Reaction preloading construction method and system for super-large zero-block support of cable-stayed bridge in water area
By using the anchoring method of pre-embedded fine-rolled rebar on the pier top and the double-walled steel cofferdam in the water area cable-stayed bridge, combined with the synchronous loading of through-core jacks, the problem of reaction force prediction of the super-large zero-block bracket of the water area cable-stayed bridge is solved. The problem of weak anchorage and construction risks of pressure was eliminated, and efficient and safe preloading construction was achieved.
Patent Information
- Application Number
- CN202111543262.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-16
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2041-12-16
AI Technical Summary
The reaction force preloading of the super-large zero-block bracket of the cable-stayed bridge in the water area has problems such as weak anchorage and high construction risks due to the influence of the construction environment. The traditional stacking preloading method is cumbersome and time-consuming, making it difficult to efficiently complete the preloading task.
The precision-rolled rebar is embedded in the pier top and anchored in the pier body. A reaction frame is installed, and a steel strand is installed at the front end of the reaction frame to anchor it to the double-walled steel cofferdam in the water. The reaction frame is synchronously raised using through-core jack equipment. Press down the No. 0 block bracket to achieve preloading purpose.
It simplifies the construction process, reduces construction risks, improves construction efficiency, ensures stable preloading of the zero-block bracket, and is easy to install and disassemble. It is suitable for a variety of scenarios and reduces safety hazards.
Smart Images

Figure CN114214919B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a reaction force preloading construction method and system for an extra-large zero-block support of a cable-stayed bridge in waters, and belongs to the field of bridge construction. Background Art
[0002] The low-tower cable-stayed bridge is also called the "partial cable-stayed bridge". It is a new type of bridge structure between the continuous beam bridge and the cable-stayed bridge. Because it has the characteristics of both cable-stayed bridges and continuous beam bridges and the characteristics of combining rigidity and flexibility, it conforms to the structural force characteristics. Therefore, it has the advantages of economy, beautiful appearance, high rigidity, and easy construction. It has great development potential and has been fully used in high-speed railway construction.
[0003] The beams of some cable-stayed bridges are generally concrete beams, which have high requirements for cross-sectional stiffness. Generally, the cross-sectional size of the No. 0 block is large and the volume of concrete is large. It is precisely because of this feature that it is difficult to pre-stress the No. 0 block support during water construction.
[0004] The common pre-stressing method of the support is stacking pre-stressing. This pre-stressing method has complicated procedures, is time-consuming and labor-intensive, and has high construction risks. It greatly slows down the construction progress and increases the construction cost.
[0005] With the development of bridge technology, a tooling and corresponding construction procedures have emerged for pre-stressing the reaction frame by using a jack on the bracket installed on the zero block. However, due to the influence of the construction environment, direct use of this method for cable-stayed bridges in waters has the problem of insufficient anchoring distance for the installation of the reaction frame, resulting in loose anchoring and high risk of construction on the water surface. Therefore, there are still many difficulties to be solved in the reaction pre-stressing of the super-large zero block bracket of cable-stayed bridges in waters. Summary of the invention
[0006] In order to address the deficiencies in the prior art, the present invention provides a reaction preloading construction method and system for an extra-large No. 0 block support of a cable-stayed bridge in water areas. Pre-embedded fine-rolled threaded steel bars are anchored in the pier body on the pier top, a reaction frame is installed, and a steel strand is installed at the front end of the reaction frame and anchored in the double-walled steel cofferdam in water. The No. 0 block support is pressed down by synchronously pushing up the reaction frame with a jack device to achieve the purpose of preloading. The method and system have the advantages of simple installation, convenient disassembly, high versatility, wide application and reduced safety risks.
