An optimization method for receiving-end power grid planning scheme based on multi-infeed short-circuit ratio verification
Optimizing the power grid structure through multi-infeed short-circuit ratio check and comprehensive evaluation method solves the problem that traditional power grid planning methods are difficult to optimize in large AC and DC hybrid power grids, improves the planning level and plan rationality, and meets the requirements of multi-infeed DC System strength assessment and voltage stability requirements.
Patent Information
- Application Number
- CN202111391998.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-11-19
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2041-11-19
AI Technical Summary
It is difficult for traditional power grid planning methods to effectively consider the planning level and scheme rationality of AC-DC hybrid large power grids. Especially in the case of multiple DC feed-ins, it is impossible to fully optimize the AC power grid topology to meet the requirements of new energy consumption capacity and economic costs. Complex multi-objective programming problems.
Adopt the receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio check. Through short-circuit check, power flow analysis, stability check and multi-infeed short-circuit ratio calculation, the grid structure is adjusted and the DC placement point and AC grid are optimized. Improve the system's strength assessment and fault stability, and obtain the final planning solution based on the comprehensive assessment method.
It improves the planning level and scheme rationality of the AC-DC hybrid large power grid, reduces the workload of planners, enhances the applicability and feasibility of the scheme, and can meet the strength assessment and voltage stability requirements of multi-feed DC systems.
Smart Images

Figure CN114021845B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of power system planning, and in particular to a receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification. Background Art
[0002] Conventional grid planning is a demand-oriented grid planning method based on factors such as load demand forecasting, power source planning layout, and grid construction conditions. It is based on source-grid coordination. In the verification of traditional planning schemes, the main focus is on the power balance and peak load balance of the power system, as well as the short-circuit current verification of the main grid, typical flow analysis, and system stability verification under common faults. After multiple rounds of flow, short-circuit and stability verification and scheme optimization and adjustment, the recommended optimal or relatively optimal grid planning scheme is finally given.
[0003] With the rapid development of DC transmission technology and engineering practice, there are more and more centralized DC feed-ins across the country. After multiple DC lines are centralized, they will inevitably have complex mutual influences on the AC power grid. Traditional power grid planning methods take fewer factors into consideration and are still unable to significantly improve the planning level and rationality of large AC / DC hybrid power grids. The structural optimization of the AC / DC hybrid receiving-end power grid needs to consider safety goals such as reducing power flow through, reducing conventional DC commutation failures, and controlling short-circuit currents, as well as the new energy absorption capacity and economic costs. It is a complex multi-objective planning problem. Therefore, how to comprehensively consider multiple factors, reasonably optimize the AC power grid topology, and propose planning optimization technologies and methods for AC / DC hybrid receiving-end power grids is an urgent problem to be solved in the current power grid planning field. Summary of the invention
[0004] The purpose of the present invention is to overcome the defects of the above-mentioned prior art and provide a receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification.
[0005] The purpose of the present invention can be achieved by the following technical solutions:
[0006] A receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification, the method comprising:
[0007] Determine the receiving power grid to be optimized and obtain the basic power grid planning scheme of the receiving power grid to be optimized;
[0008] Two sets of verification processes are performed on the basic power grid planning scheme at the same time to obtain two sets of scheme results; wherein the first verification process includes a short-circuit verification step, a power flow analysis step, and a stability verification step performed in sequence; the second verification process includes a multi-infeed short-circuit ratio verification step;
[0009] The two sets of scheme results obtained by verification are judged to see whether they meet the actual planning requirements. If so, the corresponding scheme results are used as the recommended planning scheme, and the final scheme is obtained after the next evaluation operation. Otherwise, the scheme results obtained by verification are adjusted to obtain the recommended planning scheme that meets the actual planning requirements.
[0010] Perform a comprehensive evaluation of the recommended planning schemes for actual planning requirements to obtain the final planning scheme.
