An integrated production planning and scheduling method for oriented electrical steel production lines
By introducing an automated production planning scheduling method based on L4 in the steel industry, and using core process progressive scheduling and genetic algorithm optimization, the problems of low production planning efficiency and low target hit rate in the existing technology are solved, and the more High equipment utilization and overall control of production planning.
Patent Information
- Application Number
- CN202110980762.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-08-25
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2041-08-25
AI Technical Summary
The existing steel industry production planning scheduling methods are inefficient in operation and cannot be adjusted in time, resulting in low target hit rate and low equipment utilization rate, and lack of a global understanding of the overall production plan.
Using the automated production planning scheduling method based on L4, through the progressive scheduling of core processes, combined with evaluation factors and optimization algorithms (such as genetic algorithms), comprehensive evaluation results are formed and production plans are determined to ensure the connection between processes and materials to materials. Time to achieve process error-proof operation and planning adjustment.
It improves the efficiency of production planning, enhances production operators' mastery of overall plans, reduces unit switching, and improves equipment utilization and production capacity.
Smart Images

Figure CN114004388B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of manufacturing and automation, and in particular relates to an integrated production planning and scheduling method suitable for an oriented electrical steel production line. Background Art
[0002] Production planning refers to the planning to meet the three elements of customer requirements: "delivery time, quality, and cost" on the one hand; on the other hand, it enables the company to obtain appropriate benefits by making overall arrangements for production tasks and specifically formulating plans for the variety, quantity, quality, and progress of production products.
[0003] The main processes of the oriented silicon steel production line include normal pickling, cold rolling, decarburization annealing, high temperature furnace, hot stretch annealing (including notching), and finishing. Oriented silicon steel products are different from conventional thin plate products such as automotive plates and non-oriented silicon steel. Conventional thin plate products generally use the contract completion node as the ultimate goal of planning and scheduling. However, due to the complex process and low target grade hit rate of oriented silicon steel, a large number of carryover products will be produced at the same time. When organizing production, it is not entirely based on individual contract input production. It must be combined with the overall structure of all online contracts and input according to appropriate specifications and proportions in order to maximize the completion of online contracts. Specifically, in the preparation of the unit production plan, the production plan scheduling of the entire production line is centered around the bottleneck process.
[0004] At present, the production planning and scheduling in the steel industry mainly adopts the method of manual compilation by planners, which is compiled according to the material supply of the previous process and appropriate consideration of the needs of the subsequent process. The main defects of this method are: 1. The plan is compiled for steel coils, the operation granularity is small, and the compilation efficiency is low. 2. The front-line production operators of the unit can only see the production plan of this unit, and cannot understand whether there are subsequent plans for the same batch, and the requirements of the subsequent process for the production sequence of this unit cannot be intuitively obtained. 3. When the current and subsequent process plans change due to objective reasons (such as equipment failure), they cannot be adjusted in time. 4. Production planners need to wait for the output of the previous unit before they can compile the production plan for the next unit. The operation frequency is high, which affects work efficiency.
[0005] The invention application with application number: CN201410670170.0 discloses "a method for preparing a hot rolling roll schedule". The present invention discloses a method for preparing a hot rolling roll schedule, comprising: a first electronic device creates M virtual slabs according to the requirement information of an order for the slabs, the M virtual slabs respectively correspond to M virtual slab numbers, M is a positive integer, wherein the requirement information of the order for the slabs comprises: the requirement of the order for the steel type of the slabs, the requirement of the order for the specification of the slabs, the requirement of the order for the surface of the slabs, and the requirement of the order for the quantity of the slabs; the first electronic device arranges and combines the M virtual slabs according to hot rolling rules to create a material preparation plan, wherein the material preparation plan contains the M virtual slab numbers; the first electronic device sends the material preparation plan to a second electronic device.
[0006] The invention application with application number: CN201810813197.9 discloses "a method for magnetic material forming-sintering planning control and detailed scheduling", which includes the following steps: 1) taking the sintering process of magnetic material production as the bottleneck process, establishing a forming-sintering production planning DBR control model centered on the sintering process; 2) obtaining a strategy for formulating the overall plan of the forming-sintering process based on production constraints and target decision variables; 3) formulating a heuristic-based forming-sintering process production plan based on the forming-sintering production planning DBR control model and the overall plan of the forming-sintering process.
