A method for constructing a large-diameter vertical shaft using a vertical shaft boring machine to break the ground
Through the shaft boring machine and comprehensive construction methods, the problems of low construction efficiency and poor safety of large-diameter shafts in broken strata are solved, and efficient and safe construction results are achieved, which is suitable for the construction of large-diameter shafts.
Patent Information
- Application Number
- CN202210504514.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-05-10
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2042-05-10
AI Technical Summary
Existing shaft construction methods have low construction efficiency in fractured strata, are difficult to control safely, and are difficult to meet the construction needs of large-diameter shafts.
A comprehensive method is adopted to carry out the excavation and support of the wellhead section, the construction of geological guide holes and primary guide shafts, the expansion of secondary guide shafts, the expansion of shallow hole smooth blasting and the initial support structure of large-diameter shafts using shaft boring machines. Drilling equipment, raise drilling rigs, geological drilling rigs, blasting technology and concrete lining are used to gradually expand the diameter and provide support.
It improves the adaptability of the shaft boring machine in the construction of broken strata, reduces the disturbance of the surrounding rock, ensures construction safety, improves the construction efficiency and mechanization level, and is suitable for the construction of large-diameter shafts.
Smart Images

Figure CN114837667B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of shaft construction, in particular to a large-diameter shaft construction method using a shaft boring machine to break up strata. Background Art
[0002] As a channel to enter underground space, vertical shafts are widely used in engineering construction in the fields of hydropower, coal mining, transportation, and military. With the growing demand for underground space utilization, the number of large-diameter vertical shafts built in broken strata is increasing, and the construction of large-diameter vertical shafts in broken strata has gradually become a major problem facing underground engineering.
[0003] Although the existing ordinary well drilling method, shaft drilling method and reverse drilling method have mechanized well drilling equipment, these methods still have shortcomings such as slow well completion progress, high labor intensity of workers, and difficult to control construction safety. As a high-efficiency mechanical rock-breaking equipment, the shaft boring machine can realize the simultaneous construction of excavation and support during the excavation process, and has the advantages of high construction efficiency, less disturbance to the surrounding rock, and high level of mechanization. Therefore, it is particularly important to study the construction method of large-diameter shafts in broken formations using shaft boring machines for the construction efficiency and construction safety of large-diameter shafts in broken formations. At present, there have been some structural innovations in the construction method of shaft boring machines: such as a pilot shaft shaft boring machine starting process disclosed in application number 202110614508.0. The reinforcement measures of the bottom strata of the shaft are not considered in the preparation work before the shaft boring machine enters the shaft, which may cause instability of the surrounding rock at the bottom of the shaft during the construction of the guide hole. The application number 201310589632.1 discloses a shaft drilling process for expanding a shaft boring machine and a guide shaft of a raise drilling machine. The process is only applicable to shaft drilling projects using shaft boring machines. When the shaft boring machine excavation diameter is smaller than the shaft diameter, the process is difficult to meet the construction needs of large-diameter shaft projects. Summary of the invention
[0004] The object of the present invention is to provide a method for constructing a large-diameter vertical shaft by using a vertical shaft boring machine to break the ground, so as to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above object, the present invention provides the following technical solution: a method for constructing a large-diameter vertical shaft by using a vertical shaft boring machine to break the stratum, characterized in that it comprises the following steps:
[0006] (a) Excavation of the wellhead section and construction of the supporting structure: Use drilling equipment to carry out excavation from top to bottom until entering the stable rock layer. After excavation, the initial support structure and the first-phase concrete lining structure are promptly constructed. The rock debris generated during the construction is discharged from the wellhead through the slag discharge equipment;
[0007] (b) Wellhead section reinforcement and concrete backfill construction: construct the wellhead section bottom reinforcement structure at the bottom of the wellhead section, set up a buffer structure on the surface of the first phase concrete lining structure of the wellhead section, and backfill concrete until the wellbore reaches the required diameter for the shaft boring machine construction;
[0008] (c) Construction of geological guide hole and primary guide shaft: A geological guide hole is drilled on the reinforcement structure at the bottom of the wellhead section by a geological drilling rig until the geological guide hole is connected with the traffic tunnel at the bottom of the vertical shaft. The geological drilling rig is dismantled and a raise bore rig is installed at the wellhead. The raise bore rig reaming drill bit is installed at the bottom of the geological guide hole. The raise bore rig reams the hole from bottom to top to form a primary guide shaft. Rock debris falls to the bottom of the well and is transported out through the traffic tunnel at the bottom of the well.