[0011] Furthermore, the second verification process also includes a short circuit verification step, a short circuit ratio calculation step, and a voltage stability verification step after a DC fault, which are arranged after the multi-infeed short circuit ratio verification step.
[0012] The specific content of the second verification process is:
[0013] According to the type, capacity and main control mode of the DC power grid that has been built or is planned to be built, establish the DC model and parameters for multi-infeed short-circuit ratio calculation and fill them into the power grid simulation data file;
[0014] Calculate the DC multi-infeed effective short-circuit ratio MESCR for different typical operation modes, different grid schemes and specific conditions, and statistically analyze the calculation results;
[0015] The strength of multi-infeed AC / DC systems is divided into the following standard categories: extremely weak system: MESCR<2, weak system: 2≤MESCR<3, strong system: MESCR≥3. The strength of the planned power grid system or the pros and cons of each planning scheme is evaluated based on the calculation results.
[0016] Furthermore, the specific contents of the short circuit verification step are:
[0017] The short-circuit current verification step is performed on the basic power grid planning scheme to determine whether it meets the equipment safety requirements within the upper limit of the switch breaking capacity when fully powered on, fully connected or in a specific operating mode. The short-circuit current verification includes three-phase and single-phase short-circuit current verification, or DC component and voltage coefficient value verification.
[0018] Furthermore, the power flow analysis step includes judging the rationality of power flow distribution under four typical modes: normal conditions in summer peak / trough and winter peak / trough, and after N-1 and N-2 faults.
[0019] Furthermore, the adjustment step of the scheme adjustment follows a short-circuit verification step, a power flow analysis step and a stability verification step, or a multi-input short-circuit ratio verification step, which are performed in sequence.
[0020] The content of the scheme adjustment includes but is not limited to: adjusting the line or main connection topology, increasing, decreasing or replacing lines / transformers, increasing or decreasing parallel capacitors / parallel reactors / series reactors / STATCOM, optimizing DC landing point / unit access scheme, installing small reactors / resistors at the neutral point of the main transformer, and adjusting electrical partitions and power supply range.
[0021] Furthermore, a comprehensive evaluation is performed on the recommended planning schemes required by the actual planning, and the specific contents of the final planning scheme are obtained as follows:
[0022] 1) A preliminary grid plan is given, clarifying the four typical operation modes of summer high / summer low / winter high / winter low in the planning year;
[0023] 2) Calculate the conventional power flow of each mode and the power flow distribution after N-1 fault occurs, and verify the transient safety and stability of the system;
[0024] 3) Calculate the multi-infeed effective short-circuit ratio MESCR of the DC system under various modes;
[0025] 4) Calculate the impact of AC grid disconnection on MESCR, and select the AC lines with the highest impact on the existing DC MESCR after disconnection of the AC lines;
[0026] 5) By forcing DC commutation failure and lockout fault, and comparing other DC commutation failures and AC voltage fluctuations, select DC projects with greater impact;
[0027] 6) Strengthen the grid structure and voltage support capacity of the receiving-end power grid by adding AC lines, phase regulators or SVG reactive compensation equipment;
[0028] 7) Strengthen the grid to conduct review calculations, check the N-1 safety stability under various modes, and recalculate the MESCR under various modes;
[0029] 8) Compare the MESCR after grid reinforcement and the voltage fluctuation after DC fault, select the comparison scheme, use the evaluation method to compare the index weights, and conduct a comprehensive evaluation of each optimization scheme;
[0030] 9) Provide the best recommended solution based on comprehensive evaluation to guide the planning and construction of the receiving power grid.
[0031] Furthermore, in step 4), the top three AC lines in terms of impact on the existing DC MESCR after disconnecting the AC line are selected.
[0032] Furthermore, in step 8), the top three schemes in terms of MESCR increase value and voltage fluctuation reduction are selected as the comparison schemes.
