An assembled steel structure anti-collapse scaffolding for ventilation shaft in civil air defense projects

By designing prefabricated steel structure anti-collapse scaffolding and cover structures in civil air defense projects, the problem in the existing technology that the height of reinforced concrete anti-collapse scaffolding affects the city appearance and the long solidification time is solved, and rapid installation in wartime and peacetime are achieved. Reduce the impact on city appearance and improve usage flexibility and installation efficiency.

CN114856230BActive Publication Date: 2024-10-22JINAN CIVIL AIR DEFENSE BUILDING DESIGN & RES INST
View PDF 27 Cites 0 Cited by

Patent Information

Application Number
CN202210675381.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-15
Publication Date
2024-10-22
Estimated Expiration
2042-06-15

AI Technical Summary

Technical Problem

The anti-collapse scaffolding of ventilation shafts in existing civil air defense projects is very high during normal use, which affects the city appearance, and the reinforced concrete takes a long time to solidify, making it difficult to quickly put it into use in wartime.

Method used

A prefabricated steel structure anti-collapse scaffold was designed, including a steel structure scaffold and a cover structure. The steel structure scaffold was installed on the waterproof retaining wall through embedded components, and the cover structure was used to cover the ventilation shaft in normal times to reduce the risk of collapse. Height and protection of embedded components.

Benefits of technology

It realizes the rapid installation and use of steel structure scaffolding during wartime, reduces the impact on the city appearance in peacetime, improves the flexibility of use and installation efficiency, extends the service life of the support vertical poles, and saves maintenance costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114856230B_ABST
    Figure CN114856230B_ABST
Patent Text Reader

Abstract

The invention discloses an assembled steel structure anti-collapse scaffold for ventilation shaft in civil air defense engineering, including a steel structure scaffold and a cover plate structure, the ventilation shaft is provided with a waterproof retaining wall exposed to an outdoor floor, the waterproof retaining wall is provided with a pre-embedded component, in wartime, the steel structure scaffold is installed on the waterproof retaining wall through the pre-embedded component, in peacetime, the waterproof retaining wall is provided with a cover plate structure for protecting the pre-embedded component and shielding the ventilation shaft. The invention can not only be put into use as soon as possible in wartime, but also reduce the impact on the city appearance in peacetime.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of civil air defense projects, and in particular to an assembled steel structure anti-collapse scaffold for a ventilation shaft in a civil air defense project. Background Art

[0002] In civil air defense projects, air pollution caused by conventional and nuclear weapons during wartime, water vapor and harmful and explosive gases emitted from the strata, exhaust gas emitted by internal combustion engines, and water vapor and carbon dioxide emitted by workers when breathing will accumulate in large quantities, forming unsafe factors. In order to ensure safety, ventilation facilities need to be set up. Ventilation shafts are one type of ventilation facilities. One end of the ventilation shaft is connected to the space of the underground building, and the other end of the ventilation shaft is equipped with a waterproof retaining wall that exposes the outdoor floor.

[0003] According to the requirements of "Design Code for Civil Air Defense Basements GB50038-2005", in wartime, it is necessary to build anti-collapse scaffolding above the waterproof retaining wall. The anti-collapse scaffolding is used to prevent the ventilation shaft from being blocked. At the same time, the anti-collapse scaffolding can prevent collapse under the predetermined shock wave and ground building collapse load.

[0004] Existing anti-collapse scaffolding, such as Fig.29 As shown, a reinforced concrete anti-collapse scaffold 10 is used, the height H2 of the reinforced concrete anti-collapse scaffold 10 is 1200 mm, the height H1 of the waterproof retaining wall 11 is 500 mm, a window 101 is arranged on the reinforced concrete anti-collapse scaffold 10, and a shutter 102 is arranged in the window 101.

[0005] Since it takes 7-28 days for reinforced concrete to solidify, which is a long time, and the time for conversion before war is tight, cast-in-place reinforced concrete is not allowed. Therefore, reinforced concrete anti-collapse scaffolding is usually built on the waterproof retaining wall so that it can be put into use as soon as possible in wartime.

[0006] However, if the above-mentioned reinforced concrete anti-collapse scaffolding continues to be used on the ventilation shafts of civil air defense projects in public places such as squares and playgrounds, the city appearance will often be seriously affected due to the high height of the reinforced concrete anti-collapse scaffolding.

[0007] Therefore, developing an anti-collapse scaffolding that can not only be put into use as quickly as possible in wartime but also reduce the impact on the cityscape in peacetime is a technical problem that needs to be urgently solved by technicians in this field. Summary of the invention

[0008] The present invention aims at the above-mentioned deficiencies in the prior art and provides an assembled steel structure anti-collapse scaffold for ventilation shafts in civil air defense projects. The present invention can not only be put into use as soon as possible in wartime, but also reduce the impact on the city appearance in peacetime.

[0009] To achieve the above purpose, the invention provides the following technical solutions:

[0010] An assembled steel anti-collapse scaffold for a ventilation shaft in a civil air defense project comprises a steel scaffold and a cover plate structure. The ventilation shaft is provided with a waterproof retaining wall exposed to an outdoor floor, and embedded components are arranged on the waterproof retaining wall. In wartime, the steel scaffold is installed on the waterproof retaining wall through the embedded components. In peacetime, the waterproof retaining wall is provided with a cover plate structure for protecting the embedded components and shielding the ventilation shaft.

[0011] Furthermore, the steel structure scaffolding includes a supporting frame, a main supporting rod, a secondary supporting rod, a rainproof tile, and a guardrail. At least two supporting frames are arranged side by side, and the long sides of the supporting frames are arranged longitudinally. The lower ends of the supporting frames are connected to the embedded components. Two main supporting rods arranged side by side are arranged between two adjacent supporting frames, and the long sides of the main supporting rods are arranged transversely. A plurality of secondary supporting rods are laid transversely on the upper end surfaces of the two main supporting rods, and the long sides of the secondary supporting rods are arranged longitudinally. The upper end surfaces of the secondary supporting rods are covered with rainproof tiles along the longitudinal direction, and the long sides of the rainproof tiles are arranged transversely. Guardrails are provided between the two adjacent supporting frames and in the inner circle of the support frames.

