A method for constructing a shallow rainwater drainage system at an urban scale

By establishing a three-dimensional geographical model and small and micro basin units in the urban planning area and building a shallow flow rainwater discharge system, the problem of prone to waterlogging and sewage in the existing technology is solved, and the process is short and purification effect is achieved , reducing the risks of urban waterlogging and pollution.

CN113742896BActive Publication Date: 2024-11-12厦门市城市规划设计研究院有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110916643.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-08-11
Publication Date
2024-11-12
Estimated Expiration
2041-08-11

AI Technical Summary

Technical Problem

The existing urban rainwater discharge system changes the natural drainage rules, resulting in prone to waterlogging and is mixed with the sewage system, which cannot effectively reduce the risk of urban waterlogging and pollution, and it is difficult to maintain the natural state of the water system.

Method used

By establishing a three-dimensional geographical model of the planning area, dividing small and micro basin units, building shallow flow stormwater discharge system, including site, municipal roads and river green corridor systems, simulation and adjustments are carried out until the target discharge and storage are reached, to maximize the Retain natural hydrological characteristics to the limit.

Benefits of technology

Effectively reduce the risk of urban waterlogging, reduce non-point source pollution, avoid mismatch and incoherence of sewage systems, achieve short processes and purification effects, and improve the feasibility and superiority of the drainage system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113742896B_ABST
    Figure CN113742896B_ABST
Patent Text Reader

Abstract

The present invention provides a method for constructing a shallow rainwater drainage system at an urban scale, and relates to the field of urban drainage technology. The construction method includes: establishing a three-dimensional geographical model of a planning area; determining the confluence path of the planning area and forming a plurality of small micro-watershed units according to the confluence path; determining the target water storage and target drainage of the planning area according to the analysis of the hydrological characteristics before and after the development of the planning area; constructing a shallow rainwater drainage system in each small micro-watershed unit, which includes a shallow flow drainage system of a site, a municipal road and a river green corridor that are connected in sequence; performing simulation analysis on the system, and adjusting the shallow rainwater drainage system according to the results until the shallow rainwater drainage system reaches the target discharge volume. The method is based on the principle of retaining natural hydrological characteristics to the maximum extent, and has the advantages of short process, shallow flow, smooth connection, purification, etc. It can effectively reduce the risk of urban waterlogging and reduce urban non-point source pollution, and has high feasibility and superiority.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of urban planning, and in particular to a method for constructing a shallow surface flow rainwater drainage system at an urban scale. Background Art

[0002] The traditional urban rainwater drainage system mainly guides rainwater to the underground pipe network system artificially, and finally discharges it into the river system. The design of the rainwater pipe network system aims to drain all rainwater within the city as quickly and efficiently as possible. However, with the process of urbanization, the surface runoff increases, the peak flow increases, the peak time is advanced, and the natural groundwater recharge decreases. It is difficult to fundamentally solve the ecological and environmental problems such as waterlogging disasters and rainwater and sewage mixed flow pollution faced by the city by simply expanding the cross-section of the rainwater pipe. It can be seen that the existing rainwater pipe network system is no longer compatible with the large-scale urbanization development, strongly interferes with the original hydrological ecosystem of the city, and destroys the natural benign water system cycle. Therefore, starting from the background conditions of the urban hydrological ecosystem, it is urgent to explore a new urban rainwater drainage system, minimize the impact of urban development and construction on its original hydrological characteristics, maintain and maintain its original water system, and coordinate urbanization construction with the ecological environment.

