Grouting device and construction method for equipment installation
By using grouting devices and adjusting components during the installation of mechanical equipment, the problem of excessive size of the reserved bolt holes is solved, and the equipment is accurately adjusted without lifting after grouting for one time, reducing construction costs and improving efficiency.
Patent Information
- Application Number
- CN202111414670.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-11-25
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2041-11-25
AI Technical Summary
During the installation of mechanical equipment, the size of the reserved bolt hole is too large, resulting in the equipment slurry pad being unable to be installed, and the equipment is lifted multiple times, which increases labor costs, machinery costs and construction period.
A grouting device including a grouting unit body and an adjustment component is designed. By adjusting the adjustment component, the distance between the equipment foundation and the base is adjusted, so that the equipment is not required to be lifted out for precise adjustment after one grouting.
It effectively reduces construction costs, improves construction efficiency, and reduces multiple lifting operations to achieve the purpose of reducing costs and increasing efficiency.
Smart Images

Figure CN113914353B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of mechanical equipment installation, and relates to situations where the size of bolt holes reserved around mechanical equipment is too large to adopt grouting construction, and in particular, to a grouting device and construction method for equipment installation. Background Art
[0002] In the mechanical equipment installation industry, it is often necessary to design the anchor bolts around the mechanical equipment as reserved bolts, and grout the reserved bolts once after the equipment is roughly adjusted during installation. After the grouting reaches the strength, the equipment is fine-tuned for a second time using the shim group to complete the equipment installation work. Due to various reasons, the size of the reserved bolt hole is often much larger than the bolt hole arranged on the base of the mechanical equipment, resulting in the inability to install the equipment seat grouting pad. For this situation, the conventional construction method is to hoist the equipment into place for rough adjustment, and then grout the anchor bolts and reserved bolt holes once. After the grouting concrete strength reaches a certain level, the equipment is hoisted out of the installation position for the pad seat grouting construction. After the pad seat grouting is completed, the equipment is fine-tuned and grouted for a second time to meet the equipment installation requirements. This construction method requires the use of a crane to hoist the equipment many times, which increases labor costs, machinery costs and other equipment costs, and also affects the increase in construction period. Therefore, a new grouting device and construction method for equipment installation are needed to solve the above problems. Summary of the invention
[0003] In order to solve the above-mentioned technical problems, the present invention provides a grouting device and construction method for equipment installation, which can solve the problems of the equipment seat grouting pad being unable to be installed, multiple equipment hoisting, and time-consuming and labor-intensive problems.
[0004] The technical solution adopted by the present invention is: a grouting device for equipment installation, which is used to be installed between the equipment foundation and the equipment base, and the equipment anchor bolts are close to the grouting device for equipment installation, characterized in that it includes a grouting unit and an adjustment component, the grouting unit is located on the upper part of the equipment foundation and covers the equipment anchor bolts, the adjustment component is located between the grouting unit and the equipment base, and the distance between the equipment foundation and the equipment base is adjusted by adjusting the adjustment component.
[0005] Furthermore, the adjustment assembly includes a first washer, a second washer, a third washer and a screw rod, and the upper part of the grouting unit is provided with the first washer, the second washer and the third washer in sequence, the second washer and the third washer are bonded to each other, and the screw rod is provided at the end of the second washer that is perpendicular to the equipment foundation.
[0006] Furthermore, the adjustment assembly also includes a washer top block, the washer top block connects the first washer and the third washer, and the screw rod passes through the washer top block.
[0007] Furthermore, the grouting unit includes a first hinge, a second hinge, a first side panel, a second side panel and a third side panel, the first side panel, the second side panel and the third side panel form a cavity, the first side panel and the second side panel are connected by the first hinge, and the second side panel and the three side panels are connected by the second hinge.
[0008] Furthermore, a pull ring is provided on the side of the third side plate away from the cavity to facilitate taking out the grouting unit after the construction is completed.
[0009] Furthermore, the grouting unit also includes a stopper, and the end of the first side plate away from the first hinge and / or the end of the third side plate away from the second hinge is provided with the stopper, and the stopper is located outside the cavity.