[0012] Furthermore, a support connecting plate is provided at the lower end of the support frame, and the support connecting plate is provided with a support connecting hole. The embedded components are provided at the corners of the waterproof retaining wall, and the embedded components include an embedded plate and anchor bolts. The embedded plate is provided with an embedded connecting hole. The lower part of the anchor bolt is embedded in the waterproof retaining wall, and the upper part of the anchor bolt passes through the embedded connecting hole and the support connecting hole from bottom to top in sequence. A mounting nut is provided on the upper part of the anchor bolt, and the support connecting plate is clamped between the mounting nut and the embedded plate.

[0013] Furthermore, the support frame includes two support vertical bars arranged side by side and two support cross bars arranged side by side, the long sides of the support vertical bars are arranged vertically, the long sides of the support cross bars are arranged longitudinally, the two support vertical bars and the two support cross bars are connected to form a rectangular frame structure, and the support connecting plate is provided at the lower end of the support vertical bar.

[0014] Furthermore, the supporting vertical rod includes a first vertical channel steel and a second vertical channel steel connected to each other, the groove of the first vertical channel steel and the groove of the second vertical channel steel are arranged face to face, the lower end of the first vertical channel steel and the lower end of the second vertical channel steel are both connected to the supporting connecting plate, and the upper end of the first vertical channel steel and the upper end of the second vertical channel steel are both provided with a supporting sealing plate.

[0015] Furthermore, the supporting vertical rod also includes a third vertical channel steel, the second vertical channel steel is provided with a third vertical channel steel on a side away from the first vertical channel steel, the groove of the third vertical channel steel is arranged facing the second vertical channel steel, the lower end of the third vertical channel steel is connected to the supporting connecting plate, the upper end of the third vertical channel steel is lower than the upper end of the second vertical channel steel, the upper end of the third vertical channel steel is provided with a supporting sealing plate, the supporting sealing plate is provided with a main connecting plate, and the main connecting plate is connected to the second vertical channel steel; the main supporting rod includes a first main channel steel, a second main channel steel, and a spacer, the groove of the first main channel steel and the groove of the second main channel steel are arranged back to back, the spacer is arranged between the first main channel steel and the second main channel steel, the first main channel steel and the second main channel steel are both connected to the spacer, the main connecting plate is arranged between the first main channel steel and the second main channel steel, and the first main channel steel and the second main channel steel and the main connecting plate are connected by a first fastener.

[0016] Furthermore, a secondary connecting plate is provided on the upper end surface of the main supporting rod, and the secondary supporting rod is connected to the secondary connecting plate via a second fastener.

[0017] Furthermore, the rainproof tile is connected to the auxiliary supporting rod through a connecting assembly, which includes a connecting bolt and a connecting nut. The connecting bolt is arranged between two adjacent auxiliary supporting rods. The lower end of the connecting bolt is provided with a connecting hook for hooking the auxiliary supporting rod. The upper end of the connecting bolt passes through the rainproof tile. The upper end of the connecting bolt is provided with a connecting nut. The rainproof tile is clamped between the auxiliary supporting rod and the connecting nut.

[0018] Furthermore, the guardrail includes a guard frame and a baffle, a plurality of baffles are provided in the inner circle of the guard frame, a latch is provided in the outer circle of the guard frame, the support frame is provided with a guard connecting plate, the guard connecting plate is provided with a plug, and the latch is plugged into and matched with the plug.

[0019] Furthermore, the cover plate structure includes an enclosure structure and a shielding structure, the enclosure structure surrounds the embedded component, and a shielding structure for covering the ventilation shaft is provided above the enclosure structure.

[0020] Compared with the prior art, the invention has the following beneficial effects:

[0021] 1. In peacetime and after the war, it is necessary to use a cover structure to cover the ventilation shaft and enclose the embedded components located at the upper end of the waterproof retaining wall. On the one hand, it can prevent people from falling into the ventilation shaft and ensure people's safety; on the other hand, it can prevent external falling objects from falling into the ventilation shaft to avoid clogging the ventilation shaft, thereby reducing the pressure on the maintenance of the ventilation shaft; on the other hand, it can prevent the embedded components from being damaged by the outside world, so that the embedded components can be put into use as soon as possible in wartime; more importantly, compared with the reinforced concrete anti-collapse scaffolding used in the background technology, the height is greatly reduced, thereby reducing the impact on the city appearance in peacetime.

[0022] In wartime, the cover structure needs to be removed first, and then the steel structure scaffolding must be installed on the waterproof retaining wall through embedded components. Since the steel structure scaffolding does not need to wait for the reinforced concrete to solidify, the installation is quick, which is conducive to putting the steel structure scaffolding into use as soon as possible and better adapting to the urgency of pre-war conversion of ventilation shafts.

[0023] In summary, the assembled steel structure anti-collapse scaffolding for ventilation shafts in civil air defense projects provided by the present invention can not only be put into use as soon as possible in wartime, but also reduce the impact on the cityscape in peacetime, thereby realizing the dual use of the assembled steel structure anti-collapse scaffolding for ventilation shafts in civil air defense projects in peacetime and wartime, and improving the flexibility of use.

[0024] In addition, in order to further improve the installation efficiency of the steel structure scaffolding on the waterproof retaining wall, the steel structure scaffolding of the present invention can be assembled in the factory in advance and directly installed on site, which can save time and be put into use more quickly in wartime.

[0025] 2. In the anti-collapse scaffolding of the present invention, the steel structure scaffolding makes rational use of steel materials, which is beneficial to saving steel materials and reducing the cost of civil air defense projects.

[0026] 3. The supporting vertical bars, supporting horizontal bars, main supporting bars, secondary supporting bars and guardrails used to form the supporting frame in the present invention have simple structures, are easy to obtain materials and process, are conducive to improving processing efficiency, and are more conducive to further improving the construction efficiency of the steel structure anti-collapse scaffolding of the present invention.