[0003] At present, the solution to urban rainwater storage is usually to adopt temporary or long-term storage, reuse and infiltration of rainwater to reduce the amount of urban drainage to natural water bodies; or to partially transform the urban rainwater drainage system by setting up storage and facilities. The existing rainwater drainage has the following defects:

[0004] (1) The existing rainwater drainage system changes the natural drainage law and is prone to waterlogging. The current rainwater drainage system usually relies on the determined urban planning plots, road network layout and verticality to carry out river network water system and rainwater pipeline planning and design. It lacks the analysis of the hydrological ecological texture before urban development and construction. It often straightens, deletes and merges the existing natural water system, resulting in the extension of the rainwater collection process. The scale of the rainwater pipeline continues to increase, and its burial depth continues to deepen. Further, the downstream river system needs to increase the depth of the riverbed to meet the discharge requirements of the rainwater pipeline network. Compared with the natural state before urban development and construction, not only the drainage capacity is reduced, which is easy to form waterlogging, but also the water system is narrow, deep and has steep slopes, and the overall landscape quality and hydrophilicity are greatly reduced. Although the existing technology has partially expanded the capacity and increased the storage of the rainwater system, it is still essentially using long-distance underground rainwater pipelines for rainwater collection and discharge, and still has the above-mentioned technical shortcomings.

[0005] (2) The existing rainwater drainage system and sewage drainage system are parallel and are prone to mixing and misconnection. The current rainwater drainage system and sewage system are laid together underground. Although they belong to the same drainage system, the water quality is completely different. The common sewage pipes connected to the rainwater system and the rainwater pipes connected to the sewage system will have an impact on their respective systems. At present, the problem of mixing and misconnection between rainwater and sewage pipes is common and exists in large quantities in new and old urban areas. Even the existing rainwater and sewage mixed and misconnected renovation technology is limited by objective conditions such as pipe network inspection accuracy, renovation space, and construction quality. It is impossible to achieve complete rainwater and sewage diversion, and there is still a risk of pollution to the water quality of the receiving water body at the end. Summary of the invention

[0006] In order to solve the above technical problems, the present invention provides a method for constructing a shallow flow rainwater drainage system at an urban scale.

[0007] The present invention is achieved in that:

[0008] A method for constructing a shallow rainwater drainage system at an urban scale comprises the following steps:

[0009] S1, establish a three-dimensional geographic model of the planning area;

[0010] S2, determining the confluence path of the planning area according to the three-dimensional geographic model and dividing the confluence path into a plurality of small micro-watershed units;

[0011] S3, determining the target discharge amount of the planning area based on analyzing the hydrological characteristics of the planning area before and after development;

[0012] S4, constructing a shallow rainwater drainage system in each of the small micro-watershed units, wherein the shallow rainwater drainage system includes a site shallow drainage system, a municipal road shallow drainage system and a river green corridor shallow drainage system connected in sequence;

[0013] S5, performing simulation analysis on the shallow flow rainwater drainage system, and adjusting the shallow flow rainwater drainage system according to the analysis result until the shallow flow rainwater drainage system reaches the target drainage volume and the target water storage volume.

[0014] The construction method of the shallow rainwater drainage system of the present invention has the following beneficial effects:

[0015] When constructing the urban drainage system, the present invention changes the traditional practice of "water will flow into the city" such as land creation first, water management later, straightening the bends, cutting high and filling low, etc., and first builds a three-dimensional geographical model of the planning area, analyzes and sorts out the hydrological characteristics of the planning area before and after development, retains the natural hydrological characteristics as much as possible, forms multiple small micro-watershed units, and plans in the small micro-watershed units to control the collection and discharge of urban rainwater runoff on the shallow surface of the ground. The drainage planning is turned from plane to three-dimensional, and a shallow water drainage system of land plots-municipal roads-river green corridors is established. The rainwater discharge is realized through the vertical connection of the multi-level shallow water drainage system. Compared with traditional rainwater drainage systems, this system is based on the principle of retaining natural hydrological characteristics to the greatest extent possible. It has the advantages of short flow, shallow flow, smooth connection, and purification. It can effectively reduce the risk of urban waterlogging and reduce urban non-point source pollution. It also avoids the disadvantages of mixing with the sewage system and difficulty in connecting with the terminal water system. It has strong feasibility and superiority, and can provide a reference for cities to build new rainwater drainage systems. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0017] Figure 1 This is a construction framework diagram of a shallow flow rainwater drainage system according to an embodiment of the present invention;

