Three-dimensional visual operation and maintenance management methods and related devices applied to rail transit

By analyzing the difference in position data of rail transit tools and adjusting the communication transmission path, the delay problem existing in rail transit management by existing three-dimensional management operation and maintenance technology is solved, and the rail transit network situation is achieved without lag, which is improved. Management efficiency.

CN114860817BActive Publication Date: 2025-02-11GUANGZHOU METRO DESIGN & RES INST CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202110152151.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-02-03
Publication Date
2025-02-11
Estimated Expiration
2041-02-03

AI Technical Summary

Technical Problem

The existing three-dimensional management operation and maintenance technology has a large delay in rail transit management, making it difficult to master the rail transit network without lag.

Method used

By obtaining the location data of the vehicle, analyzing the time stamp difference. If the preset time threshold is exceeded, the communication transmission path will be modified and the data will be re-acquired; if it is less than the threshold, three-dimensional visualization will be performed to generate three-dimensional visual operation and maintenance of rail transit Graphics.

Benefits of technology

It has achieved the ability to grasp the network situation without lag in rail transit management, reduce delays and improve management efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114860817B_ABST
    Figure CN114860817B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of three-dimensional modeling, and discloses a three-dimensional visual operation and maintenance management method and related devices applied to rail transit. The method includes: obtaining the location data of N vehicles to obtain a location data set, wherein N is a positive integer greater than 2; analyzing the timestamps corresponding to all the location data in the location data set, and capturing the maximum timestamp and the minimum timestamp; judging whether the difference between the maximum timestamp and the minimum timestamp is greater than a preset time threshold; if greater than, modifying the communication transmission path of the location data in the location data set, and re-obtaining the location data of the vehicle; if less than, obtaining the punctuation data of all preset sensors, and based on the Unity platform system, three-dimensionally visualizing all the punctuation data to obtain a three-dimensional visual operation and maintenance graph of rail transit.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of three-dimensional modeling, and in particular to a three-dimensional visual operation and maintenance management method and related devices applied to rail transit. Background Art

[0002] In modern cities, transportation is becoming more and more developed. From the perspectives of sea, land and air, there are airplanes in the sky, transport ships in the ocean, and rail transportation and electromechanical vehicles on land. The exchange and circulation of materials are becoming more and more convenient, making people's lives more and more convenient. Goods from any corner of the earth can reach the department store of the target city in a very short time.

[0003] However, the increasingly complex transportation network has brought great management difficulties. The crisscrossing urban subways and intercity rails transport people and goods in various complex terrains. At present, most management solutions are based on two-dimensional plane management. Even if there is a three-dimensional visualization system, there is a delay in the information transmission process, which makes the entire rail transportation management lag behind. A three-dimensional technology is needed to grasp the overall situation of the rail transportation network without lag. Summary of the invention

[0004] The main purpose of the present invention is to solve the technical problem that the existing three-dimensional management and operation technology has a large transmission delay.

[0005] A first aspect of the present invention provides a three-dimensional visual operation and maintenance management method applied to rail transit, comprising the steps of:

[0006] Acquire location data of N vehicles to obtain a location data set, where N is a positive integer greater than 2;

[0007] Analyze the timestamps corresponding to all the location data in the location data set, and extract the maximum timestamp and the minimum timestamp;

[0008] Determine whether the difference between the maximum timestamp and the minimum timestamp is greater than a preset time threshold;

[0009] If the time is greater than the threshold, modify the communication transmission path of the location data in the location data set to reacquire the location data of the vehicle;

[0010] If it is less than the time threshold, the punctuation data of all preset sensors are obtained, and based on the Unity platform system, all the punctuation data are three-dimensionally visualized to obtain a three-dimensional visual operation and maintenance graph of rail transit.

[0011] Optionally, in a first implementation of the first aspect of the present invention, modifying the communication transmission path of the location data in the location data set to reacquire the location data of the vehicle includes:

[0012] Sending a test signal to a calibrated vehicle among the N vehicles to obtain a feedback duration;

[0013] Determining whether the feedback duration is less than a preset transmission threshold;

[0014] If it is less than the transmission threshold, the timestamp corresponding to the position data of the calibrated vehicle is determined as the test timestamp, and the test timestamp is compared and changed with the timestamps corresponding to all the position data according to the preset path change algorithm to obtain N new communication transmission paths of the vehicles;

[0015] Re-acquire the location data of the vehicle;

[0016] If it is greater than the transmission threshold, the calibrated vehicle among the N vehicles is removed, and a test signal is sent to another calibrated vehicle among the N-1 vehicles to obtain a new feedback duration.