[0010] Furthermore, the grouting unit also includes a fastening card, the first side plate and the third side plate are connected by the fastening card, and the fastening card is arranged between the stop block and the cavity to fasten the grouting unit.
[0011] Furthermore, it also includes a supporting washer, which is placed on the upper part of the equipment foundation and between two equipment anchor bolts to play a temporary supporting role.
[0012] The construction method of the grouting device for equipment installation using any one of the above-mentioned items is characterized by comprising the following steps:
[0013] Connect the equipment anchor bolts to the equipment base and place them together at the installation location on the equipment foundation;
[0014] Place the equipment anchor bolts in the reserved bolt holes on the equipment foundation;
[0015] After the rough part of the equipment base is leveled and aligned, grouting is performed on the reserved bolt holes and equipment anchor bolts;
[0016] Place the grouting unit on both sides of the equipment anchor bolts;
[0017] Put grouting material into the grouting unit body, fill it up and compact it initially, and then place the adjustment component on the upper part of the grouting unit body;
[0018] Tighten the equipment anchor bolts and adjust the adjustment components to ensure that the equipment foundation, grouting unit, adjustment components and equipment base are in close contact with each other;
[0019] Take out the grouting unit and complete the grouting process;
[0020] Adjust the adjustment assembly again to make precise adjustments to the device.
[0021] The advantages and positive effects of the present invention are as follows: after the reserved bolt holes are grouted once, the equipment does not need to be hoisted out of the installation position, and the first shim is pressed into the grouting layer of the cavity by utilizing the increased thickness of the second shim and the third shim, so that the first shim, the second shim, the third shim and the equipment base are in close contact with each other, and then the equipment is fine-tuned for a second time using the adjustment assembly, which effectively reduces construction costs, improves construction efficiency, and achieves the purpose of reducing costs and increasing efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the structure of an embodiment provided by the present invention;
[0023] Figure 2 is a three-dimensional diagram of a grouting unit according to an embodiment of the present invention;
[0024] Figure 3 is a top view of a grouting unit according to an embodiment of the present invention;
[0025] Figure 4 It is a schematic diagram of the structure of the embodiment provided by the present invention in use.
[0026] In the figure:
[0027] 1. Grouting unit; 11. First hinge; 12. Second hinge; 13. First side panel; 14. Second side panel; 15. Third side panel; 16. Pull ring; 17. Fastening card; 18. Block; 19. Support block; 21. First shim; 22. Second shim; 23. Third shim; 24. Screw; 25. Shim top block; 3. Cavity; 4. Equipment base; 5. Equipment anchor bolts; 6. Reserved bolt holes; 7. Equipment foundation; 8. Support shim. DETAILED DESCRIPTION
[0028] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments.
[0029] Reference Figure 1As shown, a grouting device for equipment installation is used to be installed between the equipment foundation 7 and the equipment base 4, and the equipment anchor bolts 5 are close to the grouting device for equipment installation, which is characterized by comprising a grouting unit 1 and an adjustment component 2 (not shown in the figure), the grouting unit 1 is located on the upper part of the equipment foundation 7 and covers the equipment anchor bolts 5, and the adjustment component 2 is located between the grouting unit 1 and the equipment base 4, and the distance between the equipment foundation 7 and the equipment base 4 is adjusted by adjusting the adjustment component 2. After the reserved bolt hole 6 is grouted once, when the grouting concrete strength reaches the design strength, the equipment does not need to be hoisted out of the installation position, and the adjustment component 2 can be used to perform secondary fine adjustment on the equipment, which effectively reduces the construction cost, improves the construction efficiency, and achieves the purpose of reducing costs and increasing efficiency.
[0030] Preferably, the adjustment assembly 2 includes a first washer 21, a second washer 22, a third washer 23 and a screw 24. The upper part of the grouting unit 1 is provided with the first washer 21, the second washer 22 and the third washer 23 in sequence. The second washer 22 and the third washer 23 are bonded to each other, and a screw 24 is provided at the end of the second washer 22 that is perpendicular to the equipment foundation 7.