[0027] 4. The present invention provides a support cover plate and a supporting cover plate at the upper end of the support vertical rod in the support frame, thereby being able to cover the upper end opening of the support vertical rod to prevent rain, snow and dust from entering the interior of the support vertical rod, thereby reducing the risk of corrosion starting from the interior of the support vertical rod, extending the service life of the support vertical rod and saving maintenance costs.

[0028] 5. The present invention allows the main connecting plate located at the upper end of the supporting vertical rod to be inserted between the first main channel steel and the second main channel steel of the main supporting rod, and uses the first fastener to connect the main supporting rod and the main connecting plate. This can increase the contact area between the main connecting plate and the main supporting rod, thereby facilitating the improvement of the reliability of the main connecting plate and the main supporting rod being fixedly installed using the first fastener, thereby facilitating the improvement of the structural reliability of the present invention.

[0029] 6. The present invention uses a first fastener to connect the main supporting rod and the main connecting plate, and uses a second fastener to connect the secondary connecting plate and the secondary supporting rod, which can facilitate the disassembly and assembly of the main supporting rod and the secondary supporting rod, is beneficial to improving the disassembly and assembly efficiency, and is convenient for the replacement and maintenance of the main supporting rod and the secondary supporting rod.

[0030] 7. The connecting assembly provided by the present invention for mounting the rainproof tile on the auxiliary supporting rod has a simple structure and is convenient for disassembly and assembly of the rainproof tile on the auxiliary supporting rod, thereby helping to improve the efficiency of disassembly and assembly of the rainproof tile on the auxiliary supporting rod and also facilitating the replacement and maintenance of the rainproof tile.

[0031] 8. The present invention can facilitate the disassembly and assembly of the guardrail by arranging a latch on the guardrail and arranging a plug on the support frame, thereby facilitating the replacement and maintenance of the guardrail. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 This is a top view of the steel structure scaffolding;

[0033] Figure 2 for Figure 1 Middle A 1 -A 1 A cross-sectional view at

[0034] Figure 3 for Figure 1 Middle A 2 -A 2 A cross-sectional view at

[0035] Figure 4 It is a top view of the embedded components;

[0036] Figure 5 This is the main view of the embedded component;

[0037] Figure 6 This is the main view of the supporting frame;

[0038] Figure 7 It is the left view of the supporting frame;

[0039] Figure 8 for Figure 6 Medium B 1 -B 1 A cross-sectional view at

[0040] Fig. 9 This is the main view of the reinforcement rib;

[0041] Fig.10 for Figure 6 Medium B 2 -B 2 A cross-sectional view at

[0042] Fig.11 for Figure 6 Medium B 3 -B 3 A cross-sectional view at

[0043] Fig.12 for Figure 6 Medium B 4 -B4 A cross-sectional view at

[0044] Fig.13 for Fig.12 Sectional view at CC;

[0045] Fig.14 The main view of the main supporting rod;

[0046] Fig.15 for Fig.14 Middle D 1 -D 1 A cross-sectional view at

[0047] Fig.16 for Fig.14 Middle D 2 -D 2 A cross-sectional view at

[0048] Fig.17 It is the front view of the secondary supporting rod;

[0049] Fig.18 for Fig.17 Medium E 1 -E 1 A cross-sectional view at

[0050] Fig.19 for Fig.17 Medium E 2 -E 2 A cross-sectional view at

[0051] Fig. 20 It is the main view of the auxiliary connecting plate;

[0052] Fig.21 for Fig. 20 Cross-sectional view at FF;

[0053] Fig. 22 It is a schematic diagram of the assembly structure of the rainproof tile and the auxiliary supporting rod;

[0054] Fig.23 This is the main view of the guardrail;

[0055] Fig.24 It is a schematic diagram of the assembly structure of the protection frame and the latch;

[0056] Fig.25 It is a schematic diagram of the assembly structure of the latch and the insert;

[0057] Fig.26 for Fig.25 Cross-sectional view at GG in FIG.

[0058] Fig. 27 It is a schematic diagram of the assembly structure of the guardrail and the supporting vertical rod;

[0059] Fig.28 is a structural schematic diagram of the cover plate structure;

[0060] Fig.29 It is a structural schematic diagram of a reinforced concrete anti-collapse scaffold in the background technology.

[0061] In the figure:

[0062] 1- Ventilation shaft,

[0063] 11- Waterproof retaining wall,

[0064] 12-embedded components, 121-embedded plates, 1211-embedded connection holes, 122-anchor bolts,

[0065] 2- Support frame,

[0066] 21-support connecting plate, 211-support connecting hole,

[0067] 22-supporting vertical rod, 221-reinforcement rib, 222-first vertical channel steel, 223-second vertical channel steel, 224-supporting sealing plate, 225-third vertical channel steel, 226-main connecting plate, 227-supporting sealing plate, 228-protective connecting plate, 2281-insertion pipe,

[0068] 23-support crossbar, 231-first transverse channel steel, 232-second transverse channel steel,

[0069] 3-main supporting rod, 31-first main channel steel, 32-second main channel steel, 33-spacer, 34-secondary connecting plate,

[0070] 4-Secondary support rod,

[0071] 5- Rainproof tiles,

[0072] 51-connecting assembly, 511-connecting bolt, 5111-connecting hook, 512-connecting nut, 513-rubber pad, 514-washer,

[0073] 6- Guardrails,

[0074] 61-protective frame, 611-latch,

[0075] 62-Bar,

[0076] 7- Red brick masonry structure,

[0077] 8- Precast reinforced concrete cover slab,

[0078] 9-Find the slope layer,

[0079] 10-Reinforced concrete anti-collapse scaffolding, 101-Windows, 102-Shutters. DETAILED DESCRIPTION

[0080] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0081] Example:

[0082] like Figure 1-3 As shown, an assembled steel structure anti-collapse scaffold for a ventilation shaft in a civil air defense project comprises a steel structure scaffold and a cover plate structure.

[0083] The steel structure scaffolding includes a supporting frame 2, a main supporting rod 3, a secondary supporting rod 4, rainproof tiles 5, and a guardrail 6. Figure 1 This is a top view of the steel structure scaffolding of this embodiment. In order to clearly show the positional relationship between the support frame 2 and the main supporting rod 3, the secondary supporting rod 4 and the rainproof tile 5 are not shown.

