A construction method for an open-cut shallow-buried tunnel under an existing road without interrupting traffic
The Bailey beam simply-supported girder bridge system supported by temporary abutments and the open-cut shallow burial method are used to separate road and tunnel construction, solving the problems of low safety and high cost of shallow-buried tunnels under existing road construction, and achieving safety and efficiency. The advanced construction technology reduces project costs and embodies the concept of green environmental protection.
Patent Information
- Application Number
- CN202210306001.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-03-25
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2042-03-25
AI Technical Summary
The construction safety of shallow-buried large-section tunnels under existing roads is low, and it is easy to damage the upper road structure and affect traffic safety. The construction period is long and the cost is high, making it difficult to ensure completion on schedule.
Temporary abutments are used to support Bailey beams to form a stable system for simply supported girder bridges, which separate the upper road traffic from the lower tunnel construction. Gradual excavation and backfilling are carried out through open excavation and shallow burial methods to reduce the impact on existing roads and utilize reusable Bailey beams and backfill materials reduce construction costs.
It improves the safety of roads and tunnels, shortens the construction period, avoids traffic interruptions, reduces project costs, and achieves green and sustainable construction.
Smart Images

Figure CN114575859B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of road construction, and particularly relates to a construction method for an open-cut shallow-buried tunnel passing under an existing road without interrupting traffic. Background Art
[0002] At present, the construction safety of shallow buried large-section tunnels under existing roads is low. Direct blasting and excavation can easily cause damage and destruction to the pavement structure of the existing road above, endangering the road and driving safety. It is inevitable that the traffic on the existing road will be affected during the construction period. In addition, the tunnel construction process is often affected by various unfavorable geological conditions, human-machine-material and on-site management factors, and it is impossible to ensure completion on schedule, which seriously affects the normal traffic on the existing road above, resulting in large and uncontrollable project costs. Summary of the invention
[0003] In view of this, the present invention provides a construction method for an open-cut shallow tunnel passing under an existing road without interrupting traffic, adopts a temporary abutment to support the Bailey beam to form a simply supported beam bridge stability system, separates the upper road traffic from the lower tunnel construction, thereby avoiding traffic interruption, improving the safety of existing roads and tunnels, shortening the construction period, saving construction costs, and reducing the project cost.
[0004] The present invention provides a construction method for an open-cut shallow-buried tunnel passing under an existing road without interrupting traffic. A temporary abutment is used to support a Bailey beam to form a simply supported beam bridge stability system. The system replaces the existing road and effectively connects the front and rear extension sections of the existing road to ensure smooth road traffic, separate the upper road traffic from the lower tunnel construction, and then construct the tunnel in the open-cut shallow-buried section, so as to improve the safety of the road and the tunnel and shorten the construction period.
[0005] The specific steps include:
[0006] 1) Alternately close half of the existing road, and leave the other half of the existing road open to traffic. Excavate the foundation at the beginning and end of the closed existing road, and build a temporary abutment. The temporary abutment has two steps, namely the Bailey beam support platform and the concrete structure slab support platform;
[0007] 2) If the existing road is a concrete structure, the bottom surface of the concrete structure slab support platform is flush with the bottom surface of the concrete structure slab, and the vertical height of the concrete structure slab support platform is equal to the thickness of the concrete structure slab; if the existing road is an asphalt concrete structure, the bottom surface of the concrete structure slab support platform is flush with the bottom surface of the concrete structure slab, and the vertical height of the concrete structure slab support platform is equal to the thickness of the concrete structure slab plus the thickness of the asphalt layer;
[0008] 3) The height of the Bailey beam support platform is the same as that of the Bailey beam trestle, and the width of the temporary abutment is not less than the width of the concrete structural slab;
[0009] 4) After the construction of the temporary abutment is completed and the concrete strength reaches the requirement, a Bailey beam trestle is erected on the Bailey beam support platform so that the Bailey beam trestle is flush with the bottom surface of the Bailey beam support platform, and the surface of the Bailey beam trestle is effectively connected with the existing road to meet normal traffic requirements;
[0010] 5) After the construction of the temporary abutment and the erection of the Bailey beam trestle is completed, the concrete structure slab and slope are excavated by open-cut method. The excavation is carried out in stages and layers until the tunnel invert and the lowest elevation of the filling are reached. The excavated materials are piled nearby for backfilling;
[0011] 6) After the concrete structure slab and slope excavation are completed, no initial support is applied, and the secondary lining trolley is used to apply the secondary lining of the tunnel;
[0012] 7) After the tunnel secondary lining construction is completed, the slope should be backfilled in time. The backfilling should be done in layers and grades until the bottom of the concrete structure slab is backfilled and the concrete structure slab pavement structure layer is repaved;
[0013] 8) Dismantle the Bailey beam trestle, repair the temporary abutment, restore the original design elevation of the re-paved concrete structure slab and the existing road, and finally restore the original landform.
