Model-Based Scheduling for Substrate Handling Systems
By applying machine learning models in semiconductor manufacturing to predict and optimize the scheduling parameters of substrate processing tools, the problems of unstable output and long waiting times in the existing technology are solved, and an efficient semiconductor manufacturing process is achieved.
Patent Information
- Application Number
- CN202080039804.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-03-24
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2040-03-24
AI Technical Summary
Existing semiconductor substrate processing tools lack systematicity in the selection of scheduling parameters, resulting in unstable output and long wafer waiting times. Moreover, the scheduler rules are complex and it is difficult to achieve a balance between optimal output and minimum waiting time.
Adopt an intelligent scheduling system based on machine learning, using artificial neural networks and support vector regression methods to train models, predict optimal scheduling parameters, and optimize the operation of substrate processing tools, including preventive maintenance, analysis of wafer-free automatic cleaning times and yield patterns , adjust the model to adapt to tool changes and performance drift.
It achieves the minimization of wafer idle time during the semiconductor manufacturing process, improves manufacturing efficiency, ensures the best output of tools and optimizes waiting time, and reduces tool holding costs.
Smart Images

Figure CN113874993B_ABST
Abstract
Description
[0001] CROSS-REFERENCE TO RELATED APPLICATIONS
[0002] This disclosure is a PCT international patent application of U.S. Patent Application No. 62 / 826,185 filed on March 29, 2019. The entire disclosure of the above-referenced applications is incorporated herein by reference. Technical Field
[0003] The present disclosure relates generally to substrate processing systems and, more particularly, to model-based scheduling for substrate processing systems. Background Art
[0004] The background description provided here is for the purpose of generally presenting the context of the present disclosure. The work of the presently designated inventors is neither explicitly nor implicitly admitted to be prior art against the present disclosure to the extent that it is described in this background section and in aspects of the specification that were not determined to be prior art at the time the application was filed.
[0005] Semiconductor manufacturers use one or more substrate processing tools during the manufacture of semiconductor wafers to perform deposition, etching, cleaning and / or other substrate processing. Each substrate processing tool may include multiple processing chambers that perform the same type of processing (e.g., deposition, etching, or cleaning) or different processing, such as a series or sequence of processing on a substrate.
[0006] The processing chambers in a substrate processing tool typically repeat the same task on multiple substrates. The processing chambers operate based on a recipe that defines the processing parameters. For example, the recipe defines the sequence, operating temperature, pressure, gas chemistry, plasma usage, parallel modules, time period for each operation or sub-operation, substrate routing approach, and / or other parameters. Substrates can be transferred between two or more processing chambers in a specific sequence for different processing. Summary of the invention
[0007] A system for processing semiconductor substrates in a tool, the tool comprising a plurality of processing chambers configured to process the semiconductor substrates according to a recipe, the system comprising: a processor; and a memory storing instructions for execution by the processor. The instructions are configured to: receive first data from the tool regarding processing the semiconductor substrates in the plurality of processing chambers according to the recipe; and receive second data regarding the configuration of the tool and the recipe. The instructions are configured to simulate a plurality of processing schemes and scheduling parameters for the plurality of processing schemes for processing the semiconductor substrates in the plurality of processing chambers according to the recipe using the second data. The instructions are configured to simulate processing the semiconductor substrates in the plurality of processing chambers according to the recipe using the plurality of processing schemes and the scheduling parameters for the plurality of processing schemes. The instructions are configured to train a model using the first data and data generated by the simulation to predict optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe. The instructions are configured to receive input from the tool regarding processing one of the semiconductor substrates in the plurality of processing chambers according to the recipe. The instructions are configured to use the model to predict, based on the input, optimal scheduling parameters for processing the one of the semiconductor substrates in the plurality of process chambers according to the recipe. The instructions are configured to schedule operations of the tool based on the optimal scheduling parameters for processing the one of the semiconductor substrates in the plurality of process chambers according to the recipe.
[0008] In another feature, the instructions are configured to perform the operations of the tool based on the optimal scheduling parameters for processing the one of the semiconductor substrates in the plurality of processing chambers according to the recipe.
[0009] In other features, the optimal scheduling parameters minimize idle time of the one of the semiconductor substrates during processing according to the recipe in the plurality of processing chambers, and the optimal scheduling parameters maximize throughput of the tool.
[0010] In another feature, the instructions are configured to train the model using machine learning methods including artificial neural networks and support vector regression.
[0011] In other features, the instructions are configured to: analyze the first data received from the tool and the data generated by the simulation; based on the analysis, detect patterns regarding preventive maintenance operations, waferless autoclean time, wait time, recipe time and yield of the tool; and train the model based on the detected patterns.
[0012] In another feature, the instructions are configured to train the model to predict the optimal scheduling parameters for one of the plurality of processing scenarios.
[0013] In another feature, the instructions are configured to train the model to predict the optimal scheduling parameters for all of the plurality of processing scenarios.
[0014] In another feature, the instructions are configured to train the model to perform only etching operations on the one of the semiconductor substrates.
[0015] In another feature, the instructions are configured to train the model for performing both etching and stripping operations on the one of the semiconductor substrates.
[0016] In other features, the model is implemented remotely from the tool, and wherein the instructions are configured to train the model based on data received from a plurality of tools.
[0017] In another feature, the instructions are configured to adjust the model for tool-to-tool variations in configuration and operation.
[0018] In another feature, the model is implemented in the cloud as software as a service (SaaS), and the tool is configured to access the model over a network.
[0019] In other features, the instructions are configured to train a second model based on data from a second tool; and the model and the second model are implemented remotely from the tool and the second tool. The tool and the second tool are respectively configured to access the model and the second model via one or more networks.
[0020] In another feature, the instructions are configured to cause the tool and the second tool to select the model and the second model based on configurations of the tool and the second tool, respectively.
[0021] In other features, the model is implemented on the tool, and the instructions are configured to use the model to predict the optimal scheduling parameters for processing the one of the semiconductor substrates in the plurality of processing chambers according to the recipe using data generated by the tool.
[0022] In other features, the model is implemented on the tool and the instructions are configured to adjust the model for any drift in performance of the tool.
[0023] In another feature, the first data received from the tool includes data from preventive maintenance operations performed on the tool and data regarding recipe times and waferless autoclean times for the tool.
[0024] In another feature, the data generated by the simulation includes data generated based on a configuration of the tool, a wafer flow type, an operation plan, a recipe time, and a waferless auto-clean time obtained from the tool.
[0025] In another feature, the input received from the tool includes data regarding a number of preventive maintenance operations, recipe times, and waferless autoclean times for the tool.
[0026] In another feature, the instructions are configured to predict the optimal scheduling parameters by taking into account one or more skipped preventive maintenance operations.
[0027] In other features, the instructions are configured to schedule, using the model, a plurality of operations for processing the one of the semiconductor substrates in the plurality of processing chambers according to the recipe. The tool undergoes a plurality of states in response to performing the plurality of operations, respectively. The state of the tool includes an indication of resources of the tool and an indication of a processing state of the one of the semiconductor substrates. The instructions are configured to send, to the model, for each of the plurality of states, a current state of the plurality of states and a plurality of schedulable operations for progressing to a next state of the plurality of states, receive from the model an optimal operation of the plurality of schedulable operations selected by the model based on the current state to progress to the next state, and simulate execution of the optimal operation to simulate progressing to the next state. The instructions are configured to train the model to recommend the optimal operation as the plurality of operations in response to the tool going through the plurality of states when processing the semiconductor substrates in the plurality of processing chambers according to the recipe.
[0028] In still other features, a system for processing semiconductor substrates in a tool (the tool includes a plurality of processing chambers configured to process the semiconductor substrates according to a recipe) includes: a processor; and a memory storing instructions for execution by the processor. The instructions are configured to: schedule a plurality of operations for processing semiconductor substrates in the plurality of processing chambers according to the recipe using a model. The tool undergoes a plurality of states in response to executing the plurality of operations, respectively. The state of the tool includes an indication of resources of the tool and an indication of a processing state of the semiconductor substrate. The instructions are configured to send the model, for each of the plurality of states, a current state of the plurality of states and a plurality of schedulable operations for progressing to a next state of the plurality of states, receive from the model an optimal operation of the plurality of schedulable operations selected by the model based on the current state to progress to the next state, and simulate execution of the optimal operation to simulate progressing to the next state. The instructions are configured to train the model to recommend the optimal operation as the plurality of operations in response to the tool going through the plurality of states when processing the semiconductor substrates in the plurality of processing chambers according to the recipe.
[0029] In other features, the instructions are configured to train the model using historical data about processing of the semiconductor substrates received from the tool and by simulating a plurality of processing scenarios of the tool to predict optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe. The instructions are configured to receive input from the tool about processing the semiconductor substrates in the plurality of processing chambers according to the recipe. The instructions are configured to use the model to predict optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe based on the input. The instructions are configured to schedule the plurality of operations based on the optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe.
[0030] In another feature, the instructions are configured to perform the plurality of operations based on the optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe.
[0031] In other features, the optimal scheduling parameters minimize idle time of the semiconductor substrates during processing according to the recipe in the plurality of processing chambers, and the optimal scheduling parameters maximize throughput of the tool.
[0032] In another feature, the instructions are configured to train the model using machine learning methods including artificial neural networks and support vector regression.
[0033] In other features, the instructions are configured to: analyze the historical data received from the tool and the data generated by simulating the multiple processing schemes of the tool; based on the analysis, detect patterns regarding preventive maintenance operations, waferless autoclean time, wait time, recipe time and yield of the tool; and train the model based on the detected patterns.
[0034] In another feature, the instructions are configured to train the model to predict the optimal scheduling parameters for one of the plurality of processing scenarios.
[0035] In another feature, the instructions are configured to train the model to predict the optimal scheduling parameters for all of the plurality of processing scenarios.
[0036] In another feature, the instructions are configured to train the model to perform only etching operations on the semiconductor substrate.
[0037] In another feature, the instructions are configured to train the model for performing both etching and stripping operations on the one of the semiconductor substrates.
[0038] In other features, the model is implemented remotely from the tool, and the instructions are configured to train the model based on data received from a plurality of tools.
[0039] In another feature, the instructions are configured to adjust the model for tool-to-tool variations in configuration and operation.
[0040] In other features, the model is implemented in the cloud as software as a service (SaaS), and wherein the tool is configured to access the model over a network.
[0041] In other features, the model is implemented on the tool, and the instructions are configured to use the model to predict the optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe using data generated by the tool.
[0042] In other features, the model is implemented on the tool and the instructions are configured to adjust the model for any drift in performance of the tool.
[0043] In another feature, the data received from the tool includes data from preventive maintenance operations performed on the tool and data regarding recipe times and waferless autoclean times for the tool.
[0044] In another feature, simulating the plurality of process plans includes generating data based on a configuration of the tool, a wafer flow type, a run plan, a recipe time, and a waferless auto clean time obtained from the tool.
[0045] In another feature, the input received from the tool includes data regarding a number of preventive maintenance operations, recipe times, and waferless autoclean times for the tool.
[0046] In another feature, the instructions are configured to predict the optimal scheduling parameters by taking into account one or more skipped preventive maintenance operations.
[0047] In still other features, a tool for processing semiconductor substrates includes: a first robot, a plurality of processing chambers, a second robot, and a controller. The first robot is configured to input the semiconductor substrate into the tool for processing the semiconductor substrate in the tool. The plurality of processing chambers are configured to process the semiconductor substrate in the tool according to a recipe. The second robot is configured to transfer the semiconductor substrate between the plurality of processing chambers according to the recipe. The controller is configured to use a model trained by simulating the tool and the recipe to predict: a processing time for processing the semiconductor substrate in the plurality of processing chambers; a transfer time for the second robot to transfer the semiconductor substrate between the plurality of processing chambers; a route for transferring the semiconductor substrate between the plurality of processing chambers based on the processing time and the transfer time; and a time for the first robot to schedule additional semiconductor substrates for processing in the tool based on the processing time and the transfer time. Processing the semiconductor substrate according to the predicted route and processing the additional semiconductor substrate according to the predicted time optimizes the waiting time of the semiconductor substrate along the predicted path and optimizes the yield of the tool.