[0009] (d) Construction of the secondary pilot shaft: After the shaft boring machine is installed and positioned in the shaft, the shaft boring machine excavates from top to bottom along the primary pilot shaft, expanding the primary pilot shaft to form a secondary pilot shaft. The construction of the temporary support structure of the secondary pilot shaft is carried out on the upper construction platform of the shaft boring machine. The excavation of the shaft boring machine and the construction of the temporary support structure of the secondary pilot shaft are carried out simultaneously. After the construction of the secondary pilot shaft is completed, the shaft boring machine is dismantled. During the excavation process, rock debris is transported out through the traffic tunnel at the bottom of the shaft;
[0010] (e) Expansion of vertical shaft by blasting and construction of initial support structure for large-diameter vertical shaft: adopt shallow hole smooth blasting method, drill vertical blastholes, charge and blast to remove the wellhead section and backfill with concrete, retain the initial support structure and first-phase concrete lining structure already constructed in the wellhead section, expand the secondary pilot shaft to the designed diameter of the vertical shaft through vertical blasting construction to form a large-diameter vertical shaft, and construct the initial support structure of the large-diameter vertical shaft in time after blasting;
[0011] (f) Second phase concrete lining construction of the shaft: After the shaft is expanded by blasting and the initial support structure of the large diameter shaft is constructed, the second phase concrete lining is constructed from the bottom of the shaft to the wellhead using the slipform construction method.
[0012] Furthermore, the initial support structure is composed of shotcrete, anchor rods, steel mesh, keel bars and steel arch frames, which can form a closed structure on the shaft wall to support the surrounding rock. The construction sequence is to first construct the anchor rods, then install the keel bars after the steel mesh, then install the steel arch frame, and finally construct shotcrete to form a closed initial support structure. The initial support structure is divided into multiple types according to the support material and support density. Different types of initial support structures are selected according to the surrounding rock conditions revealed by the large-diameter shaft construction.
[0013] Furthermore, the temporary support structure is composed of temporary shotcrete, temporary anchor rods and temporary steel mesh, which can form a closed structure on the wall of the secondary pilot shaft to support the surrounding rock. The construction sequence is to first construct the temporary anchor rod, then the temporary steel mesh, and finally the temporary shotcrete to form a closed temporary support structure. The temporary support structure is divided into multiple types according to the support material and support density. Different types of temporary support structures are selected according to the surrounding rock conditions revealed by the secondary pilot shaft construction.
[0014] Furthermore, the construction method of the rock reinforcement structure at the bottom of the wellhead section is as follows: backfill concrete at the bottom of the wellhead section to form a concrete cushion layer of a certain thickness, vertical steel bars are vertically inserted into the concrete cushion layer until they reach the bottom, lower oblique steel bars and ring bars are welded and tied at the junction of the vertical steel bars and the upper surface of the concrete cushion layer, concrete is backfilled to half the height of the vertical steel bars, upper oblique steel bars and ring bars are welded and tied at half the height of the vertical steel bars, and concrete is backfilled to cover the vertical steel bars to complete the rock reinforcement treatment at the bottom of the wellhead section.
[0015] Furthermore, two different grades of concrete were used in the backfill concrete construction of the wellhead section. C20 concrete was used in the range of 1-3m below the wellhead, and C15 concrete was used in the remaining wellhead section. The backfill concrete was constructed in layers, with each layer having a construction height of 1.5m.
[0016] Furthermore, the construction parameters of the secondary pilot well blasting and expansion are as follows:
[0017] (1) Drilling parameters: The blasthole direction is vertical, with a total of 3 rings, including two inner rings of caving holes and one outer ring of peripheral holes. The caving holes are 2m deep, with a spacing of 0.7m between adjacent holes. The spacing between the two rings of caving holes is 0.75m. The minimum resistance line of the inner caving holes is 0.7m. The peripheral holes are 2.5m deep, with a spacing of 0.5m between adjacent holes and a minimum resistance line of 0.75m.
