Intelligent safety control method and system for substation infrastructure based on precise positioning technology
By adopting precise positioning technology and neural network models at the substation infrastructure site, positioning and monitoring operators and construction equipment in real time, generating electronic fences and early warning areas, the problem of difficulty in safety control on site of substation infrastructure is solved, and efficient safety control and accidents are achieved Early warning improves construction safety.
Patent Information
- Application Number
- CN202210119336.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-02-08
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2042-02-08
AI Technical Summary
The site safety control of substation infrastructure is difficult and wide, resulting in poor control effects of operating personnel and construction vehicles, and poses safety hazards.
Using intelligent safety control method for substation infrastructure based on precise positioning technology, by dividing dangerous areas in the three-dimensional model, positioning workers and construction equipment in real time, generating electronic fences and early warning areas, outputting alarm information, improving safety control effect, and combining with neural networks The model accurately segments and warnings the lifting equipment, monitors the body temperature and sweat data of the operators, and realizes a warning for heat stroke.
Effectively reduce accidents, improve construction safety, enhance safety control effects on operators and construction equipment, realize real-time positioning and trajectory analysis, and improve the level of safe production.
Smart Images

Figure CN114494630B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of power monitoring, and in particular to a method and system for intelligent safety management and control of substation infrastructure based on precise positioning technology. Background Art
[0002] Substations are an important part of the power system. With the continuous improvement of my country's economic level and energy demand, the number and overall scale of substations have grown rapidly.
[0003] Many construction operations of substations require a large number of personnel. Since substations are relatively special and important places, they have high requirements on the professional skills and quality of construction workers. With the rapid expansion of the scale of power grid construction, higher requirements are placed on safe production. However, at present, the safety management and control work at the substation infrastructure site is multi-point and wide-ranging, which makes it difficult to control the workers and construction vehicles and the safety management and control effect is poor. Summary of the invention
[0004] In order to improve the safety management and control effect, the present application provides a substation infrastructure intelligent safety management method and system based on precise positioning technology.
[0005] In the first aspect, the present application provides a method for intelligent safety management and control of substation infrastructure based on precise positioning technology, which adopts the following technical solutions:
[0006] The intelligent safety control method of substation infrastructure based on precise positioning technology includes the following steps:
[0007] According to the design drawings, build a 3D basic model of the substation in 3D, establish an information database of the substation, and form a visual 3D model based on the 3D basic model and the information database;
[0008] Divide the corresponding danger zone on the three-dimensional model according to the live equipment in the information database, and generate the first electronic fence and boundary warning zone around the danger zone;
[0009] Acquire first position information of the operator and second position information of the construction equipment;
[0010] Mapping the first position information and the second position information to a three-dimensional model for display;
[0011] It is determined whether the first location information and the second location information are within the first electronic fence or the boundary warning area. If so, the corresponding alarm information will be output.
[0012] By adopting the above technical solution, a visual three-dimensional model of the substation is established, and dangerous areas are divided according to live equipment. By real-time positioning and capturing of operating personnel and construction equipment, when the operating personnel and construction equipment enter the first electronic fence or boundary warning area, an alarm message is sent to the corresponding personnel to remind the corresponding personnel, so as to achieve safety management and control of the operating personnel and construction equipment, and display the situation of the operating personnel and construction equipment in a visual three-dimensional model to improve the safety management and control effect.
[0013] Preferably, the method of determining whether the first location information and the second location information are within the first electronic fence or the boundary warning area, and if so, outputting the corresponding warning information, further includes:
[0014] Determine whether the construction equipment is in a moving state according to the second position information, and if so, establish a fence area for the construction equipment according to the equipment number, and update the fence area in real time according to the second position information;
[0015] It is determined whether the first position information is within the fence area. If so, a first warning signal is sent to the operator of the construction equipment and the corresponding operating personnel.
[0016] By adopting the above technical solution, when the construction equipment is in a moving state, a fenced area is established around the construction equipment. When a worker enters the fenced area, a first warning signal is sent to the operator of the construction equipment and the worker, which can reduce the occurrence of accidents and further improve the safety management and control effect.