[0048] In another feature, the controller is configured to further train the model incrementally based on data generated by the semiconductor substrate and the additional semiconductor substrate during the processing in the tool.
[0049] In another feature, the controller is configured to use the further trained model to predict: a second processing time, a second transfer time, and a second route for processing the additional semiconductor substrate in the tool; and a second time for scheduling a next group of semiconductor substrates for processing in the tool. Processing the additional semiconductor substrates according to the second route and processing the next group of semiconductor substrates according to the second time further optimizes the waiting time for the additional semiconductor substrates and the throughput of the tool.
[0050] In another feature, the controller is configured to adjust the model in response to any changes to the recipe, the tool, or both.
[0051] In another feature, the model includes: a first plurality of neural networks configured to respectively predict the processing times of the plurality of processing chambers; a second plurality of neural networks configured to respectively predict the transfer times of the first and second robots; and a third neural network coupled to the first and second plurality of neural networks and configured to predict the routes for transferring the semiconductor substrates between the plurality of processing chambers and predict the time when the first robot will schedule the additional semiconductor substrate for processing in the tool.
[0052] In another feature, the module is further trained by simulating a plurality of tool configurations and a plurality of recipes.
[0053] In another feature, the further trained model is configured to output a recommendation for a tool configuration in response to receiving recipe information as input.
[0054] In another feature, the recipe is for depositing a plurality of layers on the semiconductor substrate. The plurality of processing chambers include one or more processing chambers for depositing the plurality of layers, and a pre-processing chamber and a post-processing chamber for processing the semiconductor substrate before and after depositing the plurality of layers, respectively. The second robot is configured to transfer the semiconductor substrate between the plurality of processing chambers according to the predicted route to optimize the waiting time of the semiconductor substrate. The first robot is configured to schedule the additional semiconductor substrates for processing in the tool according to the predicted time to optimize the yield of the tool.
[0055] In still other features, a system for optimizing throughput and latency during processing of semiconductor substrates in a semiconductor processing tool includes: a processor; and a memory storing instructions for execution by the processor. The instructions are configured to simulate a plurality of routes to route the semiconductor substrate between a plurality of processing chambers of the semiconductor processing tool based on a configuration of the semiconductor processing tool and a recipe to be executed on the semiconductor substrate in the semiconductor processing tool. The instructions are configured to simulate processing of the semiconductor substrate in the semiconductor processing tool according to the recipe along the plurality of routes. The instructions are configured to simulate a plurality of timing schedules based on the processing of the semiconductor substrate to subsequently process additional semiconductor substrates in the semiconductor processing tool. The instructions are configured to simulate processing of the additional semiconductor substrates according to the plurality of timing schedules. The instructions are configured to train a model based on data generated by the simulation. The instructions are configured to predict an optimal route for transferring the semiconductor substrate between the plurality of processing chambers using the model on the semiconductor processing tool when processing the semiconductor substrate in the semiconductor processing tool according to the recipe. The instructions are configured to use the model on the semiconductor processing tool to predict an optimal time to schedule the additional semiconductor substrate for processing in the semiconductor processing tool. The instructions are configured to process the semiconductor substrate in the semiconductor processing tool according to the optimal route to optimize the waiting time of the semiconductor substrate along the optimal route. The instructions are configured to process the additional semiconductor substrate in the semiconductor processing tool at the optimal time to optimize the yield of the semiconductor processing tool.
[0056] In other features, the instructions are configured to train the model based on the data generated by the simulation to predict: processing time for processing the semiconductor substrate in the multiple processing chambers; transfer time of a robot of the semiconductor processing tool for transferring the semiconductor substrate between the multiple processing chambers; the optimal route for arranging the semiconductor substrate between the multiple processing chambers based on the processing time and the transfer time; and the optimal time for scheduling additional semiconductor substrates for processing in the semiconductor processing tool based on the processing time and the transfer time.
[0057] In another feature, the instructions are configured to further incrementally train the model based on data generated by the semiconductor substrate and the additional semiconductor substrate during the processing in the semiconductor processing tool.
[0058] In another feature, the instructions are configured to adjust the model for any changes to the recipe, the semiconductor processing tool, or both.
[0059] In other features, the instructions are configured to generate the model based on the data generated by the simulation, and the model includes: a first plurality of neural networks configured to predict processing times for processing the semiconductor substrates in the plurality of processing chambers, respectively. The model includes: a second plurality of neural networks configured to predict transfer times for the first and second robots, respectively. The first and second robots are configured to transfer the semiconductor substrates into the semiconductor processing tool and between the plurality of processing chambers, respectively. The model includes: a third neural network coupled to the first and second plurality of neural networks and configured to predict the optimal route for routing the semiconductor substrates between the plurality of processing chambers and predict the optimal time to schedule the additional semiconductor substrates for processing in the semiconductor processing tool.
[0060] In another feature, the instructions are configured to train the model by simulating configurations of a plurality of semiconductor processing tools and a plurality of recipes.
[0061] In another feature, the instructions are configured to train the model in response to receiving recipe information as input to output recommendations for tool configuration.
[0062] Any of the features described above and below may be implemented separately (ie, independently of the other features described above and below). In some embodiments, any of the features described above and below may be combined with the other features described above and below.
[0063] Further scope of applicability of the present disclosure will become apparent from the detailed description, claims and drawings.The detailed description and specific examples are intended for purposes of illustration only and are not intended to limit the scope of the disclosure. BRIEF DESCRIPTION OF THE DRAWINGS
[0064] The present disclosure will be more fully understood from the detailed description and accompanying drawings, in which:
[0065] Figure 1 is a functional block diagram of an example substrate processing tool including one or more processing chambers;
[0066] Figure 2 is a functional block diagram of an example substrate processing system including a processing chamber;
[0067] Figure 3 is a functional block diagram of an example data collection system;
[0068] Figure 4 A functional block diagram of a system for generating and training a machine learning assisted model to schedule wafer processing operations of a substrate processing tool is shown;
[0069] Figure 5A-8 A method for generating and training a machine learning assisted model is shown;
[0070] Figure 9-11 An example of a deep neural network used to generate the model described herein is shown;
[0071] Fig.12 A functional block diagram of a system for training a reinforcement learning model using a discrete event simulator is shown;
[0072] Fig.13 A method for training a reinforcement learning model using a discrete event simulator is shown;
[0073] Fig.14 A system for training a model with a nested neural network using an offline simulator and online real-time data from a tool to schedule and adjust wafer processing in the tool is shown;
[0074] Fig.15A and 15B A method for training a model with a nested neural network using an offline simulator and online real-time tool data to schedule and adjust wafer processing in a tool is shown;
[0075] Fig.16 An example of a tool including multiple process modules (e.g., electroplating cells) is shown;
[0076] Fig.17 Shown for Fig.16 Examples of process modules (e.g., plating cells) in a tool; and
[0077] Fig.18 An example of a wafer fab data collection system is shown, which is Fig.14 The offline simulator is used in conjunction with the training for scheduling and tuning tools (e.g. Fig.16 A model of wafer processing in a tool).
[0078] Among the drawings, reference numerals may be repeated to identify similar and / or identical elements. DETAILED DESCRIPTION
[0079] Typically, an operator of a substrate processing tool (hereinafter referred to as a "tool") manually selects scheduling parameter values based on past experience, experimentation, or by utilizing a trial-and-error approach. This is because simple criteria for selecting scheduling parameter values are not easily established. Since different substrate processing schemes of a tool (e.g., an etching tool) may require different sets of scheduling parameter values to achieve optimal throughput for the tool, the operator may have to manually input the scheduling parameter values into the system software controlling the tool before starting each wafer flow running on the tool.
[0080] In some tools, the scheduler in the system software can use a set of scheduling rules and scoring systems to make scheduling decisions. However, as the complexity of the tool's system configuration, operating scenarios, and scheduling constraints increases, the complexity of the scheduling decision scheme also increases, which requires more development work to achieve and maintain optimal system throughput.
[0081] Furthermore, in batch (multiple substrate) processing tools for multiple parallel material deposition processes, which have constraints on wafer wait time, pacing the tool's scheduler to achieve optimal throughput and minimum wafer wait time can be very difficult. Scheduler rules are very dynamic, and incorrect schedule calculations can result in abnormal wafers or reduced yield due to wafer drying, which increases the cost-of-ownership of the tool. Furthermore, different customer applications make pacing predictions more complex. For example, long processing time recipes (e.g., mega-pillar recipes) bottleneck the processing module, while short processing time recipes (e.g., redistribution layer recipes or RDL recipes) bottleneck the back-end robot (with several arms for processing batches / multiple substrates together).
[0082] The present disclosure addresses these issues as follows by using a trained model and further by using reinforcement learning. For an etching tool, a neural network model (hereinafter referred to as the "model") is trained to predict the optimal scheduling parameter values. The model is trained using data collected from preventive maintenance operations (PM), recipe time, and waferless automatic cleaning (WAC) time as inputs to the model. The model is used to obtain the underlying relationship between the scheduling parameter values and various wafer processing schemes to make predictions accordingly, thereby eliminating the need to establish criteria for optimal value selection.
[0083] Prior to training, identify the set of important scheduling parameters predicted by the model. Collect a large amount of training data from the tool used by semiconductor manufacturers. Generate additional training data using simulations to cover the various process scenarios used by semiconductor manufacturers using the tool. Determine the optimal neural network structure to support a model that provides consistent prediction accuracy across the scheduling parameter space. Although a dedicated model for a wafer process scenario can be used, a single model that can cover a variety of process scenarios can also be produced by training the model over time using data collected from other process scenarios.
[0084] To facilitate model maintenance, the model can be run outside the tool's system software. That is, the model can be outside the tool's system software, separate from the tool's system software, and not integrated into the tool's system software. The model can receive input parameters from the system software based on the wafer flow selected by the operator. The model can then calculate and predict the optimal scheduling parameter values and send them back to the system software. For example, an equipment manufacturer can deploy the model in the cloud as software-as-a-service that semiconductor manufacturers can subscribe to. Alternatively, the equipment manufacturer can apply the model to the tool's system software.
[0085] Using a trained model enables the basic behavior of the scheduler built into the system software to be captured into a neural network model, which can then be used to predict the best scheduling parameter values to be used. Operators no longer need to conduct extensive simulation studies to select the best scheduling parameter values. Using a trained model also enables the system software to automatically select scheduling parameter values when a new wafer flow is about to start.
[0086] In addition, the dispatcher's dispatch rules and scoring system can be replaced by a neural network model. The model is trained using a discrete event simulator and reinforcement learning to self-explore and memorize the best dispatch decision for a given state of the system. This enables the system to achieve and maintain optimal production performance.
[0087] The self-exploration process uses a discrete event simulator to automate the effort to find the best possible way to operate the system with the best throughput performance (e.g., find the best path to move a wafer through a tool). By running the self-training process on the tool, the neural network model can be optimized for the specific tool configuration, wafer handling scheme, and constraints unique to the tool.
[0088] Therefore, the present invention provides an intelligent machine learning assisted scheduler. The intelligent scheduler uses a self-learning process to train a neural network model to make optimal scheduling decisions for a given state of the system. These decisions help achieve and maintain the tool in optimal yield conditions under semiconductor manufacturer-specific operating scenarios and scheduling constraints.
[0089] For example, for each recipe, the smart scheduler can ensure that the wafer idle time can be less than 2% of the total processing time and the manufacturing efficiency (actual cycle time / theoretical cycle time) can be greater than 97%. In addition, the smart scheduler can compensate for differences between tools and performance drifts that may occur over time within the same tool. In addition, the smart scheduler can optimize the scheduling parameter values by considering preventive maintenance that may have to be skipped or delayed to meet manufacturing deadlines. These and other features of the smart scheduler will be described in detail below.
[0090] Furthermore, as explained below, in order to improve the accuracy of scheduler adjustments used in tools for multiple parallel material deposition (e.g., multi-layer plating) processes, the present disclosure proposes a nested neural network-based machine learning approach for accurately predicting scheduler adjustments for different processes. Using this approach, a model is initially developed and trained offline using simulations, and then trained online using actual tools for predicting wafer routing paths and schedules to achieve the highest tool / fleet utilization, the shortest wait time, and the fastest throughput.