[0033] The receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification provided by the present invention has at least the following beneficial effects compared with the prior art:
[0034] 1) Compared with the traditional planning method that only focuses on the power balance and peak load balance of the power system, as well as the short-circuit current verification of the main grid, typical mode flow analysis and system stability verification under common faults, this application introduces multi-infeed short-circuit ratio verification, which can measure the strength and mutual influence of multiple DC-infeed AC systems, and can assist in the planning and scheme optimization of power grids containing multiple DC. Compared with the existing technology, it can further improve the planning level and scheme rationality of large AC / DC hybrid power grids.
[0035] 2) The recommended planning schemes are obtained through two sets of verification operations, and the final scheme is determined after comprehensive evaluation of the recommended planning schemes. This can not only reduce the workload of planners, but also apply expert experience, making this method more feasible in practical applications.
[0036] 3) It can meet the requirements of short-circuit current, multi-input DC short-circuit ratio, power flow, stability calculation verification, and verification comparison with the target grid, and has high applicability. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 It is a flow chart of a method for optimizing a receiving-end power grid planning scheme based on multi-infeed short-circuit ratio verification in an embodiment;
[0038] Figure 2 This is a schematic diagram of the comprehensive evaluation process in the embodiment;
[0039] Figure 3 Schematic diagram of the key indicator system for safety assessment of AC / DC hybrid systems in DC-intensive areas in the embodiment. DETAILED DESCRIPTION
[0040] The present invention is described in detail below in conjunction with the accompanying drawings and specific embodiments. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work should belong to the scope of protection of the present invention. Example
[0041] The multi-infeed short-circuit ratio is one of the important indicators to measure the strength and mutual influence of a multi-DC-fed AC system, and can be used as an auxiliary for the planning and optimization of power grids containing multiple DCs. Based on this, the present invention takes the calculation of the multi-infeed short-circuit ratio as the core of the planning scheme optimization work, and provides a receiving-end power grid planning scheme optimization method based on the multi-infeed short-circuit ratio verification, including the short-circuit current review of the AC system, the calculation of the short-circuit ratio of the DC multi-infeed, the voltage stability verification of the system after the DC feed-in, and the reactive compensation optimization configuration, etc. As a supplement to the traditional power grid planning work, it can further improve the planning level and scheme rationality of large AC / DC hybrid power grids. The scheme optimization based on the multi-infeed short-circuit ratio verification proposed in the present invention, together with the traditional power grid planning method, jointly forms a number of recommended schemes, and further carries out a comprehensive evaluation of the scheme, combining technical and economic feasibility, implementation feasibility and other policies, environment and other factors, and after expert review and comprehensive decision-making, gives the final power grid planning optimization scheme.
[0042] Specifically, Figure 1 The work flow shown in the figure, the receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification provided by the present invention comprises the following steps:
[0043] 1. First, obtain the basic grid planning steps
[0044] Determine the receiving power grid to be optimized and obtain its basic power grid planning scheme. The basic power grid planning scheme includes the collected planning base year and target year data, including base year power supply, load, and grid data, target year planned power supply, predicted load, and new substation site selection, etc.
[0045] 2. After obtaining the basic grid planning scheme, two sets of verification processes are performed on the scheme at the same time. The first is to perform the short-circuit verification step, the power flow analysis step and the stability verification step in sequence to obtain the result of the first scheme. The second is to perform the multi-input short-circuit ratio verification step at the same time to obtain the result of the second scheme.
[0046] 3. Determine whether the results obtained from the two sets of verification processes meet the actual planning requirements. If so, the output is used as the recommended solution, and the final solution is obtained after the next evaluation operation. Otherwise, the solution is adjusted. The adjustment steps still follow the short-circuit verification step, power flow analysis step, and stability verification step or multi-input short-circuit ratio verification step.