[0017] Preferably, the construction equipment includes a hoisting device, and the determining whether the first location information and the second location information are within the first electronic fence or the boundary warning area, and if so, outputting the corresponding warning information, further includes:
[0018] Obtaining the original image of the hoisted object; inputting the original image into the neural network model to obtain a contour image;
[0019] Establishing the outer area of the hoisted object based on the contour image;
[0020] Obtain the hoisting height of the hoisted object and the top height of the boom in real time;
[0021] A viewing cone is established according to the external area, the hoisting height and the vertex height, wherein the vertex of the boom is used as the vertex of the viewing cone;
[0022] Analyze the view cone to obtain the hoisting area, and build a second electronic fence around the hoisting area;
[0023] It is determined whether the first position information is within the second electronic fence. If so, a second warning signal is sent to the operator of the hoisting equipment and the corresponding operating personnel.
[0024] Preferably, the step of inputting the original image into the neural network model to obtain the contour image comprises:
[0025] The original image is input into CNN, and CNN extracts features from the original image to obtain a feature map;
[0026] Generate anchor boxes through RPN and select the corresponding number of anchor boxes to form proposal windows;
[0027] Map the proposed window to the feature map of the last layer of CNN, and use the RoI Align layer to generate a fixed-size RoI feature map for each proposed window;
[0028] The fully connected layer is used to classify RoI and regress the bounding box, and the mask of each RoI is generated through FCN, which is segmented to obtain the contour image.
[0029] By adopting the above technical solution, the original image of the hoisted object is segmented using a neural network model to obtain a more accurate contour image. When the hoisting equipment is hoisting the corresponding object, by establishing a corresponding hoisting area, when the operator enters the hoisting area, a second warning signal is sent to the operator and the operator of the hoisting equipment to remind the corresponding personnel, reduce collisions and injuries caused by falling objects, and improve construction safety. The hoisting area is updated according to the hoisting height of the hoisted object, that is, as the hoisting height increases, the hoisting area increases, making the setting of the hoisting area more reasonable.
[0030] Preferably, the method of determining whether the first location information and the second location information are within the first electronic fence or the boundary warning area, and if so, outputting the corresponding warning information, further includes:
[0031] Obtain the sweat volume and Na+ content of the workers detected in multiple time periods, and draw a sweat curve according to the sweat volume and Na+ content;
[0032] Obtain the temperature data of the operators detected in multiple periods, and draw a temperature curve based on the temperature data;
[0033] The sweat curve and body temperature curve are identified. If the sweat curve shows a trend of rising and then falling, while the body temperature curve shows an upward trend and the body temperature reaches the warning temperature, a health warning signal is sent to the operator and manager.
[0034] By adopting the above technical solution, in a high-temperature working environment, the temperature data and sweat data of the operators are checked. If the temperature data and sweat data are abnormal, the operators are at risk of heat stroke, and health warning signals are sent to the operators and managers, which can further improve the safety management effect. Because the symptoms of heat stroke cause confusion in the sweat gland system, the sweat secretion is high before heat stroke, but after heat stroke, the sweat secretion is less. Therefore, the sweating situation is recorded, and the sweat curve is drawn, and then combined with the body temperature for comprehensive judgment, it can play a better role in heat stroke warning.
[0035] Preferably, after mapping the first position information and the second position information to the three-dimensional model for display, the method further includes:
[0036] The first location information and the second location information are stored to form a historical track;
[0037] receiving a query request, wherein the query request includes a target object and a time period;
[0038] The historical track to be replayed is determined based on the query request, the playback time is determined, and the historical track points corresponding to the time of the historical track to be replayed are displayed at a preset display time interval in the order of the time, and the historical track is replayed in the three-dimensional model.
[0039] By adopting the above technical solution, it is possible to query the historical trajectory of the target object and time period, and to realize the backtracking and analysis of the subsequent operation trajectory through real-time positioning and trajectory tracking of the operating personnel or construction equipment.