[0007] The invention application with application number: CN201811550211.7 discloses "a discrete manufacturing collaborative production planning and scheduling method". In this method, each order consists of a product name and its quantity, and each product consists of multiple parts. The generation of parts and product assembly involve multiple process steps, and there are dependencies between the processes. The method first generates multiple feasible solutions and then decides on the optimal feasible solution. By decomposing a complex optimization calculation process into many simple small problems, it makes the call to computing resources more flexible and can effectively utilize parallel computing resources or distributed computing resources. Summary of the invention
[0008] In order to solve the above problems, the present invention provides an integrated production planning and scheduling method applicable to a grain-oriented electrical steel production line, and its technical solution is as follows:
[0009] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line, characterized in that: based on L4, an automatic production planning and scheduling of the entire grain-oriented electrical steel production line is established through the following steps:
[0010] S1: Based on the necessary data required for scheduling, take the core process as the starting point of scheduling, and complete the scheduling of the previous process and the subsequent process in sequence to form an initial plan schedule;
[0011] S2: Establish a comprehensive evaluation based on the set evaluation factors for the initial plan scheduling, and form a comprehensive evaluation result data set consisting of comprehensive evaluation results;
[0012] S3: Establish optimization algorithm operation for the comprehensive evaluation result data set and determine the production plan schedule based on the operation results.
[0013] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0014] A process error prevention operation is established for the production plan schedule determined according to step S3, and the final production plan schedule is determined according to the process error prevention operation result.
[0015] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0016] Taking the production process as the smallest unit block, complete the production plan block of the core process and the setting of the quantity of materials that can be produced in each plan block; search the plan blocks or the quantity of schedulable materials in the front warehouse of the unit and the front warehouse of each process before the current process according to the set plan block, and complete the core process scheduling in step S1 according to the search results.
[0017] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0018] The core process is taken as the first process, and the scheduling of the subsequent process between adjacent processes is carried out according to the material arrival time requirements of the previous process scheduling results (to ensure the time connection between the previous and next processes in the entire process).
[0019] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0020] If the production plan schedule cannot be generated in step S3, a new round of automatic production plan schedule is triggered to start from step S1 until the production plan schedule can be generated.
[0021] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0022] The comprehensive evaluation based on the set evaluation factors described in step S2 is as follows:
[0023] P=P A +PB +P C +P D +P E +P F ,
[0024] in,
[0025] P: total penalty points;
[0026] P A : Unit utilization evaluation factor;
[0027] P B : Contract plan fulfillment rate evaluation factor;
[0028] P C : Inventory overdue assessment factor;
[0029] P D : Production batch evaluation factor;
[0030] P E : Process specification jump assessment factor;
[0031] P F : Process annealing temperature jump assessment factor;
[0032] The solution operation based on the optimization algorithm is established with the minimum P value as the objective function.
[0033] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0034] The optimization algorithm is a genetic algorithm.
[0035] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0036] Each material is planned as a physical material in the production schedule of the current unit, and as a virtual material in the production schedule of each unit after the current unit; the process error prevention operation based on this is specifically as follows:
[0037] The production process design of the next process is completed according to the production results of the previous process, and this production process design is compared with the original scheduled production process of the next process. If they are the same, the production plan of each unit of the next process is implemented, otherwise the production plan of each unit of the next process is withdrawn.
[0038] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0039] The unit utilization evaluation factors are as follows:
[0040]
[0041] in,
[0042] Δt wi : Unit working time of unit i,
[0043] t si ,t ei are the production start and end time of unit i, respectively.
[0044] Δt ti is the planned downtime of unit i,
[0045] w ui is the utilization weight of unit i,
[0046] w A It is the penalty factor for non-utilization of the unit.
[0047] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0048] The contract plan fulfillment rate assessment factors are as follows:
[0049]
[0050] in,
[0051] W byi : The material processing quantity of unit i in the scheduling plan that meets the production date requirements of the contract plan process,
[0052] W bi : Schedule the total amount of material processing,
[0053] w B : Penalty factor for non-fulfillment of contract plan.
