Construction method for rapid repair of existing railway riverside station embankment after water damage

By adopting a stepped roadbed repair method of 4:6 fine stone concrete and rubble mixture at the Railway Binhe Station, combined with the design of a counter-pressure berm and a hanging skirt isolation wall, the secondary collapse and construction of the embankment after water damage were solved The problem of slow speed is solved, and the repair effect is achieved quickly and safely.

CN113981750BActive Publication Date: 2024-10-01ZHENGZHOU ENG CO LTD CHINA RAILWAY SEVENTH GRP +1
View PDF 14 Cites 0 Cited by

Patent Information

Application Number
CN202111363074.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-17
Publication Date
2024-10-01
Estimated Expiration
2041-11-17

AI Technical Summary

Technical Problem

In extreme weather such as storms, the roadbed of railway stations along the river is prone to collapse. Existing repair methods have problems such as secondary collapse, difficulty in controlling construction quality, and slow speed.

Method used

A 4:6 mixture of fine stone concrete and rubble was used to repair the step-wide roadbed. The sand and pebbles from the diverted river were used to fill the counter-pressure berm as a construction platform. The concrete surface layer and slope edge concrete were poured layer by layer, and vertical walls were installed. A skirt isolation wall and temporary steel pipe piles are used for protection.

Benefits of technology

It achieves fast, safe and quality-reliable embankment repair, reduces construction costs, and is suitable for the rapid repair needs of the railway riverside station.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113981750B_ABST
    Figure CN113981750B_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for rapid repair of an existing railway riverside station embankment after water damage, comprising: ① cleaning the collapsed and damaged site; ② relocating the river channel, and filling the anti-pressure berm at the foot of the water-damaged embankment with the excavated sand and pebbles as a construction platform; ③ building a stepped widening roadbed layer by layer on the construction platform until it is equal to the existing roadbed, each layer of the widening roadbed uses a 4:6 fine stone concrete and a stone mixture as a filler, burying a drainage pipe on the top of the filler and pouring a concrete surface layer; ④ trimming the slope surface, and pouring the slope edge concrete layer from the foot to the top of the slope in layers from bottom to top; ⑤ setting a temporary steel pipe pile on the anti-pressure berm outside the widening roadbed for protection, and then building a vertical skirt water-blocking wall; ⑥ pulling out the temporary steel pipe pile, and pouring a vertical skirt top surface sealing layer under the condition that the soil strength between the vertical skirt water-blocking wall and the widening roadbed meets the requirements, and completing the construction. The invention has a fast construction speed, stable quality, and small safety hazards, and is suitable for rapid repair.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of rapid emergency rescue and driving recovery of operating line embankments, and in particular to a construction method for rapid emergency repair of an existing railway riverside station embankment after water damage. Background Art

[0002] For railway stations built along the river, their roadbeds are eroded by water for a long time. When encountering extremely bad weather such as storms, they are prone to collapse and damage, which affects normal traffic. At present, the same materials as the existing embankments are mostly used to repair the embankment width by digging steps and filling in layers. However, after the water damage of the riverside section, the existing embankment soil has a large water content. The conventional digging of steps to widen the embankment is very likely to cause secondary collapse, which poses certain safety hazards. At the same time, since the water content of the existing embankment soil is difficult to control, the use of the same materials to widen the embankment is difficult to guarantee the construction quality, and the construction speed is relatively slow, which is not suitable for emergency rescue. Summary of the invention

[0003] In order to solve the above problems, the present invention provides a construction method for rapid repair of the embankment of an existing railway riverside station after water damage, and the following technical solutions can be specifically adopted:

[0004] The construction method for rapid repair of an existing railway riverside station embankment after water damage according to the present invention comprises the following steps:

[0005] The first step is to clean up the collapsed and damaged site caused by the flood;

[0006] The second step is to divert the river channel away from the water-damaged embankment, and use the sand and gravel excavated from the diverted river channel to build a counter-pressure berm at the foot of the water-damaged embankment as a construction platform;

[0007] The third step is to build a stepped wide roadbed layer by layer on the construction platform until it is the same height as the existing roadbed. Each layer of the wide roadbed is filled with a 4:6 fine stone concrete and flaked stone mixture. A drainage pipe is buried on the top of the filling and a concrete surface layer is poured.