[0084] like Figure 1 As shown, at least two support frames 2 are arranged side by side. When the lateral span is less than or equal to 2100 mm, two support frames 2 can be arranged side by side. When the lateral span is greater than 2100 mm, multiple support frames need to be arranged side by side. The long sides of the support frames 2 are arranged longitudinally, and two main supporting rods 3 arranged side by side are arranged between two adjacent support frames 2. The long sides of the main supporting rods 3 are arranged transversely. Figure 2 for Figure 1 Middle A 1 -A 1 The cross-sectional view at Figure 3 for Figure 1 Middle A 2 -A 2 In order to clearly show the positional relationship between the main supporting rod 3 and the secondary supporting rod 4, Figure 2 and Figure 3 The rainproof tiles 5 are not shown. Figure 2-3 As shown, the upper end surfaces of the two main supporting rods 3 are evenly laid with a plurality of secondary supporting rods 4 in the horizontal direction, and the long sides of the secondary supporting rods 4 are arranged in the longitudinal direction. The upper end surfaces of the secondary supporting rods 4 are covered with rainproof tiles 5 in the longitudinal direction, as shown in FIG. Fig. 22 As shown, the long edge of the rainproof tile 5 is arranged horizontally. Figure 2-3 As shown, guardrails 6 are provided between two adjacent support frames 2 and in the inner circle of the support frames 2, so that the four sides of the entire steel structure scaffolding are all provided with guardrails 6.

[0085] like Figure 2-3As shown, the ventilation shaft 1 is provided with a waterproof retaining wall 11 exposed to the outdoor floor, and the waterproof retaining wall 11 can prevent water on the outdoor floor from entering the ventilation shaft 1. The waterproof retaining wall 11 is a reinforced concrete structure.

[0086] In order to facilitate the installation of the steel structure scaffolding of this embodiment on the waterproof retaining wall 11, when the waterproof retaining wall 11 is being built, embedded components 12 are embedded at the four corners of the waterproof retaining wall 11, and the embedded components 12 are used to connect the steel structure scaffolding of this embodiment.

[0087] like Figure 4-5 As shown, the embedded assembly 12 includes an embedded plate 121 and an anchor bolt 122. The embedded plate 121 can be an embedded iron plate, and four embedded connection holes 1211 are provided on the embedded plate 121. The upper portion of the anchor bolt 122 with an external thread passes through the embedded connection hole 1211, and the lower portion of the anchor bolt 122 with a hook is embedded in the waterproof retaining wall 11. After the waterproof retaining wall 11 is solidified, the upper end surface of the embedded plate 121 is flush with the upper end surface of the waterproof retaining wall 11, and the upper portion of the anchor bolt 122 with an external thread is exposed from the upper end surface of the embedded plate 121. The anchor bolt 122 exposed from the upper end surface of the embedded plate 121 is used to connect the steel structure scaffold of this embodiment.

[0088] like Figure 1-3 As shown, the support frame 2 is the basic structure of the steel structure scaffolding of this embodiment, and the support frame 2 is directly installed with the waterproof retaining wall 11. A support connecting plate 21 is welded and fixed at the lower end of the support frame 2, and the support connecting plate 21 is provided with a support connecting hole 211. The support connecting hole 211 is used for the portion provided with an external thread on the upper part of the anchor bolt 122 to pass upward, so that the support connecting plate 21 is pressed on the embedded plate 121 by screwing the mounting nut (not shown in the figure) on the anchor bolt 122, thereby realizing the installation of the support frame 2 on the upper end surface of the waterproof retaining wall 11.

[0089] When it is necessary to install the steel structure scaffolding of this embodiment on the ventilation shaft 1, the steel structure scaffolding of this embodiment can be assembled in the factory in advance, and the steel structure scaffolding can be directly installed on site. Because the waterproof retaining wall 11 part of the ventilation shaft 1 exposed to the outdoor floor is in direct contact with the support frame 2 in the steel structure scaffolding, it is only necessary to directly install the support frame 2 on the waterproof retaining wall 11. When installing the support frame 2 on the waterproof retaining wall 11, the following operations need to be performed: first, the worker aligns the support connection hole 211 on the support connection plate 21 at the lower end of the support frame 2 with the anchor bolt 122; then the worker lowers the support frame 2 and allows the anchor bolt 122 to pass through the support connection hole 211; finally, the worker screws the installation nut on the anchor bolt 122 and presses the support connection plate 21 onto the embedded plate 121 to complete the installation.

[0090] When it is necessary to dismantle the steel structure scaffolding of the present embodiment from the ventilation shaft 1, it is only necessary to dismantle the supporting frame 2 from the waterproof retaining wall 11. The dismantling operation is as follows: first, the worker unscrews the installation nut from the anchor bolt 122; then the worker lifts the steel structure scaffolding of the present embodiment upward so that the anchor bolt 122 is withdrawn from the supporting connection hole 211, and the steel structure scaffolding of the present embodiment can be dismantled from the ventilation shaft 1.

[0091] Through the above process, it can be known that the setting of the embedded components 12 and the supporting connecting plates 21 can facilitate the disassembly and assembly of the steel structure scaffolding and the ventilation shaft 1 of this embodiment, which is not only conducive to improving the installation efficiency, but also conducive to improving the disassembly efficiency, and is more adaptable to the urgency of the pre-war conversion of the ventilation shaft 1.

[0092] Next, the specific structure of the steel structure scaffolding of this embodiment is specifically introduced.

[0093] like Figure 1-3 As shown, the support frame 2 is the basic structure of the steel structure scaffolding of this embodiment. In this embodiment, two support frames 2 are arranged side by side, and the long sides of the support frames 2 are arranged longitudinally. Figure 6 As shown, each support frame 2 includes a support vertical rod 22 and a support cross rod 23. Two support vertical rods 22 are arranged side by side, and two support cross rods 23 are also arranged side by side. The long sides of the support vertical rods 22 are arranged vertically, and the long sides of the support cross rods 23 are arranged longitudinally. The two support vertical rods 22 and the two support cross rods 23 are welded around to form a rectangular frame structure. Figure 6-8 As shown, a supporting connecting plate 21 is welded to the lower end of each supporting vertical rod 22 .