[0007] The technical solution adopted by the present invention to solve the technical problem is: a reaction force preloading construction method for an oversized zero-block support of a water area cable-stayed bridge is provided, comprising the following steps:
[0008] S1. Pre-embedded parts for bracket installation: a set of steel pipe pile column feet are embedded on the uncast foundation, anchor bars are set on the embedded pile heads of the steel pipe pile column feet, climbing cone embedded parts are embedded on the side of the pier body, and fine-rolled threaded steel bars are embedded on the top of the pier body;
[0009] S2. Extension of the support steel pipe pile: After the foundation is poured, the steel pipe pile is extended, and a steel pipe connection system is installed on the side of the steel pipe pile. After the steel pipe pile is poured with micro-expansion concrete, the supporting wall steel pipe is installed through the climbing cone embedded parts and the steel pipe connection system;
[0010] S3. Install the steel pipe diagonal brace: install the steel pipe outer diagonal brace and the steel pipe inner diagonal brace on the upper side of the steel pipe pile;
[0011] S4. Laying the distribution longitudinal beam: a horizontal square hole is opened on the top of the steel pipe pile, and the distribution longitudinal beam is passed through the square hole. The top ends of the steel pipe outer diagonal brace and the steel pipe inner diagonal brace are respectively welded to the bottom ends of the distribution longitudinal beam;
[0012] S5. Laying load-bearing beams: Laying a group of load-bearing beams on the distribution longitudinal beams, setting unloading blocks between the load-bearing beams and the distribution longitudinal beams, and welding the contact positions with each other;
[0013] S6. Laying the longitudinal beams of the lower reaction frame and the longitudinal and transverse beams of the reaction frame: laying a set of longitudinal beams of the lower reaction frame on the load-bearing transverse beams, and then laying the transverse beams of the reaction frame on the longitudinal beams of the lower reaction frame;
[0014] S7. Install the tensioning unit: install a set of through-type jacks above the crossbeam of the reaction frame;
[0015] S8. Laying the upper reaction frame longitudinal beam: Install the upper reaction frame longitudinal beam above the through-type jack;
[0016] S9. Install cofferdam anchors and cofferdam pressure beams: Install cofferdam anchors on the cofferdam as lower end anchor points;
[0017] S10, installing the combined compression beams; installing a group of combined compression beams on the longitudinal beams of the upper reaction frame, wherein the combined compression beams located within the pier body are anchored by the precision-rolled threaded steel bars pre-buried on the top of the pier body, and the combined compression beams located at the ends of the longitudinal beams of the upper reaction frame are anchored on the cofferdam by the steel strands connected to the cofferdam anchoring device;
[0018] S11, pre-tightening steel strands and finished rolled threaded steel: pre-tightening steel strands and finished rolled threaded steel respectively;
[0019] S12. The whole is preloaded by synchronously tensioning the through-type jack, and graded preload loading is adopted.
[0020] In step S1, the climbing cone embedded part installed at the end of the buttress steel pipe includes climbing cone embedded part plates connected to each other and climbing cone nuts and bolts are provided at the end of the connecting screw rod.
[0021] In step S4, after the distribution longitudinal beam is passed through the square hole of the steel pipe pile, a steel plate is used to block the gap between the steel pipe pile and the distribution longitudinal beam.
[0022] In step S9, the cofferdam anchoring pressure beam and the anchoring plate in the cofferdam anchoring device are connected via a pin, and the anchoring plate and the cofferdam are connected by welding.
[0023] In step S12, the graded preloading includes the following process: monitoring and recording the displacement of each monitoring point at intervals of 6 hours, and when the difference in the average displacement value monitored for 12 consecutive hours is not greater than 2 mm, unloading is performed to observe the preloading deformation data.
[0024] The present invention also provides a reaction prestressing system for an oversized zero-block support of a water area cable-stayed bridge based on the above-mentioned construction method, comprising steel pipe piles distributed on both sides of the pier body, the steel pipe piles being fixed to the side of the pier body through a group of buttress steel pipes from top to bottom, the buttress steel pipes being connected to the steel pipe piles through a steel pipe connection system installed on the side of the steel pipe piles, and being connected to the pier body through a climbing cone embedded part embedded in the side of the pier body, a horizontal square hole being opened on the top of the steel pipe pile, a distribution longitudinal beam passing through the square hole, the bottoms of both ends of the distribution longitudinal beam being respectively connected to the tops of the steel pipe outer diagonal brace and the steel pipe inner diagonal brace, the steel pipe outer diagonal brace and the steel pipe inner diagonal brace The bottom is fixed to the side of the steel pipe pile, a group of load-bearing beams are laid on the distribution longitudinal beams, a group of lower reaction frame longitudinal beams are laid on the load-bearing beams, a group of reaction frame beams are laid on the lower reaction frame longitudinal beams, the reaction frame longitudinal beams are laid above the reaction frame beams through through-type jacks, and combined pressure beams are installed at both ends of the reaction frame longitudinal beams. The combined pressure beams located within the pier body are anchored by the fine-rolled threaded steel embedded in the top of the pier body, and the combined pressure beams located at the ends of the upper reaction frame longitudinal beams are anchored on the cofferdam through steel strands connected to the cofferdam anchoring device, and the bottom of the steel strands are fixed to the cofferdam through the cofferdam anchoring device.