[0047] For the first set of verification operations, the specific contents are:
[0048] 1) Short circuit verification steps
[0049] Short-circuit verification refers to the calculation and verification of short-circuit current for the relevant basic power grid planning scheme to determine whether the equipment safety requirements within the upper limit of the switch interrupting capacity are met under full startup, full wiring or specific operation mode. Short-circuit current verification includes three-phase and single-phase short-circuit current. The influence of DC component and voltage coefficient value can also be considered as needed. Attention should be paid to the influence of wind power and photovoltaic grid-connected inverters, flexible DC converters and filters, etc.
[0050] 2) Steps of power flow analysis
[0051] The power flow analysis step is to calculate and analyze the typical power flow mode of the target year of the planned power grid, which generally includes four typical modes: summer peak / trough and winter peak / trough. Specific modes such as waist load, peak load regulation, and new energy generation can also be considered as needed. The main purpose is to check the rationality of the power flow distribution of the normal power grid and after N-1 and N-2 faults, as well as whether the power flow of local lines, main transformers and receiving sections exceeds the limit.
[0052] 3) Stability verification steps
[0053] Planning the calculation and verification of the safety and stability of the power grid after fault disturbances, in general, considers the system power angle stability, frequency stability, and voltage stability under three-phase short-circuit grounding faults, and can further verify the system stability under small disturbances according to research needs. Combined with the new situation of large-scale grid connection of new energy such as wind power and photovoltaic power, AC and DC hybrid operation, calculation and verification of system frequency stability, broadband or low-frequency oscillation after new energy faults are disconnected from the grid, as well as safety and stability verification under the interactive influence of AC and DC faults are carried out.
[0054] For the second set of verification operations, the specific contents are:
[0055] 1) DC model construction
[0056] According to the type, capacity and main control method of the DC built or planned in the power grid, a DC model and parameters suitable for multi-infeed short-circuit ratio calculation are established and filled in the power grid simulation data file.
[0057] 2) Calculation of effective short-circuit ratio of multiple infeeds
[0058] According to research needs, the DC multi-infeed effective short circuit ratio (Multi Effective Short Circuit Ratio, MESCR) is calculated for different typical operating modes, different grid schemes and specific conditions, and the calculation results are statistically analyzed.
[0059] 3) Evaluation of effective short-circuit ratio of multiple infeeds
[0060] It is generally believed that the standard for dividing the strength of multi-infeed AC and DC systems is: extremely weak system: MESCR < 2, weak system: 2 ≤ MESCR < 3, strong system: MESCR ≥ 3. The strength of the planned power grid system or the advantages and disadvantages of each planning scheme are evaluated based on the calculation results.
[0061] Furthermore, in the second set of verification operations, taking into account the verification needs of the receiving-end power grid with multiple DC centralized feeds, the short-circuit circuit verification step, the short-circuit ratio calculation step, and the voltage stability verification after a DC fault can also be introduced after the multiple-feed short-circuit ratio verification step.
[0062] In the present invention, if the result of any one of the two sets of verification operations does not meet the requirements, it is necessary to perform the scheme adjustment step:
[0063] Adjustments shall be made to the grid planning schemes that do not meet the relevant requirements, including but not limited to the following aspects: adjusting the line or main connection topology, adding (reducing) or replacing lines / transformers, adding (reducing) shunt capacitors / shunt reactors / series reactors / STATCOM and other equipment, optimizing the DC point / unit access scheme, installing small reactors / resistors at the neutral point of the main transformer, adjusting the electrical partitions and power supply range, etc. The purpose of the scheme adjustment is to control the short-circuit current level not to exceed the standard, the power flow distribution is reasonable and does not exceed the limit, the reactive local balance voltage does not exceed the limit, and the system can maintain or recover to a stable state after a fault.
[0064] For planning schemes that meet the requirements or meet the requirements after the scheme adjustment steps, they can enter the comprehensive evaluation stage. The core evaluation process is as follows: Figure 2 shown.