[0017] Optionally, in a second implementation of the first aspect of the present invention, the comparing and changing the test timestamp with the timestamps corresponding to all the position data according to the preset path change algorithm to obtain N new communication transmission paths of the transportation means includes:

[0018] The test timestamp and the timestamps corresponding to all the position data are subjected to absolute difference processing to obtain N-1 time differences;

[0019] Determine in sequence whether the time difference is less than a preset qualified threshold;

[0020] If it is less than the qualified threshold, the position data corresponding to the time difference is determined as not needing to be changed;

[0021] If it is greater than the qualified threshold, the position data corresponding to the time difference is determined to be to be changed;

[0022] The communication transmission paths corresponding to all the position data to be modified are modified to obtain new communication transmission paths corresponding to the vehicle for all the position data to be modified.

[0023] Optionally, in a third implementation of the first aspect of the present invention, the step of acquiring the punctuation data of all preset sensors, and three-dimensionally visualizing all the punctuation data based on the Unity platform system to obtain a three-dimensional visual operation and maintenance graph of rail transit includes:

[0024] Acquire punctuation data of all preset sensors, and generate a punctuation matrix according to all the punctuation data;

[0025] Establishing a communication connection with the Unity platform system, and sending the punctuation matrix to the Unity platform system;

[0026] The feedback data from the Unity platform system is received, and based on the plant simulation platform, the feedback data is simulated and processed to obtain a three-dimensional visual operation and maintenance graph of rail transit.

[0027] Optionally, in a fourth implementation of the first aspect of the present invention, establishing a communication connection with the Unity platform system includes:

[0028] Realize two-way communication connection with the Unity platform system through Socket communication.

[0029] Optionally, in a fifth implementation of the first aspect of the present invention, analyzing the timestamps corresponding to all the location data in the location data set to capture the maximum timestamp and the minimum timestamp includes:

[0030] According to a preset coding algorithm, converting the timestamps corresponding to all the position data in the position data set into binary numbers;

[0031] Compare and sort all the binary numbers to obtain a time sort;

[0032] The binary data at both ends of the time sorting are captured, the sizes of the two binary data are determined, the larger binary data is determined as the maximum timestamp, and the smaller binary data is determined as the minimum timestamp.

[0033] Optionally, in a sixth implementation of the first aspect of the present invention, before acquiring the position data of N vehicles, the method further includes:

[0034] Construct a plan map of rail transit to facilitate the selection and viewing of N types of transportation tools in three-dimensional visualization.

[0035] A second aspect of the present invention provides a three-dimensional visual operation and maintenance management device applied to rail transit, comprising:

[0036] An acquisition module is used to acquire the location data of N vehicles to obtain a location data set, where N is a positive integer greater than 2;

[0037] An analysis module, used to analyze the timestamps corresponding to all the location data in the location data set, and to capture the maximum timestamp and the minimum timestamp;

[0038] A judging module, used to judge whether the difference between the maximum timestamp and the minimum timestamp is greater than a preset time threshold;

[0039] A reset module, configured to modify the communication transmission path of the location data in the location data set and reacquire the location data of the vehicle if the time is greater than the time threshold;

[0040] A construction module is used to obtain the punctuation data of all preset sensors if the time is less than the time threshold, and to perform three-dimensional visualization of all the punctuation data based on the Unity platform system to obtain a three-dimensional visual operation and maintenance graph of rail transit.

[0041] The third aspect of the present invention provides a three-dimensional visual operation and maintenance management device applied to rail transit, comprising: a memory and at least one processor, the memory storing instructions, the memory and the at least one processor being interconnected via lines; the at least one processor calling the instructions in the memory so that the three-dimensional visual operation and maintenance management device applied to rail transit executes the above-mentioned three-dimensional visual operation and maintenance management method applied to rail transit.

[0042] A fourth aspect of the present invention provides a computer-readable storage medium, in which instructions are stored, which, when executed on a computer, enable the computer to execute the above-mentioned three-dimensional visual operation and maintenance management method applied to rail transit.

[0043] In the embodiment of the present invention, by comparing the signal times of the transportation vehicles in the entire rail transit, the communication path of the delayed vehicles is changed and switched, ensuring that the three-dimensional stereoscopic image of the entire transportation management can accurately reflect the current transportation situation, realize efficient management of transportation management, and reduce the delay of the entire rail transportation network. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] Figure 1 A schematic diagram of an embodiment of a three-dimensional visual operation and maintenance management method applied to rail transit in an embodiment of the present invention;

[0045] Figure 2 It is a schematic diagram of another embodiment of the three-dimensional visual operation and maintenance management method applied to rail transit in an embodiment of the present invention;

[0046] Figure 3 A schematic diagram of an embodiment of a three-dimensional visual operation and maintenance management device applied to rail transit in an embodiment of the present invention;

[0047] Figure 4 It is a schematic diagram of another embodiment of a three-dimensional visual operation and maintenance management device applied to rail transit in an embodiment of the present invention;

[0048] Figure 5 It is a schematic diagram of an embodiment of a three-dimensional visual operation and maintenance management device applied to rail transit in an embodiment of the present invention. DETAILED DESCRIPTION

[0049] Embodiments of the present invention provide a three-dimensional visual operation and maintenance management method, device, equipment and storage medium applied to rail transit.