[0091] The present disclosure is arranged as follows. Figure 1 , shows and describes examples of tools. Figure 2 , an example of a substrate processing system including a processing chamber is shown and described. Figure 3 , shows and describes an example of a data collection system for collecting data from various tools. Figure 4 , a system for generating and training a machine learning assisted model is shown and described. Figure 5A-8 , shows and describes a method for generating and training a machine learning assisted model. Figure 9-11 , shows and describes an example of a deep neural network used to generate the model described herein. Fig.12 , shows and describes a system for training reinforcement learning models using a discrete event simulator. Fig.13 , shows and describes a method for training reinforcement learning models using a discrete event simulator. Fig.14 , a system for training a model with a nested neural network using an offline simulator and online real-time tool data to schedule and adjust wafer processing in a tool is shown and described. Fig.15A and 15B , shows and describes a method for training a model with a nested neural network using an offline simulator and online real-time tool data to schedule and adjust wafer processing in a tool. Fig.16 , an example of a tool including multiple process modules (e.g., electroplating cells) is shown and described. Fig.17 , shows and describes Fig.16 An example of a processing module for a tool. Fig.18 , shows and describes an example of a wafer fab data collection system that is used in conjunction with an offline simulator to train a model for scheduling and adjusting wafer processing in a tool.
[0092] Figure 1 An example of a substrate processing tool 100 is shown. The substrate processing tool 100 includes a plurality of processing chambers 104-1, 104-2, ... and 104-M (collectively referred to as processing chambers 104) (where M is an integer greater than 1). By way of example only, each processing chamber 104 may be configured to perform one or more types of substrate processing. In other words, a substrate may be loaded into one of the processing chambers 104 for processing, then moved to one or more of the other processing chambers 104 (if at least one performs a different process) and / or removed from the substrate processing tool 100 (if all perform the same process).
[0093] The substrate to be processed is loaded into the substrate processing tool 100 via a port of a loading station of an atmosphere to vacuum (ATV) transfer module 108. In some examples, the ATV transfer module 108 includes an equipment front end module (EFEM). The substrate is then transferred to one or more processing chambers 104. For example, a transfer robot 112 is arranged to transfer the substrate from the loading station 116 to an airlock or load chamber 120, and a vacuum transfer robot 124 of a vacuum transfer module 128 is arranged to transfer the substrate from the load chamber 120 to each processing chamber 104.
[0094] A chamber controller 130, a transport controller 134, and / or a system controller 138 may be provided. The transport controller 134 controls the robots 112 and 124, actuators and sensors associated with transporting substrates into and out of the substrate processing tool 100. The chamber controller 130 controls the operation of the process chamber 104. Generally, the chamber controller 130 monitors sensors 135, such as temperature sensors, pressure sensors, position sensors, etc., and controls actuators 136, such as robots, ports, heaters, gas delivery systems, electrostatic chucks (ESCs), radio frequency (RF) generators, etc. The chamber controller 130 associated with the process chamber 104 generally follows a recipe that specifies the timing of steps, process gases to be supplied, temperature, pressure, RF power, etc.
[0095] Figure 2An example of a substrate processing system 200 for processing a substrate is shown to illustrate an example of the type of data generated during operation of a processing chamber. Although a particular type of processing chamber is shown, other types of processing chambers may be used. The substrate processing system 200 includes a processing chamber 202 that surrounds the other components of the substrate processing system 200 and contains an RF plasma. The substrate processing system 200 includes an upper electrode 204 and a substrate support, such as an electrostatic chuck (ESC) 206. During operation, a substrate 208 is disposed on the ESC 206.
[0096] By way of example only, the upper electrode 204 may include a showerhead 209 that introduces and distributes process gases, such as deposition precursors, etching gases, carrier gases, etc. The ESC 206 includes a conductive bottom plate 210 that serves as a lower electrode. The bottom plate 210 supports a heating plate 212, which may correspond to a ceramic multi-zone heating plate. A thermal resistance layer 214 may be disposed between the heating plate 212 and the bottom plate 210. The bottom plate 210 may include one or more coolant channels 216 for flowing a coolant through the bottom plate 210.
[0097] The RF generation system 220 generates and outputs an RF voltage to one of the upper electrode 204 and the lower electrode (e.g., the bottom plate 210 of the ESC 206). The other of the upper electrode 204 and the bottom plate 210 may be DC grounded, AC grounded, or floating. By way of example only, the RF generation system 220 may include an RF voltage generator 222 that generates an RF voltage supplied to the upper electrode 204 or the bottom plate 210 by a matching and distribution network 224. In other examples, the plasma may be generated inductively or remotely.
[0098] The gas delivery system 230 includes one or more gas sources 232-1, 232-2, ... and 232-N (collectively referred to as gas sources 232), where N is an integer greater than zero. The gas source 232 supplies one or more deposition precursors, etching gases, carrier gases, etc. A vaporized precursor may also be used. The gas source 232 is connected to the manifold 238 via valves 234-1, 234-2, ... and 234-N (collectively referred to as valves 234) and mass flow controllers 236-1, 236-2, ... and 236-N (collectively referred to as mass flow controllers 236). The output of the manifold 238 is supplied to the processing chamber 202. By way of example only, the output of the manifold 238 is supplied to the showerhead 209.
[0099] An optical emission spectroscopy (OES) sensor 239 may be positioned adjacent to a window 240 disposed on a chamber surface 241. The OES sensor 239 selectively generates OES data. A temperature controller 242 may be connected to a plurality of thermal control elements (TCEs) 244 disposed in the heating plate 212. For example, the TCEs 244 may include, but are not limited to, individual giant TCEs corresponding to each zone in the multi-zone heating plate and / or an array of micro-TCEs disposed throughout the plurality of zones of the multi-zone heating plate. The temperature controller 242 may be used to control the plurality of TCEs 244 to control the temperature of the ESC 206 and the substrate 208.
[0100] The temperature controller 242 may be in communication with the coolant assembly 246 to control the flow of coolant through the passage 216. For example, the coolant assembly 246 may include a coolant pump and a reservoir. The temperature controller 242 operates the coolant assembly 246 to selectively flow coolant through the passage 216 to cool the ESC 206.
[0101] The valve 250 and pump 252 can be used to evacuate reactants from the processing chamber 202. The controller 260 can be used to control the components of the substrate processing system 200. The robot 270 can be used to transport substrates to the ESC 206 and move substrates away from the ESC 206. For example, the robot 270 can transfer substrates between the ESC 206 and the loading chamber 272. Although shown as a separate controller, the temperature controller 242 can be implemented in the controller 260.
[0102] During the processing and transfer of substrates, substrate processing tools generate a large amount of discrete data and streaming data. Event data can be used to determine the location and residence time in various components. For example, the residence time in a module or front-opening wafer transfer box (FOUP) may cause processing differences between substrates. The system log records system-level data. During substrate transfer, additional data is recorded. Each processing chamber also records data during substrate processing. The recorded data includes different data types, sampling rates and / or formats. Some data is only stored locally in the processing chamber, while other data is stored at the wafer factory level.
[0103] Data is usually sent from the tool to the host in a message format at a fixed frequency. Data is not usually sent on a substrate basis. Instead, data is sent on a time basis. Data is usually collected in files based on a fixed frequency or file size. Data is usually collected continuously and without boundaries. In some systems, data is collected at the beginning of a recipe and at the end of a recipe during processing of the first and last substrates, respectively, but not for intermediate substrates.
[0104] From this data, non-confidential operational data can be collected and analyzed using big data tools and / or machine learning to build and train models that provide optimal scheduling parameters to improve productivity and system output. In addition, simulation can be used to generate additional model training data based on tool configuration and recipe data.
[0105] Semiconductor manufacturers may combine data from different files with different formats. In some examples, the data collected from customer tools may be in a general structured file format that supports encryption and forward / backward compatibility. In some examples, the data format may be consistent with a technical data management solution (TDMS) file format. In some examples, the data format may be accessible and can be read by the customer using a key (e.g., an application programming interface (API) key). The data context and collection may be consistent across different data types to enable use and analysis without having to perform cleanup, reformatting, and / or other work on the collected data.
[0106] In some examples, data may be collected from the moment the substrate leaves the cassette until the substrate returns to the cassette. In some examples, the data may be stored in a single file. In some examples, the file format may be self-consistent. In some examples, data may be collected at different frequencies based on the type and context of the data. In some examples, the data may be formatted using TDMS with encryption. In some examples, data adapters may be used to support legacy data and backward compatibility, incorporate new data types, and support host messaging and streaming data.
[0107] Figure 3 A wafer fab data collection system 300 for a semiconductor processing system is shown. The wafer fab data collection system 300 includes N substrate processing tools 320-1, 320-2, ... and 320-N (where N is an integer) (collectively referred to as substrate processing tools 320). Each substrate processing tool 320 includes one or more process chamber controllers 340-1, 340-2, ... and 340-N (collectively referred to as process chamber controllers 340) to control the operation of the process chambers, as described above. Examples of data collected by the process chambers include substrate or wafer data logs, automatic preventive maintenance, high-speed data, optical emission spectroscopy (OES), tracking data, OES snapshots, susceptor temperature maps and other data, calibration files, equipment constants, sensor data, and / or other data.
[0108] Each substrate processing tool 320 may include a transport controller 344-1, 344-2, ..., and 344-N (collectively referred to as a transport controller 344) to control dynamic alignment and store calibration files, platform tracking data logs, equipment constants, transfer module actions, and / or other data. Dynamic alignment refers to the position of a substrate relative to other chamber components (e.g., the center of a pedestal, edge ring, or other object).
[0109] Each substrate processing tool 320 may include a tool system controller 348-1, 348-2, ..., and 348-N (collectively referred to as a tool system controller 348). The tool system controller 348 records batch history, detailed event logs, batch-based alarms, time-based alarms, tool controller health, part tracking, part history, material scheduling, and other data.
[0110] Each substrate processing tool 320 further includes a data diagnostic service computer 350-1, 350-2, ..., and 350-N (collectively referred to as a data diagnostic service computer 350) and a data storage device 362-1, 362-2, ..... and 362-N (collectively referred to as a data storage device 362). In other examples, the data diagnostic service computer 350 can be shared by two or more tools, or each tool can include more than one data diagnostic service computer 350. The substrate processing tool 320 is connected to the host server 364 via one or more buses such as a tool data bus or network 364-1 and a streaming data bus or network 364-2.
[0111] In some examples, the host server 364 includes a security module 366 and a data selector module 367. The security module 366 provides security, such as encryption or password protection. The security module 366 uses encryption or passwords to grant or deny access to data stored by the substrate processing tool 320 and / or access to the data selector module 367. The host server 364 further includes a data selector module 367 to enable the user computer 380 to select one or more data categories from one or more substrate processing tools and filter data using one or more data context fields. In other examples, the security module 366 and / or the data selector module 367 can be implemented using separate servers.
[0112] The host server 364 is connected to a machine learning computer 374 and / or one or more user computers 380 via a network 368 such as a wide area network (WAN) or a local area network (LAN). The data set returned by the host server 364 can be accessed by the machine learning computer 374 for further analysis. In some examples, the machine learning computer 374 includes a security module 375 to control access to the data. The machine learning computer 374 uses one or more data files generated by the data collection system 300 selected by the user to perform machine learning. Since the file formats from different substrate processing tools are the same, the data can be merged into a single file and analyzed. This allows the same process to be analyzed in multiple machines.
[0113] The number T of substrate processing tools 320 is not limited. In addition, the substrate processing tools 320 need not be located at the same facility. In some examples, an equipment manufacturer may be granted access to data stored by multiple semiconductor manufacturers. In some examples, the sampling rates of some or all data generating devices (except streaming or HSD devices) may be aligned to a common sampling period, and data may be added to a common file based on the sampling period.
[0114] Figure 4 A system 400 for generating and training a machine learning assisted model according to the present disclosure is shown. For example, the system 400 may include a machine learning computer (e.g., Figure 3 Element 374 shown). The system 400 includes a data collector 402, a simulator 404, a data analyzer 406, and a model generator 408. The data collector 402 collects data from one or more tools for generating and training a neural network model. The simulator 404 generates additional training data based on the hardware configuration, wafer flow type, run plan, recipe time, and waferless automatic cleaning (WAC) time obtained from the tool.