[0094] like Figure 6-9 As shown, in order to improve the stability of the support vertical rod 22 standing on the support connecting plate 21, a reinforcing rib 221 is provided between the support vertical rod 22 and the support connecting plate 21, the lower end side wall of the support vertical rod 22 is welded and fixed to the side of the reinforcing rib 221, and the lower end of the reinforcing rib 221 is welded and fixed to the upper end surface of the support connecting plate 21.

[0095] like Figure 8 , 10 As shown in FIGS. 12 and 13, the support vertical rod 22 includes two channel steels. For the convenience of description, the two channel steels are respectively recorded as the first vertical channel steel 222 and the second vertical channel steel 223. The groove of the first vertical channel steel 222 and the groove of the second vertical channel steel 223 are arranged face to face, and the first vertical channel steel 222 and the second vertical channel steel 223 are welded and fixed. Figure 6-8As shown, the lower end of the first vertical channel steel 222 and the lower end of the second vertical channel steel 223 are both welded to the upper end surface of the support connecting plate 21, and the upper end of the first vertical channel steel 222 is flush with the upper end of the second vertical channel steel 223. As can be seen from this introduction, the support vertical rod 22 has a simple structure, is easy to obtain materials, and is easy to process, which is conducive to improving the processing efficiency of the support vertical rod 22.

[0096] like Fig.13 As shown, in order to prevent rain, snow and dust from entering the grooves of the first vertical channel steel 222 and the second vertical channel steel 223, support sealing plates 224 are welded and fixed to the upper ends of the first vertical channel steel 222 and the second vertical channel steel 223. The setting of the support sealing plates 224 can prevent rain, snow and dust from entering the grooves of the first vertical channel steel 222 and the second vertical channel steel 223, thereby reducing the risk of corrosion starting from the inside of the support vertical rod 22, extending the service life of the support vertical rod 22, and saving maintenance costs.

[0097] like Fig.11 As shown, the support cross bar 23 includes two channel steels. For the convenience of description, the two channel steels are respectively recorded as a first transverse channel steel 231 and a second transverse channel steel 232. The groove of the first transverse channel steel 231 and the groove of the second transverse channel steel 232 are arranged face to face, and the first transverse channel steel 231 and the second transverse channel steel 232 are welded and fixed. Figure 6 , 8 As shown, the ends of the first transverse channel steel 231 and the second transverse channel steel 232 are both welded and fixed to the support vertical rod 22. As can be seen from this introduction, the support cross bar 23 has a simple structure, is easy to obtain materials, and is easy to process, which is conducive to improving the processing efficiency of the support cross bar 23.

[0098] like Figure 1-3 As shown, two main supporting rods 3 are arranged side by side, and the long sides of the main supporting rods 3 are arranged horizontally. The two main supporting rods 3 are fixedly installed together with the upper ends of the two supporting frames 2. Figure 1 From the top view shown, the two main supporting rods 3 and the two supporting frames 2 surround and form a rectangular frame structure, and the main supporting rods 3 serve as the foundation for the construction of the secondary supporting rods 4.

[0099] like Figure 8 , 10 As shown in Figures 13, in order to improve the reliability of the main supporting rod 3 being installed on the supporting frame 2, the supporting vertical rod 22 in the supporting frame 2 also includes a third vertical channel steel 225. The third vertical channel steel 225 is arranged on the side of the second vertical channel steel 223 away from the first vertical channel steel 222. The groove of the third vertical channel steel 225 faces the second vertical channel steel 223. The third vertical channel steel 225 is welded and fixed to the second vertical channel steel 223. The lower end of the third vertical channel steel 225 is welded and fixed to the upper end surface of the supporting connecting plate 21, as shown in Figures 13 and 13. Fig.13 As shown, the upper end of the third vertical channel steel 225 is lower than the upper end of the second vertical channel steel 223. Figure 6 , 7 As shown in Figures 12 and 13, a main connecting plate 226 is welded and fixed to the upper end of the third vertical channel steel 225, and the side of the main connecting plate 226 is welded and fixed to the second vertical channel steel 223. The main connecting plate 226 is fixedly installed with the main supporting rod 3 through a first fastener (such as a bolt, not shown in the figure). It can be seen from this introduction that the main connecting plate 226 can be supported by the third vertical channel steel 225, thereby improving the reliability of the main connecting plate 226, and further improving the reliability of the main supporting rod 3 installed with the main connecting plate 226.

[0100] like Figure 12-13 As shown, in order to prevent rain, snow and dust from entering the groove of the third vertical channel steel 225, a supporting sealing plate 227 is welded and fixed to the upper end of the third vertical channel steel 225, and the lower end of the main connecting plate 226 is welded and fixed to the upper end surface of the supporting sealing plate 227. The setting of the supporting sealing plate 227 can prevent rain, snow and dust from entering the groove of the third vertical channel steel 225, thereby reducing the risk of corrosion starting from the inside of the supporting vertical rod 22, extending the service life of the supporting vertical rod 22, and saving maintenance costs.

[0101] like Figure 14-16 As shown, the main supporting rod 3 includes a spacer 33 and two channel steels. For the convenience of description, the two channel steels are recorded as the first main channel steel 31 and the second main channel steel 32. The groove of the first main channel steel 31 and the groove of the second main channel steel 32 are arranged back to back, and the spacer 33 is arranged between the first main channel steel 31 and the second main channel steel 32. The first main channel steel 31 and the second main channel steel 32 are both welded and fixed to the spacer 33. The spacer 33 is arranged to separate the first main channel steel 31 and the second main channel steel 32, so that the gap between the first main channel steel 31 and the second main channel steel 32 can allow the main connecting plate 226 to be inserted, thereby increasing the contact area between the main connecting plate 226 and the main supporting rod 3, so as to improve the reliability of fixing the main connecting plate 226 and the main supporting rod 3 using the first fastener. In addition, as can be seen from this paragraph, the main supporting rod 3 has a simple structure, is easy to obtain materials, and is easy to process, which is conducive to improving the processing efficiency of the main supporting rod 3.