[0025] The climbing cone embedded part comprises mutually connected climbing cone embedded part plates and a connecting screw rod, and the end of the connecting screw rod is provided with a climbing cone nut and a bolt.
[0026] The cofferdam anchoring device comprises a cofferdam anchoring pressure beam and an anchoring plate connected with the cofferdam anchoring pressure beam through a pin shaft, and the anchoring plate is welded to the cofferdam.
[0027] The beneficial effects of the present invention based on its technical solution are:
[0028] (1) The present invention replaces the traditional preloading method by using a through-type jack to load synchronously, thereby solving the shortcomings of the traditional preloading construction method, such as complex procedures, high lifting risks, and low work efficiency;
[0029] (2) The present invention solves the problems of weak anchorage and stress risk in the installation of large-scale zero-block water construction counter-pressure frames by using the double-wall cofferdam wall as the anchor point of the counter-pressure frame;
[0030] (3) The present invention fixes the bracket by combining pre-embedded climbing cones with steel plates, which is convenient for accurate fixation, reduces the impact on the appearance of the pier concrete, and provides convenience for subsequent dismantling. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 A cross-sectional schematic diagram of the reaction preloading construction method of the super-large zero-block support of a water area cable-stayed bridge provided by an embodiment of the present invention.
[0032] Figure 2 A top view of the reaction preloading construction method state of the super-large zero-block support of a water area cable-stayed bridge provided by an embodiment of the present invention.
[0033] Figure 3 Schematic diagram of the steel pipe pile diagonal bracing structure.
[0034] Figure 4 Schematic diagram of the cofferdam anchoring structure.
[0035] In the figure: 1-steel pipe pile, 2-steel pipe outer diagonal brace, 21-steel pipe inner diagonal brace, 3-supporting wall steel pipe, 4-steel pipe connection system, 5-distribution longitudinal beam, 6-load-bearing cross beam, 6a-unloading block, 7-lower reaction frame longitudinal beam, 8-reaction frame cross beam, 9-through-type jack, 10-upper reaction frame longitudinal beam, 11-combined pressure beam, 12-embedded climbing cone pre-embedded parts, 121-climbing nut, 122-connecting screw rod, 123-climbing cone embedded plate, 124-bolt, 13-cofferdam anchoring structure, 131-cofferdam anchoring pressure beam, 132-pin shaft, 133-anchor plate, 14-fine-rolled threaded steel, 15-steel strand, 16-anchoring reinforcement, 17-cap, 18-pier body. DETAILED DESCRIPTION
[0036] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0037] The present invention provides a reaction force preloading construction method for an oversized zero-block support of a water area cable-stayed bridge, referring to Figures 1 to 4 , including the following steps:
[0038] S1. Install embedded parts on the bracket: 6 steel pipe pile column feet are embedded on the uncast foundation 17, and anchor bars 16 are set on the embedded pile heads of the steel pipe pile column feet. When constructing the pier body, a climbing cone embedded part 12 is embedded on the side of the pier body 18. The climbing cone embedded part includes a climbing cone embedded part plate 123 connected to each other and a climbing cone nut 121 and a bolt 124 are provided at the end of the connecting screw rod 122. During the pier body concrete construction, a φ32 finely rolled threaded steel bar 14 is embedded at the top of the pier body;
[0039] S2. Extension of the support steel pipe pile: After the foundation is poured, the steel pipe pile 1 is extended, and the steel pipe connection system 4 is installed on the side of the steel pipe pile. After C50 micro-expansion concrete is poured into the steel pipe pile, the supporting wall steel pipe 3 is installed through the climbing cone embedded parts and the steel pipe connection system;
[0040] S3, installing the steel pipe diagonal brace: the diagonal brace components are processed in advance, and the steel pipe outer diagonal brace 2 and the steel pipe inner diagonal brace 21 are installed on the upper side of the steel pipe pile;
[0041] S4, laying distribution longitudinal beams: a horizontal square hole is opened on the top of each steel pipe pile, and the distribution longitudinal beam 5 is inserted into the square hole. A steel plate is used to block the gap between the steel pipe pile and the distribution longitudinal beam, and the top of the steel pipe outer diagonal brace and the steel pipe inner diagonal brace are respectively welded to the bottom of both ends of the distribution longitudinal beam;