[0040] In the second aspect, this application provides a substation infrastructure intelligent safety management and control system based on precise positioning technology, which adopts the following technical solutions:
[0041] The intelligent safety management and control system for substation infrastructure based on precise positioning technology includes:
[0042] 3D building module: used to build a 3D basic model of the substation in 3D according to the design drawings, establish an information database of the substation, and form a visual 3D model based on the 3D basic model and the information database;
[0043] Division generation module: used to divide the corresponding dangerous areas on the three-dimensional model according to the live equipment in the information database, and generate the first electronic fence and boundary warning area around the dangerous area;
[0044] Acquisition module: used to acquire the first position information of the operator and the second position information of the construction equipment;
[0045] Mapping display module: used to map the first position information and the second position information into a three-dimensional model for display;
[0046] The judgment and alarm module is used to judge whether the first location information and the second location information are within the first electronic fence or the boundary warning area. If so, the corresponding alarm information will be output.
[0047] By adopting the above technical solution, a visual three-dimensional model of the substation is established, and dangerous areas are divided according to live equipment. By real-time positioning and capturing of operating personnel and construction equipment, when the operating personnel and construction equipment enter the first electronic fence or boundary warning area, an alarm message is sent to the corresponding personnel to remind the corresponding personnel, so as to achieve safety management and control of the operating personnel and construction equipment, and display the situation of the operating personnel and construction equipment in a visual three-dimensional model to improve the safety management and control effect.
[0048] In a third aspect, the present application provides a computer device, which adopts the following technical solution:
[0049] A computer device comprises a memory and a processor, wherein the memory stores a computer program that can be loaded by the processor and execute any one of the above methods.
[0050] In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution:
[0051] A computer-readable storage medium stores a computer program that can be loaded by a processor and execute any one of the above methods.
[0052] In summary, the present application includes at least one of the following beneficial technical effects:
[0053] 1. By real-time positioning and capturing of operators and construction equipment, when operators and construction equipment approach dangerous areas, warning information is sent to relevant personnel to remind them, so as to achieve safety management and control of operators and construction equipment, thereby improving the safety management and control effect;
[0054] 2. Establish a fenced area around the construction equipment. When the operator enters the fenced area, the first warning signal is sent to the operator of the construction equipment and the operator, which can reduce the occurrence of accidents;
[0055] 3. By establishing corresponding hoisting areas, when workers enter the hoisting areas, a second warning signal is sent to the workers and the operators of the hoisting equipment to remind the corresponding personnel, reduce collisions and injuries caused by falling objects, and improve construction safety;
[0056] 4. By recording the sweating situation and drawing the sweat curve, and then making a comprehensive judgment based on the body temperature, it can play a better role in early warning of heat stroke;
[0057] 5. Through real-time positioning and trajectory tracking of operating personnel or construction equipment, the subsequent operation trajectory can be traced back and analyzed. BRIEF DESCRIPTION OF THE DRAWINGS
[0058] Figure 1 This is a flow chart of a method for intelligent safety control of substation infrastructure based on precise positioning technology in one embodiment of the present application;
[0059] Figure 2 is a flow chart of a method for intelligent safety management and control of substation infrastructure based on precise positioning technology in another embodiment of the present application;
[0060] Figure 3 is a schematic diagram of the external area in this application;
[0061] Figure 4 is a schematic diagram of the viewing cone in this application. DETAILED DESCRIPTION
[0062] In order to make the purpose, technical solutions and advantages of this application more clear, the following Figure 1-4 It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0063] The present application embodiment discloses a method for intelligent safety control of substation infrastructure based on precise positioning technology, referring to Figure 1 , including the following steps:
[0064] S1: According to the design drawings, build a 3D basic model of the substation in 3D, establish an information database of the substation, and form a visual 3D model based on the 3D basic model and the information database.
[0065] Specifically, the information database includes equipment component information, equipment coding information, equipment connection information, voltage level information, pipeline cable information and GIS equipment online monitoring data.
[0066] S2: Divide corresponding danger zones on the three-dimensional model according to the energized equipment in the information database, and generate a first electronic fence and a boundary warning zone around the danger zone.