[0115] The data analyzer 406 analyzes the data collected by the data collector 402 and the data generated by the simulator 404 using techniques for analyzing big data. The data analyzer 406 obtains the basic relationship between the scheduling parameter values and the wafer processing plan. The model generator 408 generates a model by applying machine learning techniques to the data analyzed by the data analyzer 406. The model generator 408 defines, trains, and validates one or more models, as described in detail below.
[0116] In system 400, all components 402-408 may be controlled by a single computer (e.g., Figure 3Each of the elements 402-408 may be implemented by a separate computer. One or more of the elements 402-408 may be implemented by a separate computer. In other words, the elements 402-408 may be implemented using one or more computing devices.
[0117] Each computing device may include one or more hardware processors (eg, CPUs). Each computing device may include a memory that stores data corresponding to the following references: Figure 5A-8 Instructions of the method shown and described. A hardware processor of a computing device may execute instructions stored in a memory of the computing device.
[0118] One or more of the elements 402-408 may be communicatively interconnected via one or more networks. For example, the network may include a LAN, WAN, the Internet, a cloud-based network system, or any other distributed communication system (eg, a network system based on a client-server architecture).
[0119] For example, the data collector 402 may be implemented as Figure 3 The wafer fab data collection system 300 is shown. The data collector 402 collects data from one or more tools (e.g., Figure 1 The one or more tools may be located at the same customer location. The one or more tools may be located at different locations of the same customer. The one or more tools may be located at different customer locations. The data collected from the tools does not include the customer's private and confidential data, but includes all other operational data that can be used to generate and train the model.
[0120] By way of example only, the tool (from which data is collected) may be an etching tool and may have the following configuration. The tool may have up to 4 air locks. The wafer flow configuration may be level 1 (etch only) and / or level 2 (etch and strip) with a cooling station. Recipe types may include wafer handling, waferless automated cleaning, pre-processing, and post-processing, etc. The operating scheme may include single stream and / or multiple streams running in parallel. The tool may include up to six processing chambers, including one or more etching chambers, one or more stripping chambers, cleaning chambers, etc.
[0121] In system 400, model generator 408 applies machine learning (ML) methods to historical data obtained from tool and simulator 404 and analyzed by data analyzer 406 to generate a yield prediction model. Using the model, the tool's scheduler can schedule the processing of the wafer using the optimal scheduling parameters provided by the model for a given tool configuration. Due to the complex relationship between the basic variables, simple linear regression does not work well. Instead, using machine learning methods provides flexibility to handle complex nonlinear data. Examples of machine learning methods include artificial neural networks (ANN), support vector regression (SVR), etc.
[0122] Model generator 408 may use other methods instead of or in addition to machine learning methods. Examples of other methods include metaheuristics and mathematical methods (e.g., Petri nets). Metaheuristic methods are a branch of artificial intelligence (AI) and are automatic trial and error methods to find a near-optimal scheduling mode that meets predetermined performance requirements. Then, scheduling parameter values can be extracted from the selected scheduling mode. Examples of algorithms for finding near-optimal scheduling modes include genetic algorithms and genetic programming.
[0123] Using the selected machine learning method, the model generator 408 trains a model to predict the optimal scheduling parameter values. The model is trained using data collected from, for example, preventive maintenance operations (PM), recipe times, and waferless automatic cleaning (WAC) times of the tool. The model is used to obtain the basic relationship between the scheduling parameter values and various wafer processing schemes to make corresponding predictions, thereby eliminating the need to establish criteria for optimal value selection. The model can provide consistent prediction accuracy across the parameter space.
[0124] The model generator 408 can generate and train a dedicated model for a specific wafer processing scenario. In other words, the model can be trained for a specific tool. Alternatively, the model generator 408 can generate and train a single model that can cover multiple scenarios. In other words, the model can be trained to work on multiple tools. For example, a dedicated model trained for a specific tool can be further trained to work on multiple tools using data collected from other tools over time from other scenarios.
[0125] To determine whether a model can cover all possible scenarios or whether a dedicated model is needed, the model generator 408 can apply the selected machine learning method to generate the model based on the data collected from multiple tool configurations and operation scenarios to check whether the prediction accuracy can meet the success criteria. The success criteria can include whether the model can compensate for the changes between tools and the performance drift that may occur over time within the same tool. The success criteria can further include whether the model can optimize the scheduling parameter values by considering skipped preventive maintenance. The success criteria can also include whether the wafer idle time is less than a small percentage (e.g., 2%) of the total processing time of all wafers, and whether the manufacturing efficiency (actual cycle time / theoretical cycle time) of each recipe will be high (e.g., greater than 97%).
[0126] When in use, the model may receive input parameters from the tool's system software (e.g., from the system controller 138 of the tool 100) based on the wafer flow selected by the operator. For example, the model may receive as input the number of PMs, recipe times, and WAC times. The model may then calculate and predict the optimal scheduling parameter values and send them back to the system software. The trained model captures the underlying behavior of the scheduler built into the system software, which may then be used to predict the optimal scheduling parameter values to be used when processing a group of wafers according to the selected wafer flow. Using the trained model also enables the tool's system software to automatically select scheduling parameter values when a new wafer flow is about to begin. The tool operator no longer needs to conduct extensive simulation studies to select the optimal scheduling parameter values.
[0127] The model can be implemented in many ways. For example, the model can be integrated into the system software of the tool. Alternatively, the model can be implemented remotely independent of the system software of the tool, and the prediction results generated by the model can be supplied to the system software of the tool. For example, to facilitate model maintenance, the model can be run outside the system software of the tool. The model can receive input parameters from the system software based on the wafer flow selected by the operator. The model can then calculate and predict the optimal scheduling parameter values and send them back to the system software. For example, the model can be used in the cloud as software as a service.
[0128] When the model is integrated into the system software of the tool, the model can generate the best scheduling parameters for a given operating scenario on the tool based on the tool acquisition data based on each tool. Therefore, in this embodiment, the predictions of the model are based on the actual tool data. The model is also adaptable to differences between tools. The model can be updated to adjust for tool performance drift. However, in this embodiment, intensive calculations are performed on the tool itself. In addition, the tool acquisition data may not be sufficient for the model to provide an optimal solution. The adequacy of the data can be determined by using the model with a set of data from the tool and evaluating whether the data set is sufficient to predict the optimal scheduling parameters.
[0129] When the model is implemented separately from the tool, the model generator 408 can identify and store the optimal configuration and operating scheme set for each tool, and store the set for automatic selection. The simulator 404 can generate training data for multiple combinations of tool configurations, wafer flow types, recipes / WAC times, and operating schemes. The model generator 408 can identify the best machine learning method to generate the best prediction model based on the training data set to produce the best system output. The model can then be used to generate the optimal scheduling parameter set for each tool configuration and scheme. The model result set can be encoded into the user interface so that the tool operator can make automatic scheduling parameter selection based on the tool configuration and operating scheme selected by the tool operator.
[0130] In this implementation, the calculations performed on the tools are limited. However, the model generator 408 performs extensive calculations to cover multiple configurations and scenarios for multiple tools. In addition, the model's predictions are based on simulation data, not acquisition data for multiple tools. Therefore, model performance depends on the quality of the simulation data. The model may also not support all possible tool configurations and operating scenarios. In addition, the model may not adapt to differences between tools and may not adjust for tool performance drift.
[0131] Figure 5A A method 500 for generating a machine learning assisted model and operating a tool based on scheduling parameters generated using the model is shown. The method 500 may be performed by Figure 4 For example, one or more of the elements 402 - 408 of the system 400 may perform one or more of the following steps of the method 500 .
[0132] At 502, data for generating and training a model is received from one or more tools. At 504, configuration and recipe data for one or more tools is received. At 506, a simulator (e.g., the one described above) is used to generate and train a model. Figure 4 Element 406 is shown and described to generate additional data for generating and training the model based on the configuration and recipe data. Figure 5B , further explaining the operation of the simulator in detail.
[0133] At 508, a model is generated and trained using machine learning methods by analyzing data received from the tool and simulator. Figure 5C , which explains the process of analyzing the data in further detail. Figure 6 and 7 , further explaining the model generation and training process in detail.
[0134] At 510, the model is tested and validated. Figure 8, the model validation process is further explained in detail.
[0135] At 512, the method 500 determines whether the test criteria of the model are met. If the test criteria are not met, the method 500 returns to 502. At 514, if the test criteria are met, the model is deployed for use. The model is integrated into the system software of the tool, or implemented separately from the system software of the tool, as described above.
[0136] At 516, the model receives input from the system software of the tool, which is related to the processing to be performed on the wafer set. At 518, based on the received input, the model provides optimal scheduling parameter values to the system software of the tool for processing the wafer set. At 520, based on the received scheduling parameter values, the system software of the tool schedules operations to process the wafer set.
[0137] Figure 5B The operation of the simulator 404 is shown as a method 550 performed by the simulator 404. Figure 5A As described in 504, receiving configuration and recipe data for the one or more tools. Figure 5B In the embodiment of the present invention, at 552, the simulator 404 simulates the processing environment of the tool using the hardware configuration and recipe data of the tool, etc. At 554, the simulator 404 simulates the processing of the wafer in the simulated environment of the tool. At 556, the simulator 404 generates additional data based on the simulated processing of the wafer in the simulated environment of the tool to generate and train the model.
[0138] Figure 5C The operation of the data analyzer 406 is shown, which is presented in the form of a method 580 performed by the data analyzer 406. Figure 5A As described in 508, the model is generated and trained by analyzing the data received from the tool and the simulator. Figure 5C In the example embodiment, at 582, the data analyzer 406 analyzes the data collected from the tool and from the simulator 404. At 584, the data analyzer 406 analyzes the data using a technique for analyzing data.
[0139] At 586, the data analyzer 406 detects patterns regarding PM, WAC time, wait time, recipe time, and production volume of the tools based on the analysis of the collected data. At 588, the data analyzer 406 detects variations between the tools and variations of the same tool. At 590, the data analyzer 406 provides the detected patterns and variations to the model generator 408 for use in model training using machine learning.
[0140] Figure 6 and 7 The model generation and training process is shown in more detail. Figure 6, which shows a method 600 for generating a model. At 602, a model is defined. At 604, the model is trained. At 606, the model is validated.
[0141] exist Figure 7 , which shows a method 700 for generating a model. At 702, a model is defined by selecting a network topology for a deep neural network. Examples of deep neural networks are as follows Fig. 9 For example, selecting a network topology includes selecting the number of inputs, the number of neurons, and the number of layers of a deep neural network.
[0142] From 704 to 710, the model is trained. At 704, the model is run on training data (e.g., data collected from the tool and data generated by the simulator). At 706, the output predicted by the model is checked against the training data. At 708, the model parameters and / or network technology are adjusted to produce a better match between the model's predictions and the actual data. At 710, it is determined whether the model meets predetermined criteria.
[0143] For example, the predetermined criteria include determining whether the model can compensate for tool-to-tool variations and performance drift of the same tool, and whether the model can be optimized for unavailable PM. In addition, the predetermined criteria may include determining whether the model output ensures small wafer idle time (e.g., less than 2%) and high manufacturing efficiency (e.g., greater than 97%). If one of the predetermined criteria is not met, the method 700 returns to 704. At 712, the model is validated by testing the model with new data from the tool if the predetermined criteria are met.
[0144] Figure 8 A method 800 for validating a model is further shown in detail. The method is called a K-fold validation method. At 802, the data for validation is divided into K partitions, where K is an integer greater than 1. At 804, the same model is instantiated. At 806, each model is trained on a partition and evaluated on the remaining partitions. A validation score is assigned to each evaluation. At 808, the validation score of the model is the average of the K validation scores of the model. The model with the highest validation score is used for use.
[0145] Other validation methods can be used to validate the model. For example, an N-fold cross-validation method can be used. In this method, the entire data set is divided into a final test set and N other subsets, where N is an integer greater than 1. Each model is trained on all but one of the subsets to obtain N different validation error rate estimates. The model with the lowest validation error rate is used.
[0146] Fig. 9 and10 An example of a deep neural network used to generate the model described herein using machine learning techniques is shown. Machine learning is a method for designing complex models and algorithms that aid in prediction. Models generated using machine learning can produce reliable, repeatable decisions and results, and discover hidden insights by learning from historical relationships and trends in data.