[0042] S5. Laying load-bearing beams: laying 6 load-bearing beams 6 on the distribution longitudinal beams, setting unloading blocks 6a between the load-bearing beams 5 and the distribution longitudinal beams 6, and welding the contact positions with each other;
[0043] S6. Laying the longitudinal beams of the lower reaction frame and the longitudinal and transverse beams of the reaction frame: laying a set of longitudinal beams 7 of the lower reaction frame on the load-bearing transverse beams, and then laying the transverse beams 8 of the reaction frame on the longitudinal beams of the lower reaction frame;
[0044] S7, install the tensioning unit: install a set of through-type jacks 9 above the reaction frame beam as a tensioning unit, and set 9 through-type jacks on one side, for a total of 18;
[0045] S8. Laying the upper reaction frame longitudinal beams: Install four upper reaction frame longitudinal beams 10 above the through-type jack;
[0046] S9, installing cofferdam anchors and cofferdam pressure beams: installing the cofferdam anchor device 13 as the lower end anchor point on the double-walled steel cofferdam, the cofferdam anchor pressure beam 131 is connected to the anchor plate 133 through the pin 132, and the anchor plate 133 is connected to the cofferdam by welding;
[0047] S10, installing the combined compression beams; installing a group of combined compression beams 11 on the longitudinal beams of the upper reaction frame, arranging three on one side, wherein the combined compression beams located within the pier body are anchored by the finely rolled threaded steel bars pre-buried on the top of the pier body, and the combined compression beams located at the ends of the longitudinal beams of the upper reaction frame are anchored on the cofferdam by the steel strands 15 connected to the cofferdam anchoring device;
[0048] S11, pre-tightening steel strands and finished rolled threaded steel: pre-tightening steel strands and finished rolled threaded steel respectively;
[0049] S12. Perform overall preloading by synchronously tensioning the through-hole jack, adopt graded preloading loading, monitor and record the displacement of each monitoring point at intervals of 6 hours, and only when the difference in the average displacement value monitored for 12 consecutive hours is no more than 2mm, can unloading work be carried out and preloading deformation data be observed.
[0050] The present invention also provides a reaction prestressing system for an oversized zero-block support of a cable-stayed bridge in waters based on the above-mentioned construction method, comprising steel pipe piles distributed on both sides of the pier body, the steel pipe piles being fixed to the side of the pier body by a group of supporting wall steel pipes from top to bottom, a horizontal square hole being opened on the top of the steel pipe pile, a distribution longitudinal beam passing through the square hole, the bottoms of both ends of the distribution longitudinal beam being respectively connected to the tops of the steel pipe outer diagonal brace and the steel pipe inner diagonal brace, the bottoms of the steel pipe outer diagonal brace and the steel pipe inner diagonal brace being fixed to the side of the steel pipe pile, a group of load-bearing crossbeams being laid on the distribution longitudinal beams, a group of lower reaction frame longitudinal beams being laid on the load-bearing crossbeams, a group of reaction frame crossbeams being laid on the lower reaction frame longitudinal beams, and the reaction frame longitudinal beams being laid above the reaction frame crossbeams by through-type jacks.
[0051] The jacks are set above the intersections of the 2nd, 4th, 5th and 7th anti-pressure longitudinal beams and anti-pressure cross beams. Jacks are set at each intersection, and multiple jacks are used for synchronous loading and preloading. The reaction frame is a standard component processed in the factory and transported to the construction site. After that, the reaction preloading system is formed by pre-embedded fine-rolled threaded steel on the top of the pier and anchoring the anchor beam and steel strands installed in the cofferdam. According to the simulation calculation, the specifications of the rear anchor steel strands designed and installed according to the stress position of the zero block are 10×φ15.2mm steel strands for the middle 2 bundles and 5×φ15.2mm steel strands for the surrounding 4 bundles.
[0052] Combined compression beams are installed at both ends of the reaction frame longitudinal beam. The combined compression beam located within the pier body is anchored by the fine-rolled threaded steel bars pre-embedded in the top of the pier body, and the combined compression beam located at the end of the upper reaction frame longitudinal beam is anchored on the cofferdam by a steel strand connected to the cofferdam anchoring device.