[0102] like Figure 3 As shown, a plurality of auxiliary supporting rods 4 are arranged side by side, and all the auxiliary supporting rods 4 are evenly laid on the upper end surface of the main supporting rod 3 in the horizontal direction, and the long sides of the auxiliary supporting rods 4 are arranged in the longitudinal direction. The upper end surface of the main supporting rod 3 is welded and fixed with an auxiliary connecting plate 34. Fig.17 FIG. 3 shows that a secondary connecting plate 34 is welded to a partial area of ​​the main supporting rod 3. Figure 20-21 As shown, the auxiliary connecting plate 34 is made of angle steel, such as Figure 17-19As shown, the secondary supporting rod 4 is made of channel steel. The secondary supporting rod 4 is fixedly installed with the secondary connecting plate 34 by a second fastener (such as a bolt, not shown in the figure). From this introduction, it can be seen that the secondary supporting rod 4 has a simple structure, is easy to obtain materials and easy to process, and is conducive to improving the processing efficiency of the secondary supporting rod 4; and the connection method between the secondary supporting rod 4 and the main supporting rod 3 is simple, which is conducive to improving the disassembly and assembly efficiency and facilitating the replacement and maintenance of the secondary supporting rod 4.

[0103] A plurality of protective tiles are arranged side by side, and all protective tiles are longitudinally spread over the upper end surface of the secondary support rod 4, and the long edges of the protective tiles are arranged transversely. In this embodiment, the rainproof tiles 5 are made of corrugated transparent fiberglass tiles. Fig. 22 As shown, in order to facilitate the disassembly and assembly of the rainproof tile 5 and the secondary supporting rod 4, the rainproof tile 5 is installed on the secondary supporting rod 4 through a connecting assembly 51. The connecting assembly 51 includes a connecting bolt 511 and a connecting nut 512. The connecting bolt 511 is arranged between two adjacent secondary supporting rods 4, and a connecting hook 5111 is arranged at the lower end of the connecting bolt 511. The connecting hook 5111 can hook the secondary supporting rod 4, and the upper end of the connecting bolt 511 passes through the rainproof tile 5. Specifically, a hole (not shown in the figure) can be arranged on the rainproof tile 5, and the connecting bolt 511 can pass through the hole from bottom to top, so that the connecting bolt 511 can pass through the rainproof tile 5. The upper end of the connecting bolt 511 is threadedly connected with a connecting nut 512, and the rainproof tile 5 is sandwiched between the secondary supporting rod 4 and the connecting nut 512.

[0104] like Fig. 22 As shown, when the rainproof tile 5 is installed on the secondary supporting rod 4 using the connecting assembly 51, the following operations need to be performed: (1) The worker passes the upper end of the connecting bolt 511 through the rainproof tile 5. (2) The worker lowers the connecting bolt 511 so that the connecting hook 5111 at the lower end of the connecting bolt 511 is inserted between two adjacent secondary supporting rods 4. The worker rotates the connecting bolt 511 to adjust the position of the connecting hook 5111 so that the connecting hook 5111 is rotated to the bottom of the secondary supporting rod 4. (3) The worker lifts the connecting bolt 511 so that the connecting hook 5111 abuts against the secondary supporting rod 4. (4) The worker screws the connecting nut 512 onto the connecting bolt 511 so that the rainproof tile 5 is clamped between the secondary supporting rod 4 and the connecting nut 512, thereby realizing the installation of the rainproof tile 5 on the secondary supporting rod 4. According to the above installation method, the rainproof tile 5 can be spread all over the upper end surface of the secondary supporting rod 4.

[0105] like Fig. 22As shown, when removing the rainproof tile 5 from the secondary supporting rod 4, the following operations are required: (1) The worker unscrews the connecting nut 512 from the upper end of the connecting bolt 511, and the worker pinches the upper end of the connecting bolt 511 and pushes down the connecting bolt 511, so that the connecting hook 5111 is separated from the secondary supporting rod 4. (2) The worker rotates the connecting bolt 511, so that the connecting hook 5111 is rotated between two adjacent secondary supporting rods 4, so as to prevent the connecting hook 5111 from being blocked by the secondary supporting rod 4 when the connecting bolt 511 is lifted. (3) The worker lifts the connecting bolt 511, so that the connecting hook 5111 can smoothly come out of the gap between the two adjacent secondary supporting rods 4. At this time, the rainproof tile 5 penetrated by the connecting bolt 511 can be lifted, so that the rainproof tile 5 is separated from the secondary supporting rod 4, and the separation of the rainproof tile 5 and the secondary supporting rod 4 can be achieved.

[0106] Through the above-mentioned disassembly and assembly process of the rainproof tile 5 and the auxiliary supporting rod 4, it can be known that the setting of the connecting assembly 51 can facilitate the disassembly and assembly of the rainproof tile 5 on the auxiliary supporting rod 4, thereby helping to improve the disassembly and assembly efficiency of the rainproof tile 5 on the auxiliary supporting rod 4, and can also facilitate the replacement and maintenance of the rainproof tile 5.

[0107] like Fig. 22 As shown, in order to prevent the rainproof tile 5 from being crushed by the connecting nut 512, the connecting assembly 51 also includes a rubber pad 513 and a washer 514. The rubber pad 513 and the washer 514 are arranged between the rainproof tile 5 and the connecting nut 512. The rubber pad 513 and the washer 514 are both sleeved on the connecting bolt 511.

[0108] In addition, in order to improve the effect of the rainproof tiles 5 in shielding rain and snow, longer rainproof tiles 5 can be used to increase the coverage area of ​​the rainproof tiles 5, which is beneficial to improve the effect of shielding rain and snow.