[0147] The purpose of using a deep neural network based model and training it using machine learning is to directly predict the dependent variables without converting the relationship between the variables into mathematical form. The neural network model contains a large number of neurons that operate in parallel and are arranged in layers. The first layer is the input layer and receives the raw input data. Each successive layer modifies the output from the previous layer and sends it to the next layer. The last layer is the output layer and produces the output of the system.
[0148] In the input layer, each input node is associated with a value, which can be any real number. In each layer, each connection from an input node has a weight associated with it, which can also be any real number (see Fig.10 ).exist Fig. 9 , which shows a fully connected neural network where every neuron in a given layer is connected to every neuron in the next layer.
[0149] In the input layer, the number of neurons is equal to the number of features (columns) in the data set. The output layer can have multiple continuous outputs. The layers between the input and output layers are hidden layers. The number of hidden layers can be one or more (one hidden layer is probably enough for most applications). A neural network with no hidden layers can represent linearly separable functions or decisions. A neural network with one hidden layer can perform a continuous mapping from one finite space to another finite space. A neural network with two hidden layers can approximate any smooth mapping to any degree of accuracy.
[0150] The number of neurons can be optimized. At the beginning of training, the network configuration will most likely have too many nodes. During training, nodes that do not significantly affect the network's performance can be removed from the network. For example, nodes whose weights are close to zero after training can be removed (pruned). The number of neurons can result in underfitting (not adequately capturing the signal in the dataset) or overfitting (not enough information to train all neurons; the network performs well on the training dataset but poorly on the test dataset).
[0151] A variety of methods can be used to measure the performance of a model. For example, the root mean square error (RMSE) measures the average difference between the observed values and the model's predictions. The coefficient of determination (R 2) measures the correlation (not accuracy) between observations and predicted outcomes. If the data vary widely, the method is unreliable. Other performance measures include irreducible noise, model bias, and model variance. High bias indicates that the model is not capturing the true relationship between predictors and outcomes. Model variance can indicate whether the model is unstable (small perturbations in the data can significantly change the model fit).
[0152] Fig.11 Examples of high bias and high variance are shown. High variance may indicate overfitting. A variety of methods may be used to prevent overfitting. For example, regularization may be used, where large weights may be penalized using a penalty or constraint of their squared value (L2 penalty) or absolute value (L1 penalty). In addition, more data may be used. Furthermore, pruning (deleting neurons with near-zero weight factors) and / or bagging (training the model on different subsets of the training data) may be used to prevent overfitting.
[0153] Fig.12 A system 1200 for training a reinforcement learning model using a discrete event simulator is shown. For example, the model produced by the system 400 described above can be further trained using reinforcement learning using the system 1200 as described below. The system 1200 includes a discrete event simulator 1202 and a reinforcement learning model 1204. The discrete event simulator 1202 is used in conjunction with the system software of the tool (e.g., Figure 1 The controller 138 of the tool 100 shown, which executes the system software of the tool) and the reinforcement learning model 1204 (e.g., Figure 4 The model generated by the system 400 shown) communicates.
[0154] In system 1200, all elements 138, 1202, and 1204 may be implemented by a single computer. Each of elements 138, 1202, and 1204 may be implemented by a separate computer. One or more of elements 138, 1202, and 1204 may be implemented by a separate computer. In other words, elements 138, 1202, and 1204 may be implemented using one or more computing devices.
[0155] Each computing device may include one or more hardware processors (e.g., CPUs). Each computing device may include a memory that stores data corresponding to the following references: Fig.13 The hardware processor of the computing device executes the instructions stored in the memory of the computing device.
[0156] One or more of the elements 138, 1202, and 1204 may be communicatively interconnected via one or more networks. For example, the network may include a LAN, WAN, the Internet, a cloud-based network system, or any other distributed communication system (e.g., a network system based on a client-server architecture).
[0157] In addition, components 1202 and 1204 can be connected with Figure 4 The system 400 is shown integrated (eg, with the model generator 408). In other words, the system 1200 can be integrated with the system 400.
[0158] As mentioned above, in some tools, the scheduler in the system software can use a set of scheduling rules and scoring systems to make scheduling decisions. However, as the complexity of the tool's system configuration, operating scenarios, and scheduling constraints increases, the complexity of the scheduling decision scheme also increases, which requires more development work to achieve and maintain optimal system output.
[0159] The scheduling rules and scoring system of the scheduler can be replaced with a neural network model 1204. This model 1204 can be trained using a discrete event simulator 1200 and reinforcement learning to self-explore and memorize the best scheduling decision for a given state of the tool. This enables the best production performance of the tool to be achieved and maintained.
[0160] For reference Fig.13 Explaining in further detail, the self-exploration process uses a discrete event simulator 1202 to automatically try to find the best possible way to operate the system with the best throughput performance (e.g., find the best path to move a wafer through the tool). By running a self-training process on the tool, the neural network model 1204 can be optimized for a specific tool configuration, wafer handling scheme, and constraints unique to the tool.
[0161] The discrete event simulator 1202 is a fast simulator. For example, the discrete event simulator 1202 can simulate a wafer processing sequence that takes about an hour in less than one minute. The discrete event simulator 1202 can simulate level 1 and level 2 wafer processing sequences and run WAC in the PM. The discrete event simulator 1202 includes an application programming interface (API) based on a built-in HTTP server to facilitate information exchange between the discrete event simulator 1202 and the model 1204. The discrete event simulator 1202 outputs scheduling cycle information in JSON format via the API. The model 1204 processes the JSON file to select the next operation, which is returned to the discrete event simulator 1202 via the API.
[0162] In addition, model 1204 includes a deep neural network, which is trained using a reinforcement learning method, as shown below Fig.13Explained in further detail. Reinforcement learning involves an agent, a set of states S, and a set of actions A for each state. The agent can transition between states by performing actions "a" from this set A. Performing an action in a particular state provides the agent with a reward (a numerical score). The agent's goal is to maximize the total (future) reward. The agent achieves this goal by adding the maximum reward it can get from future states to the reward for achieving its current state, which effectively influences its current action through potential future rewards. This potential reward is the weighted sum of the expected values of the rewards for all future steps starting from the current state.
[0163] For example, the reinforcement learning method used by model 1204 may include Q-learning. Q-learning is a reinforcement learning method for machine learning. The goal of Q-learning is to learn a policy that informs the agent what actions to take under what circumstances. Q-learning can handle random transitions and reward problems without adaptation. Q-learning finds the best policy for any finite Markov decision process (FMDP). Q-learning starts from the current state and maximizes the expected value of the total reward in all consecutive steps.
[0164] Fig.13 A method 1300 for training a reinforcement learning model 1204 using a discrete event simulator 1202 is shown. The method 1300 may be performed by Fig.12 For example, one or more of the elements 138 , 1202 , and 1204 of the system 1200 may perform one or more of the following steps of the method 1300 .
[0165] At 1302, the discrete event simulator 1202 is generated from a tool (e.g., Figure 1 The discrete event simulator 1202 receives data representing the current state of the tool from system software running on the system controller 138 of the tool 100. For example, the state information of the tool may include the state of the tool resources (e.g., PM, gas lock, etc.) in the processing state of the wafer.
[0166] At 1304, the discrete event simulator 1202 generates all possible next-schedule-level operation groups that can be executed by the tool to transition to the next state. At 1306, the discrete event simulator 1202 outputs the next-schedule-level operation group to the model 1204. At 1308, the model 1204 selects the best next operation to schedule, which will provide the best system performance. At 1310, the model 1204 memorizes the best next operation for the tool state to schedule. At 1312, the discrete event simulator 1202 executes the best next operation to simulate the next state.
[0167] At 1314, the discrete event simulator 1202 determines whether a final state has been reached. The discrete event simulator 1202 repeats steps 1304-1312 until the final state is reached. At 1316, after the final state is reached, the reinforcement training of the model 1204 is complete. At 1318, the model 1204 uses the memorized best next action for each state when that particular state occurs in the tool during actual wafer processing. In this way, using the model 1204, when transitioning from one state to another, the tool always chooses the best path to move the wafer through the tool to achieve the best throughput performance.
[0168] Therefore, system 1200, together with system 400, provides an intelligent machine learning assisted scheduler. The intelligent scheduler uses a self-learning process to train a neural network model to make optimal scheduling decisions for a given system state. These decisions help achieve and maintain the tool in optimal yield conditions under semiconductor manufacturer-specific operating scenarios and scheduling constraints. For example, for each recipe, the intelligent scheduler can ensure that the wafer idle time can be less than 2% of the total processing time and the manufacturing efficiency (actual cycle time / theoretical cycle time) can be greater than 97%.
[0169] In addition, in order to improve the accuracy of scheduler adjustments used in tools for multiple parallel material deposition (e.g., multi-layer electroplating) processes, the present invention proposes a nested neural network-based model trained using machine learning. Specifically, as explained in detail below, the nested neural network-based model is initially designed and trained offline using simulation data, and then trained online using actual tool data to predict wafer routing paths and scheduling. The model can achieve the highest tool / flock utilization, the shortest waiting time, and the fastest output.
[0170] Currently, due to the dynamic nature of the scheduler rules for parallel recipes, the scheduling usually has the following problems. Pacing is the ability to predict the scheduler behavior (e.g., wafer routing) and decide when to send the next group of wafers (usually a pair of wafers) to the tool for processing (e.g., plating). Sometimes, the scheduler behavior cannot be accurately predicted. As a result, wafers may be assigned to the tool too late or too early. Assigning wafers too late reduces the output of the tool, while assigning wafers too early reduces the wafer yield by increasing the wafer waiting time (causing the wafers to dry out). Therefore, the scheduler needs to accurately predict when to send the wafers to the tool to achieve maximum output and yield.
[0171] Specifically, tools typically use two robots for wafer transfer: a front-end (FE) robot transfers a pair of wafers into the tool, and a back-end (BE) robot transfers a pair of wafers from one process module in the tool to another process module in the tool. The same or different processes may be performed on the wafers in one or more process modules of the tool. The scheduling of these two robots needs to be coordinated with the availability of the process modules. Once the wafer enters the tool, there needs to be an available process module at the right time and in the right order. Otherwise, the wafer must wait until the next process module (to which the wafer is scheduled) becomes available, which may cause the wafer to dry out, thereby reducing yield.
[0172] An additional challenge of complex scheduling schemes is that the processing times for different processes may vary widely (e.g., from a few minutes for one process to nearly an hour for another process). For example, a simple recipe may include processing a wafer having a single layer. In this case, the wafer entering the tool will first be transferred to the pre-processing module, then to the plating module, and then to the post-processing module before the wafer leaves the tool. For a two-layer processing recipe, the wafer entering the tool will first be transferred to the pre-processing module, then to the first processing module, then to the second processing module, then to the post-processing module before the wafer leaves the tool, etc. It will be appreciated that recipes with more processing layers will have longer processing times.
[0173] However, for some recipes, there is some flexibility in the tool that can be used to improve robot scheduling and wafer routing. For example, for a multi-layer process recipe, if the process materials for N layers are the same, and if there are N process modules that can deposit the same process layers, then the wafer can be transferred between any of the N process modules. This routing flexibility provides the opportunity for more than one routing path to transfer the wafer between the N process modules. However, knowing which of the N process modules will be available at what time is necessary to coordinate and schedule wafer routing. In addition, knowing the availability of the transfer robot is also necessary to coordinate and schedule wafer routing.
[0174] Therefore, parallel recipes have a variety of FE / BE robot transfer times (between tools and between modules within a tool). For most cases, the current tuning method is usually to use static FE / BE robot reservation times without routing path prediction. In addition, the current scheduling method faces the following dilemma between wafer waiting time and throughput: reducing FE / BE robot reservation time can increase throughput but may cause wafers to wait longer in the processing module, while increasing FE / BE robot reservation time can minimize wafer waiting time but may cause reduced wafer per hour (WPH) throughput (for example, in redistribution layer or RDL recipes). In addition, currently, the program run time estimation is not always accurate for different parameter sets and options enabled on these tools.
[0175] To address these issues, the present invention proposes a dynamic adjustment method (scheduler layer neural network) to predict wafer routing paths and output based on the following inputs: 1) tool configuration; 2) recipe structure (e.g., parallel processing modules, single / multi-layer, etc.); 3) accurate program run time estimates (provided by module layer neural network based on inputs of parameter group values and start / stop options); 4) the status of each processing module on the routing path (e.g., online / offline, number of wafers going to the processing module, remaining processing time, time remaining before servicing the program, etc.); 5) a third layer neural network that can be added for a group of tools to optimize batch allocation between tools.