[0053] The material of the distribution longitudinal beam 5 is 3I56a. Before pouring concrete on the steel pipe pile 1, the distribution longitudinal beam 5 must be installed first. The material of the load-bearing longitudinal beam 6 is 2I56a. Before installing the load-bearing longitudinal beam 6, the unloading block 6a made of 4I20a must be laid first. The contact part between the distribution longitudinal beam 5 and the steel pipe pile 1 is welded with four-sided corner welds, and the weld angle height hf=8mm.
[0054] The buttress steel pipe is connected to the steel pipe piles through the steel pipe connection system installed on the side of the steel pipe piles, and is also connected to the pier body through the climbing cone embedded parts embedded in the side of the pier body.
[0055] The climbing cone embedded part comprises mutually connected climbing cone embedded part plates and a connecting screw rod, and the end of the connecting screw rod is provided with a climbing cone nut and a bolt.
[0056] The bottom of the steel strand is fixed to the cofferdam through a cofferdam anchoring device.
[0057] The cofferdam anchoring device comprises a cofferdam anchoring pressure beam and an anchoring plate connected with the cofferdam anchoring pressure beam through a pin shaft, and the anchoring plate is welded to the cofferdam.
[0058] The present invention provides a reaction preloading construction method and system for an extra-large No. 0 block support of a cable-stayed bridge in water areas. The method comprises the following steps: pre-embedding fine-rolled threaded steel bars on the pier top and anchoring them in the pier body; installing a reaction frame; and installing a steel strand at the front end of the reaction frame and anchoring it in a double-walled steel cofferdam in water. The reaction frame is synchronously pushed up by a jack device to press down the No. 0 block support to achieve the purpose of preloading, thereby solving the problem of insufficient anchoring distance of large No. 0 blocks in water. The method has the advantages of simple installation, convenient disassembly, high versatility, wide application and reduced safety risks.
Claims
1. A reaction force preloading construction method for super-large zero-block bracket of a water cable-stayed bridge, Features The following steps are involved: S1. Pre-embedded parts for bracket installation: a group of steel pipe pile column feet are pre-embedded on the uncast foundation (17), anchor bars (16) are arranged on the pre-embedded pile heads of the steel pipe pile column feet, climbing cone pre-embedded parts (12) are pre-embedded on the side of the pier body (18), and fine-rolled threaded steel (14) is embedded on the top of the pier body; the climbing cone pre-embedded parts installed at the end of the supporting wall steel pipe include climbing cone embedded parts plates (123) connected to each other and the ends of the connecting screw rods (122) are provided with climbing cone nuts (121) and bolts (124); S2, extension of the support steel pipe pile: after the foundation is poured, the steel pipe pile (1) is extended, a steel pipe connection system (4) is installed on the side of the steel pipe pile, and after micro-expansion concrete is poured into the steel pipe pile, the supporting wall steel pipe (3) is installed through the climbing cone embedded parts and the steel pipe connection system; S3, installing the steel pipe diagonal brace: installing the steel pipe outer diagonal brace (2) and the steel pipe inner diagonal brace (21) on the upper side of the steel pipe pile; S4, laying the distribution longitudinal beam: a horizontal square hole is opened on the top of the steel pipe pile, the distribution longitudinal beam (5) is inserted into the square hole, and the top ends of the steel pipe outer diagonal brace and the steel pipe inner diagonal brace are respectively welded to the bottom ends of the distribution longitudinal beam; S5. Laying load-bearing crossbeams: laying a group of load-bearing crossbeams (6) on the distribution longitudinal beams, setting unloading blocks (6a) between the load-bearing crossbeams and the distribution longitudinal beams, and welding the contact positions thereof; S6. Laying the longitudinal beams of the lower reaction frame and the longitudinal and transverse beams of the reaction frame: laying a set of longitudinal beams of the lower reaction frame (7) on the load-bearing transverse beams, and then laying the transverse beams of the reaction frame (8) above the longitudinal beams of the lower reaction frame; S7, installing the tensioning unit: installing a set of through-type jacks (9) above the reaction frame beam; S8. Laying the upper reaction frame longitudinal beam: Install the upper reaction frame longitudinal beam (10) above the through-type jack; S9, installing the cofferdam anchor and the cofferdam pressure beam: installing the cofferdam anchor device (13) on the cofferdam as a lower end anchor point; S10, installing the combined pressure beams; installing a group of combined pressure beams (11) on the longitudinal beams of the upper reaction frame, wherein the combined pressure beams located within the pier body are anchored by the finely rolled threaded steel bars pre-buried on the top of the pier body, and the combined pressure beams located at the ends of the longitudinal beams of the upper reaction frame are anchored on the cofferdam by steel strands (15) connected to the cofferdam anchoring device; S11, pre-tightening steel strands and finished rolled threaded steel: pre-tightening steel strands and finished rolled threaded steel respectively; S12. The whole is preloaded by synchronously tensioning the through-type jack, and graded preload loading is adopted.