[0109] like Figure 2-3 As shown, guardrails 6 are provided between the two support frames 2 and in the inner circle of the support frames 2, so that the four sides of the steel structure scaffolding of this embodiment are equipped with guardrails 6. Fig.23 As shown, the guardrail 6 includes a guard frame 61 and a blocking rod 62. A plurality of blocking rods 62 are evenly arranged in the inner circle of the guard frame 61, and the blocking rods 62 are welded and fixed to the guard frame 61. The guard frame 61 is a rectangular frame structure welded with steel pipes. The blocking rod 62 can be directly made of round steel. It can be seen from this introduction that the guardrail 6 has a simple structure, is easy to obtain materials, and is easy to process, which is conducive to improving the processing efficiency of the guardrail 6.

[0110] like Figure 23-26As shown, in order to facilitate the installation of the guardrail 6, a latch 611 is welded on the outer ring of the guard frame 61, and the latch 611 can be an inverted U-shaped steel bar. A protective connecting plate 228 is welded on the support vertical rod 22, and a plug 2281 is welded on the protective connecting plate 228. When the latch 611 is inserted into the plug 2281, the guardrail 6 can be installed; when the latch 611 is pulled out of the plug 2281, the guardrail 6 can be removed. It can be seen from the above-mentioned operation of disassembling and assembling the guardrail 6 that the provision of the latch 611 and the plug 2281 can facilitate the disassembly and assembly of the guardrail 6, thereby facilitating the replacement and maintenance of the guardrail 6.

[0111] In addition, if the guardrail 6 needs to be fixed, the pin 611 can be inserted into the insert tube 2281 and then welded to the insert tube 2281, so that the guardrail 6 can be fixed. In addition, a shutter can be installed between the two support frames 2 and in the inner circle of the support frame 2. In order to prevent the shutter from interfering with the guardrail 6, the shutter is located further outward than the guardrail 6. Considering that the steel structure scaffolding provided in this embodiment is a steel structure, it needs to be placed in the protective component warehouse when it is not needed in normal times, and attention should be paid to rust prevention and maintenance.

[0112] The cover plate structure is used to cover the ventilation shaft 1 and protect the embedded components 12 embedded in the upper end of the waterproof retaining wall 11 in normal times, so that the embedded components 12 can be put into use immediately after the cover plate structure is removed.

[0113] like Fig.28 As shown, the cover structure includes an enclosure structure and a shielding structure. The enclosure structure is used to surround the embedded component 12 located at the upper end of the waterproof retaining wall 11. A shielding structure is provided above the enclosure structure, and the shielding structure is used to cover the ventilation shaft 1.

[0114] Specifically, the enclosure structure adopts a red brick masonry structure 7, which is a circle of machine-made red bricks (machine-made red bricks are red bricks produced by machines) arranged around the upper end surface of the waterproof retaining wall 11. The machine-made red bricks are laid on the upper end surface of the waterproof retaining wall 11 using cement mortar to form the red brick masonry structure 7, and the embedded components 12 are located in the inner circle of the red brick masonry structure 7.

[0115] The shielding structure adopts a prefabricated reinforced concrete cover plate 8, which is built on the top of the red brick masonry structure 7 to cover the upper end of the ventilation shaft 1.

[0116] In order to improve the waterproof effect of the cover plate structure, the cover plate structure also includes a slope layer 9 and a waterproof layer (not shown in the figure). Cement mortar is used to lay a slope on the upper end surface of the reinforced concrete prefabricated cover plate 8 to form the slope layer 9. A base treatment agent is applied to the upper end surface of the slope layer 9, and a polymer modified asphalt waterproof membrane is laid as a waterproof layer.

[0117] In order to improve the protective effect of the cover structure, the cover structure also includes a protective layer. A steel mesh is laid on the waterproof layer and fine stone concrete is applied. After the fine stone concrete solidifies, a protective layer is formed.

[0118] A method for using the assembled steel structure anti-collapse scaffolding in a ventilation shaft in a civil air defense project of this embodiment is as follows:

[0119] In peacetime (i.e. non-wartime) and after the war, it is necessary to use a cover structure to cover the ventilation shaft 1 and enclose the embedded components 12 located at the upper end of the waterproof retaining wall 11. On the one hand, it can prevent people from falling into the ventilation shaft 1 to ensure people's safety; on the other hand, it can prevent external falling objects from falling into the ventilation shaft 1 to avoid blockage of the ventilation shaft 1, thereby reducing the pressure on the maintenance of the ventilation shaft 1; on the other hand, it can prevent the embedded components 12 from being damaged by the outside world, so that the embedded components 12 can be put into use as soon as possible in wartime; more importantly, compared with the reinforced concrete anti-collapse scaffolding used in the background technology, the height is greatly reduced, thereby reducing the impact on the city appearance in peacetime.

[0120] In wartime, it is necessary to first remove the cover structure, and then install the steel structure scaffolding on the waterproof retaining wall 11 through the embedded components 12. Since the steel structure scaffolding does not need to wait for the reinforced concrete to solidify, the installation is fast, which is conducive to putting the steel structure scaffolding into use as soon as possible and better adapting to the urgency of the pre-war conversion of the ventilation shaft 1.

[0121] To sum up, the assembled steel structure anti-collapse scaffolding for ventilation shaft in civil air defense projects provided in this embodiment can not only be put into use as soon as possible in wartime, but also reduce the impact on the cityscape in peacetime, thereby realizing the dual use of the assembled steel structure anti-collapse scaffolding for ventilation shaft in civil air defense projects in this embodiment in peacetime and wartime, and improving the flexibility of use.

[0122] In addition, in order to further improve the installation efficiency of the steel structure scaffolding on the waterproof retaining wall 11, the steel structure scaffolding of this embodiment can be assembled in the factory in advance and directly installed on site, which can save time and be put into use more quickly in wartime.

[0123] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. An assembled steel structure anti-collapse scaffold for a ventilation shaft in a civil air defense project, wherein the ventilation shaft is provided with a waterproof retaining wall exposed to the outdoor floor, characterized in that: It includes a steel structure scaffold and a cover plate structure, wherein the waterproof retaining wall is provided with embedded components. In wartime, the steel structure scaffold is installed on the waterproof retaining wall through the embedded components, and in peacetime, the waterproof retaining wall is provided with a cover plate structure for protecting the embedded components and shielding the ventilation shaft; The cover structure includes an enclosure structure and a shielding structure. The enclosure structure surrounds the embedded components, and a shielding structure for covering the ventilation shaft is provided above the enclosure structure. The enclosure structure adopts a red brick masonry structure. The red brick masonry structure is to surround a circle of machine-made red bricks on the upper end face of the waterproof retaining wall, and use cement mortar to lay the machine-made red bricks on the upper end face of the waterproof retaining wall to form a red brick masonry structure. The embedded components are located in the inner circle of the red brick masonry structure; The shielding structure adopts precast reinforced concrete cover slab, which is built on top of the red brick masonry structure to seal the upper end of the ventilation shaft.