[0176] The proposed dynamic scheduler adjustment method uses a nested neural network based model, which is trained using machine learning to solve the dynamic wafer scheduling problem during wafer processing and wafer / batch allocation and routing (at the module, tool and cluster level). Initially, simulation is used to generate data to train and test the neural network. Therefore, the simulation needs to be accurate, which requires accurate program run time estimation. A neural network layer is used to accurately predict the program run time. In this layer, one neural network is used for each processing module to predict the program run time. In addition, one neural network is used for each robot to predict the transfer time of each robot.
[0177] The method employs both offline learning using simulation and online learning using real-time tool data. Offline learning is based on data collected on the simulator or tool to minimize computational complexity during generation. The weights determined for the neural network during offline training are applied to the scheduler adjustment algorithm before wafer / lot allocation. Online learning is then used to dynamically adjust the neural network based on real-time data.
[0178] Therefore, in the proposed method, a model for scheduler adjustment is built using a nested neural network or other machine learning algorithm. The model is initially built, trained and tested offline using simulation. Subsequently, the model is further refined and trained continuously in situ on the actual tool by progressively using the data stream from the tool to further adjust the model, which reflects the tool-specific and recipe-specific robot transfer times and compensates for any process drift. The in situ training also adjusts the model for any recipe changes and / or tool hardware changes.
[0179] A dynamic scheduler adjustment method using nested neural networks improves tool / flock throughput and utilization for parallel recipes (with multi-layer material deposition and wait time constraints) and prevents wafer drying issues. The method can recommend recipe / wafer allocation combinations with maximum tool utilization. The method can also predict routing paths involving front-end robots and back-end robots and wafer aligners, inbound paths to processing modules, paths between processing modules, and paths from processing to outbound modules. In addition, the method can recommend the best tool hardware configuration for a given application.
[0180] The dynamic scheduler is designed, developed and implemented in stages. The first stage includes the following offline training of a single neural network. The simulator is used to simulate multiple scheduling schemes and wafer routing paths that may be feasible in actual tools using actual transfer times in actual tools. The simulator performs these simulations based on the hardware configuration of different tools and based on various processes in tools that can be used to process wafers. In cyclic mode, wafer cycles are simulated based on test schemes in the simulator to collect a large number of data sets. The neural network is trained offline using machine learning. The calculated weights (generated by the simulator to optimize wafer scheduling and routing) and the neural network inputs are then supplied to the scheduler scheduling algorithm, and yield improvements are observed at the same waiting time.
[0181] In the second phase, a nested neural network is trained offline for a tool in a fleet of tools as follows. In the initial layer of the model, a module-level neural network (i.e., a neural network for a processing module) is trained to predict program run times for different processes. In the same layer, a neural network for each robot in the tool is trained to predict transfer times for different processes. In subsequent layers of the model, the outputs of the neural network from the initial layer (i.e., predictions of program run times and transfer times) are input to the next layer, which includes a scheduler-level neural network.
[0182] The inputs to the scheduler-level neural network are expanded to other tool configurations, combinations of recipe types, processing times, multiple layers to be processed on a wafer, scheduler modes, etc. Coupled (i.e., nested) with the module-level neural network, the scheduler-level neural network with the expanded inputs provides recommendations for the best product / recipe / wafer combination to achieve the highest tool / fleet utilization, thereby reducing the cost of ownership of the tool. That is, a dynamic scheduler based on a nested neural network (which is trained using different tool hardware configurations and different recipe types) can now recommend the best tool hardware configuration for one or more given recipes. Such recommendations can be provided using only simulator-based training.
[0183] The third phase involves online real-time and unsupervised learning. Online continuous neural network training using machine learning is based on actual production data from a tool or a group of tools. Online training is used to dynamically adjust the weights of the neural network inputs that are trained offline using a simulator as described above. Since the process recipe and / or hardware may change, continuous (i.e., uninterrupted) training is required. When such changes occur, the model needs to adapt to these changes, which can be achieved through continuous training. Therefore, the dynamic scheduler progresses from supervised to unsupervised machine learning and develops the ability to learn from mistakes and make better trained predictions next time.
[0184] Due to the continuous nature of training, the data generated by the tool is automatically labeled to enable incremental training. That is, after a group of wafers are processed in the current process, the data from the current process is automatically labeled so that these data can supplement or replace corresponding data in the previous process for incremental learning. These and other aspects of the dynamic scheduler are described in further detail below.
[0185] As reference Figure 14-15B As used herein, wait time is the amount of time a wafer must wait after wafer processing is completed in a process module until wafer processing can begin in the next process module. Wait time occurs when the next process module is not yet ready to process a wafer (e.g., because the next process module has not yet completed and is still processing other wafers). Program run time or process time is the amount of time it takes for a process module to complete wafer processing. Robot transfer time is the amount of time it takes for a robot to move a wafer from point A to point B (e.g., from one process module to another, or from an airlock to a process module, and from a tool's loading station to an airlock).
[0186] Fig.14 The use of an offline simulator 1404 and from a tool 1406 (e.g., Fig.16The system 1400 of FIG. 1406 is used to train a model 1402 having nested neural networks using online real-time data from a tool 1600 (shown in FIG. 1406 ) to schedule and adjust wafer processing in a tool 1406 . The model 1402 includes a plurality of module-level neural networks and a scheduler-level neural network. The plurality of module-level neural networks include a plurality of processing modules (e.g., Fig.16 A neural network for each manipulator in tool 1406 (e.g., for Fig.16 The neural networks are shown as 1410-1, ... and 1410-N, where N is an integer greater than 1, and are collectively referred to as neural network 1410. Neural network 1410 outputs a processing module (e.g., Fig.16 The processing module 1602 shown in FIG. 1602 ) predicts the program running time and the robot (eg, Fig.16 Prediction of transfer time for robots 1610 and 1614) shown.
[0187] The scheduler-level neural network is shown as 1412 and receives as input the output of neural network 1410. Scheduler-level neural network 1412 schedules the routing of wafers between processing modules within the tool and outputs a prediction as to when the next pair of wafers will be transferred to the tool for processing. Neural network 1410 and scheduler-level neural network 1412 output their respective predictions (e.g., when the task is performed by the operator) during their initial training on simulator 1404 and subsequent actual use and continued training on tool 1406. Fig.16 When implemented or integrated with the system controller 1616 shown).
[0188] By way of example only, simulator 1404 may be implemented using a computing device, such as a computer including one or more hardware processors (e.g., a CPU) and one or more memory devices storing one or more computer programs that simulate the operation and processing environment of a tool (e.g., tool 1406) on the computer. The computer programs further include instructions for generating, training, and validating neural network 1410 of model 1402 and scheduler-level neural network 1412 on simulator 1404, as described below with reference to Fig.15A and 15B The one or more hardware processors execute the one or more computer programs.
[0189] The simulator 1404 and the tool 1406 may be communicatively interconnected via one or more networks. For example, the network may include a LAN, a WAN, the Internet, a cloud-based network system, or any other distributed communication system (e.g., a network system based on a client-server architecture).
[0190] For example, simulator 1404 may utilize Fig.18 The wafer fab data collection system 1800 shown collects / receives data from the tool 1406. Fig.14 Only one tool is shown, but data may be collected / received from more than one tool. The one or more tools may be located at the same customer location. The one or more tools may be located at different locations of the same customer. The one or more tools may be located at different customer locations. The data collected from the tools does not include the customer's private and confidential data, but includes all other operational data that can be used to generate and train the model.
[0191] As an example only, tool 1406 (data is collected from tool 1406) can perform multiple parallel material deposition (e.g., plating) processes, and can have the following configuration. The tool may include up to two platforms and two manipulators, each platform including multiple processing modules. For example, multiple processing modules may include a pre-processing module, a post-processing module, and four processing modules for performing plating processes. The tool may further include a scheduler to control the wafer processing in the tool. These processes may include single-layer plating or multi-layer plating.
[0192] The simulator 1404 simulates the tool configuration and simulates the processing of the wafer in the tool. The simulator 1404 includes one or more systems that utilize machine learning to generate, train, and validate the neural networks 1410 and 1412 of the model 1402 using data generated by the simulator 1404 by simulating the processing of the wafer. Using the trained model 1402, the scheduler of the tool can schedule the processing of the wafer and provide the best yield and wait time. The trained model 1402 can also recommend the best hardware configuration of the tool to be used for a given application.
[0193] Fig.15A and 15B A method 1500 is shown for training a model with a nested neural network using an offline simulator and online real-time tool data to schedule and adjust wafer processing in a tool. For example, Fig.14 The system controller (e.g., Fig.16 One or more of the elements 1616 shown may perform one or more of the following steps of method 1500.
[0194] At 1502, the method 1500 obtains data regarding the hardware configuration of the tool and the recipes for the processes (e.g., multi-layer plating) to be performed on the wafers in the tool. At 1504, using a simulator, the method 1500 simulates various routing and scheduling scenarios for processing the wafers based on the obtained data. At 1506, using the simulator, the method 1500 simulates wafer processing using the various routing and scheduling scenarios.
[0195] At 1508, the method 1500 collects data from simulated wafer processing performed using the simulator. At 1510, using the collected data, the method 1500 designs and trains a plurality of neural networks. The plurality of networks includes one neural network for each processing module in the tool, one neural network for each robot in the tool, and one neural network for a scheduler used by the tool to route wafers through the tool and schedule when the next set of wafers will be processed in the tool. For example, the method for generating and training a neural network may be similar to that described in reference to Figure 6-11 The method described.
[0196] At 1512, the method 1500 uses the respective neural networks to predict the program run time for each process module and predict the transfer time for the robot. At 1514, the method 1500 uses data obtained from the tool to validate the neural networks for the process modules and the robot.
[0197] At 1516, the method 1500 determines whether the neural network for the processing module and the manipulator was successfully verified. For example, the method for verifying the neural network can be similar to reference Figure 6-11 For example, the validation criteria may be based on how accurately the convergence properties of the neural network can predict program run time and robot transfer time. If the neural network for the processing module and robot is not successfully validated, the method 1500 returns to 1508 for further training.
[0198] At 1518, if the neural network for the processing module and robot is successfully validated, then using the simulator, the method 1500 inputs the predicted times and weights generated by the neural network for optimizing yield and latency into the scheduler-level neural network. At 1520, using the scheduler-level neural network, the method 1500 predicts wafer routing and scheduling data, including when to schedule the processing of the next group of wafers in the tool.
[0199] At 1524, the method for verifying the scheduler-level neural network can be similar to reference Figure 6-11For example, the criteria for validation may be based on how accurately the scheduler-level neural network can predict wafer routing and scheduling. If the scheduler-level neural network is not successfully validated, the method 1500 returns to 1518 to further train the scheduler-level neural network using a simulator.
[0200] At 1526, if the scheduler-level neural network is successfully validated, the model including all neural networks for the processing modules, manipulators, and scheduler is integrated into the tool's controller (e.g., Fig.16 1616). The model can now predict program run times, robot transfer times, and wafer routing and scheduling on the tool.
[0201] The model continues to be incrementally trained online (i.e., trained in situ on the tool) using actual production data from the tool at 1528. The automatically labeled data (from processing of the current wafer set) is used in addition to or in place of corresponding data from processing of the previous wafer set to incrementally and continuously train the model on the tool.
[0202] Fig.16 An example of a tool 1600 including a plurality of process modules 1602 is shown. For example, the tool 1600 may include a lower platform and an upper platform. Each platform may include four process modules 1602, such that the tool 1600 may include a total of eight process modules 1602. Alternatively, each platform may include the eight process modules 1602 shown (only one platform is shown), such that the tool 1600 may include a total of sixteen process modules 1602. For example, a process module 1602 may include an electroplating tank (e.g., see Fig.17 ). In addition, each platform may also include multiple pre-processing and post-processing modules 1604. In addition to electroplating, tool 1600 may perform spin cleaning, spin drying, wet etching, pre-wet and pre-chemical treatment, electroless deposition, reduction, annealing, photoresist stripping, surface pre-activation, etc.
