A method for constructing a standard duration calculation system for system-level power outage maintenance plan
The system-level power outage maintenance plan standard duration calculation system addresses the inefficiency in maintenance duration determination by using a seven-layer structure and historical data optimization to generate rational maintenance durations, enhancing maintenance efficiency and reducing resource waste.
Patent Information
- Application Number
- CN202111524856.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-14
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2041-12-14
AI Technical Summary
Power companies lack a scientific basis for determining the duration of maintenance plans, often relying on experience, leading to inefficient resource allocation and prolonged maintenance periods.
A method for constructing a system-level power outage maintenance plan standard duration calculation system, utilizing a seven-layer structure to generate standard durations based on historical maintenance data, optimizing formulas, and applying coefficients to determine maintenance durations for equipment types without historical data.
This method scientifically determines maintenance durations, reducing resource waste and improving efficiency by providing a rational basis for maintenance plan evaluation and review.
Smart Images

Figure CN114418292B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of electric power maintenance, and in particular relates to a method for constructing a standard duration calculation system for a system-level power outage maintenance plan. Background Art
[0002] The maintenance period is an important indicator for evaluating the workload of the maintenance plan. When applying for a power outage maintenance plan, the power company needs to fill in the start time, end time and maintenance period of the maintenance plan. The maintenance period is directly related to the length of the maintenance plan execution period (end time minus start time). Many regions directly report and review the length of the maintenance plan execution period as the maintenance period.
[0003] When power companies declare and review maintenance plans, they can often scientifically arrange when the power outage maintenance plan will be implemented from the perspectives of power grid safety and economy. However, due to the lack of scientific theoretical basis, they can only rely on experience or historical maintenance period information to declare and review the execution length and maintenance period of the power outage maintenance plan. If the equipment has no historical maintenance information for reference, it can only rely on experience. In order to avoid insufficient maintenance plan duration, the duration declared based on experience is often much longer than the actual required duration, resulting in a waste of resources and reducing the work efficiency of maintenance business. Summary of the invention
[0004] In order to address the deficiencies in the prior art, the present invention provides a method for constructing a standard duration calculation system for a system-level power outage maintenance plan, which can scientifically and reasonably determine the maintenance duration of different maintenance types, especially the standard duration of equipment-related maintenance types without historical data support, thereby avoiding resource waste caused by unreasonable duration setting and improving maintenance efficiency.
[0005] To achieve the above-mentioned purpose, the technical solution adopted by the present invention is: a method for constructing a system-level power outage maintenance plan standard duration calculation system, including: a. defining the duration benchmark values of various types of equipment in the system layer by layer according to the four dimensions of region, equipment type, voltage level, and equipment capacity, and constructing the first five layers of the system-level power outage maintenance plan standard duration calculation system; b. based on the first five layers of the structure, generating a maintenance type layer as the sixth layer according to the maintenance type, and generating the initial benchmark value of each unit set using the historical maintenance duration information; c. generating the different maintenance types within each unit set using the historical maintenance duration information. 1. The standard construction period calculation formula based on the construction period benchmark value; 2. Modify the construction period benchmark value within each unit set based on the historical maintenance construction period information and the standard construction period calculation formula; 3. Take the minimum total absolute value of the difference between the historical maintenance construction period of each equipment in the unit set and the calculated standard construction period of each type as the optimization goal, and optimize and iterate to generate the optimal formula and optimal benchmark value within the unit set; 4. Use the standard construction period calculation formula of the adjacent unit set to simulate the standard construction period calculation formula for the maintenance type that does not have historical maintenance construction period information in this unit set, and complete the construction of the seventh formula layer of the system-level power outage maintenance plan standard construction period calculation system.
[0006] Furthermore, the first five layers of the structure of the standard duration calculation system for the system-level power outage maintenance plan are, respectively, the regional layer, the equipment type layer, the voltage level layer, the equipment capacity layer, and the benchmark value layer; among them, equipment belonging to the same category shares the same duration benchmark value, and the set of equipment using the same duration benchmark value is a unit set.
[0007] Furthermore, the maintenance type layer classifies the existing historical maintenance duration information of the equipment within the unit set according to maintenance types, and the maintenance types include major maintenance, medium maintenance, minor maintenance, Class A maintenance and Class B maintenance.