[0050] The terms "first", "second", "third", "fourth", etc. (if any) in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments described herein can be implemented in an order other than that illustrated or described herein. In addition, the terms "including" or "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0051] For ease of understanding, the specific process of the embodiment of the present invention is described below. Figure 1 , an embodiment of a three-dimensional visual operation and maintenance management method applied to rail transit in an embodiment of the present invention includes:

[0052] 101. Obtain location data of N vehicles to obtain a location data set, where N is greater than

[0053] A positive integer greater than 2;

[0054] In this embodiment, N vehicles are distributed at various locations in the entire rail transit transportation network, and the location data of the N vehicles are directly acquired, wherein each location data carries a timestamp of sending and receiving.

[0055] 102. Analyze the timestamps corresponding to all the location data in the location data set, and extract the maximum timestamp and the minimum timestamp;

[0056] In this embodiment, what is compared are the receiving timestamps of the location data sent by N vehicles. The receiving timestamps are taken as the objects of comparison, the timestamps are sorted, the difference between the first receiving time and the last receiving time in the timestamps is captured, the first receiving timestamp is determined as the minimum timestamp, and the last receiving timestamp is determined as the maximum timestamp.

[0057] 103. Determine whether the difference between the maximum timestamp and the minimum timestamp is greater than a preset time threshold;

[0058] In this embodiment, the maximum timestamp and the minimum timestamp are first converted into binary data and then subtracted to obtain a numerical value, which is then converted into a time format to determine whether the difference in duration is greater than 80 ms.

[0059] 104. If the time is greater than the time threshold, modify the communication transmission path of the location data in the location data set and reacquire the location data of the vehicle;

[0060] In this embodiment, if it is greater than 80ms, it means that there are vehicles with abnormal communication in the rail transit network, then the communication transmission path of the vehicle with abnormal communication is changed, and after the change is completed, the position data of N vehicles are read again to determine whether there are any vehicles with abnormal transmission.

[0061] 105. If it is less than the time threshold, the punctuation data of all preset sensors are obtained, and based on the Unity platform system, all the punctuation data are three-dimensionally visualized to obtain a three-dimensional visual operation and maintenance graph of rail transit.

[0062] In this embodiment, if there is no abnormality, the punctuation data of the sensors installed under N vehicles are read. The sensors are installed and distributed throughout the vehicle according to the outline of the vehicle. The punctuation data is filled in a matrix in a fixed format, and the written matrix is ​​sent to the Unity platform system to construct a three-dimensional image. The three-dimensional image fed back by the Unity platform system is received to obtain the three-dimensional visual operation and maintenance graphics required for rail transit.

[0063] In the embodiment of the present invention, by comparing the signal times of the transportation vehicles in the entire rail transit, the communication path of the delayed vehicles is changed and switched, ensuring that the three-dimensional stereoscopic image of the entire transportation management can accurately reflect the current transportation situation, realize efficient management of transportation management, and reduce the delay of the entire rail transportation network.

[0064] See also Figure 2 Another embodiment of the three-dimensional visual operation and maintenance management method applied to rail transit in the embodiment of the present invention includes:

[0065] 201. Build a plan map of rail transit to facilitate the selection and viewing of N types of transportation tools in 3D visualization

[0066] In this embodiment, a plan map of rail transit and a rail route map are provided, and when viewing a specific three-dimensional image, only the transportation tool that requires a three-dimensional image needs to be viewed.

[0067] 202. Acquire location data of N vehicles to obtain a location data set, where N is a positive integer greater than 2;

[0068] This embodiment is similar to the first embodiment. Please refer to the first embodiment and will not be described in detail here.

[0069] 203. Convert the timestamps corresponding to all the location data in the location data set into binary numbers according to a preset coding algorithm;

[0070] 204. Compare and sort all binary numbers to obtain time sorting;

[0071] 205. Capture the binary data at both ends of the time sorting, determine the sizes of the two binary data, determine the larger binary data as the maximum timestamp, and determine the smaller binary data as the minimum timestamp;

[0072] In embodiments 203-205, the date in the format of XXXX.XX.XX XX:XX:XX:XX is converted into binary data, and then the binary data is sorted by size to obtain the sorting size of the time, the smallest sorting value is determined as the minimum timestamp, and the largest sorting value is determined as the maximum timestamp.

[0073] 206. Determine whether the difference between the maximum timestamp and the minimum timestamp is greater than a preset time threshold;

[0074] This embodiment is similar to the first embodiment. Please refer to the first embodiment and will not be described in detail here.