[0054] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0055] The inventory overdue assessment factors are as follows:
[0056]
[0057] in,
[0058] N ci : The number of materials whose storage time has exceeded the limit in the previous warehouse of unit i,
[0059] w c : Inventory overdue penalty coefficient.
[0060] The present invention provides an integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line, characterized in that:
[0061] The production batch evaluation factors are as follows:
[0062]
[0063] in,
[0064] N pi : Schedule production batch for unit i,
[0065] N si : Production batch requirement of unit i,
[0066] w Di : The production batch penalty coefficient of unit i.
[0067] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0068] The process specification jump assessment factors are as follows:
[0069]
[0070] in,
[0071] N ei : The number of materials with process specifications exceeding the limit of the previous and next materials of unit i,
[0072] w Ei : Specification jump penalty coefficient of unit i
[0073] An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line according to the present invention is characterized in that:
[0074] The process annealing temperature jump assessment factor is as follows:
[0075]
[0076] in,
[0077] N fi : The number of materials with excessive process annealing temperature jumps before and after the material of unit i,
[0078] w Fi : Process annealing temperature jump penalty coefficient of unit i.
[0079] The integrated production planning and scheduling method suitable for the oriented electrical steel production line of the present invention can achieve a large degree of automation, greatly improve the efficiency of production plan compilation, enhance the overall grasp of the production plan by front-line production operators, and automatically respond to the plan quickly according to the equipment status and plan execution status; reduce unit switching, improve the effective operation rate of the unit, and improve the unit production capacity. BRIEF DESCRIPTION OF THE DRAWINGS
[0080] Figure 1 It is a schematic diagram of the steps of the present invention;
[0081] Figure 2 Schematic diagram of the overall scheduling process in an embodiment of the present invention;
[0082] Figure 3 It is a schematic diagram of the automatic cancellation plan flow of process error prevention in an embodiment of the present invention. DETAILED DESCRIPTION
[0083] Below, an integrated production planning and scheduling method applicable to a grain-oriented electrical steel production line of the present invention is further described in detail according to the accompanying drawings and specific implementation methods of the specification.
[0084] like Figure 1 The integrated production planning and scheduling method for the oriented electrical steel production line shown in FIG. is based on L4 and establishes the automatic production planning and scheduling of the entire oriented electrical steel production line through the following steps:
[0085] S1: Based on the necessary data required for scheduling, take the core process as the starting point of scheduling, and complete the scheduling of the previous process and the subsequent process in sequence to form an initial plan schedule;
[0086] S2: Establish a comprehensive evaluation based on the set evaluation factors for the initial plan scheduling, and form a comprehensive evaluation result data set consisting of comprehensive evaluation results;
[0087] S3: Establish optimization algorithm operation for the comprehensive evaluation result data set and determine the production plan schedule based on the operation results.
[0088] in,
[0089] A process error prevention operation is established for the production plan schedule determined according to step S3, and the final production plan schedule is determined according to the process error prevention operation result.
[0090] in,
[0091] Taking the production process as the smallest unit block, complete the production plan block of the core process and the setting of the quantity of materials that can be produced in each plan block; search the plan blocks or the quantity of schedulable materials in the front warehouse of the unit and the front warehouse of each process before the current process according to the set plan block, and complete the core process scheduling in step S1 according to the search results.
[0092] in,
[0093] The core process is taken as the first process, and the scheduling of the subsequent process between adjacent processes is carried out according to the material arrival time requirements of the previous process scheduling results (to ensure the time connection between the previous and next processes in the entire process).
[0094] in,
[0095] If the production plan schedule cannot be generated in step S3, a new round of automatic production plan schedule is triggered to start from step S1 until the production plan schedule can be generated.
[0096] in,
[0097] The comprehensive evaluation based on the set evaluation factors described in step S2 is as follows:
[0098] P=P A +P B +P C +P D +P E +P F ,
[0099] in,
[0100] P: total penalty points;
[0101] P A : Unit utilization evaluation factor;
[0102] P B : Contract plan fulfillment rate evaluation factor;
[0103] P C : Inventory overdue assessment factor;
[0104] P D : Production batch evaluation factor;
[0105] P E : Process specification jump assessment factor;
[0106] P F : Process annealing temperature jump assessment factor;
[0107] The solution operation based on the optimization algorithm is established with the minimum P value as the objective function.