[0008] Furthermore, the initial benchmark value adopts the average duration of the maintenance type with the largest number of historical maintenance times.
[0009] Furthermore, the historical construction period values of each equipment under the same maintenance type are used as the sample space to simulate and generate the standard construction period calculation formula: T = f(G), where T is the construction period and G is the benchmark value.
[0010] Furthermore, in the unit set, using the existing formulas corresponding to each maintenance type and the historical maintenance period of each equipment, the formula Solve the sample benchmark value of each device, calculate the average value of all sample benchmark values in the unit set, and use this value as the new benchmark value of this unit set.
[0011] Furthermore, the optimization objective is to minimize the absolute sum of the differences between the historical maintenance duration of all equipment in the unit set and the calculated standard duration of the corresponding maintenance type. The optimization objective calculation formula is as follows:
[0012]
[0013] Where N is the number of devices in the unit set, H is the number of historical maintenance times of the device, and T ij历史 is a historical maintenance period of the equipment, T ij标准 The standard construction period calculated by the formula corresponding to the maintenance type of the historical maintenance plan of the equipment.
[0014] Furthermore, after the optimal formulas and optimal benchmark values are generated within all cell sets, for the maintenance types in the cell set that have no historical maintenance duration information, an adjacent cell set with the same maintenance type that has generated a standard duration calculation formula is selected, and another maintenance type with formulas generated on both sides is selected from the two cell sets as a template formula; in the adjacent cells, the coefficient of the difference between the formula parameters of the maintenance type and the formula parameters of the template maintenance type is calculated, and then these coefficients are used to correct the formula parameters of the template maintenance type in the cell set to generate a standard duration calculation formula corresponding to the maintenance type that has no historical maintenance duration information.
[0015] Compared with the prior art, the present invention has the following beneficial effects:
[0016] (1) The present invention makes full use of the historical maintenance duration information in the system to construct a system-level power outage maintenance plan standard duration calculation system. It scientifically generates standard durations for equipment-related maintenance types that are not supported by historical data through feature extraction and other methods. It can scientifically and reasonably determine the maintenance durations of different maintenance types, thereby avoiding resource waste caused by unreasonable duration setting and improving maintenance efficiency.
[0017] (2) It provides a new evaluation standard for the rationality of the maintenance plan duration in addition to the historical average duration, enriches the maintenance plan duration evaluation system, and improves the scientific nature of maintenance plan submission and review. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of a system-level power outage maintenance plan standard duration calculation system constructed by an embodiment of the present invention;
[0019] Figure 2 It is a flowchart of an embodiment of the present invention for constructing a system for calculating a standard duration of a system-level power outage maintenance plan. DETAILED DESCRIPTION
[0020] The present invention will be further described below in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection scope of the present invention.
[0021] A method for constructing a standard construction period calculation system for a system-level power outage maintenance plan comprises: defining construction period benchmark values of various types of equipment in the system in accordance with four dimensions of region, equipment type, voltage level and equipment capacity, and constructing the first five layers of the structure of the standard construction period calculation system for a system-level power outage maintenance plan; based on the first five layers of the structure, generating a maintenance type layer as the sixth layer according to the maintenance type, and generating initial benchmark values of various unit sets by using historical maintenance construction period information; generating standard construction period calculation formulas based on construction period benchmark values for different maintenance types within each unit set by using historical maintenance construction period information; correcting construction period benchmark values within each unit set based on historical maintenance construction period information and standard construction period calculation formulas; taking the minimum total absolute value of the difference between the historical maintenance construction period of each equipment in the unit set and the calculated standard construction period of various types as the optimization target, optimizing and iterating to generate the optimal formula and optimal benchmark value within the unit set; using the standard construction period calculation formula of the adjacent unit set to simulate and generate the standard construction period calculation formula of the maintenance type without historical maintenance construction period information in the unit set, and completing the construction of the seventh formula layer of the standard construction period calculation system for a system-level power outage maintenance plan.