[0018] (2) Charging parameters: The continuous charging method is used for the explosive rolls. The explosives are rock emulsion explosives and bulk expanded explosives. The charge amount per hole is controlled at 250-300g / m. The blasthole and plugging materials are a uniform mixture of yellow mud and sand. The plugging depth is not less than 50cm.
[0019] (3) The blast holes are connected in series with non-electric millisecond plastic detonating cords and connected in parallel to form a blasting network. Electromagnetic detonators are used for detonation, and the blasting cycle footage is 1.8m.
[0020] Compared with the prior art, the present invention has the following beneficial effects:
[0021] The present invention uses a shaft boring machine to dig a primary guide shaft in a broken stratum to form a secondary guide shaft, and expands the secondary guide shaft by blasting to form a large-diameter shaft, thereby improving the adaptability of the shaft boring machine in the construction of shafts in broken strata, reducing the disturbance of blasting construction to the surrounding rock of the broken stratum, and ensuring the stability of the surrounding rock of the broken stratum. Compared with the traditional construction method, the present invention has the advantages of high mechanized operation level, fast overall construction speed, and good construction environment for operators. It can not only ensure construction safety, but also reduce the workload of operators, improve the efficiency of shaft construction, and is suitable for large-diameter shaft construction in broken strata, and can also bring actual economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a flow chart of the construction method of the present invention;
[0023] Figure 2 It is a schematic diagram of the wellhead section structure, geological pilot hole and primary pilot well of the present invention;
[0024] Figure 3 It is a schematic diagram of the initial support structure of the present invention;
[0025] Figure 4 It is a schematic diagram of the secondary pilot shaft, shaft boring machine and temporary support structure of the present invention;
[0026] Figure 5 It is a schematic diagram of a temporary support structure of the present invention;
[0027] Figure 6 It is a schematic diagram of the initial support structure of a large diameter vertical shaft of the present invention;
[0028] Figure 7 It is a schematic diagram of the blasting hole (plane) arrangement of the present invention.
[0029] Description of the markings in the figure:
[0030] 1-wellhead section structure, 11-initial support structure, 111-sprayed concrete, 112-anchor rods, 113-steel mesh, 114-keel bars, 115-steel arch frame, 12-first-phase concrete lining structure, 13-wellhead section bottom reinforcement structure, 14-buffer structure, 15-backfill concrete, 2-geological guide hole, 3-first-level guide well, 4-raised well drilling rig, 41-raised well drilling rig expansion drill bit, 5-secondary guide well, 6-shaft boring machine, 61-shaft boring machine hoisting platform, 7-temporary support structure, 71-temporary sprayed concrete, 72-temporary anchor rods, 73-temporary steel mesh, 8-initial support structure of large-diameter shaft, 9-blast hole, 91-caving hole, 92-peripheral holes. DETAILED DESCRIPTION
[0031] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0032] See also Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 5 This embodiment provides a method for constructing a large-diameter vertical shaft by using a vertical shaft boring machine to break the ground, and the steps are as follows:
[0033] (a) Excavation of the shaft head section and construction of the support structure 1: A backhoe excavator is used to excavate from top to bottom with an excavation diameter of 12 m until the stable rock layer is reached. The excavation depth is 19 m. After excavation, the initial support structure 11 and the first-phase concrete lining structure 12 are constructed in a timely manner. The rock debris generated by the excavation construction is discharged from the shaft head through the slag discharge equipment;
[0034] (b) Wellhead section reinforcement and concrete backfill construction: construct the wellhead section bottom reinforcement structure 13 at the bottom of the wellhead section, after the surface buffer structure 14 (a layer of quilt is set) of the first phase concrete lining structure 12 of the wellhead section, backfill concrete 15 until the shaft reaches the required diameter of 6m for the shaft boring machine construction, and the backfill concrete width is 2.1m;
[0035] (c) Construction of geological guide hole 2 and primary guide shaft 3: A geological drill is used to drill a geological guide hole 2 on the reinforcement structure 13 at the bottom of the wellhead section until the geological guide hole 2 is connected with the traffic tunnel at the bottom of the vertical shaft. The diameter of the geological guide hole 2 is 0.27 m. The geological drill is removed and a raise borer 4 is installed at the wellhead. After the installation of the raise borer reaming drill bit 41 at the bottom of the geological guide hole 2, the raise borer 4 is expanded from bottom to top to form a primary guide shaft 3. The diameter of the primary guide shaft 3 is 1.4 m. The primary guide shaft 3 is not supported. Rock debris falls to the bottom of the well through the geological guide hole and is transported out through the traffic tunnel at the bottom of the well.