[0018] Figure 2 Schematic diagram of the construction of the small micro-watershed unit of this embodiment;

[0019] Figure 3 This is an image of the Xiamen Hongtang River Basin in this embodiment;

[0020] Figure 4 It is a terrain analysis map of the Xiamen Hongtang River Basin in this embodiment;

[0021] Figure 5 Schematic diagram of a small watershed unit of Xiamen Hongtangxi watershed in this embodiment;

[0022] Figure 6 is a schematic diagram of the construction of a shallow surface flow drainage system for a site according to an embodiment of the present invention;

[0023] Figure 7 Schematic diagram of the construction of a municipal road shallow flow drainage system according to an embodiment of the present invention;

[0024] Figure 8It is a vertical connection schematic diagram of a shallow flow rainwater drainage system according to an embodiment of the present invention. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention. Therefore, the following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the invention claimed for protection, but merely represents the selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0026] Example

[0027] Reference Figure 1 As shown, an embodiment of the present invention provides a method for constructing a shallow flow rainwater drainage system at an urban scale, comprising the following steps:

[0028] S1, establish a three-dimensional geographic model of the planning area.

[0029] Specifically, establishing a three-dimensional geographic model of the planning area includes: obtaining digital elevation model data and water system data of the planning area, and using ArcGIS analysis tools to establish a three-dimensional geographic model of the planning area. The three-dimensional geographic model includes the distribution of water systems before urban development and construction, the composition of the underlying surface of the plot, the type of land use, and the spatial distribution of land use.

[0030] It is understandable that ArcGIS analysis tool is a commonly used hydrological analysis tool in this field, and the specific steps of building the model will not be repeated here.

[0031] S2, according to the three-dimensional geographic model, determine the confluence path of the planning area and divide it into multiple small micro-watershed units according to the confluence path. In the three-dimensional geographic model, it is possible to identify natural drainage elements, which include naturally formed water systems, gullies, depressions, etc. According to the natural drainage elements, the original confluence path of the planning area is obtained.

[0032] In one embodiment, the specific steps of determining the confluence path of the planning area and dividing the confluence path into a plurality of small micro-watershed units include:

[0033] S21, in the three-dimensional geographic model, such as Figure 2As shown, with the original confluence path A as the center, the range of the preset flow radius is extended outward, the terrain high points within the preset flow radius are identified, and the watershed line B is drawn along the line connecting the terrain high points, and each small micro-watershed unit C is formed according to the watershed line. Furthermore, the capillary section of the original confluence path radiates outward with the preset flow radius to plan the small micro-watershed unit. The preset flow radius is determined according to factors such as the local design rainfall intensity, terrain slope, and the size of the open ditch of the municipal road. In this embodiment, the preset flow radius is 0.5 to 2 km.

[0034] S22, in the area not covered by the micro-watershed unit C, obtain the terrain low point of the area, add an artificial confluence path A' according to the terrain low point, identify the terrain high point within the range of the artificial runoff path, draw a watershed line B' forming the newly added artificial confluence path along the line connecting the terrain high points, and form a new micro-watershed unit C' according to the watershed line until the micro-watershed unit covers the entire planning area. Furthermore, the artificial confluence path is formed by newly setting up drainage channels such as dry streams and water systems.

[0035] S23. In each micro-watershed unit, plan the urban road network and plots. The urban road network is planned according to the overall slope towards the water system, and the road slope of the urban road network is controlled to be greater than 0.3%; the plots are planned according to the overall vertical slope from the center to the surrounding roads.