[0008] The fourth step is to finish the slope surface after the widening roadbed is completed, and then pour the slope edge concrete in layers from the foot of the slope to the top of the slope;

[0009] Step 5: After the slope edge concrete construction is completed, temporary steel pipe piles are set on the anti-pressure berm outside the widening roadbed for protection, and then the vertical skirt watertight wall is built;

[0010] Step 6. After the construction of the vertical skirt watertight wall is completed, pull out the temporary steel pipe piles, and under the condition that the soil strength between the vertical skirt watertight wall and the side width roadbed meets the requirements, pour the vertical skirt top surface sealing layer to complete the construction.

[0011] The first step also includes covering the exposed surface of the water-damaged embankment with a waterproof sheet to prevent secondary collapse.

[0012] In the third step, railway freight cars are used to transport the stone slabs directly to the collapsed section of the embankment, and the materials are unloaded manually with the help of excavators. When constructing each layer of the roadbed, the edges are firstly laid manually, and then the excavators are used for rapid paving operations. After completion, fine stone concrete is poured through a pump truck. During the pouring process, the excavators are used to stir the concrete in time to fully mix the fine stone concrete with the stone slabs.

[0013] The thickness of each filler layer in the widening roadbed is 100 cm, and the thickness of the concrete surface layer is 30 cm; the thickness of the slope edge concrete is 100 cm.

[0014] The drainage pipe is a horizontally arranged cast iron pipe, one end of which is buried in the existing roadbed soil and is provided with a non-woven fabric filter layer, and the other end extends to the outside of the slope edge concrete.

[0015] The bottom of the vertical skirt watertight wall is located on the extension line of the side slope of the widening roadbed and is at least 2m below the scouring surface of the river channel.

[0016] The distance between the vertical skirt water-retaining wall and the slope foot of the wide roadbed is 6-8m.

[0017] The vertical skirt watertight wall is constructed by adopting the process of segmented excavation and underwater pouring and coagulation.

[0018] In the sixth step, if the soil strength between the vertical skirt watertight wall and the side width roadbed does not meet the requirements, surface grouting reinforcement is first adopted, and then the vertical skirt top surface sealing layer is poured.

[0019] The thickness of the sealing layer on the top surface of the hanging skirt is 50 cm.

[0020] The invention provides a construction method for rapid repair of an existing railway riverside station embankment after water damage, which adopts a 4:6 fine stone concrete and rubble mixture to widen the damaged roadbed, and when widening, it is not necessary to excavate steps at the junction of the new and old roadbeds, and local materials can be used, so the construction speed is relatively fast, the construction quality can be guaranteed, the safety hazards during the construction process are relatively small, and the construction cost is relatively low. The invention is particularly suitable for rapid repair of an existing railway riverside station embankment after water damage. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a schematic diagram of the damaged section roadbed structure after repair in the present invention.

[0022] Figure 2 yes Figure 1 Schematic diagram of the structure of the drainage pipe.

[0023] Figure 3a-3f It is a schematic diagram of the construction steps of the present invention. DETAILED DESCRIPTION

[0024] The following is a detailed description of an embodiment of the present invention in conjunction with the accompanying drawings. This embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation method and a specific construction process are given, but the protection scope of the present invention is not limited to the following embodiment.

[0025] like Figures 1 to 3f As shown, the construction method for rapid repair of the existing railway riverside station embankment after water damage described in the present invention comprises the following steps:

[0026] The first step is to clean up the collapsed and damaged site caused by the flood.

[0027] Specifically, Figure 3a As shown, when an embankment adjacent to a river collapses due to a sudden flood, an excavator should be used to promptly clean up the collapsed structures, pumice, tree roots and other debris within the collapsed area. At the same time, the exposed embankment caused by the collapse should be covered with waterproof cloth and other impermeable materials to prevent the collapsed surface from being disturbed again and causing another collapse, thus creating a safe construction environment for emergency rescue.

[0028] The second step is to divert the river channel to a side away from the water-damaged embankment, and use the sand and gravel excavated from the diverted river channel to build a counter-pressure berm 1 at the foot of the water-damaged embankment as a construction platform;

[0029] like Figure 3b As shown, the river channel is excavated and relocated by an excavator to make it as far away from the water-damaged embankment as possible, reduce the scouring effect of the river water on the embankment, and prevent the recurrence of floods. At the same time, in order to speed up the construction progress and save construction costs, the sand and gravel excavated by the excavator are used as the filling material of the counter-pressure berm 1, and the counter-pressure berm 1 is built at the foot of the slope of the water-damaged embankment, which not only achieves the purpose of temporarily reinforcing the foot of the slope of the water-damaged embankment, but also can use the counter-pressure berm as a construction platform.