[0065] In the planning scheme, considering the receiving-end power grid with multiple DC feeds, different grid structures and voltage support strengths will react differently to faults in the power grid. On the one hand, disconnecting any line on the AC side will affect the converter station, that is, changes in the grid structure will change the grid structure parameters of the converter station; even under the same grid structure, different operating modes will affect the scale of power reception, thereby changing the system impedance parameters; in addition, commutation failures, lockouts and other faults at the receiving-end converter station will cause large-scale power flow transfer, thereby causing voltage fluctuations in other DC converter buses. Therefore, when planning the power grid, any new construction project needs to first conduct a preliminary screening of various situations, identify the weak links in the grid structure, and conduct detailed calculations and analysis on this basis.
[0066] Figure 2 A comprehensive evaluation flow chart of the AC / DC chain reaction of the receiving-end power grid is given. The specific evaluation steps are as follows:
[0067] Step 1: Preliminarily give the power grid plan and clarify the four typical operation modes of summer high / summer low / winter high / winter low in the planning year;
[0068] Step 2: Calculate the conventional power flow of each mode and the power flow distribution after N-1 fault occurs, and check the transient safety and stability of the system;
[0069] Step 3: Calculate the multi-infeed effective short-circuit ratio MESCR of the DC system under each mode;
[0070] Step 4: Calculate the impact of AC grid disconnection on MESCR, and select the top three AC lines with the highest impact on the existing DC MESCR after disconnection of the AC lines;
[0071] Step 5: By checking the DC forced commutation failure, lockout and other faults, and comparing other DC commutation failures and AC voltage fluctuations, select the DC projects with greater impact;
[0072] Step 6: Strengthen the grid structure and voltage support capacity of the receiving end by adding AC lines, phase regulators or SVG reactive compensation equipment;
[0073] Step 7: Review and calculate the reinforced grid, check the N-1 safety stability under each mode, and recalculate the MESCR under each mode;
[0074] Step 8: Compare the MESCR after grid reinforcement and the voltage fluctuation after DC fault, select the top three schemes with the highest MESCR increase and the top three schemes with the highest voltage fluctuation reduction as the comparison schemes, use the evaluation method to compare the index weights, and conduct a comprehensive evaluation of each optimization scheme;
[0075] Step 9: Provide the best recommended solution based on comprehensive evaluation to guide the planning and construction of the receiving power grid.
[0076] Furthermore, when conducting AC / DC system evaluation, it is necessary to establish an AC / DC chain reaction evaluation index system for the receiving power grid, and consider incorporating multiple infeed short-circuit ratios into the evaluation indexes. The establishment of the index system should take into account both the actual operation of the power system and the difficulty and feasibility of data acquisition and the post-processing and calculation of the data. Therefore, the establishment of the evaluation index system needs to meet the following principles:
[0077] 1) Consistency with the purpose of evaluation. The report studies a series of characteristics of the power grid to evaluate whether the AC and DC faults in the receiving power grid will cause a chain reaction. To be more specific, it is to find the weak links in the power grid or the nodes with strong coupling relationships. For AC power grids, static and transient stability are two important aspects; for DC, the coupling coefficient between DC and the short-circuit ratio of multiple inputs are important considerations. Therefore, the evaluation of the chain reaction of the receiving power grid constructs a comprehensive evaluation index system based on static and transient stability and AC / DC hybrid indicators.
[0078] 2) Ease of obtaining evaluation data. When evaluating the AC and DC chain reaction of power grids, the feasibility of the evaluation indicators should be considered, the selected indicators should be easy to quantify, and the quantitative data of the indicators should be easy to obtain.
[0079] 3) Independence of each indicator. The evaluation indicators should be independent of each other, without overlap, and each indicator should not interfere with each other in the evaluation of the AC / DC chain reaction of the power grid, so that the evaluation results obtained are more scientific and objective.