[0036] Through the above steps, the original confluence path is divided into small micro-basin units. Each small micro-basin unit actually constitutes a drainage partition. On the basis of the small micro-basin unit (i.e., drainage partition), the subsequent shallow flow rainwater discharge system is constructed. This step is an important basis for achieving shallow flow control of rainwater runoff throughout the entire process. By constructing various small micro-basin units, the mountain and water base and natural terrain can be retained to the greatest extent, and it can fully ensure that after urban development and construction, it still conforms to the natural drainage law and is not prone to urban waterlogging; on the other hand, the basin is small and the process is short, which can quickly collect and discharge rainwater runoff to the planned reserved water system, gullies, depressions, etc., and also create good conditions for municipal roads to use appropriately sized drainage ditches as transfer facilities.

[0037] Specifically, steps S1-2 are described by taking Xiamen Hongtang River Basin as an example.

[0038] like Figure 3 The image of Xiamen Hongtang River Basin is shown. Xiamen Hongtang River Basin is in the early stage of development and construction. The overall terrain is high in the north and low in the south, with elevations ranging from 5m to 110m. At present, Hongtang River and its tributaries flow from northeast to southwest into the downstream Longdong River, with a basin area of ​​about 9km 2 .

[0039] Analysis of terrain characteristics of Xiamen Hongtang River Basin, such as Figure 4Shown is a topographic analysis map of the Xiamen Hongtangxi River Basin, which preserves naturally formed water systems, gullies, depressions and other natural drainage elements to the greatest extent, and constructs an urban drainage network foundation that conforms to the laws of natural drainage.

[0040] exist Figure 4 Based on the terrain analysis, the terrain high points within the maximum rainfall collection range of the capillary segments of each drainage vein are identified, the watershed lines are drawn, and small micro-watershed units centered on the capillary segments of the drainage veins are constructed. Figure 5 Shown is a schematic diagram of the small watershed unit in the Hongtangxi watershed in Xiamen.

[0041] S3, determining the target discharge volume and target water storage volume of the planning area based on analyzing the hydrological characteristics of the planning area before and after development.

[0042] Specifically, the steps of determining the target drainage volume and target water storage volume of the planning area include:

[0043] S31, obtaining the urban comprehensive rainfall runoff coefficient ψ1 before the development of the planning area.

[0044] Specifically, the following table 1 shows the annual runoff control rate targets and comprehensive rainfall runoff coefficient indicators for various types of construction land. When calculating the comprehensive rainfall runoff coefficient ψ1, first determine the comprehensive rainfall runoff coefficients of different types of planned land, and then obtain ψ1 by weighted average based on the planned area of ​​each type of land.

[0045] Table 1

[0046]

[0047]

[0048] S32, determining the total amount control rate of rainwater runoff and the comprehensive rainfall runoff coefficient ψ3 after the low-impact development of the planning area. The specific calculation process refers to the method in S31.

[0049] S33, determining the design rainfall h of the planning area according to the design recurrence period target of the rainwater system in the planning area and the corresponding rainfall duration, where the unit of the design rainfall is mm.

[0050] S34, determining the target drainage volume P of the planning area according to the following formula (1):

[0051] P = ψ1*h*F (1);

[0052] Wherein, in formula (1), P is the target drainage volume of the planning area, in m 3 ; ψ1 is the urban comprehensive rainfall runoff coefficient before the development of the planning area; h is the design rainfall of the planning area, in mm; F ​​is the area of ​​the planning area, in hm2 .

[0053] S35, determining the target water storage capacity X of the planning area according to the following formula (2):

[0054] X = (ψ3-ψ1)*h*F, (2);

[0055] In formula (2), X is the target water storage capacity of the planning area, in m 3 ψ1 is the urban comprehensive rainfall runoff coefficient before the development of the planning area; ψ3 is the urban comprehensive rainfall runoff coefficient after the planning area is developed according to low impact; h is the design rainfall of the planning area, in mm; F ​​is the area of ​​the planning area, in hm 2 .

[0056] Compared with traditional development, the drainage reduction of low-impact development in this embodiment is shown in the following formula (3):

[0057] △P=(ψ2-ψ1)*h*F, (3);

[0058] Among them, △P is the drainage reduction, the unit is m 3 ; h is the design rainfall of the planning area, in mm; F ​​is the area of ​​the planning area, in hm 2 , ψ2 is the urban comprehensive rainfall runoff coefficient ψ2 after the planning area is developed in a traditional way, and ψ2 is determined based on the built-up areas around the planning area.