[0067] Specifically, the Beidou technology is combined with the three-dimensional model to locate the equipment and facilities of the substation. The substation is divided into regions in the three-dimensional model, where the area where the live equipment is located is divided into dangerous areas.
[0068] S3: Acquire the first position information of the operator and the second position information of the construction equipment.
[0069] Specifically, the workers wear safety helmets with corresponding numbers. The safety helmets are equipped with cameras, 5G communication modules and alarm devices. The workers are positioned and captured in real time through the Beidou system and 5G communication module to obtain the workers' location information, i.e., the first location information.
[0070] The construction machinery is installed with Beidou vehicle-mounted positioning terminal and numbered according to different equipment. The Beidou vehicle-mounted positioning terminal is used to locate and capture the construction machinery in real time to obtain the location information of the construction machinery, that is, the second location information.
[0071] S4: Map the first position information and the second position information to a three-dimensional model for display.
[0072] Specifically, the actual positions of the workers and construction equipment are associated with the display positions in the three-dimensional model. For example, if the actual position of the workers is room A of the substation, then in the three-dimensional model, the display position of the workers is room A of the substation in the three-dimensional model.
[0073] S5: Determine whether the first location information and the second location information are within the first electronic fence or boundary warning area. If so, output corresponding alarm information.
[0074] Specifically, the operating personnel and construction equipment are positioned in real time. When the operating personnel and construction equipment enter the first electronic fence or boundary warning area, an alarm message is sent to the operating personnel and the operator of the construction equipment, and the alarm device on the operating personnel's safety helmet sounds an alarm.
[0075] When the workers or construction equipment leave the first electronic fence or boundary warning area, the alarm stops. If the workers or construction equipment do not leave the danger zone, and the alarm lasts for a preset time, the management personnel will be notified to go to the site for processing.
[0076] refer to Figure 2 Optionally, after step S5, the method further includes:
[0077] S6: judging whether the construction equipment is in a moving state according to the second position information, and if so, establishing a fence area of the construction equipment according to the equipment number, and updating the fence area in real time according to the second position information.
[0078] S7: Determine whether the first position information is within the fence area, and if so, send a first warning signal to the operator of the construction equipment and corresponding workers.
[0079] Specifically, the equipment number is entered into the system. The equipment number includes the vehicle type and vehicle model. For example, the vehicle types include transport vehicles, cranes, and bulldozers. The size of the vehicle can be obtained through the vehicle model. The construction machinery is positioned in real time. Through the change in the position of the construction machinery, it can be determined whether the construction machinery is moving. When the construction machinery is moving, a fence area is established around the construction machinery, and the position of the fence area is updated according to the change in the position of the construction machinery.
[0080] The workers are positioned in real time. When the workers enter the fenced area, the construction equipment may pose a threat to the workers. At this time, the first early warning signal is sent to the workers and the operators of the construction equipment. The alarm device on the worker's safety helmet sounds an alarm, and the alarm device on the operator's safety helmet also sounds an alarm, which effectively improves the safety of construction.
[0081] In this embodiment, the height position of the operator can also be monitored in real time. When the operator climbs to the alarm height, an alarm signal is sent to the operator, and the alarm device on the operator's safety helmet sounds an alarm.
[0082] Optionally, after step S5, the method further includes:
[0083] S8: Obtain an original image of the hoisted object; input the original image into the neural network model to obtain a contour image.
[0084] S9: Establishing an outer area of the hoisted object based on the contour image.
[0085] S10: Obtain the hoisting height of the hoisted object and the top height of the boom.
[0086] S11: A viewing cone is established according to the external area, the hoisting height and the vertex height, wherein the vertex of the boom serves as the vertex of the viewing cone.
[0087] S12: Analyze the viewing cone to obtain a hoisting area, and establish a second electronic fence around the hoisting area.
[0088] S13: Determine whether the first location information is within the second electronic fence. If so, send a second warning signal to the operator of the lifting equipment and corresponding operating personnel.