[0203] A plurality of substrates 1606 are fed into the tool 1600 via a front opening pod (FOUP) 1608. A front end robot 1610 transfers the substrates 1606 from the FOUP 1608 to a spindle 1612 and then to one of the pre-processing modules 1604. After pre-processing, a back end robot 1614 transfers the substrates 1606 from the pre-processing module 1604 to one or more processing modules 1602 for electroplating. Thereafter, the back end robot 1614 transfers the substrates 1606 to one of the post-processing modules 1604.
[0204] The tool 1600 further includes a system controller 1616 that controls the front-end and back-end robots 1610, 1614 and the processes performed in the process modules 1602, 1604. The controller 1616 schedules and controls the processing of the substrate 1606 using the trained model 1402 and the dynamic scheduler adjustment method as described above.
[0205] Fig.17 An example of a process module 1602 is shown. For example, the process module 1602 includes an electroplating cell 1700. The electroplating cell 1700 includes an anode 1702 in a separated anode chamber (SAC) 1704. The SAC 1704 is separated from the rest of the electroplating cell 1700 by a membrane. The SAC 1704 includes a first liquid that is chemically different from a second liquid in the rest of the electroplating cell 1700.
[0206] The plating tank 1700 also includes a high resistance virtual anode (HRVA) 1706 (mounting assembly not shown). During electroplating, the HRVA 1706 directs the flow of the second liquid toward a portion of the wafer (not shown) as the wafer is lowered from the top of the plating tank 1700 into the plating tank 1700. The main tank (reservoir) 1708 supplies the second liquid to the plating tank 1700 via a pump 1710 and a filter 1712. The tower 1714 fills the SAC 1704 with the first liquid using a pump 1716. The processing module 1602 may include any other type of plating tank.
[0207] Fig.18 An example of a wafer fab data collection system 1800 is shown. For example, the system 1800 includes a host computer 1802, a data collector 1804, and a monitoring computer 1806, which are connected to a fab local area network (LAN) 1808 in a semiconductor manufacturing plant using one or more tools (e.g., tool 1600). The host computer 1802 communicates with one or more tools (e.g., tool 1600). The host computer 1802 is used by an operator to send commands to the tool 1600, provide recipes, etc.
[0208] The data collector 1804 receives various types of data from the tool 1600 without interfering with the communication between the host computer 1802 and the tool 1600. The monitoring computer 1806 is used to view and monitor the tool performance. The monitoring computer 1806 graphically shows the tool settings and reads the values of various tool parameters. The monitoring computer 1806 is used to troubleshoot problems with the tool 1600. The host computer 1802 communicates with the data collector 1804 and the monitoring computer 1806.
[0209] The system 1800 further includes a server 1810 connected to the tool 1600 via a facility LAN 1812. The server 1810 communicates with the host computer 1802 via the plant LAN 1808. The server 1810 collects data from the tool 1600 and supplies the data to the host computer 1802. One or more user interface (UI) computers 1814 are located on the side of the tool 1600 opposite the loader side of the tool 1600. The loader side is 100-level clean, while the UI computer side where the operator operates the tool 1600 is 1000-level clean. The UI computer 1814 is connected to the facility LAN 1812. A monitoring computer 1816 is connected to the tool 1600 via the facility LAN 1812. The monitoring computer 1816 monitors the tool 1600 and communicates with the monitoring computer 1806 via the plant LAN 1808.
[0210] A system controller 1818 (e.g., system controller 1616) of the tool 1600 controls the tool 1600. A plurality of module controllers 1820 control the various processing modules 1602, 1604. A plurality of input / output (I / O) controllers 1822 control the various operations of the processing modules 1602, 1604. The system controller 1818 also communicates with one or more of the I / O controllers 1822 (e.g., to control the manipulators 1610, 1614; and to control features other than the processing modules 1602, 1604 of the tool). Various switches 1824 are used to access the appropriate I / O controller 1818.
[0211] References Figure 14-17 The functions and operations described may be performed by the system controller 1818, the monitoring computer 1816, or both. Additionally or alternatively, reference may be made to Fig.18 The other computing devices described above may also execute the above reference Figure 14-17 At least some of the functions and operations described.
[0212] The foregoing description is merely illustrative in nature and is in no way intended to limit the present disclosure, its application or use. The broad teachings of the present disclosure can be implemented in various forms. Therefore, although the present disclosure includes specific examples, the true scope of the present disclosure should not be so limited, because other modifications will become apparent upon studying the drawings, description and appended claims.
[0213] It should be understood that one or more steps in the method may be performed in different orders (or simultaneously) without changing the principles of the present disclosure. In addition, although each embodiment is described above as having certain features, any one or more of those features described with respect to any embodiment of the present disclosure may be implemented in the features of any other embodiment and / or combined with the features of any other embodiment, even if the combination is not explicitly described. In other words, the described embodiments are not mutually exclusive, and the permutation of one or more embodiments with respect to each other remains within the scope of the present disclosure.
[0214] Various terms are used to describe the spatial and functional relationships between elements (e.g., between modules, between circuit elements, between semiconductor layers, etc.), including "connected," "engaged," "coupled," "adjacent," "next to," "on top of," "above," "below," and "disposed." Unless the relationship between a first and a second element is explicitly described as "direct," when such a relationship is described in the above disclosure, the relationship can be a direct relationship, in which there are no other intervening elements between the first and second elements, but can also be an indirect relationship, in which there are one or more intervening elements (spatially or functionally) between the first and second elements. As used herein, the phrase "at least one of A, B, and C" should be interpreted to mean a logical (A or B or C), using a non-exclusive logical OR, and should not be interpreted to mean "at least one of A, at least one of B, and at least one of C."
[0215] In some implementations, the controller is part of a system, which can be part of the above examples. Such a system can include a semiconductor processing device, which includes one or more processing tools, one or more chambers, one or more platforms for processing, and / or specific processing components (wafer pedestals, gas flow systems, etc.). These systems can be integrated with electronic devices for controlling their operation before, during, and after processing of semiconductor wafers or substrates. The electronic device can be referred to as a "controller", which can control various components or subcomponents of one or more systems.
[0216] For example, depending on the process requirements and / or system type, the controller can be programmed to control any of the processes disclosed herein, including the delivery of process gases, temperature settings (e.g., heating and / or cooling), pressure settings, vacuum settings, power settings, radio frequency (RF) generator settings, RF matching circuit settings, frequency settings, flow rate settings, fluid delivery settings, position and operation settings, wafer transfer into and out of tools and other transfer tools and / or load locks connected to or interfaced with a particular system.
[0217] In general, a controller may be defined as an electronic device having various integrated circuits, logic, memory, and / or software that receive instructions, issue instructions, control operations, enable cleaning operations, enable endpoint measurements, etc. The integrated circuits may include chips in the form of firmware that store program instructions, digital signal processors (DSPs), chips defined as application specific integrated circuits (ASICs), and / or one or more microprocessors or microcontrollers that execute program instructions (e.g., software).
[0218] Program instructions may be instructions sent to a controller in the form of various individual settings (or program files) that define operating parameters for performing a particular process on or for a semiconductor wafer or system. In some embodiments, the operating parameters may be part of a recipe defined by a process engineer to accomplish one or more processing steps during the fabrication of one or more layers, materials, metals, oxides, silicon, silicon dioxide, surfaces, circuits, and / or dies of a wafer.
[0219] In some implementations, the controller can be part of or coupled to a computer that is integrated with the system, coupled to the system, otherwise networked to the system, or a combination thereof. For example, the controller can be in the "cloud" or all or part of a wafer fab host system that can allow remote access to wafer processing. The computer can enable remote access to the system to monitor the current progress of a manufacturing operation, check the history of past manufacturing operations, check trends or performance standards for multiple manufacturing operations, change parameters of a current process, set processing steps to follow a current process, or start a new process.
[0220] In some examples, a remote computer (e.g., a server) can provide a process recipe to the system over a network (which can include a local network or the Internet). The remote computer can include a user interface that enables input or programming of parameters and / or settings, which are then sent from the remote computer to the system. In some examples, the controller receives instructions in the form of data that specify parameters for each process step to be performed during one or more operations. It should be understood that the parameters can be specific to the type of process to be performed and the type of tool that the controller is configured to interface with or control.
[0221] Thus, as described above, the controller may be distributed, for example, by including one or more discrete controllers networked together and working toward a common purpose (e.g., processing and control as described herein). An example of a distributed controller for such a purpose is one or more integrated circuits on a chamber that communicate with one or more integrated circuits remotely (e.g., at a platform level or as part of a remote computer), which combine to control processing on the chamber.
[0222] Example systems may include, but are not limited to, plasma etch chambers or modules, deposition chambers or modules, spin rinse chambers or modules, metal plating chambers or modules, cleaning chambers or modules, chamfer edge etch chambers or modules, physical vapor deposition (PVD) chambers or modules, chemical vapor deposition (CVD) chambers or modules, atomic layer deposition (ALD) chambers or modules, atomic layer etch (ALE) chambers or modules, ion implantation chambers or modules, track chambers or modules, and any other semiconductor processing system that may be associated with or used in the manufacture and / or preparation of semiconductor wafers.
[0223] As described above, depending on one or more processing steps to be performed by the tool, the controller can communicate with one or more other tool circuits or modules, other tool components, cluster tools, other tool interfaces, adjacent tools, neighboring tools, tools located throughout the factory, a host computer, another controller, or tools used in material transport to transport wafer containers to and from tool locations and / or load ports in a semiconductor manufacturing facility.
Claims
1. A system for processing a semiconductor substrate in a tool, the tool comprising a plurality of processing chambers configured to process the semiconductor substrate according to a recipe, the system include: processor; as well as a memory storing instructions for execution by the processor, wherein the instructions are configured to: receiving first data from the tool regarding processing the semiconductor substrates in the plurality of processing chambers according to the recipe; receiving second data regarding a configuration of the tool and the recipe; using the second data to simulate a plurality of processing plans for processing the semiconductor substrates in the plurality of processing chambers according to the recipe and scheduling parameters for the plurality of processing plans; simulating processing the semiconductor substrates in the plurality of processing chambers according to the recipe using the plurality of processing plans and the scheduling parameters for the plurality of processing plans; training a model using the first data and data generated by the simulation to predict optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe; receiving input from the tool regarding processing one of the semiconductor substrates in the plurality of processing chambers according to the recipe; using the model, predicting, based on the input, optimal scheduling parameters for processing the one of the semiconductor substrates in the plurality of processing chambers according to the recipe; as well as Operations of the tool are scheduled based on the optimal scheduling parameters for processing the one of the semiconductor substrates in the plurality of processing chambers according to the recipe.
2. The system of claim 1, wherein the instructions are configured to perform the operation of the tool based on the optimal scheduling parameters for processing the one of the semiconductor substrates in the plurality of processing chambers according to the recipe.
3. The system of claim 1 , wherein the optimal scheduling parameters minimize idle time of the one of the semiconductor substrates during processing according to the recipe in the plurality of processing chambers, and wherein the optimal scheduling parameters maximize throughput of the tool.
4. The system of claim 1, wherein the instructions are configured to train the model using machine learning methods including artificial neural networks and support vector regression.
5. The system of claim 1, wherein the instructions are configured to: analyzing the first data received from the tool and the data generated by the simulation; Based on the analysis, detecting patterns regarding preventive maintenance operations, waferless autoclean time, wait time, recipe time, and throughput of the tool; and Based on the detected patterns, the model is trained.
6. The system of claim 1, wherein the instructions are configured to train the model to predict the optimal scheduling parameters for one of the plurality of processing scenarios.
7. The system of claim 1, wherein the instructions are configured to train the model to predict the optimal scheduling parameters for all of the plurality of processing scenarios.
8. The system of claim 1, wherein the instructions are configured to train the model for performing only etching operations on the one of the semiconductor substrates.
9. The system of claim 1, wherein the instructions are configured to train the model for performing both etching and stripping operations on the one of the semiconductor substrates.
10. The system of claim 1, wherein the model is implemented remotely from the tool, and wherein the instructions are configured to train the model based on data received from a plurality of tools.
11. The system of claim 1 , wherein the instructions are configured to adjust the model for tool-to-tool variations in configuration and operation.
12. The system of claim 1, wherein the model is implemented in the cloud as software as a service (SaaS), and wherein the tool is configured to access the model over a network.