[0030] The third step is to build a stepped wide roadbed 2 layer by layer on the construction platform until it is the same height as the existing roadbed, and at the same time restore the contact network poles and the cable troughs at the shoulders. Each layer of the wide roadbed uses a 4:6 fine stone concrete and rubble mixture 201 as filler, bury a drainage pipe 202 on the top of the filler and pour a concrete surface layer 203.

[0031] like Figure 3cAs shown, in order to improve the transportation efficiency of embankment fillers, buy time for emergency rescue, and make full use of the advantages of existing railways, railway freight cars are used to transport stone flakes directly to the collapsed section of the embankment, and the materials are unloaded manually with the help of excavators. When constructing the widening roadbed 2, it is carried out in layers from bottom to top, and is set into steps according to the slope of the slope. In each layer, the edges are first manually stacked, and then the excavator is used for rapid paving operations. After completion, fine stone concrete is used for grouting by a pump truck. The mass ratio of the above-mentioned stone flakes to fine stone concrete is 4:6 (the performance is better than that of existing roadbed fillers). During the pouring process, the excavator is stirred in time to fully mix the fine stone concrete and the stone flakes. The thickness of the filling layer after paving is about 100 cm; afterwards, a horizontal cast iron drainage pipe 202 is buried on the filling layer after paving, one end of which is coated with non-woven fabric 204 as a filter layer (see Figure 2 ) and then buried in the existing roadbed soil, and the other end should extend to the outside of the slope edge concrete 3 to ensure that the groundwater in the existing roadbed can be discharged smoothly; finally, pour a 30cm thick concrete surface layer 203 on the top of the filling layer.

[0032] When unloading the above-mentioned stone chips, some of them will roll down and hit the train wheels, which can easily cause damage to the wheel shock absorbers and brake components. During construction, some of the stone chips will roll behind the wheels under the train, making it difficult to clean them manually. The use of bamboo plywood 205 to protect the wheels on site and the use of excavators to promptly clean up the stone chips accumulated at the door during unloading can solve the above problems.

[0033] The above-mentioned pump truck runs on the back-pressure berm 1 serving as a construction operation platform, ensuring the efficiency and quality of concrete pouring during the rescue process.

[0034] Step 4: After the widening roadbed 2 is built, the slope surface is trimmed, and then the slope edge concrete 3 is poured layer by layer from the slope foot to the slope top;

[0035] like Figure 3d As shown, slope correction refers to trimming the slope line and reserved platform, as well as chiseling away excess stones and slope concrete slurry. If the cast iron drainage pipe 202 is short, it needs to be extended, and then 100 cm thick edge concrete 3 is poured to protect the newly built embankment filler and prevent the slope from being eroded when floods strike again. It can also serve as a retaining wall for the embankment along the river. When pouring the edge concrete 3, it is poured in layers from the foot of the slope to the top of the slope, and the layer thickness is not more than 200 cm. During pouring, the template uses a steel template and is pumped into the template.

[0036] Step 5: Figure 3eAs shown, after the construction of the slope edge concrete 3 is completed, temporary steel pipe piles 4 are set on the anti-pressure berm 1 outside the widening roadbed 2 for protection, and then the vertical skirt watertight wall 5 is built; the bottom of the vertical skirt watertight wall 5 is located on the extension line of the slope of the widening roadbed 2 and at least 2m below the scouring surface of the river channel. In general, the vertical skirt watertight wall 5 is 6-8m away from the slope foot of the widening roadbed 2. If there is a lot of groundwater and it is difficult to drain when the vertical skirt watertight wall 5 is excavated, the segmented excavation and underwater pouring concrete process can be adopted.

[0037] Step 6: Figure 3f As shown, after the construction of the vertical skirt water-blocking wall 5 is completed, the temporary steel pipe piles 4 are pulled out, and the strength of the soil between the vertical skirt water-blocking wall 5 and the widening roadbed 2 is tested. If it does not meet the relevant requirements, the soil needs to be reinforced by surface grouting, and then tested again until the strength requirements are met; then, 50 cm thick concrete is used to seal this area, that is, the vertical skirt top surface sealing layer 6 is poured, and it is cast as a whole with the edging concrete 3. Thereby, not only the stability of the slope edging concrete 3 is guaranteed, but also the slope foot of the widening roadbed 2 is protected from river erosion. Finally, the back pressure berm 1 is raised to complete the construction.