[0036] (d) Construction of the secondary pilot shaft 5: After the shaft boring machine 6 is installed and positioned in the shaft, the shaft boring machine 6 excavates from top to bottom along the primary pilot shaft 3, expanding the primary pilot shaft to form a secondary pilot shaft 5 with a diameter of 5.8m. The construction of the temporary support structure 7 of the secondary pilot shaft 5 is carried out in the upper construction hoisting platform 61 of the shaft boring machine. The excavation of the shaft boring machine and the construction of the temporary support structure of the secondary pilot shaft can be carried out simultaneously. After the construction of the secondary pilot shaft is completed, the shaft boring machine 6 is dismantled. During the excavation process, the rock debris falls to the bottom of the shaft through the primary pilot shaft and is transported out through the traffic tunnel at the bottom of the shaft;
[0037] (e) Shaft blasting and excavation and construction of initial support structure 8 for large-diameter shaft: adopt shallow hole smooth blasting method, drill vertical blasthole 9, charge blasting to remove wellhead section and backfill concrete 15, retain the initial support structure 11 and first-phase concrete lining structure 12 already constructed in wellhead section, expand secondary pilot shaft 5 to the shaft design diameter through blasting construction of vertical blasthole 9, form a large-diameter shaft with a diameter of 10m, and construct initial support structure 8 for large-diameter shaft in time after blasting;
[0038] (f) Second phase concrete lining construction of the shaft: After the shaft is expanded by blasting and the initial support structure 8 of the large diameter shaft is constructed, the second phase concrete lining is constructed from the bottom of the shaft to the wellhead using the slipform construction method.
[0039] The designed diameter of the shaft is larger than the excavation diameter of the shaft boring machine. Furthermore, the initial support structure 11 is composed of shotcrete 111, anchor rods 112, steel mesh 113, keel bars 114 and steel arch frame 115, which are constructed in sequence. The construction order is to first construct the anchor rod 112, then install the keel bars 114 after constructing the steel mesh 113, and then install the steel arch frame 115, and finally construct the shotcrete 111 to form a closed initial support structure 11. It can form a closed structure on the shaft wall to support the surrounding rock. The initial support structure 11 is divided into multiple types according to the support material and support density. Different types of initial support structures 11 are selected according to the surrounding rock conditions revealed by the construction of large-diameter shafts. The initial support structures include four types: A, B, C and D. The Class A initial support structure includes: anchor rods with a length of 4.5m, a diameter of 25mm, a longitudinal spacing of 1.2m and a circumferential spacing of 1.2m, C30 shotcrete with a thickness of 15cm, steel mesh with a diameter of 8mm, a longitudinal spacing of 15cm and a circumferential spacing of 15cm, and keel bars with a diameter of 16mm, a longitudinal spacing of 1.2m and a circumferential spacing of 1.2m, which are suitable for Class III and Class IV1 surrounding rock. The Class B initial support structure includes: anchor rods with a length of 6m, a diameter of 28mm, a longitudinal spacing of 1.2m and a circumferential spacing of 1.2m, C30 shotcrete with a thickness of 25cm, steel mesh with a diameter of 8mm, a longitudinal spacing of 15cm and a circumferential spacing of 15cm, keel bars with a diameter of 16mm, a longitudinal spacing of 1.2m and a circumferential spacing of 1.2m, and I16 steel arch frames with a longitudinal spacing of 1.2m, which are suitable for Class IV2 surrounding rock. The Class C initial support structure includes: pre-treatment with advanced consolidation grouting, anchor rods with a length of 6m, a diameter of 28mm, a longitudinal spacing of 0.8m and a circumferential spacing of 0.8m, C30 shotcrete with a thickness of 25cm, steel mesh with a diameter of 8mm, a longitudinal spacing of 10cm and a circumferential spacing of 10cm, keel bars with a diameter of 16mm, a longitudinal spacing of 0.8m and a circumferential spacing of 0.8m, and I16 steel arch frames with a longitudinal spacing of 0.8m. The Class D initial support structure includes: pre-treatment with advanced consolidation grouting, anchor rods with a length of 6m, a diameter of 28mm, a longitudinal spacing of 0.8m and a circumferential spacing of 0.8m, C30 shotcrete with a thickness of 25cm, steel mesh with a diameter of 8mm, a longitudinal spacing of 10cm and a circumferential spacing of 10cm, keel bars with a diameter of 16mm, a longitudinal spacing of 0.8m and a circumferential spacing of 0.8m, and I16 steel arch frames with a longitudinal spacing of 0.8m, which are suitable for the wellhead section.