[0031] Preferably, the adjustment assembly 2 further comprises a washer top block 25, wherein the washer top block 25 connects the first washer 21 and the third washer 23, and the screw 24 penetrates the washer top block 25. In one embodiment, the second washer 22 and the third washer 23 are designed as inclined washer, and the second washer 22 can be moved by the screw 24 to achieve the purpose of squeezing the first washer 21, while the washer top block 25 presses the first washer 21 and the third washer 23 tightly, and after the strength of the grouting layer in the cavity 3 reaches the design strength, the first washer 21 can be used to adjust the equipment accuracy, thereby saving costs and improving construction efficiency. In addition, the cavity 3 is a grouting layer, which is also used for grouting and leveling the first washer 21, thereby improving construction efficiency.
[0032] Preferably, the grouting unit 1 includes a first hinge 11, a second hinge 12, a first side panel 13, a second side panel 14 and a third side panel 15. The first side panel 13, the second side panel 14 and the third side panel 15 form a cavity 3. The first side panel 13 and the second side panel 14 are connected by the first hinge 11, and the second side panel 14 and the third side panel 15 are connected by the second hinge 12.
[0033] Preferably, a pull ring 16 is provided on the side of the third side plate 13 away from the cavity 3 to facilitate taking out the grouting unit 1 after the construction is completed.
[0034] Preferably, the grouting unit 1 further includes a stopper 18, and the end of the first side plate 13 away from the first hinge 11 and / or the end of the third side plate 15 away from the second hinge 12 is provided with a stopper 18, and the stopper 18 is located outside the cavity 3. It should be noted that the stopper 18 can be set to one, two, three, or even more, which is not limited here, as long as the same function can be achieved.
[0035] Preferably, the grouting unit 1 also includes a fastening card 17, and the first side plate 13 and the third side plate 15 are connected by the fastening card 17. The fastening card 17 is arranged between the stopper 18 and the cavity 3 to fasten the grouting unit 1. In one embodiment, a wedge-shaped opening is opened on one side of the fastening card 17 to fasten the first side plate 13 and the third side plate 15. After the construction is completed, the fastening card 17 is taken out and the grouting unit 1 is opened, which is convenient for maintenance and replacement and also improves the service life of the equipment. It should be noted that the material and shape of the fastening card 17 are not limited here, as long as the same function can be achieved.
[0036] Preferably, it also includes a support washer 8, which is placed on the upper part of the equipment foundation 7 and between the two equipment anchor bolts 5 to play a temporary support role. In the actual construction process, the support washer 8 is used to support the equipment base 4 and the support pad for rough adjustment of the equipment. The number of support washer 8 can be flexibly set according to actual conditions without specific restrictions, thereby improving the safety and stability of the construction process.
[0037] The construction method of the grouting device for equipment installation using any one of the above-mentioned items is characterized by comprising the following steps:
[0038] Connect the equipment anchor bolts 5 and the equipment base 4, and place them together at the installation position on the equipment foundation 7;
[0039] Place the equipment anchor bolts 5 in the reserved bolt holes 6 on the equipment foundation 7;
[0040] After the rough part of the equipment base 4 is leveled and aligned, the reserved bolt holes 6 and the equipment anchor bolts 5 are grouted;
[0041] Place the grouting unit 1 on both sides of the equipment anchor bolts 5;
[0042] Put grouting material into the grouting unit 1, fill it up and tamp it, and then place the adjustment component 2 on the top of the grouting unit 1;
[0043] Tighten the equipment anchor bolts 5, and adjust the adjustment assembly 2, so that the equipment foundation 4, the grouting unit 1, the adjustment assembly 2, and the equipment base 4 are in close contact with each other;
[0044] Take out the grouting unit 1 to complete the grouting process;
[0045] Adjust the adjustment component 2 again to make precise adjustments to the device.