[0108] in,
[0109] The optimization algorithm is a genetic algorithm.
[0110] in,
[0111] Each material is planned as a physical material in the production schedule of the current unit, and as a virtual material in the production schedule of each unit after the current unit; the process error prevention operation based on this is specifically as follows:
[0112] The production process design of the next process is completed according to the production results of the previous process, and this production process design is compared with the original scheduled production process of the next process. If they are the same, the production plan of each unit of the next process is implemented, otherwise the production plan of each unit of the next process is withdrawn.
[0113] in,
[0114] The unit utilization evaluation factors are as follows:
[0115]
[0116] in,
[0117] Δt wi : Unit working time of unit i,
[0118] t si ,t ei are the production start and end time of unit i, respectively.
[0119] Δt ti is the planned downtime of unit i,
[0120] w ui is the utilization weight of unit i,
[0121] w A It is the penalty factor for non-utilization of the unit.
[0122] in,
[0123] The contract plan fulfillment rate assessment factors are as follows:
[0124]
[0125] in,
[0126] W byi : The material processing quantity of unit i in the scheduling plan that meets the production date requirements of the contract plan process,
[0127] W bi : Schedule the total amount of material processing,
[0128] w B: Penalty factor for non-fulfillment of contract plan.
[0129] in,
[0130] The inventory overdue assessment factors are as follows:
[0131]
[0132] in,
[0133] N ci : The number of materials whose storage time has exceeded the limit in the previous warehouse of unit i,
[0134] w c : Inventory overdue penalty coefficient.
[0135] in,
[0136] The production batch evaluation factors are as follows:
[0137]
[0138] in,
[0139] N pi : Schedule production batch for unit i,
[0140] N si : Production batch requirement of unit i,
[0141] w Di : The production batch penalty coefficient of unit i.
[0142] in,
[0143] The process specification jump assessment factors are as follows:
[0144]
[0145] in,
[0146] N ei : The number of materials with process specifications exceeding the limit of the previous and next materials of unit i,
[0147] w Ei : Specification jump penalty coefficient of unit i
[0148] in,
[0149] The process annealing temperature jump assessment factor is as follows:
[0150]
[0151] in,
[0152] N fi: The number of materials with excessive process annealing temperature jumps before and after the material of unit i,
[0153] w Fi : Process annealing temperature jump penalty coefficient of unit i.
[0154] Working process, principle and implementation example
[0155] Combine the following Figure 1 , 2 3. The steps of the overall actual operation process of the integrated production planning and scheduling method applicable to the oriented electrical steel production line of the present invention are described as follows:
[0156] The overall process of the method is shown in Figure 2 , the steps include:
[0157] Step 1: Determine the core process. According to the importance, process complexity, and switching cost of each process in the entire manufacturing process, determine the process with the highest importance, process complexity, and switching cost as the core process. This step is generally only performed once when determining the scheduling method for a specific production line, and the process is assumed to be the core process in subsequent scheduling.
[0158] Step 2: Obtain the necessary data required for scheduling as the input of the planning and scheduling model, including but not limited to material data, planning data, process data, equipment data, unit hourly output data, unit planning procedures, etc.
[0159] Among them, material data includes the physical and chemical properties of physical materials and virtual materials that can be produced by each process on the current production line, and other data required to be considered in the planning procedures; planning data includes the plans that have been scheduled but not yet completed for each process and the materials included in the plans; process data includes the process quality design requirements for materials and production contracts in each process; equipment data includes the monthly planned maintenance time of the unit, planned roller replacement and other planned downtime, the current equipment status of the unit, the estimated end time of the fault processing of the current faulty unit, and the unit operation and adjustment arrangements in the short term; production data includes the production speed or hourly output of the unit corresponding to different specifications and process materials, which is used to calculate the time required for material production. The production plan for each material can be generated according to the production time to ensure the connectivity of the production of the previous and next processes; planning procedures include the requirements for specification switching, process switching and replacement cycle of worn parts of each unit.