[0080] The safety and stability assessment of the power system includes static safety analysis and transient safety analysis. The static safety analysis of the power system is an important part of the power system safety analysis and one of the basic issues to be considered in the planning and operation of the power system. Its task is to study the state of the system after individual system components exit operation under a specific operation mode. Its purpose is to verify whether the system can operate safely under a given power generation operation mode and system wiring mode, that is, whether there are overloaded components or nodes with too low voltage and the resulting cascading failures. Static safety analysis mainly includes two parts: line overload analysis and voltage over-limit analysis. With the development of the system, the problems of static voltage collapse and cascading failures have gradually become prominent. The transient safety analysis of the power system is to study whether the interconnected power grid can remain stable after a fault occurs. There are many kinds of faults, such as three-phase short circuit faults, three-phase short circuit single-phase refusal to operate faults, single-pole and double-pole locking faults of DC lines, etc. These serious faults will have a huge impact on the system.
[0081] The reliability assessment of AC power grid at home and abroad mainly considers static safety and transient stability comprehensively, and extracts characteristic quantities from voltage, frequency and power angle to characterize the system state. In the safety consideration, N-1 check and N-2 check are necessary.
[0082] According to the research of relevant scholars and institutions, in general, static safety evaluation indicators can include: static N-1 pass rate, static N-2 pass rate, voltage deviation pass rate, line flow pass rate, short-circuit current pass rate; transient stability evaluation indicators can include: transient N-1 pass rate, transient N-2 pass rate, flow transfer ratio, etc.; specific evaluation indicators of AC / DC hybrid power grids include: short-circuit ratio, multi-input interaction factor, transient voltage support strength, commutation failure coefficient, etc.
[0083] Taking Shanghai and even the Yangtze River Delta region as an example, AC and DC have a great influence on each other, and the AC and DC chain reaction fault transmission will lead to more severe system risks. Therefore, it is the key content of building a comprehensive evaluation index system for planned power grids to comprehensively consider system application indicators and grid operation requirements, sort out key factors affecting system safety and stability, and evaluate grid structure, frequency requirements, reactive power support capacity, and line flow transfer. Combining the research results of various aspects, for AC and DC hybrid systems in DC-intensive areas, the key indicator system for safety evaluation is as follows: Figure 3 As shown. The key indicator system for safety assessment includes grid structure indicators, low-frequency load reduction requirements, reactive power support capacity indicators and line flow transfer indicators, operation mode arrangement, low-frequency load reduction requirements. Each power grid has its own specific requirements and principles, which can be determined according to the power grid under study. Among them, grid structure indicators include static N-1, N-2 qualified rates, operation mode arrangement and multi-feed short-circuit ratio; low-frequency load reduction requirements include low-frequency load reduction requirements; reactive power support capacity indicators include multi-feed interaction factors, voltage deviation qualified rate and commutation failure coefficient; flow transfer indicators include flow uniformity and flow transfer ratio.
[0084] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person familiar with the technical field can easily think of various equivalent modifications or substitutions within the technical scope disclosed by the present invention, and these modifications or substitutions should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope of the claims.
Claims
1. A receiving-end power grid planning optimization method based on multi-infeed short-circuit ratio verification, characterized in that: include: Determine the receiving power grid to be optimized and obtain the basic power grid planning scheme of the receiving power grid to be optimized; Two sets of verification processes are performed on the basic power grid planning scheme at the same time to obtain two sets of scheme results; wherein the first verification process includes a short-circuit verification step, a power flow analysis step, and a stability verification step performed in sequence; the second verification process includes a multi-infeed short-circuit ratio verification step; The two sets of scheme results obtained by verification are judged to see whether they meet the actual planning requirements. If so, the corresponding scheme results are used as the recommended planning scheme, and the final scheme is obtained after the next evaluation operation. Otherwise, the scheme results obtained by verification are adjusted to obtain the recommended planning scheme that meets the actual planning requirements. Perform comprehensive evaluation on recommended planning schemes that meet actual planning requirements to obtain the final planning scheme; The second verification process further includes a short-circuit current verification step, a short-circuit ratio calculation step, and a voltage stability verification step after a DC fault, which are arranged after the multi-infeed short-circuit ratio verification step; The specific content of the second verification process is: According to the type, capacity and main control mode of the DC power grid that has been built or is planned to be built, establish the DC model and parameters for multi-infeed short-circuit ratio calculation and fill them into the power grid simulation data file; Calculate the DC multi-infeed effective short-circuit ratio MESCR for different typical operation modes, different grid schemes and specific conditions, and statistically analyze the calculation results; The strength of multi-infeed AC / DC systems is divided into the following standard categories: extremely weak system: MESCR<2, weak system: 2≤MESCR<3, strong system: MESCR≥3. The strength of the planned power grid system or the pros and cons of each planning scheme is evaluated based on the calculation results.