[0040] Furthermore, the temporary support structure 7 is composed of temporary shotcrete 71, temporary anchor rods 72 and temporary steel mesh 73. The construction sequence is to first construct the temporary anchor rods 72, then construct the temporary steel mesh 73, and finally construct the temporary shotcrete 71 to form a closed temporary support structure 7. It can form a closed structure on the wall of the secondary pilot shaft 5 to support the surrounding rock. The temporary support structure 7 is divided into multiple types according to the support material and support density. Different types of temporary support structures (7) are selected according to the surrounding rock conditions revealed by the construction of the secondary pilot shaft 5. The temporary support structure includes three types: a, b and c. The type a temporary support structure includes: setting a temporary anchor rod with a length of 2m, a diameter of 25mm, a longitudinal spacing of 1.2m and a circumferential spacing of 1.2m, setting a temporary steel mesh with a diameter of 8mm, a longitudinal spacing of 15cm and a circumferential spacing of 15cm, and a 20cm thick C30 temporary shotcrete, which is suitable for Class V surrounding rock. The Class B temporary support structure includes: temporary anchor rods with a length of 2m, a diameter of 25mm, a longitudinal spacing of 1.5m and a circumferential spacing of 1.5m, temporary steel mesh with a diameter of 8mm, a longitudinal spacing of 15cm and a circumferential spacing of 15cm, and 10cm thick C30 temporary shotcrete, which is suitable for Class IV2 surrounding rock. The Class C temporary support structure includes: temporary C30 shotcrete with a thickness of 10cm, which is suitable for Class III and Class IV1 surrounding rock.
[0041] Furthermore, the construction method of the rock reinforcement structure 13 at the bottom of the wellhead section is as follows: backfill C20 concrete at the bottom of the wellhead section to form a concrete cushion layer with a thickness of 20 cm, vertically insert 68 vertical steel bars with a length of 2.2 m into the concrete cushion layer until they reach the bottom, weld and tie the lower oblique steel bars and ring bars at the junction of the vertical steel bars and the upper surface of the concrete cushion layer, and then backfill 1 m thick C20 concrete, weld and tie the upper oblique steel bars and ring bars at a height of 1.2 m of the vertical steel bars, backfill concrete to cover the vertical steel bars, the total thickness of the backfill concrete is 2.2 m, there are 51 ring bars and 68 oblique steel bars, and the diameter of all steel bars is 25 mm, completing the rock reinforcement treatment at the bottom of the wellhead section.
[0042] Furthermore, two different grades of concrete are used in the construction of the wellhead section backfill concrete 15. C20 concrete is used in the range of 1-3m below the wellhead, and C15 concrete is used in the remaining wellhead section. The backfill concrete 15 is constructed in a layered manner, with each layer having a construction height of 1.5m.