[0014] The backfill materials for the backfill slope are selectively made from raw materials piled nearby after open excavation, and slope support is carried out when necessary.
[0015] The Bailey beams are removed and recycled by mechanical and manual lifting, and the recycled Bailey beams are reused.
[0016] Compared with the prior art, the present invention has the following beneficial effects:
[0017] The present invention includes temporary abutment construction, Bailey beam erection, soil excavation above the tunnel, tunnel invert construction and filling, backfilling of soil above the tunnel and restoration of existing roads, Bailey beam removal and temporary abutment repair. In the on-site operation, a construction method of open-cut shallow-buried large-section tunnel under the existing road without interrupting traffic is adopted to make the temporary abutment support Bailey beam to form a simply supported beam bridge stability system, separate the upper road traffic from the lower tunnel construction, improve the safety of the existing road and tunnel, and shorten the construction period; the open-cut materials used to backfill the slope and the Bailey beam can be reused, which fully reflects the green and environmentally friendly sustainable construction concept; only secondary lining is applied during tunnel construction, saving construction costs and engineering costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the engineering construction of the present invention.
[0019] Figure 2 This is a detailed diagram of the present invention A.
[0020] Explanation of the reference numerals: 1-concrete structural slab, 2-existing road, 3-temporary abutment, 4-Bailey beam trestle, 5-slope, 6-tunnel invert and filling, 7-tunnel secondary lining, 8-secondary lining trolley, 9-Bailey beam support platform, 10-concrete structural slab support platform. DETAILED DESCRIPTION
[0021] The following is a further detailed description of the embodiments of the present invention in conjunction with the accompanying drawings and examples.
[0022] Embodiment: A construction method for an open-cut shallow-buried tunnel under an existing road without interrupting traffic, using a temporary abutment to support a Bailey beam to form a simply supported beam bridge stability system, through which the existing road is replaced and the front and rear extensions of the existing road are effectively connected to ensure smooth road traffic, and the upper road traffic is separated from the lower tunnel construction, and the tunnel is constructed after the open-cut shallow-buried section, so as to improve the safety of the road and the tunnel and shorten the construction period.
[0023] The specific steps include:
[0024] 1) Half of the existing road 2 is closed alternately, and the other half of the existing road 2 is open to traffic. The foundation is excavated at the beginning and end of the closed existing road 2, and a temporary abutment 3 is built. The temporary abutment 3 has two steps, which are a Bailey beam support platform 9 and a concrete structure slab support platform 10;
[0025] 2) If the existing road 2 is a concrete structure, the bottom surface of the concrete structure slab support platform 10 is flush with the bottom surface of the concrete structure slab 1, and the vertical height of the concrete structure slab support platform 10 is equal to the thickness of the concrete structure slab 1; if the existing road 2 is an asphalt concrete structure, the bottom surface of the concrete structure slab support platform 10 is flush with the bottom surface of the concrete structure slab 1, and the vertical height of the concrete structure slab support platform 10 is equal to the thickness of the concrete structure slab 1 plus the thickness of the asphalt layer;
[0026] 3) The height of the Bailey beam support platform 9 is the same as the height of the Bailey beam trestle 4, and the width of the temporary abutment 3 is not less than the width of the concrete structural slab 1;
[0027] 4) After the construction of the temporary abutment 3 is completed and the concrete strength reaches the requirement, the Bailey beam trestle 4 is erected on the Bailey beam support platform 9, so that the Bailey beam trestle 4 is flush with the bottom surface of the Bailey beam support platform 9, and the surface of the Bailey beam trestle 4 is effectively connected with the existing road 2 to meet the normal traffic requirements;
[0028] 5) After the construction of the temporary abutment 3 and the erection of the Bailey beam trestle 4 are completed, the concrete structure slab 1 and the slope 5 are excavated by open-cut method, and the excavation is carried out in stages and layers until the tunnel invert and the lowest elevation of the filling 6 are reached. The excavated materials are piled nearby for backfilling;
[0029] 6) After the concrete structure slab 1 and the slope 5 are excavated, no initial support is applied, and the secondary lining 7 of the tunnel is applied using the secondary lining trolley 8;
[0030] 7) After the construction of the tunnel secondary lining 7 is completed, the slope 5 is backfilled in time. The backfilling of the slope 5 is carried out in layers and grades until it reaches the bottom of the concrete structure slab 1 and the pavement structure layer of the concrete structure slab 1 is repaved;
[0031] 8) The Bailey beam trestle 4 is dismantled, and the temporary abutment 3 is repaired, so that the re-paved concrete structure slab 1 and the existing road 2 can be restored to the original design elevation and smoothly connected, and finally the original landform is restored.