[0160] Step 3: Set the production plan blocks for the core process, and divide the production plan blocks for the core process into production process blocks and the quantity of materials that can be produced in each plan block.
[0161] Step 4: Perform initial planning and scheduling for each process. The planning and scheduling starts with the core process. According to the set plan block, the schedulable materials that meet the process are searched in the front warehouse of the unit and the front warehouse of each process before the current process. The guidance quantity meets the set plan block quantity, or if the quantity is not met after the search, the core process is scheduled according to the searched material quantity, under the premise of fixed maintenance and shutdown constraints and following the process and planning regulations. After the core process (N process) is scheduled, according to the material arrival time requirements of the scheduling result of the core process, the previous process (N-1 process) of the core process is scheduled under the premise of fixed maintenance and shutdown constraints and following the process and planning regulations. Similarly, the N-2, N-3... and other front processes are planned and scheduled in turn. Similarly, the N+1, N+2... and other back processes are planned and scheduled in turn, and the initial scheduling results of each unit are finally generated. In the scheduling plan, each material is a physical material plan in the production plan corresponding to the current unit, and a virtual material plan in the production plan of each unit after the current unit.
[0162] Step 5: Run the planning optimization algorithm, and use the target evaluation scheme of the scheduling model to conduct a comprehensive evaluation of key indicators in multiple dimensions such as unit utilization, contract plan fulfillment rate, inventory overdue, production batch, process switching, specification switching, etc. Under the premise of meeting the constraints of each unit, the planning optimization algorithm is used to finally find the best possible scheduling result. That is, by scoring the key indicators item by item and summarizing them, the initial scheduling results are evaluated, and new scheduling results are iteratively generated, and the new scheduling results are scored and evaluated. After several iterations, when the scoring result optimization space converges to near zero, the result obtained is used as the final scheduling result. The penalty weights of each key indicator can be adjusted through the penalty coefficient, and the evaluation key indicators can be adjusted according to the specific unit or process requirements. If the scheduling result cannot be generated, an information prompt will be given and the execution will be restarted from step 3.
[0163] As a further preferred solution, in step 5, the target evaluation scheme of the scheduling model is as follows:
[0164] 1) Unit utilization rate evaluation: evaluate the comprehensive utilization efficiency of each unit. Unit utilization rate penalty P A The calculation formula is as follows, where Δt wi is the unit working time of unit i, t si ,t ei are the production start and end time of unit i, Δt ti is the planned downtime of unit i, w ui is the utilization weight of unit i, w A is the unit unutilized penalty coefficient. Unit utilization weight w ui The value of is proportional to the production cost of the unit; the unit utilization evaluation is of high importance in the entire scheduling, so the unutilized penalty coefficient wA The value should be greater than 5.
[0165]
[0166] 2) Contract fulfillment rate assessment: assess whether the material processing time arranged on the unit meets the contract process plan completion time. Contract fulfillment rate penalty points P B The calculation formula is as follows, where W byi is the material processing quantity of unit i in the scheduling plan to meet the production date requirements of the contract plan process, W bi is the total amount of scheduled material processing, w B is the penalty coefficient for non-fulfillment of the contract plan. The contract plan fulfillment rate evaluation is of high importance in the entire scheduling, so the non-fulfillment penalty coefficient w B The value should be greater than 5.
[0167]
[0168] 3) Inventory overdue assessment: Assessment of the production arrangement of the first-stock materials of each unit. Inventory overdue penalty points P C The calculation formula is as follows, where N ci is the number of materials whose storage time in the previous warehouse of unit i has exceeded the expiration date, w c Inventory overdue penalty coefficient. Inventory overdue penalty coefficient w c Adjust it reasonably according to the actual situation, and the value is generally between 0-3.
[0169]
[0170] 4) Production batch evaluation: evaluate whether the batch production requirements of the unit are met. Penalty points P for failure to meet the production batch requirements D The calculation formula is as follows, where N pi is the production batch size of unit i, N si is the production batch requirement of unit i, w Di is the production batch penalty coefficient of unit i. Production batch penalty coefficient w Di The values are different according to the different batching requirements of the units. APL and DCL units have higher requirements for production batching. Di The relative value is greater than that of other units.