[0043] Furthermore, the construction parameters of the shaft blasting and excavation are as follows:
[0044] (1) Drilling parameters: The blasthole 9 is vertically oriented, with a total of 3 rings of blastholes with a diameter of 42 mm, including two inner rings of diameter collapse holes 91 and one outer ring of peripheral holes 92. There are 71 collapse holes 91 and 64 peripheral holes. The collapse holes 91 are 2 m deep, with a distance of 0.7 m between adjacent holes. The row spacing of the two rings of collapse holes 91 is 0.75 m, and the minimum resistance line of the inner collapse holes 91 is 0.7 m. The peripheral holes 92 are 2.5 m deep, with a distance of 0.5 m between adjacent holes and a minimum resistance line of 0.75 m.
[0045] (2) Charging parameters: The continuous charging method is used for the explosive rolls, and the explosives are rock emulsion explosives and bulk expanded explosives. The charge amount per hole is controlled to be 250-300g / m. The plugging material for blasthole 9 is a uniform mixture of yellow mud and sand, and the plugging depth is not less than 50cm.
[0046] (3) The blast holes 9 are connected in series with non-electric millisecond plastic detonating cords and connected in parallel to form a blasting network. Electromagnetic detonators are used for detonation. The blasting cycle footage is 1.8 m.
[0047] In order to reduce the impact of blasting and excavation construction on the adjacent structures of large-diameter shafts, the following blasting protection measures are taken: According to the distribution of adjacent structures of large-diameter shafts, monitoring points are set at the position closest to the large-diameter shaft to monitor the situation during blasting. Protective structures are covered on the blastholes facing the adjacent structures to prevent the debris generated by the blasting from flying to the adjacent structures. According to the shaft blasting parameters, the safety warning distance of the shaft blasting is determined, and blocking devices and signal devices are set at the safety warning distance. Blasting safety knowledge is promoted to villagers and construction personnel around the large-diameter shaft blasting area to improve personnel safety protection awareness. All personnel and equipment are evacuated to the safety warning distance before detonation. Blasting safety warning signs are set up at both ends of the main traffic arteries in the surrounding area. A warning group is set up for each blasting, and multiple warning points are set up in different directions. Warning posts are arranged at each warning point, and the sentry personnel are responsible for blasting warning work. Shaft blasting operations are carried out within the specified time, and blind shots are checked in time after blasting. A large-diameter shaft emergency rescue organization is established, and a shaft blasting safety emergency rescue plan is prepared.
[0048] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A method for constructing a large-diameter vertical shaft in a broken stratum using a vertical shaft boring machine, characterized in that: The steps include: (a) Excavation of the wellhead section and construction of the support structure (1): Use drilling equipment to carry out excavation from top to bottom until entering the stable rock layer. After excavation, the initial support structure (11) and the first-phase concrete lining structure (12) are promptly constructed. The rock debris generated during the construction is discharged from the wellhead through the slag discharge equipment; (b) Wellhead section reinforcement and concrete backfilling construction: construct a wellhead section bottom reinforcement structure (13) at the wellhead section bottom, set a buffer structure (14) on the surface of the wellhead section first phase concrete lining structure (12), and then backfill concrete (15) until the wellbore reaches the required diameter for the shaft boring machine construction; (c) Construction of geological guide hole (2) and primary guide shaft (3): A geological drill is used to drill a geological guide hole (2) on the reinforcement structure (13) at the bottom of the wellhead section until the geological guide hole (2) is connected with the traffic tunnel at the bottom of the vertical shaft, the geological drill is removed and a reverse well drilling machine (4) is installed at the wellhead, a reverse well drilling machine expansion drill bit (41) is installed at the bottom of the geological guide hole (2), and the reverse well drilling machine (4) expands the hole from bottom to top to form a primary guide shaft (3), and rock debris falls to the bottom of the well and is transported out through the traffic tunnel at the bottom of the well; (d) Construction of the secondary pilot shaft (5): After the shaft boring machine (6) is installed and positioned in the shaft, the shaft boring machine (6) excavates from top to bottom along the primary pilot shaft (3), expands the primary pilot shaft (3) to form a secondary pilot