[0089] Specifically, refer to Figure 3 and Figure 4, construction machinery includes lifting equipment. Whether the construction machinery can lift equipment can be obtained through the equipment number. A camera device is set on the hook, and the original image of the hoisted object is captured by the camera device; the external area is the circumscribed circle area of the hoisted object contour, and the hoisting area is the circular area of the bottom surface of the field of view cone. For example, the vertex height of the boom is H, and the hoisting height of the hoisted object is h. The diameter of the external area is obtained by identification, and then the diameter of the hoisting area is calculated based on the diameter of the external area.
[0090] A positioning device is set at the top of the hook and boom of the lifting equipment. The height of the hook is used as the lifting height of the hoisted object. The TODA and AOA positioning algorithms are used to perform positioning through the time difference and angle of signal arrival and the intersection of hyperbolas.
[0091] The hook is positioned in real time through the Beidou system to obtain the height information of the hook. The height of the hook is constantly increasing, and when the height of the hook reaches the predetermined height, the camera device is started to take pictures of the hoisted object.
[0092] Optionally, in step S8, it includes:
[0093] S81: Input the original image into CNN, and CNN extracts features from the original image to obtain a feature map.
[0094] S82: Generate anchor boxes through RPN, and select a corresponding number of anchor boxes to form a proposal window;
[0095] S83: Map the proposed window to the feature map of the last layer of CNN, and use the RoI Align layer to generate a fixed-size RoI feature map for each proposed window.
[0096] S84: Use the fully connected layer to classify RoIs and regress bounding boxes, generate a mask for each RoI through FCN, and segment to obtain a contour image.
[0097] Specifically, CNN uses a set of basic conv+relu+pooling layers to extract the feature map of the hoisted object. For example, CNN contains 13 conv layers + 13 relu layers + 4 pooling layers. The pixels of the feature map are used as feature points, and each feature point generates 9 anchor frames with different widths and heights. The anchor frames are sorted from high to low according to the intersection-over-union ratio, and the top M anchor frames are taken as proposals.
[0098] The fixed-length feature vector is mapped using the fully connected layer, and the softmax function is used to determine whether the border belongs to the background or the hoisted object, and the background border is removed. The mask information of each pixel in the image is represented by 0 and 1, where 0 represents the background and 1 represents the mask value of the corresponding pixel. The mask of each RoI is generated through FCN, that is, the contour image of the hoisted object is segmented.
[0099] Optionally, after step S5, the method further includes:
[0100] S14: Obtain the sweat volume and Na+ content of the operator detected in multiple time periods, and draw a sweat curve according to the sweat volume and Na+ content.
[0101] S15: Obtaining the body temperature data of the operator detected in multiple time periods, and drawing a body temperature curve according to the body temperature data.
[0102] S16: The sweat curve and the body temperature curve are identified. If the sweat curve shows a trend of rising and then falling, and the body temperature curve shows an upward trend and the body temperature reaches the warning temperature, a health warning signal is sent to the operator and the manager.
[0103] Specifically, the helmet is provided with a temperature sensor and a sweat test patch at the forehead of the operator. The temperature sensor detects the operator's body temperature, and the sweat test patch detects the operator's sweat. For example, the operator's body temperature and sweat are tested every 3 minutes, and the test duration is 1 minute.
[0104] For example, the detected sweat amount and Na+ content are used as sweat information and Na+ information, respectively, and the sweat information and Na+ information are transmitted to the server through the 5G communication module. The server stores the sweat information and Na+ information and draws a sweat curve.
[0105] For example, the warning temperature can be set to 37 degrees. If it is detected that the sweat curve shows a trend of rising and then falling, and the body temperature reaches 37 degrees and the body temperature curve shows an upward trend, it is judged that the operator is at risk of heat stroke.
[0106] For example, when a health warning signal is issued to the operator, the health warning signal can be sent to the alarm device on the operator's helmet, and the alarm device issues a warning in the form of voice. When a health warning signal is issued to the manager, the operator's ID and location information are sent to the manager's mobile phone in the form of text messages.