[0022] This embodiment uses the historical maintenance duration of some equipment and constructs a system-level power outage maintenance plan standard duration calculation system through feature extraction. The system includes seven layers: regional layer, equipment type layer, voltage level layer, equipment capacity layer, benchmark value layer, maintenance type layer, and formula layer. This calculation system can automatically generate standard durations for various types of maintenance for all equipment in the system. This embodiment can generate standard durations for equipment-related maintenance types that are not supported by historical data, and can scientifically and reasonably determine maintenance durations for different maintenance types, thereby avoiding waste of resources due to unreasonable duration settings, while improving maintenance efficiency; at the same time, it provides a scientific basis for the declaration and review of maintenance plans. Figure 1 , Figure 2 As shown, this method includes the following six steps.
[0023] Step 1: Define the construction period benchmark values for each type of equipment in the system layer by layer according to the four dimensions of region, equipment type, voltage level, and equipment capacity, and build the first five layers of the system-level power outage maintenance plan standard construction period calculation system.
[0024] All the equipment in the system is classified layer by layer according to the four dimensions of region, equipment type, voltage level, and equipment capacity. Equipment belonging to the same minimum classification shares the same construction period reference value, thereby generating the upper five-layer structure of the region layer, equipment type layer, voltage level layer, equipment capacity layer, and reference value layer in the standard construction period calculation system of the system-level power outage maintenance plan. The region layer is divided according to the jurisdiction of the maintenance area; the equipment type layer includes conventional physical equipment type classifications such as units, transformers, busbars, switches, etc.; the voltage level layer is the voltage level of the power grid where the equipment is located, and the equipment type with multiple voltage levels (such as transformers) takes the highest voltage level; the equipment capacity layer is the rated capacity of the equipment itself. If the equipment has no rated capacity information, it is uniformly set to 0. Define the set of equipment that uses the same construction period reference value as a unit set.
[0025] Step 2: Based on the first five layers of structure, the maintenance type layer is generated as the sixth layer of structure according to the maintenance type, and the initial benchmark value of each unit set is generated using the historical maintenance duration information.
[0026] This embodiment adopts the classification of maintenance work content commonly used by power companies as the sixth maintenance type layer of the system-level power outage maintenance plan standard duration calculation system, and uses historical maintenance duration information to generate initial reference values for each unit set. The classification of maintenance work content commonly used by power companies (such as major repairs, medium repairs, minor repairs, Class A maintenance, Class B maintenance, etc.) constructs the sixth maintenance type layer of the power outage maintenance plan standard duration calculation system. The historical maintenance duration information of the equipment inside the unit set is classified according to the maintenance type, and the number of historical maintenances and the average duration of each maintenance type are counted, and the average duration of the maintenance type with the most historical maintenance times is selected as the initial reference value. Take the unit set of region A, 110kV, 300MW as an example, assuming that the historical number of A-level maintenance of all equipment in the unit set is 100, and the average duration is 600; the historical number of B-level maintenance is 50, and the average duration is 400; the historical number of C-level maintenance is 10, and the average duration is 200, and there is no historical maintenance of other maintenance types. Then the initial benchmark value of the unit set of region A, 110kV, 300MW is the average duration of the A-level maintenance with the most historical maintenance times, which is 600.
[0027] Step 3: Use historical maintenance duration information to generate standard duration calculation formulas for different maintenance types within each unit set based on duration benchmark values.
[0028] Taking the historical duration values of each equipment under the same maintenance type as the sample space, simulate and generate the standard duration calculation formula: T=f(G), where T is the duration and G is the reference value. Formulas of the same type (template formulas) are preferred for simulation analysis in the same unit set. For individual maintenance type samples that cannot be simulated with template formulas, similar high-order template formulas are used for simulation. Taking the unit set of region A, 110kV, 300MW as an example, assume that the template formula is a first-order formula T=aG+b, where a and b are formula coefficients. Artificial neural networks and other methods can be used to solve the formula coefficients that are closest to the historical maintenance duration sample data. After the simulation is completed, the formula layer in the unit set is as follows (example):
[0029]
[0030] Step 4: Modify the construction period baseline value within each unit set based on historical maintenance construction period information and standard construction period calculation formula.