[0032] The embodiments of the present invention are given for the purpose of illustration and description, and are not intended to be exhaustive or to limit the invention to the disclosed forms. Many modifications and variations will be apparent to those of ordinary skill in the art. The embodiments are selected and described in order to better illustrate the principles and practical applications of the present invention and to enable those of ordinary skill in the art to understand the present invention and thereby design various embodiments with various modifications suitable for specific uses.
Claims
1. A construction method for an open-cut shallow-buried tunnel under an existing road without interrupting traffic, characterized in that: The temporary abutments are used to support the Bailey beams to form a stable system of a simply supported beam bridge. This system is effectively connected with the existing road to ensure smooth traffic on the road. The upper road traffic is separated from the tunnel construction below. The tunnel is constructed after the open excavation of the shallow buried section, so as to improve the safety of the road and tunnel and shorten the construction period. The specific steps include: 1) alternately closing half of the existing road (2) while allowing normal traffic on the other half of the existing road (2), excavating foundations at the beginning and end of the closed existing road (2), and building a temporary abutment (3). The temporary abutment (3) has two steps, which are a Bailey beam support platform (9) and a concrete structure slab support platform (10); 2) If the existing road (2) is a concrete structure, the bottom surface of the concrete structure slab support platform (10) is flush with the bottom surface of the concrete structure slab (1), and the vertical height of the concrete structure slab support platform (10) is equal to the thickness of the concrete structure slab (1); if the existing road (2) is an asphalt concrete structure, the bottom surface of the concrete structure slab support platform (10) is flush with the bottom surface of the concrete structure slab (1), and the vertical height of the concrete structure slab support platform (10) is equal to the thickness of the concrete structure slab (1) plus the thickness of the asphalt layer; 3) The height of the Bailey beam support platform (9) is the same as the height of the Bailey beam trestle (4), and the width of the temporary abutment (3) is not less than the width of the concrete structural slab (1); 4) After the construction of the temporary abutment (3) is completed and the concrete strength reaches the required level, a Bailey beam trestle (4) is erected on the Bailey beam support platform (9) so that the Bailey beam trestle (4) is flush with the bottom surface of the Bailey beam support platform (9) and the surface of the Bailey beam trestle (4) is effectively connected with the existing road (2) to meet normal traffic requirements; 5) After the construction of the temporary abutment (3) and the erection of the Bailey beam trestle (4) is completed, the concrete structure slab (1) and the slope (5) are excavated by open-cut method. The excavation is carried out in stages and layers until the tunnel invert and the lowest elevation of the filling (6) are reached. The excavated materials are piled nearby for backfilling; 6) After the concrete structural slab (1) and the slope (5) are excavated, no initial support is applied and the secondary lining (7) of the tunnel is applied using a secondary lining trolley (8); 7) After the construction of the tunnel secondary lining (7) is completed, the slope (5) is backfilled in a timely manner. The backfilling of the slope (5) is carried out in layers and grades until it reaches the bottom of the concrete structure slab (1) and the pavement structure layer of the concrete structure slab (1) is repaved; 8) The Bailey beam trestle (4) is dismantled, and the temporary abutment (3) is repaired so that the re-paved concrete structure slab (1) and the existing road (2) can be restored to their original design elevation and smoothly connected, and finally the original landform is restored.
2. The construction method of an open-cut shallow-buried tunnel under an existing road without interrupting traffic according to claim 1 is characterized in that: The Bailey beam trestle (4) is dismantled and recovered by mechanical lifting, and the recovered Bailey beam trestle (4) is reused.
Citation Information
Patent Citations
Ultra-shallow buried tunnel cover-excavation construction method
CN104452809A
Underway structure and construction method thereof
CN104674625A
Steel composite PSC corrugated steel plate U-shaped girder simple bridge and continuous bridge
CN104790289A
High-steep terrain bridge and tunnel connection segment eiking open cut tunnel construction method
CN110159294A
Steep slope soil rock tunnel portal underground excavation bridge and tunnel and side slope parallel construction method
CN111021409A