13. The system according to claim 1, in: The instructions are configured to train a second model based on data from a second tool; said model and said second model are implemented remotely from said tool and said second tool; as well as Wherein the tool and the second tool are respectively configured to access the model and the second model via one or more networks.
14. The system of claim 13, wherein the instructions are configured to cause the tool and the second tool to select the model and the second model based on configurations of the tool and the second tool, respectively.
15. The system of claim 1, wherein the model is implemented on the tool, and wherein the instructions are configured to use the model to utilize data generated by the tool to predict the optimal scheduling parameters for processing the one of the semiconductor substrates in the plurality of processing chambers according to the recipe.
16. The system of claim 1, wherein the model is implemented on the tool, and wherein the instructions are configured to adjust the model for any drift in performance of the tool.
17. The system of claim 1, wherein the first data received from the tool includes data from preventive maintenance operations performed on the tool and data regarding recipe time and waferless autoclean time for the tool.
18. The system of claim 1, wherein the data generated by the simulation includes data generated based on a configuration of the tool, a wafer flow type, an operation plan, a recipe time, and a waferless auto-clean time obtained from the tool.
19. The system of claim 1, wherein the input received from the tool includes data regarding a number of preventive maintenance operations, recipe times, and waferless autoclean times for the tool.
20. The system of claim 1, wherein the instructions are configured to predict the optimal scheduling parameters by taking into account one or more skipped preventive maintenance operations.
21. The system of claim 1, wherein the instructions are configured to: using the model, scheduling a plurality of operations for processing the one of the semiconductor substrates in the plurality of processing chambers according to the recipe, wherein the tool undergoes a plurality of states in response to performing the plurality of operations, respectively, and wherein the state of the tool includes an indication of resources of the tool and an indication of a processing state of the one of the semiconductor substrates; for each of the plurality of states, sending to the model a current state of the plurality of states and a plurality of schedulable operations for progressing to a next state of the plurality of states, receiving from the model an optimal operation of the plurality of schedulable operations selected by the model based on the current state to progress to the next state, and simulating execution of the optimal operation to simulate progressing to the next state; as well as The model is trained to recommend the optimal operation as the plurality of operations in response to the tool experiencing the plurality of states when processing the semiconductor substrates in the plurality of process chambers according to the recipe.
22. A system for processing a semiconductor substrate in a tool, the tool comprising a plurality of processing chambers configured to process the semiconductor substrate according to a recipe, the system include: processor; as well as a memory storing instructions for execution by the processor, wherein the instructions are configured to: using a model, scheduling a plurality of operations for processing semiconductor substrates in the plurality of processing chambers according to the recipe, wherein the tool undergoes a plurality of states in response to performing the plurality of operations, respectively, and wherein the state of the tool includes an indication of resources of the tool and an indication of a processing state of the semiconductor substrate; for each of the plurality of states, sending to the model a current state of the plurality of states and a plurality of schedulable operations for progressing to a next state of the plurality of states, receiving from the model an optimal operation of the plurality of schedulable operations selected by the model based on the current state to progress to the next state, and simulating execution of the optimal operation to simulate progressing to the next state; as well as The model is trained to recommend the optimal operation as the plurality of operations in response to the tool experiencing the plurality of states when processing the semiconductor substrates in the plurality of process chambers according to the recipe.
23. The system of claim 22, wherein the instructions are configured to: training the model using historical data regarding processing of the semiconductor substrates received from the tool and by simulating a plurality of processing scenarios for the tool to predict optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe; receiving input from the tool regarding processing the semiconductor substrates in the plurality of processing chambers according to the recipe; using the model, predicting, based on the inputs, optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe; as well as The plurality of operations are scheduled based on the optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe.
24. The system of claim 23, wherein the instructions are configured to perform the plurality of operations based on the optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe.
25. The system of claim 23, wherein the optimal scheduling parameters minimize idle time of the semiconductor substrates during processing according to the recipe in the plurality of processing chambers, and wherein the optimal scheduling parameters maximize throughput of the tool.
26. The system of claim 23, wherein the instructions are configured to train the model using machine learning methods including artificial neural networks and support vector regression.
27. The system of claim 23, wherein the instructions are configured to: analyzing the historical data received from the tool and data generated by simulating the plurality of processing scenarios for the tool; detecting patterns regarding preventive maintenance operations, waferless autoclean time, wait time, recipe time, and throughput of the tool based on the analysis; as well as Based on the detected patterns, the model is trained.
28. The system of claim 23, wherein the instructions are configured to train the model to predict the optimal scheduling parameters for one of the plurality of processing scenarios.
29. The system of claim 23, wherein the instructions are configured to train the model to predict the optimal scheduling parameters for all of the plurality of processing scenarios.
30. The system of claim 23, wherein the instructions are configured to train the model to perform only etching operations on the semiconductor substrate.
31. The system of claim 23, wherein the instructions are configured to train the model for performing both etching and stripping operations on the one of the semiconductor substrates.
32. The system of claim 23, wherein the model is implemented remotely from the tool, and wherein the instructions are configured to train the model based on data received from a plurality of tools.
33. The system of claim 32, wherein the instructions are configured to adjust the model for tool-to-tool variations in configuration and operation.
34. The system of claim 23, wherein the model is implemented in the cloud as software as a service (SaaS), and wherein the tool is configured to access the model over a network.
35. The system of claim 23, wherein the model is implemented on the tool, and wherein the instructions are configured to use the model to utilize data generated by the tool to predict the optimal scheduling parameters for processing the semiconductor substrates in the plurality of processing chambers according to the recipe.
36. The system of claim 23, wherein the model is implemented on the tool, and wherein the instructions are configured to adjust the model for any drift in performance of the tool.
37. The system of claim 23, wherein the data received from the tool includes data from preventive maintenance operations performed on the tool and data regarding recipe times and waferless autoclean times for the tool.
38. The system of claim 23, wherein the plurality of process scenarios are simulated by including data generated based on configuration of the tool, wafer flow type, run scenario, recipe time, and waferless auto-clean time obtained from the tool.
39. The system of claim 23, wherein the input received from the tool includes data regarding a number of preventive maintenance operations, recipe times, and waferless autoclean times for the tool.
40. The system of claim 23, wherein the instructions are configured to predict the optimal scheduling parameters by taking into account one or more skipped preventive maintenance operations.
41. A tool for processing a semiconductor substrate, include: a first robot configured to input the semiconductor substrate into the tool to process the semiconductor substrate in the tool; a plurality of processing chambers configured to process the semiconductor substrate in accordance with a recipe in the tool; a second robot configured to transfer the semiconductor substrate between the plurality of processing chambers according to the recipe; as well as A controller configured to use a model trained by simulating the tool and the recipe to predict: a processing time for processing the semiconductor substrate in the plurality of processing chambers; a transfer time of the second robot to transfer the semiconductor substrate between the plurality of processing chambers; routing the semiconductor substrate between the plurality of process chambers based on the processing time and the transfer time; as well as a time at which the first robot is to schedule additional semiconductor substrates for processing in the tool based on the processing time and the transfer time, The semiconductor substrate is processed according to the predicted route and the additional semiconductor substrate is processed according to the predicted time, so that the waiting time of the semiconductor substrate along the predicted route is optimized and the yield of the tool is optimized.
42. The tool of claim 41, wherein the controller is configured to further train the model incrementally based on data generated during processing of the semiconductor substrate and the additional semiconductor substrate in the tool.
43. The tool of claim 42, wherein the controller is configured to use the further trained model to predict: a second processing time, a second transfer time, and a second route for processing the additional semiconductor substrate in the tool; and scheduling a next set of semiconductor substrates for processing in the tool for a second time, in, Processing the additional semiconductor substrates according to the second route and processing the next set of semiconductor substrates according to the second time further optimizes the waiting time for the additional semiconductor substrates and the throughput of the tool.
44. The tool of claim 41, wherein the controller is configured to adjust the model in response to any changes to the recipe, the tool, or both.
45. The tool of claim 41, wherein the model include: a first plurality of neural networks configured to respectively predict the processing times for the plurality of processing chambers; a second plurality of neural networks configured to predict the transfer times of the first and second manipulators, respectively; as well as A third neural network is coupled to the first and second plurality of neural networks and is configured to predict the routes for transferring the semiconductor substrates between the plurality of processing chambers and predict the times when the first robot will schedule the additional semiconductor substrates for processing in the tool.
46. The tool of claim 41, wherein the model is further trained by simulating a plurality of tool configurations and a plurality of recipes.
47. The tool of claim 46, wherein the further trained model is configured to output recommendations for tool configuration in response to receiving recipe information as input.
48. The tool of claim 41, wherein the recipe is for depositing a plurality of layers on the semiconductor substrate, and in: The plurality of processing chambers include one or more processing chambers for depositing the plurality of layers, and a pre-processing chamber and a post-processing chamber for processing the semiconductor substrate before and after depositing the plurality of layers, respectively; The second robot is configured to transfer the semiconductor substrate between the plurality of process chambers according to the predicted route so as to optimize the waiting time of the semiconductor substrate; as well as The first robot is configured to schedule the additional semiconductor substrates for processing in the tool based on the predicted time to optimize the throughput of the tool.
49. A system for optimizing throughput and latency during processing of a semiconductor substrate in a semiconductor processing tool, the system include: processor; as well as a memory storing instructions for execution by the processor, wherein the instructions are configured to: simulating a plurality of routes to route the semiconductor substrate between a plurality of processing chambers of the semiconductor processing tool based on a configuration of the semiconductor processing tool and a recipe to be executed on the semiconductor substrate in the semiconductor processing tool; simulating processing of the semiconductor substrate in the semiconductor processing tool according to the recipe along the plurality of routes; simulating a plurality of timing schedules based on the processing of the semiconductor substrate to subsequently process additional semiconductor substrates in the semiconductor processing tool; simulating processing of the additional semiconductor substrate according to the plurality of timing schedules; training a model based on the data generated by the simulation; using the model on the semiconductor processing tool to predict an optimal route for transferring the semiconductor substrate between the plurality of processing chambers when processing the semiconductor substrate in the semiconductor processing tool according to the recipe; using the model on the semiconductor processing tool to predict an optimal time to schedule the additional semiconductor substrate for processing in the semiconductor processing tool; In the semiconductor processing tool, processing the semiconductor substrate according to the optimal route so that a waiting time of the semiconductor substrate along the optimal route is optimized; as well as The additional semiconductor substrate is processed in the semiconductor processing tool at the optimal time to optimize a throughput of the semiconductor processing tool.
50. The system of claim 49, wherein the instructions are configured to train the model based on the data generated by the simulation to predict: a processing time for processing the semiconductor substrate in the plurality of processing chambers; a transfer time of a robot of the semiconductor processing tool for transferring the semiconductor substrate between the plurality of processing chambers; for arranging the optimal route of the semiconductor substrate between the plurality of processing chambers based on the processing time and the transfer time; as well as The additional semiconductor substrate is scheduled for the optimal time to be processed in the semiconductor processing tool based on the processing time and the transfer time.
51. The system of claim 49, wherein the instructions are configured to further incrementally train the model based on data generated by the semiconductor substrate and the additional semiconductor substrate during the processing in the semiconductor processing tool.
52. The system of claim 49, wherein the instructions are configured to adjust the model for any changes to the recipe, the semiconductor processing tool, or both.
53. The system of claim 49, wherein the instructions are configured to generate the model based on the data generated by the simulation, the model include: a first plurality of neural networks configured to respectively predict processing times for processing the semiconductor substrate in the plurality of processing chambers; a second plurality of neural networks configured to predict transfer times of the first and second robots, respectively, wherein the first and second robots are configured to transfer the semiconductor substrate into the semiconductor processing tool and between the plurality of processing chambers, respectively; as well as A third neural network is coupled to the first and second plurality of neural networks and is configured to predict the optimal route for routing the semiconductor substrates between the plurality of processing chambers and predict the optimal time to schedule the additional semiconductor substrates for processing in the semiconductor processing tool.
54. The system of claim 49, wherein the instructions are configured to train the model by simulating configurations of multiple semiconductor processing tools and multiple recipes.
55. The system of claim 54, wherein the instructions are configured to train the model in response to receiving recipe information as input to output recommendations for tool configuration.