[0107] Optionally, after step S4, that is, after mapping the first position information and the second position information to the three-dimensional model for display, the method further includes:
[0108] S17: The first location information and the second location information are stored to form a historical track.
[0109] S18: Receive a query request, where the query request includes a target object and a time period.
[0110] S19: Determine the historical track to be replayed based on the query request, determine the playback time, display the historical track points corresponding to the time of the historical track to be replayed in the order of the time and at a preset display time interval, and replay the historical track in the three-dimensional model.
[0111] Specifically, the target object can be a personnel ID and a device ID, and the personnel ID and the number of the helmet are associated by inputting the personnel ID or the device ID and the time period. After receiving the query request input by the user, the historical trajectory data is obtained according to the personnel ID and the time period, wherein the time period may include a playback time interval, and the playback time interval may include a start playback time and an end playback time. For example, the user can enter the ID of the target object, the start playback time and the end playback time in the playback interface. After receiving the above information, the server can return the historical trajectory data within the time period from the start playback time to the end playback time of the target object.
[0112] The present application also discloses a substation infrastructure intelligent safety management and control system based on precise positioning technology, including:
[0113] 3D building module: used to build a 3D basic model of the substation in 3D according to the design drawings, establish an information database of the substation, and form a visual 3D model based on the 3D basic model and the information database.
[0114] Division generation module: used to divide the corresponding danger zone on the three-dimensional model according to the energized equipment in the information database, and generate the first electronic fence and boundary warning area around the danger zone.
[0115] Acquisition module: used to acquire the first position information of the operator and the second position information of the construction equipment.
[0116] Mapping display module: used to map the first position information and the second position information into a three-dimensional model for display.
[0117] The judgment and alarm module is used to judge whether the first location information and the second location information are within the first electronic fence or the boundary warning area. If so, the corresponding alarm information will be output.
[0118] For the specific definition of the intelligent safety management and control system for substation infrastructure based on precise positioning technology, please refer to the definition of the intelligent safety management and control method for substation infrastructure based on precise positioning technology in the above text, which will not be repeated here. Each module in the above-mentioned intelligent safety management and control system for substation infrastructure based on precise positioning technology can be implemented in whole or in part through software, hardware and a combination thereof. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules.
[0119] An embodiment of the present application also discloses a computer device, including a memory and a processor, wherein the memory stores a computer program that can be loaded by the processor and execute the above-mentioned intelligent safety management and control method for substation infrastructure based on precise positioning technology.
[0120] The embodiment of the present application also discloses a computer-readable storage medium storing a computer program that can be loaded by a processor and execute the above-mentioned intelligent safety management and control method for substation infrastructure based on precise positioning technology.
[0121] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application may include non-volatile and / or volatile memory. Non-volatile memory may include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory may include random access memory (RAM) or external cache memory. As an illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).
[0122] The processor in the present application may include one or more processing cores. The processor calls the data stored in the memory by running or executing the instructions, programs, code sets or instruction sets stored in the memory, and executes the various functions and processing data of the present application. The processor can be at least one of an application-specific integrated circuit (ASIC), a digital signal processor (DSP), a digital signal processing device (DSPD), a programmable logic device (PLD), a field programmable gate array (FPGA), a central processing unit (CPU), a controller, a microcontroller and a microprocessor. It is understandable that for different devices, the electronic device used to realize the above-mentioned processor function can also be other, and the embodiments of the present application are not specifically limited.
[0123] Those skilled in the art can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example. In actual applications, the above-mentioned functions can be distributed and completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above.