[0059] S4, constructing a shallow flow rainwater drainage system in each of the micro-watershed units, wherein the shallow flow rainwater drainage system includes a site shallow flow drainage system, a municipal road shallow flow drainage system and a river green corridor shallow flow drainage system which are connected in sequence.

[0060] like Figure 6-8 As shown, specifically, the steps of constructing the shallow flow rainwater drainage system in each of the small micro-watershed units include:

[0061] S41, such as Figure 6 As shown, a shallow drainage system is constructed. The site is the main link in generating rainwater runoff, and the core of the shallow rainwater drainage system is runoff organization, collection and purification.

[0062] The construction of the shallow flow drainage system of the site includes the following steps:

[0063] S411, design the direction of rainwater runoff on the site. Specifically, control the vertical elevation of the center point and four corners of the site, requiring the middle to be high and the surroundings to be low, and the ground slope from the middle to the surroundings should not be less than 3‰, so as to create good surface runoff organization conditions on the site.

[0064] S412, setting up sponge facilities on the site, wherein the sponge facilities include one or more of roof greening, permeable pavement, sunken green space, ecological grass-planted ditch and bioretention facilities.

[0065] Specifically, the site plot includes the road surface, roof and other hardened areas. The road surface specifically includes ground parking spaces, pedestrian areas, non-motorized vehicle lanes and motor vehicle lanes. Permeable materials are used for paving in ground parking spaces, pedestrian areas and non-motorized vehicle lanes. Roof greening is carried out on the roof, and rainwater from the roof is connected to the sunken green space through downpipes. Furthermore, the sunken green space is designed to sink 3 to 5 cm as a whole to form a micro-sunken green space to better control surface runoff. Bioretention facilities such as rainwater gardens are further set up in the micro-sunken green space. Motor vehicle lanes and other hardened areas can also be further piled up and landscaped in combination with the needs of green space landscape. The curbstones around the green space can achieve runoff control according to the designed flat curbstones or curbstone openings.

[0066] S413, determining the site drainage volume C2 according to the site runoff volume C and the site water storage volume C1, and determining the specifications of the shallow surface flow drainage pipe ditch facilities in the site according to the site drainage volume C2.

[0067] Site runoff C = Σψ i ×F i ×h×1000 (4);

[0068] Site water storage capacity C1 = ΣA n ×H n (5);

[0069] Site drainage volume C2 = C-C1 (6),

[0070] In formulas (4)-(6), C is the site runoff, in m 3 ; C1 is the water storage capacity of the site, in m 3 ; C2 is the site drainage, unit is m 3 ψ i F is the comprehensive rainfall runoff coefficient of various underlying surfaces after low-impact development; i It is the design area of ​​various underlying surfaces after low-impact development, in hm 2 , i represents the type of underlying surface; h represents the design rainfall, in mm; A n is the design area of ​​various bioretention facilities, in hm 2 ;H n is the storage depth of various types of biological retention facilities, in meters; n means there are n types of biological retention facilities;

[0071] Table 2 below shows the design parameters of the site sponge facilities.

[0072] Table 2

[0073]

[0074]

[0075] S414, construct shallow surface flow drainage pipe ditch facilities in the site to divert the runoff in the site to the shallow surface flow drainage system of the municipal road, wherein the shallow surface flow drainage pipe ditch facilities in the site include one or more of ground drainage slopes, linear drainage ditches and ecological grass planting ditches. For example, linear drainage ditches are laid along the motor vehicle lanes to collect overflow rainwater from micro-sunken green spaces and rainwater from other pavements, roofs, and other hardened areas, and the municipal road shallow surface flow drainage system is connected through linear drainage pipes.