shaft (5), and the construction of the temporary support structure (7) of the secondary pilot shaft (5) is carried out in the upper construction hoisting platform (61) of the shaft boring machine (6). The excavation of the shaft boring machine (6) and the construction of the temporary support structure (7) of the secondary pilot shaft (5) are carried out simultaneously. After the construction of the secondary pilot shaft (5) is completed, the shaft boring machine (6) is dismantled, and the rock debris is transported out through the traffic tunnel at the bottom of the shaft during the excavation process; (e) Shaft blasting and excavation and construction of the initial support structure (8) of the large-diameter shaft: adopt the shallow hole smooth blasting method, drill the vertical blasthole (9), charge and blast to remove the wellhead section and backfill the concrete (15), retain the initial support structure (11) and the first-phase concrete lining structure (12) already constructed in the wellhead section, expand the secondary pilot shaft (5) to the shaft design diameter through the vertical blasthole (9) blasting construction, form a large-diameter shaft, and promptly construct the initial support structure (8) of the large-diameter shaft after blasting; (f) Second phase concrete lining construction of the shaft: After the shaft blasting and excavation and the initial support structure (8) of the large diameter shaft are completed, the second phase concrete lining is constructed from the bottom of the shaft to the wellhead using the slipform construction method; The initial support structure (11) is composed of shotcrete (111), anchor rods (112), steel mesh (113), keel bars (114) and steel arch frame (115), and can form a closed structure on the well wall to support the surrounding rock. The construction sequence is to first construct the anchor rods (112), then construct the steel mesh (113), then install the keel bars (114), then install the steel arch frame (115), and finally construct the shotcrete (111) to form a closed initial support structure (11); The temporary support structure (7) is composed of temporary shotcrete (71), temporary anchor rods (72) and temporary steel mesh (73), and can form a closed structure on the wall of the secondary pilot shaft (5) to support the surrounding rock. The construction sequence is to first construct the temporary anchor rods (72), then construct the temporary steel mesh (73), and finally construct the temporary shotcrete (71) to form a closed temporary support structure (7); The wellhead bottom reinforcement structure (13) is constructed as follows: backfilling concrete at the bottom of the wellhead section to form a concrete cushion layer of a certain thickness, vertically inserting vertical steel bars into the concrete cushion layer until they reach the bottom, welding and tying lower oblique steel bars and ring bars at the junction of the vertical steel bars and the upper surface of the concrete cushion layer, backfilling concrete to a position half the height of the vertical steel bars, welding and tying upper oblique steel bars and ring bars at a position half the height of the vertical steel bars, backfilling concrete to cover the vertical steel bars, and completing the rock reinforcement treatment at the bottom of the wellhead section; The construction parameters of the secondary pilot well blasting and expansion are as follows: (1) Drilling parameters: The blasthole (9) is vertically oriented and arranged in three rings, including two inner rings of cave holes (91) and one outer ring of peripheral holes (92). The cave holes (91) have a depth of 2 m and a spacing of 0.7 m between adjacent holes. The spacing between the two rings of cave holes (91) is 0.75 m. The minimum resistance line of the inner cave holes (91) is 0.7 m. The peripheral holes (92) have a depth of 2.5 m and a spacing of 0.5 m between adjacent holes. The minimum resistance line is 0.75 m. (2) Charging parameters: The continuous charging method is used for the charge rolls, and the explosives are rock emulsion explosives and bulk expanded explosives. The charge amount per hole is controlled to be 250-300 g / m. The plugging material for the blasthole (9) is a uniform mixture of yellow mud and sand, and the plugging depth is not less than 50 cm. (3) The blast holes (9) are connected in series with non-electric millisecond plastic detonating cords and connected in parallel to form a blasting network. Electromagnetic detonators are used for detonation. The blasting cycle footage is 1.8 m.
2. A method for constructing a large-diameter vertical shaft in a broken stratum using a vertical shaft boring machine according to claim 1, characterized in that: The wellhead section backfill concrete (15) is constructed using two different grades of concrete: C20 concrete is used in the range of 1 to 3 m below the wellhead, and C15 concrete is used in the remaining wellhead section. The backfill concrete (15) is constructed in layers, with each layer having a construction height of 1.5 m.