2. The anti-collapse scaffolding of the assembled steel structure of the ventilation shaft in the civil air defense project as claimed in claim 1, characterized in that: The steel structure scaffolding includes a supporting frame, a main supporting rod, a secondary supporting rod, rainproof tiles, and a guardrail. At least two supporting frames are arranged side by side, and the long sides of the supporting frames are arranged longitudinally. The lower ends of the supporting frames are connected to the embedded components. Two main supporting rods arranged side by side are arranged between two adjacent supporting frames, and the long sides of the main supporting rods are arranged transversely. A plurality of secondary supporting rods are laid transversely on the upper end surfaces of the two main supporting rods, and the long sides of the secondary supporting rods are arranged longitudinally. The upper end surfaces of the secondary supporting rods are covered with rainproof tiles along the longitudinal direction, and the long sides of the rainproof tiles are arranged transversely. Guardrails are provided between the two adjacent supporting frames and in the inner circle of the support frames.

3. The anti-collapse scaffolding of the assembled steel structure of the ventilation shaft in the civil air defense project as claimed in claim 2, characterized in that: A support connecting plate is provided at the lower end of the support frame, and a support connecting plate is provided with a support connecting hole. The embedded components are provided at the corners of the waterproof retaining wall, and the embedded components include an embedded plate and anchor bolts. The embedded plate is provided with an embedded connecting hole. The lower part of the anchor bolt is embedded in the waterproof retaining wall, and the upper part of the anchor bolt passes through the embedded connecting hole and the support connecting hole in sequence from bottom to top. A mounting nut is provided on the upper part of the anchor bolt, and the support connecting plate is clamped between the mounting nut and the embedded plate.

4. The assembled steel structure anti-collapse scaffolding for ventilation shaft in civil air defense engineering as claimed in claim 3, characterized in that: The support frame includes two support vertical bars arranged side by side and two support cross bars arranged side by side. The long sides of the support vertical bars are arranged vertically, and the long sides of the support cross bars are arranged longitudinally. The two support vertical bars and the two support cross bars are connected to form a rectangular frame structure, and the support connecting plate is provided at the lower end of the support vertical bar.

5. The assembled steel structure anti-collapse scaffolding for ventilation shaft in civil air defense engineering as claimed in claim 4, characterized in that: The supporting vertical rod includes a first vertical channel steel and a second vertical channel steel connected to each other, the groove of the first vertical channel steel and the groove of the second vertical channel steel are arranged face to face, the lower end of the first vertical channel steel and the lower end of the second vertical channel steel are both connected to the supporting connecting plate, and the upper end of the first vertical channel steel and the upper end of the second vertical channel steel are both provided with a supporting sealing plate.

6. The anti-collapse scaffolding of the assembled steel structure for ventilation shaft in civil air defense engineering as claimed in claim 5, characterized in that: The supporting vertical rod also includes a third vertical channel steel, the second vertical channel steel is provided with a third vertical channel steel on a side away from the first vertical channel steel, the groove of the third vertical channel steel is arranged facing the second vertical channel steel, the lower end of the third vertical channel steel is connected to the supporting connecting plate, the upper end of the third vertical channel steel is lower than the upper end of the second vertical channel steel, the upper end of the third vertical channel steel is provided with a supporting sealing plate, the supporting sealing plate is provided with a main connecting plate, and the main connecting plate is connected to the second vertical channel steel; The main supporting rod includes a first main channel steel, a second main channel steel, and a spacer. The groove of the first main channel steel and the groove of the second main channel steel are arranged back to back. The spacer is arranged between the first main channel steel and the second main channel steel. The first main channel steel and the second main channel steel are both connected to the spacer. The main connecting plate is arranged between the first main channel steel and the second main channel steel. The first main channel steel and the second main channel steel and the main connecting plate are connected by a first fastener.

7. The anti-collapse scaffolding of the assembled steel structure of the ventilation shaft in the civil air defense project as claimed in claim 6, characterized in that: The upper end surface of the main supporting rod is provided with a secondary connecting plate, and the secondary supporting rod is connected to the secondary connecting plate through a second fastener.

8. The assembled steel structure anti-collapse scaffolding for ventilation shaft in civil air defense engineering as claimed in claim 2, characterized in that: The rainproof tile is connected to the auxiliary supporting rod through a connecting assembly, which includes a connecting bolt and a connecting nut. The connecting bolt is arranged between two adjacent auxiliary supporting rods. The lower end of the connecting bolt is provided with a connecting hook for hooking the auxiliary supporting rod. The upper end of the connecting bolt passes through the rainproof tile. The upper end of the connecting bolt is provided with a connecting nut. The rainproof tile is clamped between the auxiliary supporting rod and the connecting nut.

9. The assembled steel structure anti-collapse scaffolding for ventilation shaft in civil air defense engineering as claimed in claim 2, characterized in that: The guardrail comprises a guard frame and a baffle, a plurality of baffles are arranged in the inner circle of the guard frame, a latch is arranged in the outer circle of the guard frame, the support frame is provided with a guard connecting plate, the guard connecting plate is provided with an insert, and the latch is plugged and matched with the insert.

Citation Information

Patent Citations

  • Modular building for deployment in disaster regions

    AU2007330481A1

  • Combined prestressed beam-slab system

    CN106193451A

  • Photovoltaic support roof structure suitable for steel structure

    CN108560801A

  • Steel structure collapse-proof shed frame for civil air defense entrance and exit motorized vehicle lane

    CN111350376A

  • Column foot joint of civil air defense project entrance and exit steel structure anti-collapse shed frame

    CN112942576A