[0171]
[0172] 5) Process specification jump evaluation: evaluate the smoothness of the process specifications of the materials produced before and after the continuous production unit. The calculation formula of the process specification jump penalty PE is as follows, where N ei is the number of materials with process specifications exceeding the limit before and after unit i, w Eiis the specification jump penalty coefficient of unit i. Production batch penalty coefficient w Ei The cost of switching the unit specifications varies according to the unit specifications. The cost of switching the APL and DCL units is higher. Ei The relative value is greater than that of other units.
[0173]
[0174] 6) Process annealing temperature jump assessment: Evaluate the smoothness of the process annealing temperature of the materials produced before and after the continuous production unit. Process annealing temperature jump penalty P F The calculation formula is as follows, where N fi is the number of materials with excessive process annealing temperature jumps before and after the material of unit i, w Fi is the process annealing temperature jump penalty coefficient of unit i. Process annealing temperature jump penalty coefficient w Fi The cost of jump switching of the unit annealing temperature varies according to the unit. The cost of switching the APL and DCL unit specifications is higher. Fi The relative value is greater than that of other units.
[0175]
[0176] 7) Summary of each sub-item evaluation: Calculate the total penalty points for each sub-item. The one with the least total penalty points is the better solution.
[0177] P=P A +P B +P C +P D +P E +P F
[0178] For different units, the above penalty factors can be selected partially or completely, or other factors can be added. In this embodiment, the RCM unit does not have an annealing process, so the process annealing temperature jump evaluation PF of the RCM unit can be eliminated, or the penalty coefficient can be adjusted to zero. However, the combination of each penalty factor is not limited to this embodiment, but different factor combinations can be selected from the above penalty factors according to the actual function and process requirements of the unit, or other factors can be added to form a new factor combination; the penalty coefficient of each factor can also be adjusted according to the importance of the factor.
[0179] Step 6: Form an integrated production plan for the entire process and output it in the form of a Gantt chart.
[0180] Step 7: Plan issuance and adjustment.
[0181] The process of plan distribution includes: if the scheduling model runs successfully and meets the requirements, the production plan and production process of each unit will be distributed to the manufacturing management system L4; the manufacturing management system L4 will feedback the reception result, if successful, the system will distribute the unit production plan to the manufacturing execution system L3; if the distribution is successful, the unit production order sequence will be distributed to the manufacturing execution system L3, and the next unit will be updated. At the same time, the next unit of the original production plan of the manufacturing execution system L3 will be updated.
[0182] The plan adjustment process includes: 1. Active cancellation, passive cancellation due to output closure / material return. If the current production plan is exited due to reasons such as full roll / half roll return of materials, active cancellation or output closure, the system will automatically and synchronously cancel the virtual plans corresponding to the subsequent processes, and correct the next unit of the previous process plan. The integrated production plan model can be started again to optimize and update the current production plan and issue it. 2. Automatic cancellation of process error prevention. When the manufacturing management system L4 receives the actual material output performance, it recalculates the production process of the next process. When the production process of the physical material does not match the production process when the virtual plan is generated, it automatically notifies the manufacturing execution system L3 by telegram to cancel the production plans of the subsequent processes. The integrated production plan model can be started again to update the production plan according to the updated material production process and issue it. See the process of automatic cancellation of process error prevention for details. Figure 3 .
[0183] Step 8: Implementation and tracking of the plan.
[0184] Plan execution and tracking include: 1. Physical replacement of virtual plans. When the materials of the previous process in the integrated plan are produced, the virtual plan of the next process is replaced according to the code of the next unit, the material type of the next process plan is updated to "physical", and the plan information is updated according to the specifications and processes of the output physical objects. 2. Compare the plan information of the current scheduling system with the plan information of the current manufacturing execution system, update the plan information of the integrated scheduling system according to the plan information of the manufacturing execution system, archive the produced plans, and update the status of the unfinished plans.
[0185] The integrated production planning and scheduling method suitable for the oriented electrical steel production line of the present invention can achieve a large degree of automation, greatly improve the efficiency of production plan compilation, enhance the overall grasp of the production plan by front-line production operators, and automatically respond to the plan quickly according to the equipment status and plan execution status; reduce unit switching, improve the effective operation rate of the unit, and improve the unit production capacity.