[0046] During construction, first place the support shim 8 on the equipment foundation 7, then connect the equipment anchor bolt 5 to the equipment base 4 and place them together on the equipment foundation 7, and then put the anchor bolt 5 into the reserved bolt hole 6. After the rough part of the equipment base 4 is leveled and aligned, the reserved bolt hole 6 and the equipment anchor bolt 5 are grouting. After the grouting concrete reaches a certain strength, the grouting unit 1 is placed on both sides of the equipment anchor bolt 5, and the stirred grouting material is placed in the cavity 3. After it is filled and initially compacted, the first shim 21 and the second shim 22 and the third shim 23 that are bonded to each other are placed on the upper part of the grouting unit 1, and the equipment anchor bolt 5 is tightened. The shim top block 25 is installed on the screw rod 24, so that the upper part of the shim top block 25 is tightly pressed against the third shim 23, and the lower part is tightly pressed against the first shim 21. Subsequently, tighten the screw 24 to move the second washer 22 outward, and use the increased thickness of the two washer 21 to press the first washer 21 into the grouting layer of the cavity 3 to compact the grouting layer, and at the same time, make the first washer 21, the second washer 22, the third washer 23 and the equipment base 4 in close contact. After the curing strength of the grouting material in the cavity 3 meets the requirements, remove the fastening card 17 to disengage the first side plate 13 and the third side plate 15, hook the pull ring 16, and detach the grouting unit 1 from the bottom of the equipment; at the same time, remove the washer top block 25 to complete the grouting process. Finally, use the second washer 22 and the third washer 23 to accurately adjust the equipment base to meet the equipment installation requirements.
[0047] Embodiment 1:
[0048] A grouting device for equipment installation is used to be installed between an equipment foundation 7 and an equipment base 4, and an equipment anchor bolt 5 is close to the grouting device for equipment installation. It is characterized in that it includes a grouting unit 1 and an adjustment component 2 (not shown in the figure), the grouting unit 1 is located on the upper part of the equipment foundation 7 and covers the equipment anchor bolt 5, the adjustment component 2 is located between the grouting unit 1 and the equipment base 4, and the distance between the equipment foundation 7 and the equipment base 4 is adjusted by adjusting the adjustment component 2.
[0049] The adjustment assembly 2 includes a first washer 21, a second washer 22, a third washer 23 and a screw 24. The upper part of the grouting unit 1 is provided with the first washer 21, the second washer 22 and the third washer 23 in sequence. The second washer 22 and the third washer 23 are bonded to each other. The end of the second washer 22 that is perpendicular to the equipment foundation 7 is provided with a screw 24.
[0050] The adjustment assembly 2 further includes a washer top block 25 , which connects the first washer 21 and the third washer 23 , and the screw rod 24 passes through the washer top block 25 .
[0051] The grouting unit 1 includes a first hinge 11, a second hinge 12, a first side panel 13, a second side panel 14 and a third side panel 15. The first side panel 13, the second side panel 14 and the third side panel 15 form a cavity 3. The first side panel 13 and the second side panel 14 are connected by the first hinge 11, and the second side panel 14 and the third side panel 15 are connected by the second hinge 12.
[0052] A pull ring 16 is provided on the side of the third side plate 13 away from the cavity 3 to facilitate taking out the grouting unit 1 after the construction is completed.
[0053] The grouting unit 1 further includes a stopper 18 . The end of the first side plate 13 away from the first hinge 11 and / or the end of the third side plate 15 away from the second hinge 12 is provided with a stopper 18 . The stopper 18 is located outside the cavity 3 .
[0054] Preferably, the grouting unit 1 further includes a fastening card 17 , and the first side plate 13 and the third side plate 15 are connected via the fastening card 17 . The fastening card 17 is disposed between the stopper 18 and the cavity 3 to fasten the grouting unit 1 .
[0055] It also includes a supporting washer 8, which is placed on the upper part of the equipment foundation 7 and between two equipment anchor bolts 5 to play a temporary supporting role.