[0076] S42, constructing a shallow flow drainage system for municipal roads;

[0077] The municipal road shallow flow drainage system is used to receive the drainage of the shallow flow drainage system of the site, and organize and purify the rainwater runoff from the motor vehicle lane, non-motor vehicle lane, sidewalk, side green belt and setback greening facilities. The specific construction steps include:

[0078] Bioretention facilities are arranged in the setback greening and side greening belts, and the motor vehicle lanes, side greening belts, non-motor vehicle lanes and sidewalks are arranged in sequence from the center line to the outside of the road with a horizontal slope; among them, the non-motor vehicle lanes and sidewalk motor vehicle lanes are paved with permeable pavement, and part of the rainwater seeps in, and the rest enters the setback greening; part of the rainwater from the motor vehicle lane enters the side greening belts, and the rest enters the setback greening or road drainage open ditch in the form of ground overflow or by setting linear drainage ditches; overflow rainwater from the setback greening enters the road drainage open ditch, and the drainage of the road drainage open ditch is connected to the shallow flow drainage system of the river green corridor.

[0079] Furthermore, the runoff of the shallow surface flow drainage system of the site enters the setback greening or road drainage open ditch. The vertical elevation of the bottom of the facilities in the setback greening is required to be 10 to 30 cm lower than the bottom elevation of the linear drainage ditch outlet of the shallow surface flow drainage system of the adjacent site and the road linear drainage ditch outlet of the municipal road shallow surface flow drainage system, so as to facilitate the acceptance of the shallow surface flow drainage of the site and the regulation and purification of road rainwater. In addition, road drainage open ditches are set up between the setback greening sections along the line to collect and transfer the overflow rainwater of the setback greening.

[0080] S43, construct a shallow flow drainage system for the river green corridor.

[0081] The river green corridor shallow flow drainage system is used to receive the drainage of the municipal road shallow flow drainage system and reduce the non-point source pollution of rainwater; the specific construction steps include:

[0082] According to the location of the drainage outlet of the municipal road shallow flow drainage system, rainwater purification wetlands are arranged in the green belts on both sides of the terminal drainage elements. The scale of the rainwater purification wetlands is determined according to the drainage volume of the municipal road shallow flow drainage system. The overflow rainwater of the rainwater purification wetlands enters the river.

[0083] Among them, the terminal drainage elements include water systems, gullies, depressions, etc. The selected location of the rainwater purification wetland is the green belt position on the normal water level on both sides of the water system, gully, and depression. It can be understood that the normal water level is determined according to the urban flood control and drainage standards and landscape water level requirements.

[0084] Furthermore, in this embodiment, the terminal bottom elevation of the site shallow flow drainage system is more than 0.1m higher than the municipal road shallow flow drainage system; the terminal bottom elevation of the municipal road shallow flow drainage system is more than 0.5m higher than the flood level of the receiving river channel to ensure the elevation connection of multiple systems.

[0085] S5, performing simulation analysis on the shallow flow rainwater drainage system, and adjusting the shallow flow rainwater drainage system according to the analysis result until the shallow flow rainwater drainage system reaches the target discharge volume.

[0086] Specifically, the XPDrainage software is used to simulate and analyze the shallow flow rainwater drainage system. XPDrainage software builds a model, and can set the basic conditions of the planning area (rainfall, evaporation, runoff coefficient), the design parameters of the rainwater drainage system (scale, size, water storage space), conduct rainfall and runoff analysis in the area, simulate the storage capacity of sponge facilities and the drainage capacity of rainwater ditches, so as to achieve the effect evaluation of the shallow flow rainwater drainage system in the planning area, and obtain the simulated discharge of the planning area. Compare and analyze the simulated discharge with the target discharge and target water storage of the planning area in step S3. If the target discharge requirements can be met, it means that the construction is completed. If not, the shallow flow rainwater discharge system is adjusted and optimized until it meets the target discharge requirements.