2. The reaction preloading construction method of the super-large zero-block support of the water area cable-stayed bridge according to claim 1, Features: In step S4, after the distribution longitudinal beam is passed through the square hole of the steel pipe pile, a steel plate is used to block the gap between the steel pipe pile and the distribution longitudinal beam.
3. The reaction force preloading construction method of the super-large zero-block support of the water area cable-stayed bridge according to claim 1, Features: In step S9, the cofferdam anchoring pressure beam (131) and the anchoring plate (133) in the cofferdam anchoring device are connected via a pin shaft (132), and the anchoring plate (133) and the cofferdam are connected by welding.
4. The reaction preloading construction method of the super-large zero-block support of the water area cable-stayed bridge according to claim 1, Features: In step S12, the graded preloading includes the following process: monitoring and recording the displacement of each monitoring point at intervals of 6 hours, and when the difference in the average displacement value monitored for 12 consecutive hours is not greater than 2 mm, unloading is performed to observe the preloading deformation data.
5. A reaction force preloading system for super-large zero-block brackets of a water area cable-stayed bridge based on the construction method of claim 1, Features: It includes steel pipe piles distributed on both sides of the pier body. The steel pipe piles are fixed to the side of the pier body through a group of buttress steel pipes from top to bottom. The buttress steel pipes are connected to the steel pipe piles through the steel pipe connection system installed on the side of the steel pipe piles, and are connected to the pier body through the climbing cone embedded parts pre-buried on the side of the pier body. A horizontal square hole is opened on the top of the steel pipe pile, and the distribution longitudinal beam runs through the square hole. The bottoms of both ends of the distribution longitudinal beam are respectively connected to the tops of the steel pipe outer diagonal brace and the steel pipe inner diagonal brace. The bottoms of the steel pipe outer diagonal brace and the steel pipe inner diagonal brace are fixed to the side of the steel pipe pile. The distribution longitudinal beam is paved on the top of the distribution longitudinal beam. A group of load-bearing crossbeams is provided, a group of lower reaction frame longitudinal beams is laid on the load-bearing crossbeams, a group of reaction frame crossbeams is laid on the lower reaction frame longitudinal beams, the reaction frame longitudinal beams are laid above the reaction frame crossbeams through through-type jacks, and combined pressure beams are installed at both ends of the reaction frame longitudinal beams. The combined pressure beams located within the pier body are anchored by precision-rolled threaded steel bars pre-embedded in the top of the pier body, and the combined pressure beams located at the ends of the upper reaction frame longitudinal beams are anchored on the cofferdam through steel strands connected to the cofferdam anchoring device, and the bottom of the steel strands are fixed to the cofferdam through the cofferdam anchoring device.
6. The reaction force preloading system for the super-large zero-block support of the water area cable-stayed bridge according to claim 5, Features: The climbing cone embedded part comprises mutually connected climbing cone embedded part plates and a connecting screw rod, and the end of the connecting screw rod is provided with a climbing cone nut and a bolt.
7. The reaction force preloading system for the super-large zero-block support of a water area cable-stayed bridge according to claim 5, Features: The cofferdam anchoring device comprises a cofferdam anchoring pressure beam and an anchoring plate connected with the cofferdam anchoring pressure beam through a pin shaft, and the anchoring plate is welded to the cofferdam.
Citation Information
Patent Citations
Prepressing construction device of cantilever box beam No.0 block and prepressing construction method thereof
CN105040598A
Underwater continuous beam bridge pier 0# block bracket pre-pressing structure
CN108193605A
Counter-force pre-pressing system and pre-pressing method for ultrahigh cantilever beam 0 # block support
CN111794127A
Counter-force pre-pressing method and tool for zero block bracket of double-limb thin-wall pier
CN112160255A
0 # block bracket of deepwater bare rock framed bent pier continuous rigid frame girder bridge and pre-pressing device of 0 # block bracket
CN113123241A