2. The receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification according to claim 1 is characterized in that: The specific contents of the short circuit verification step are: The short-circuit current verification step is performed on the basic power grid planning scheme to determine whether it meets the equipment safety requirements within the upper limit of the switch breaking capacity when fully powered on, fully connected or in a specific operating mode. The short-circuit current verification includes three-phase and single-phase short-circuit current verification, or DC component and voltage coefficient value verification.
3. The receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification according to claim 1 is characterized in that: The adjustment steps of the scheme adjustment follow the short-circuit verification step, the power flow analysis step and the stability verification step, or the multi-input short-circuit ratio verification step, which are performed in sequence.
4. The receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification according to claim 3 is characterized in that: The power flow analysis steps include judging the rationality of power flow distribution under normal conditions in four typical modes: summer peak, summer trough, winter peak, and winter trough, and after N-1 and N-2 faults.
5. The receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification according to claim 4 is characterized in that: The content of the scheme adjustment includes but is not limited to: adjusting the line or main connection topology, increasing, decreasing or replacing lines, increasing, decreasing or replacing transformers, increasing or decreasing parallel capacitors, increasing or decreasing parallel reactors, increasing or decreasing series reactors, increasing or decreasing STATCOM, optimizing DC landing points, optimizing unit access schemes, installing small reactors at the neutral point of the main transformer, installing resistors, and adjusting electrical partitions and power supply ranges.
6. The receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification according to claim 5 is characterized in that: Perform a comprehensive assessment of the recommended planning schemes for actual planning requirements, and obtain the specific contents of the final planning scheme as follows: 1) A preliminary grid plan is given to clarify the four typical operation modes of summer peak, summer trough, winter peak and winter trough in the planning year; 2) Calculate the conventional power flow of each mode and the power flow distribution after N-1 fault occurs, and verify the transient safety and stability of the system; 3) Calculate the multi-infeed effective short-circuit ratio MESCR of the DC system under various modes; 4) Calculate the impact of AC grid disconnection on MESCR, and select the AC lines with the highest impact on the existing DC MESCR after disconnection of the AC lines; 5) By forcing DC commutation failure and lockout fault, and comparing other DC commutation failures and AC voltage fluctuations, we can screen out DC projects with greater impact; 6) Strengthen the grid structure and voltage support capacity of the receiving-end power grid by adding AC lines, phase regulators or SVG reactive compensation equipment; 7) Strengthen the grid to conduct review calculations, check the N-1 safety stability under various modes, and recalculate the MESCR under various modes; 8) Compare the MESCR after grid reinforcement and the voltage fluctuation after DC fault, select the comparison scheme, use the evaluation method to compare the index weights, and conduct a comprehensive evaluation of each optimization scheme; 9) Provide the best recommended solution based on comprehensive evaluation to guide the planning and construction of the receiving power grid.
7. The receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification according to claim 6 is characterized in that: In step 4), the top three AC lines in terms of impact on the existing DC MESCR after disconnecting the AC line are selected.
8. The receiving-end power grid planning scheme optimization method based on multi-infeed short-circuit ratio verification according to claim 6 is characterized in that: In step 8), the top three schemes ranked by MESCR increase value and the top three schemes ranked by voltage fluctuation reduction are selected as the comparison schemes.