[0087] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for constructing a shallow rainwater drainage system at an urban scale, characterized in that: The following steps are involved: S1, establish a three-dimensional geographic model of the planning area; S2, determining the confluence path of the planning area according to the three-dimensional geographic model and dividing the confluence path into a plurality of small micro-watershed units; S3, determining the target water storage capacity and target water discharge capacity of the planning area according to the analysis of the hydrological characteristics of the planning area before and after the development; S4, constructing a shallow rainwater drainage system in each of the small micro-watershed units, wherein the shallow rainwater drainage system includes a site shallow drainage system, a municipal road shallow drainage system and a river green corridor shallow drainage system connected in sequence; S5, performing simulation analysis on the shallow flow rainwater drainage system, and adjusting the shallow flow rainwater drainage system according to the analysis result until the shallow flow rainwater drainage system reaches the target drainage volume and the target water storage volume; In step S2, the steps of determining the confluence path of the planning area according to the three-dimensional geographic model and dividing the confluence path into a plurality of small micro-watershed units include: S21, in the three-dimensional geographic model, with the original confluence path as the center, extending outward the range of the preset flow radius, identifying the terrain high points within the preset flow radius, drawing a watershed line along the line connecting the terrain high points, and forming various small micro-watershed units according to the watershed line; S22, in the area not covered by the small micro-watershed unit, obtain the terrain low point of the area, add an artificial confluence path according to the terrain low point, identify the terrain high point within the range of the artificial confluence path, draw a watershed line forming the newly added artificial confluence path along the line connecting the terrain high points, and form a new small micro-watershed unit according to the watershed line until the small micro-watershed unit covers the entire planning area; S23. In each micro-watershed unit, plan the urban road network and plots. The urban road network is planned according to the overall slope towards the water system, and the road slope of the urban road network is controlled to be greater than 0.3%; the plots are planned according to the overall vertical slope from the center to the surrounding roads.

2. The method for constructing a shallow rainwater drainage system at an urban scale according to claim 1, characterized in that: In step S1, establishing a three-dimensional geographic model of the planning area includes: obtaining digital elevation model data and water system data of the planning area, and using ArcGIS analysis tools to establish the three-dimensional geographic model, wherein the three-dimensional geographic model includes the water system distribution, land underlying surface composition, land use type and land spatial distribution before urban development and construction.

3. The method for constructing a shallow rainwater drainage system at an urban scale according to claim 1, characterized in that: In step S3, the step of determining the target water storage capacity and target water discharge capacity of the planning area includes: S31, obtaining the urban comprehensive rainfall runoff coefficient ψ1 before the development of the planning area; S32, determining the total amount control rate of rainwater runoff and the comprehensive rainfall runoff coefficient ψ3 after the low-impact development of the planning area; S33, determining the design rainfall h of the planning area according to the design return period target of the rainwater system of the planning area and the corresponding rainfall duration, where the unit of the design rainfall is mm; S34, determining the target drainage volume P of the planning area according to the following formula (1): P = ψ1*h*F (1); Wherein, in formula (1), P is the target drainage volume of the planning area, in m 3 ; ψ1 is the urban comprehensive rainfall runoff coefficient before the development of the planning area; h is the design rainfall of the planning area, in mm; F ​​is the area of ​​the planning area, in hm 2 ; S35, determining the target water storage capacity X of the planning area according to the following formula (2): X = (ψ3-ψ1)*h*F, (2); In formula (2), X is the target water storage capacity of the planning area, in m 3 ; ψ1 is the urban comprehensive rainfall runoff coefficient before the development of the planning area; ψ3 is the urban comprehensive rainfall runoff coefficient after the planning area is developed according to low impact; h is the design rainfall of the planning area, in mm; F ​​is the area of ​​the planning area, in hm 2 .

4. The method for constructing a shallow rainwater drainage system at an urban scale according to claim 1, characterized in that: In step S4, the step of constructing the shallow flow rainwater drainage system in the planning area includes: S41, constructing a shallow surface drainage system on site; S42, constructing a shallow flow drainage system for municipal roads; S43, construct a shallow flow drainage system for the river green corridor.