[0038] It should be noted that, in the description of the present invention, terms indicating orientation or positional relationships, such as "front", "rear", "left", "right", "vertical", "horizontal", "inside", "outside", etc., are based on the orientation or positional relationships shown in the drawings and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

Claims

1. A construction method for rapid repair of an existing railway riverside station embankment after water damage, characterized in that: The steps include: The first step is to clean up the collapsed and damaged site caused by the flood; The second step is to divert the river channel away from the water-damaged embankment, and use the sand and gravel excavated from the diverted river channel to build a counter-pressure berm at the foot of the water-damaged embankment as a construction platform; The third step is to build a stepped wide roadbed layer by layer on the construction platform until it is the same height as the existing roadbed. Each layer of the wide roadbed is filled with a 4:6 fine stone concrete and flaked stone mixture. A drainage pipe is buried on the top of the filling and a concrete surface layer is poured. The fourth step is to finish the slope surface after the widening roadbed is completed, and then pour the slope edge concrete in layers from the foot of the slope to the top of the slope; Step 5: After the slope edge concrete construction is completed, temporary steel pipe piles are set on the anti-pressure berm outside the widening roadbed for protection, and then the vertical skirt watertight wall is built; Step 6: After the construction of the vertical skirt watertight wall is completed, pull out the temporary steel pipe piles, and pour the vertical skirt top surface sealing layer under the condition that the soil strength between the vertical skirt watertight wall and the side wide roadbed meets the requirements to complete the construction; The bottom of the vertical skirt watertight wall is located on the extension line of the slope of the widening roadbed and at least 2m below the scouring surface of the river channel; the vertical skirt watertight wall is 6-8m away from the slope foot of the widening roadbed; the thickness of the sealing layer on the top surface of the vertical skirt is 50cm.

2. The construction method for rapid repair of the existing railway riverside station embankment after water damage according to claim 1 is characterized by: The first step also includes covering the exposed surface of the water-damaged embankment with a waterproof sheet to prevent secondary collapse.

3. The construction method for rapid repair of the existing railway riverside station embankment after water damage according to claim 1 is characterized by: In the third step, railway freight cars are used to transport the stone slabs directly to the collapsed section of the embankment, and the materials are unloaded manually with the help of excavators. When constructing each layer of the roadbed, the edges are firstly laid manually, and then the excavators are used for rapid paving operations. After completion, fine stone concrete is poured through a pump truck. During the pouring process, the excavators are used to stir the concrete in time to fully mix the fine stone concrete with the stone slabs.

4. The construction method for rapid repair of the existing railway riverside station embankment after water damage according to claim 1 is characterized by: The thickness of each filler layer in the widening roadbed is 100 cm, and the thickness of the concrete surface layer is 30 cm; the thickness of the slope edge concrete is 100 cm.

5. The construction method for rapid repair of the existing railway riverside station embankment after water damage according to claim 1 is characterized by: The drainage pipe is a horizontally arranged cast iron pipe, one end of which is buried in the existing roadbed soil and is provided with a non-woven fabric filter layer, and the other end extends to the outside of the slope edge concrete.

6. The construction method for rapid repair of the existing railway riverside station embankment after water damage according to claim 1 is characterized by: The vertical skirt watertight wall is constructed by adopting the process of segmented excavation and underwater pouring and coagulation.

7. The construction method for rapid repair of the existing railway riverside station embankment after water damage according to claim 1 is characterized by: In the sixth step, if the soil strength between the vertical skirt watertight wall and the side width roadbed does not meet the requirements, surface grouting reinforcement is first adopted, and then the vertical skirt top surface sealing layer is poured.

Citation Information

Patent Citations

  • Waterside road broadened embankment structure and construction method thereof

    CN103628378A

  • Light soil side wide roadbed structure for railway

    CN104928996A

  • Widening subgrade structure based on existing railway subgrade and construction method of widening subgrade structure

    CN106522037A

  • Transformation method of high speed railway by using existing embankment

    CN108560340A

  • Riverway in-situ solidifying construction method

    CN111648297A