039] The design of placing an elastic rubber sheet (12) on the square through groove (5) can prevent the pressure sensor (17) from directly contacting the anchoring agent and the mine rock formation, thereby providing protection for the pressure sensor (17);
[0040] The purpose is to comprehensively monitor the pressure changes of the internal rock strata outside the coal mine tunnel by setting up multiple groups of pressure monitoring anchor rods (1), and to carry out zoned early warning according to the pressure changes of the internal rock strata, so as to provide early warning time, so that construction personnel have sufficient time to take appropriate response measures, and effectively reduce casualties and equipment losses.
Claims
1. A safety early warning system for coal mining, Its characteristics are: The pressure monitoring anchor is hollow inside, and a plurality of square through grooves are equidistantly arranged on the upper surface of the pressure monitoring anchor along the circumferential direction. The plurality of square through grooves are close to one end of the pressure monitoring anchor, and an elastic rubber sheet is arranged on the square through groove. A fixing sleeve is arranged at one end of the pressure monitoring anchor, and two limiting slots are arranged on the inner wall of the fixing sleeve, and the two limiting slots are symmetrical about the center line of the fixing sleeve. The limiting slots are a downward opening structure, and a thread is arranged on the inner wall of the lower protective cap. The other end of the pressure monitoring anchor passes through the anchor net pressure plate and is screwed to the lower protective cap. A sealing gasket is arranged between the other end of the pressure monitoring anchor and the lower protective cap, and a rotating block is arranged in the lower protective cap. A threading hole is arranged under the lower protective cap, and the threading hole is connected to the pressure monitoring anchor, and the fastening nut is screwed to the pressure monitoring anchor, and the fastening nut is located under the anchor net pressure plate. A fixing block is arranged at one end of the inserted rod, and the fixing block is rotatably arranged in the rotating block The cam is provided with two fixing clips at the other end, and the two fixing clips are inserted into two limit slots one by one. The cam is provided with a plurality of adjusting rods equidistantly along the circumference, and the plurality of arc-shaped support plates correspond to the plurality of adjusting rods one by one. The plurality of arc-shaped support plates correspond to the plurality of square through slots one by one. A pressure sensor is provided on the outer side of the arc-shaped support plate, and an electric telescopic rod is provided between the adjusting rod and the cam. One end of the electric telescopic rod is hinged to the cam through a hinged ear, and the other end is hinged to the corresponding adjusting rod through a hinged ear. A warning light is provided on a control box, and a signal converter, a data processor, a controller and a sound alarm are respectively provided in the control box. The pressure sensor, the signal converter, the data processor, the controller, the sound alarm and the warning light are connected through a power cord.
2. A safety early warning system for coal mining according to claim 1, Features When in use, multiple groups of pressure monitoring anchor rods are set up to comprehensively monitor the pressure changes of the internal rock strata outside the coal mine tunnel, and carry out zoned early warning according to the pressure changes of the internal rock strata, which can provide early warning time and give construction personnel sufficient time to take appropriate countermeasures.
3. A safety early warning system for coal mining according to claim 1, Features The signal converter is capable of receiving the pressure signal of the pressure sensor and performing signal conversion; the data processor and the signal converter exchange information, and a computer program is stored in the data processor, which implements the following steps when executed: receiving the pressure signal transmitted by the signal converter, and performing data processing to obtain the pressure value of the rock layer inside the rock outside the current tunnel, and comparing the processed pressure value with the preset value in the data processor; the controller and the data processor exchange information, execute the instructions issued by the data processor, and can control the start and stop of the sound alarm and the color change of the warning light.
4. A safety early warning system for coal mining according to claim 1, Features The threading hole is provided with a detachable sealing ring sleeve, which can seal the threading hole and prevent dust and water vapor in the tunnel from entering the pressure monitoring anchor rod through the threading hole.
5. A safety early warning system for coal mining according to claim 1, Features A through hole is provided in the rotating block, and the through hole is divided into two sections, an upper section and a lower section.
6. A safety early warning system for coal mining according to claim 5, Features The diameter of the upper section of the through hole is smaller than the diameter of the lower section, and the length of the upper section of the through hole is greater than the length of the lower section.
7. A safety early warning system for coal mining according to claim 1, Features The hinged joint between the insertion rod and the electric telescopic rod is higher than the hinged joint between the corresponding adjustment rod and the electric telescopic rod.
8. A safety early warning system for coal mining according to claim 1, Features One end of the regulating rod is hinged to the inserting rod through a hinged ear, and the other end is hinged to a third of the corresponding arc-shaped supporting plate through a hinged ear.
9. A safety early warning system for coal mining according to claim 1, Features The thickness of the arc-shaped supporting plate gradually decreases from bottom to top.
10. A safety early warning system for coal mining according to claim 1, Features The other end of the pressure monitoring anchor rod is an open structure, and a thread is formed on the outer side of the pressure monitoring anchor rod. The thread extends from the other end of the pressure monitoring anchor rod to one third of the pressure monitoring anchor rod.
Citation Information
Patent Citations
Grading forecasting and protection type anchor rod device underground coal mine and protection method of device
CN110821541A
Roadway deformation monitoring device
CN112033276A
Dynamic monitoring system of coal mine roof plate
CN101344012A
Tunnel roof separation dynamic monitoring system based on fiber bragg grating and early-warning method thereof
CN103510986A
Mining monitoring early warning anchor rod
CN109578039A