[0056] The construction method of the grouting device for equipment installation is characterized by comprising the following steps:
[0057] Connect the equipment anchor bolts 5 and the equipment base 4, and place them together at the installation position on the equipment foundation 7;
[0058] Place the equipment anchor bolts 5 in the reserved bolt holes 6 on the equipment foundation 7;
[0059] After the rough part of the equipment base 4 is leveled and aligned, the reserved bolt holes 6 and the equipment anchor bolts 5 are grouted;
[0060] Place the grouting unit 1 on both sides of the equipment anchor bolts 5;
[0061] Put grouting material into the grouting unit 1, fill it up and tamp it, and then place the adjustment component 2 on the top of the grouting unit 1;
[0062] Tighten the equipment anchor bolts 5, and adjust the adjustment assembly 2, so that the equipment foundation 4, the grouting unit 1, the adjustment assembly 2, and the equipment base 4 are in close contact with each other;
[0063] Take out the grouting unit 1 to complete the grouting process;
[0064] Adjust the adjustment component 2 again to make precise adjustments to the device.
[0065] The advantages and positive effects of the present invention are as follows: after the reserved bolt holes are grouted once, the equipment does not need to be hoisted out of the installation position, and the first shim is pressed into the grouting layer of the cavity by utilizing the increased thickness of the second shim and the third shim, so that the first shim, the second shim, the third shim and the equipment base are in close contact with each other, and then the equipment is fine-tuned for a second time using the adjustment assembly, which effectively reduces construction costs, improves construction efficiency, and achieves the purpose of reducing costs and increasing efficiency.
[0066] The embodiments of the present invention are described in detail above, but the contents described are only preferred embodiments of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.
Claims
1. A grouting device for equipment installation, which is used to be installed between the equipment foundation and the equipment base, and the equipment anchor bolts are close to the grouting device for equipment installation, characterized in that: It includes a grouting unit and an adjustment component, wherein the grouting unit is located on the upper part of the equipment foundation and covers the equipment anchor bolts, and the adjustment component is located between the grouting unit and the equipment base, and the distance between the equipment foundation and the equipment base is adjusted by adjusting the adjustment component; the adjustment component includes a first shim, a second shim, a third shim and a screw rod, and the upper part of the grouting unit is sequentially provided with the first shim, the second shim and the third shim, the second shim and the third shim are bonded to each other, and the screw rod is provided at the end of the second shim that is perpendicular to the equipment foundation; the adjustment component also includes a shim top block, the shim top block connects the first shim and the third shim, and the screw rod passes through the shim top block.
2. The grouting device for equipment installation according to claim 1, characterized in that: The grouting unit includes a first hinge, a second hinge, a first side panel, a second side panel and a third side panel. The first side panel, the second side panel and the third side panel form a cavity. The first side panel and the second side panel are connected by the first hinge, and the second side panel and the third side panel are connected by the second hinge.
3. The grouting device for equipment installation according to claim 2, characterized in that: A pull ring is provided on the side of the second side plate away from the cavity to facilitate taking out the grouting unit after the construction is completed.
4. The grouting device for equipment installation according to claim 2, characterized in that: The grouting unit further comprises a stopper, and the end of the first side plate away from the first hinge and / or the end of the third side plate away from the second hinge is provided with the stopper, and the stopper is located outside the cavity.
5. The grouting device for equipment installation according to claim 4, characterized in that: The grouting unit also includes a fastening card, the first side plate and the third side plate are connected by the fastening card, and the fastening card is arranged between the stopper and the cavity to fasten the grouting unit.
6. The grouting device for equipment installation according to claim 1, characterized in that: It also includes a supporting washer, which is placed on the upper part of the equipment foundation and between two equipment anchor bolts to play a temporary supporting role.
7. A construction method for equipment installation using a grouting device according to any one of claims 1 to 6, characterized in that: The following steps are involved: Connect the equipment anchor bolts to the equipment base and place them together at the installation location on the equipment foundation; Place the equipment anchor bolts in the reserved bolt holes on the equipment foundation; After the rough part of the equipment base is leveled and aligned, grouting is performed on the reserved bolt holes and equipment anchor bolts; Place the grouting unit on both sides of the equipment anchor bolts; Put grouting material into the grouting unit body, fill it up and compact it initially, and then place the adjustment component on the upper part of the grouting unit body filled with grouting layer; Tighten the equipment anchor bolts and adjust the adjustment components to ensure that the equipment foundation, grouting unit, adjustment components and equipment base are in close contact with each other; Take out the grouting unit and complete the grouting process; Adjust the adjustment assembly again to make precise adjustments to the device.