[0031] In the unit set, using the existing formulas corresponding to each maintenance type and the historical maintenance period of each equipment, the inverse formula Solve the sample benchmark value of each device, calculate the average of all sample benchmark values in the unit set, and use this value as the new benchmark value of this unit set. Taking the unit set of region A, 110kV, 300MW as an example, the inverse formula of the formula layer in the unit set is:
[0032]
[0033] Put the historical maintenance period information of each equipment into the corresponding inverse formula to calculate the G corresponding to each historical maintenance i , calculate all G in the unit set i The average It is the new benchmark value for the unit set of region A, 110kV, 300MW.
[0034] Step 5: Taking the minimum sum of the absolute values of the differences between the historical maintenance duration of each equipment in the unit set and the calculated standard durations as the optimization goal, the optimal formula and optimal benchmark value within the unit set are generated through optimization iteration.
[0035] The optimization goal is to minimize the absolute sum of the differences between the historical maintenance duration of all equipment in the unit set and the calculated standard duration of the corresponding maintenance type. The optimization goal calculation formula is as follows:
[0036]
[0037] Where N is the number of devices in the unit set, H is the number of historical maintenance times of the device, and T ij历史 is a historical maintenance period of the equipment, T ij标准The standard construction period calculated by the formula corresponding to the maintenance type of the historical maintenance plan of the equipment.
[0038] Steps 3 and 4 are iterated until the formula and benchmark value that meet the optimization goal are obtained, and they are used as the optimal formula and optimal benchmark value within the unit set. Using this method, the optimal formula and optimal benchmark value of each unit set are calculated one by one.
[0039] Step 6: Use the standard duration calculation formula of the adjacent unit set to simulate the standard duration calculation formula for the maintenance type in this unit set that has no historical maintenance duration information, and complete the construction of the seventh formula layer of the system-level power outage maintenance plan standard duration calculation system.
[0040] After the optimal formula and optimal benchmark value are generated within all unit sets, for the maintenance types that do not have historical maintenance duration information in this unit set, select an adjacent unit set with the same maintenance type that has generated a standard duration calculation formula, and select another maintenance type that has generated formulas on both sides in the two unit sets as a template formula. In the adjacent cells, calculate the coefficient of the difference between the formula parameters of the maintenance type and the formula parameters of the template maintenance type, and then use these coefficients to correct the formula parameters of the template maintenance type in this unit set to generate the standard duration calculation formula corresponding to the maintenance type that does not have historical maintenance duration information. Using this method, the standard duration calculation formula corresponding to the maintenance type that does not have historical maintenance duration information in all unit sets can be generated, thereby completing the construction of the seventh formula layer of the standard duration calculation system for the system-level power outage maintenance plan. The same type of maintenance in the same unit set uses the same standard maintenance duration. Using this technical system, the standard duration of all types of maintenance for all equipment can be directly calculated. An example of the method for generating the standard duration calculation formula corresponding to the maintenance type that does not have historical maintenance duration information is as follows:
[0041] Take the unit set A of region A, 110kV, 300MW and the unit set B of region B, 110kV, 300MW as examples, assuming that the formula of unit set A is as follows:
[0042]
[0043] The formula for the adjacent cell set B is as follows:
[0044]
[0045] Find the standard construction period calculation formula T=aG+b for level D maintenance in unit set A.
[0046] Select the formula for level B maintenance that has been generated in both unit set A and unit set B as the template formula. In unit set B, calculate the coefficient of difference between the formula parameters for level D maintenance and the formula parameters for level B maintenance. Then use these coefficients to modify the formula parameters of level B maintenance in unit set A, a = 0.5*R a =0.25, b=100*R b = 20, and the standard duration calculation formula T for D-level maintenance without historical maintenance duration information is obtained. D Level maintenance = 0.25*G+20.
[0047] This embodiment makes full use of the historical maintenance duration information in the system to build a system-level power outage maintenance plan standard duration calculation system, and scientifically generates standard durations for equipment-related maintenance types that are not supported by historical data through feature extraction and other methods. It can scientifically and reasonably determine the maintenance duration of different maintenance types, thereby avoiding resource waste caused by unreasonable duration setting and improving maintenance efficiency. This embodiment also provides a new maintenance plan duration rationality evaluation standard in addition to the historical average duration, enriches the maintenance plan duration evaluation system, and improves the scientific nature of maintenance plan declaration and review.