5. The method for constructing a shallow rainwater drainage system at an urban scale according to claim 4, characterized in that: In step S41, the steps of constructing a shallow flow drainage system of the site include: S411, design site stormwater runoff direction; S412, setting up sponge facilities in the site, wherein the sponge facilities include one or more of roof greening, permeable pavement, sunken green space, ecological grass-planted ditch and bioretention facilities; S413, determine the site drainage volume C2 through the site runoff volume C and the site water storage volume C1, and determine the specifications of the shallow surface flow drainage pipe ditch facilities in the site according to the site drainage volume C2 and the designed rainfall pattern; wherein the site runoff volume C = Σψ i ×F i ×h×1000(4); Site water storage capacity C1=ΣA n ×H n (5); Site drainage C2 = C-C1 (6), in formulas (4)-(6), C is the site runoff, in units of m 3 ; C1 is the water storage capacity of the site, in m 3 ; C2 is the site drainage, unit is m 3 ψ i F is the comprehensive rainfall runoff coefficient of the i-th type underlying surface after low-impact development; i is the design area of ​​the i-th type underlying surface after low-impact development, in hm 2 ; h represents the design rainfall of the planning area, in mm; A n is the design area of ​​the nth type of bioretention facility, in m 2 ;H n is the storage depth of the nth type of biological retention facility, in meters; S414, construct shallow flow drainage ditch facilities on the site to divert the runoff on the site to the shallow flow drainage system of the municipal road, wherein the shallow flow drainage ditch facilities on the site include one or more of ground drainage slopes, linear drainage ditches and ecological grass-planted ditches.

6. The method for constructing a shallow rainwater drainage system at an urban scale according to claim 3, characterized in that: The municipal road shallow flow drainage system is used to receive the drainage of the shallow flow drainage system of the site, and organize and purify the rainwater runoff of motor vehicle lanes, non-motor vehicle lanes, sidewalks, side green belts and setback greening facilities. The specific construction steps include: Bioretention facilities are arranged in the setback greening and side greening belts, and the motor vehicle lanes, side greening belts, non-motor vehicle lanes and sidewalks are arranged in sequence from the center line to the outside of the road with a horizontal slope; among them, the non-motor vehicle lanes and sidewalk motor vehicle lanes are paved with permeable pavement, and part of the rainwater seeps in, and the rest enters the setback greening; part of the rainwater from the motor vehicle lane enters the side greening belts, and the rest enters the setback greening or road drainage open ditch in the form of ground overflow or by setting linear drainage ditches; overflow rainwater from the setback greening enters the road drainage open ditch, and the drainage of the road drainage open ditch is connected to the shallow flow drainage system of the river green corridor.

7. The method for constructing a shallow rainwater drainage system at an urban scale according to claim 3, characterized in that: The river green corridor shallow flow drainage system is used to receive the drainage of the municipal road shallow flow drainage system and reduce the non-point source pollution of rainwater; the specific construction steps include: According to the location of the drainage outlet of the municipal road shallow flow drainage system, rainwater purification wetlands are arranged in the green belts on both sides of the terminal drainage elements. The scale of the rainwater purification wetlands is determined according to the drainage volume of the municipal road shallow flow drainage system. The overflow rainwater of the rainwater purification wetlands enters the river.

8. The method for constructing a shallow rainwater drainage system at an urban scale according to claim 3, characterized in that: The terminal bottom elevation of the shallow flow drainage system of the site is more than 0.1m higher than the shallow flow drainage system of the municipal road; the terminal bottom elevation of the shallow flow drainage system of the municipal road is more than 0.5m higher than the flood level of the receiving river channel.

9. The method for constructing a shallow rainwater drainage system at an urban scale according to claim 1, characterized in that: In step S5, the XPDrainage software is used to perform simulation analysis on the shallow flow rainwater drainage system.