Claims
1. The intelligent safety management and control method of substation infrastructure based on precise positioning technology is characterized by: The following steps are involved: According to the design drawings, build a 3D basic model of the substation in 3D, establish an information database of the substation, and form a visual 3D model based on the 3D basic model and the information database; Divide the corresponding danger zone on the three-dimensional model according to the live equipment in the information database, and generate the first electronic fence and boundary warning zone around the danger zone; Acquire first position information of the operator and second position information of the construction equipment; Mapping the first position information and the second position information to a three-dimensional model for display; The height position of the operator is monitored in real time through the first position information, and when the operator is detected to have reached the alarm height, an alarm signal is sent to the operator through the alarm device on the safety helmet; it is determined whether the first position information and the second position information are within the first electronic fence or the boundary warning area, and if so, corresponding alarm information is output; Acquire an original image of the hoisted object; input the original image into the neural network model to obtain a contour image; establish an external area of the hoisted object based on the contour image; The hoisting height of the hoisted object and the vertex height of the boom are obtained in real time; a viewing cone is established according to the external area, the hoisting height and the vertex height, wherein the vertex of the boom is used as the vertex of the viewing cone; The viewing cone is analyzed to obtain the hoisting area, and a second electronic fence is established around the hoisting area; it is determined whether the first position information is within the second electronic fence, and if so, a second warning signal is sent to the operator of the hoisting equipment and the corresponding operating personnel.
2. The method according to claim 1, characterized in that: The step of determining whether the first location information and the second location information are within the first electronic fence or the boundary warning area, and if so, outputting corresponding warning information, further includes: Determine whether the construction equipment is in a moving state according to the second position information, and if so, establish a fence area for the construction equipment according to the equipment number, and update the fence area in real time according to the second position information; It is determined whether the first position information is within the fence area. If so, a first warning signal is sent to the operator of the construction equipment and the corresponding operating personnel.
3. The method according to claim 1, characterized in that The step of inputting the original image into the neural network model to obtain the contour image comprises: The original image is input into CNN, and CNN extracts features from the original image to obtain a feature map; Generate anchor boxes through RPN and select the corresponding number of anchor boxes to form proposal windows; Map the proposed window to the feature map of the last layer of CNN, and use the RoI Align layer to generate a fixed-size RoI feature map for each proposed window; The fully connected layer is used to classify RoI and regress the bounding box, and the mask of each RoI is generated through FCN, which is segmented to obtain the contour image.
4. The method according to claim 1, characterized in that: The step of determining whether the first location information and the second location information are within the first electronic fence or the boundary warning area, and if so, outputting corresponding warning information, further includes: Obtain the sweat volume and Na+ content of the workers detected in multiple time periods, and draw a sweat curve according to the sweat volume and Na+ content; Obtain the temperature data of the operators detected in multiple periods, and draw a temperature curve based on the temperature data; The sweat curve and body temperature curve are identified. If the sweat curve shows a trend of rising and then falling, while the body temperature curve shows an upward trend and the body temperature reaches the warning temperature, a health warning signal is sent to the operator and manager.
5. The method according to claim 1, characterized in that After mapping the first position information and the second position information to the three-dimensional model for display, the method further includes: The first location information and the second location information are stored to form a historical track; receiving a query request, wherein the query request includes a target object and a time period; The historical track to be replayed is determined based on the query request, the playback time is determined, and the historical track points corresponding to the time of the historical track to be replayed are displayed at a preset display time interval in the order of the time, and the historical track is replayed in the three-dimensional model.
6. A substation infrastructure intelligent safety management and control system based on precise positioning technology, used to implement the method described in any one of claims 1 to 5 above, characterized in that: include: 3D building module: used to build a 3D basic model of the substation in 3D according to the design drawings, establish an information database of the substation, and form a visual 3D model based on the 3D basic model and the information database; Division generation module: used to divide the corresponding dangerous areas on the three-dimensional model according to the live equipment in the information database, and generate the first electronic fence and boundary warning area around the dangerous area; Acquisition module: used to acquire the first position information of the operator and the second position information of the construction equipment; Mapping display module: used to map the first position information and the second position information into a three-dimensional model for display; The judgment and alarm module is used to judge whether the first location information and the second location information are within the first electronic fence or the boundary warning area. If so, the corresponding alarm information will be output.
7. A computer device, characterized in that: The method comprises a memory and a processor, wherein the memory stores a computer program which can be loaded by the processor and executes the method according to any one of claims 1 to 5.
8. A computer-readable storage medium, characterized in that: A computer program is stored which can be loaded by a processor and execute the method according to any one of claims 1 to 5.