[0048] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for constructing a system for calculating the standard duration of a system-level power outage maintenance plan, characterized in that: include: a. Define the construction period benchmark values of each type of equipment in the system layer by layer according to the four dimensions of region, equipment type, voltage level, and equipment capacity, and build the first five layers of the system-level power outage maintenance plan standard construction period calculation system; b. Based on the first five layers of structure, the maintenance type layer is generated as the sixth layer of structure according to the maintenance type, and the initial benchmark value of each unit set is generated using the historical maintenance duration information; c. Use historical maintenance duration information to generate standard duration calculation formulas based on duration benchmark values for different maintenance types within each unit set; d. Based on the historical maintenance duration information and the standard duration calculation formula, the duration benchmark value within each unit set is modified; e. Taking the minimum sum of the absolute values of the differences between the historical maintenance duration of each equipment in the unit set and the calculated standard duration of each type as the optimization goal, the optimal formula and optimal benchmark value within the unit set are generated through optimization iteration; f. Use the standard duration calculation formula of the adjacent unit set to simulate the standard duration calculation formula of the maintenance type that does not have historical maintenance duration information in the current unit set, and complete the construction of the seventh formula layer of the system-level power outage maintenance plan standard duration calculation system; The first five layers of the system-level power outage maintenance plan standard duration calculation system are, in order, the regional layer, the equipment type layer, the voltage level layer, the equipment capacity layer, and the reference value layer; the equipment belonging to the same category shares the same duration reference value, and the set of equipment using the same duration reference value is a unit set; The maintenance type layer classifies the historical maintenance duration information of the equipment within the unit set according to the maintenance type, and the maintenance type includes major maintenance, medium maintenance, minor maintenance, Class A maintenance and Class B maintenance; After the optimal formulas and optimal benchmark values within all unit sets are generated, for the maintenance types that do not have historical maintenance duration information in this unit set, select an adjacent unit set with the same maintenance type that has generated a standard duration calculation formula, and select another maintenance type that has generated formulas on both sides from the two unit sets as a template formula; in the adjacent unit sets, calculate the coefficient of the difference between the formula parameters of the maintenance type and the formula parameters of the template maintenance type, and then use these coefficients to correct the formula parameters of the template maintenance type in this unit set to generate a standard duration calculation formula corresponding to the maintenance type that does not have historical maintenance duration information.
2. The method for constructing a system-level power outage maintenance plan standard duration calculation system according to claim 1, characterized in that: The initial benchmark value adopts the average duration of the maintenance type with the most maintenance times in history.
3. The method for constructing a system-level power outage maintenance plan standard duration calculation system according to claim 1, characterized in that: Taking the historical duration values of each equipment under the same maintenance type as the sample space, the standard duration calculation formula is simulated and generated: ,in For the construction period, is the baseline value.
4. The method for constructing a system-level power outage maintenance plan standard duration calculation system according to claim 1, characterized in that: In the unit set, use the existing formulas corresponding to each maintenance type and the historical maintenance period of each equipment, and use the formula Solve the sample benchmark value of each device, calculate the average value of all sample benchmark values in the unit set, and use this value as the new benchmark value of this unit set.
5. The method for constructing a system-level power outage maintenance plan standard duration calculation system according to claim 1, characterized in that: The optimization goal is to minimize the absolute sum of the differences between the historical maintenance duration of all equipment in the unit set and the calculated standard duration of the corresponding maintenance type. The optimization goal calculation formula is as follows: ; in, is the number of devices in the cell set, is the historical maintenance times of the equipment, is a historical maintenance period of the equipment. The standard construction period calculated by the formula corresponding to the maintenance type of the historical maintenance plan of the equipment.
Citation Information
Patent Citations
Power-cut construction period judgment method based on historical data statistics
CN106845802A
Overhaul period optimization method for intelligent substation protection system
CN110110933A
Overhaul plan making method and system for power transmission equipment
CN111612170A
Optimization method and device of power distribution network maintenance power failure mode, terminal and storage medium
CN113191575A
Identifying troubleshooting options for resolving network failures
US20150271008A1