Claims
1. An integrated production planning and scheduling method suitable for a grain-oriented electrical steel production line, characterized in that: Based on the manufacturing management system, the automatic production plan scheduling of the entire oriented electrical steel production line is established through the following steps: S1: Based on the necessary data required for scheduling, take the core process as the starting point of scheduling, and complete the scheduling of the previous process and the subsequent process in sequence to form an initial plan schedule; S2: Establish a comprehensive evaluation based on the set evaluation factors for the initial plan scheduling, and form a comprehensive evaluation result data set consisting of comprehensive evaluation results; S3: Establish an optimization algorithm for the comprehensive evaluation result data set and determine the production plan schedule based on the calculation results; The comprehensive evaluation based on the set evaluation factors described in step S2 is as follows: P=P A +P B +P C +P D +P E +P F , in, P: total penalty points; P A : Unit utilization evaluation factor; P B : Contract plan fulfillment rate evaluation factor; P C : Inventory overdue assessment factor; P D : Production batch evaluation factor; P E : Process specification jump assessment factor; P F : Process annealing temperature jump assessment factor; The solution operation based on the optimization algorithm is established with the minimum P value as the objective function; The unit utilization evaluation factors are as follows: in, Δt wi : Unit working time of unit i, t si ,t ei are the production start and end time of unit i, respectively. Δt ti is the planned downtime of unit i, w ui is the utilization weight of unit i, w A is the penalty coefficient for non-utilization of the unit; The contract plan fulfillment rate assessment factors are as follows: in, W byi : The material processing quantity of unit i in the scheduling plan that meets the production date requirements of the contract plan process, W bi : Schedule the total amount of material processing, w B : Penalty coefficient for failure to fulfill the contract plan; The inventory overdue assessment factors are as follows: in, N ci : The number of materials whose storage time has exceeded the limit in the previous warehouse of unit i, w c : Inventory overdue penalty coefficient; The production batch evaluation factors are as follows: in, N pi : Schedule production batch for unit i, N si : Production batch requirement of unit i, w Di : The production batch penalty coefficient of unit i, The process specification jump assessment factors are as follows: in, N ei : The number of materials with process specifications exceeding the limit of the previous and next materials of unit i, w Ei : specification jump penalty coefficient of unit i; The process annealing temperature jump assessment factor is as follows: in, N fi : The number of materials with excessive process annealing temperature jumps before and after the material of unit i, w Fi : Process annealing temperature jump penalty coefficient of unit i; Establish process error prevention operation for the production schedule determined in step S3, and determine the final production schedule according to the result of process error prevention operation. Each material is planned as a physical material in the production schedule of the current unit, and as a virtual material in the production schedule of each unit after the current unit; the process error prevention operation based on this is specifically as follows: The production process design of the next process is completed according to the production results of the previous process, and this production process design is compared with the original scheduled production process of the next process. If they are the same, the production plan of each unit of the next process is implemented, otherwise the production plan of each unit of the next process is withdrawn.
2. The integrated production planning and scheduling method for a grain-oriented electrical steel production line according to claim 1, characterized in that: Taking the production process as the smallest unit block, complete the production plan block of the core process and the setting of the quantity of materials that can be produced in each plan block; search the plan blocks or the quantity of schedulable materials in the front warehouse of the unit and the front warehouse of each process before the current process according to the set plan block, and complete the core process scheduling in step S1 according to the search results.
3. The integrated production planning and scheduling method for a grain-oriented electrical steel production line according to claim 1, characterized in that: The core process is taken as the first process, and the scheduling of the subsequent process between adjacent processes is carried out according to the material arrival time requirements of the scheduling results of the previous process.
4. The integrated production planning and scheduling method for a grain-oriented electrical steel production line according to claim 1, characterized in that: If the production plan schedule cannot be generated in step S3, a new round of automatic production plan schedule is triggered to start from step S1 until the production plan schedule can be generated.
5. The integrated production planning and scheduling method for a grain-oriented electrical steel production line according to claim 1, characterized in that: The optimization algorithm is a genetic algorithm.