[0075] 207. If it is greater than the time threshold, a test signal is sent to a calibration vehicle among the N vehicles to obtain a feedback duration;

[0076] 208. Determine whether the feedback duration is less than a preset transmission threshold;

[0077] 209. If it is less than the transmission threshold, the timestamp corresponding to the position data of the calibrated vehicle is determined as the test timestamp;

[0078] In embodiments 207-209, a test signal is sent and a test feedback signal is received to determine whether there is a vehicle with a normal transmission time. If the transmission time is less than the transmission threshold, the vehicle is deemed to be a normally working device, and based on the normal device, the vehicle is used as a standard comparison device to compare and judge the remaining N-1 vehicles.

[0079] 210. Perform absolute value processing on the difference between the test timestamp and the timestamps corresponding to all the position data to obtain N-1 time differences;

[0080] 211. Determine in sequence whether the time difference is less than a preset qualified threshold;

[0081] 212. If the time difference is less than the qualified threshold, the position data corresponding to the time difference is determined as not needing to be changed;

[0082] 213. If it is greater than the qualified threshold, the position data corresponding to the time difference is determined to be to be changed;

[0083] In embodiments 210-213, the timestamps corresponding to the location data of standard normal vehicles are subtracted from those of other vehicles. After obtaining the numerical value, the time difference is compared with the qualified threshold of 50ms, and the signal transmission of the entire system is adjusted to reduce the delay error of the entire system.

[0084] 214. Modify the communication transmission paths corresponding to all the position data to be modified to obtain new communication transmission paths of the vehicles corresponding to all the position data to be modified;

[0085] 215. Re-acquire the location data of the vehicle;

[0086] In the 214-215 embodiments, the communication transmission path of the vehicle whose time exceeds the normal difference is adjusted, and after the adjustment is completed, the position data of the vehicle is re-acquired and re-detected and analyzed.

[0087] 216. If it is greater than the transmission threshold, remove the calibrated vehicle from the N vehicles, send the test signal to another calibrated vehicle from the N-1 vehicles, and obtain a new feedback duration;

[0088] In this embodiment, if the test data shows that the calibrated vehicle is an abnormal vehicle, a test signal is resent to another calibrated vehicle among the remaining N-1 vehicles, and a new judgment is made until the tested calibrated vehicle is determined to be communicating normally.

[0089] 217. If it is less than the time threshold, obtain the punctuation data of all preset sensors, and generate a punctuation matrix according to all the punctuation data;

[0090] 218. Establish a communication connection with the Unity platform system and send the punctuation matrix to the Unity platform system;

[0091] 219. Receive feedback data from the Unity platform system, and simulate the feedback data based on the plant simulation platform to obtain a three-dimensional visual operation and maintenance graphic of the rail transit.

[0092] In the embodiments 217-219, it is determined that there are no abnormal problems in the transmission data of N vehicles, and the current spatial position data captured by the sensor is written into the matrix according to the set coding sorting, and the punctuation matrix is ​​sent to the Unity platform to be rendered into a three-dimensional image. The three-dimensional image is then transmitted to the plant simulation platform for simulation rendering to obtain the required rail transit image data.

[0093] In the embodiment of the present invention, by comparing the signal times of the transportation vehicles in the entire rail transit, the communication path of the delayed vehicles is changed and switched, ensuring that the three-dimensional stereoscopic image of the entire transportation management can accurately reflect the current transportation situation, realize efficient management of transportation management, and reduce the delay of the entire rail transportation network.

[0094] The above describes the three-dimensional visual operation and maintenance management method applied to rail transit in the embodiment of the present invention. The following describes the three-dimensional visual operation and maintenance management device applied to rail transit in the embodiment of the present invention. Figure 3 In one embodiment of the present invention, a three-dimensional visual operation and maintenance management device applied to rail transit includes:

[0095] An acquisition module 301 is used to acquire location data of N vehicles to obtain a location data set, where N is a positive integer greater than 2;

[0096] An analysis module 302 is used to analyze the timestamps corresponding to all the location data in the location data set, and to extract the maximum timestamp and the minimum timestamp;

[0097] The judging module 303 is used to judge whether the difference between the maximum timestamp and the minimum timestamp is greater than a preset time threshold;

[0098] A reset module 304, configured to modify the communication transmission path of the location data in the location data set if it is greater than, and reacquire the location data of the vehicle;

[0099] The construction module 305 is used to obtain the punctuation data of all preset sensors if it is less than , and to perform three-dimensional visualization on all the punctuation data based on the Unity platform system to obtain a three-dimensional visual operation and maintenance graph of rail transit.

[0100] In the embodiment of the present invention, by comparing the signal times of the transportation vehicles in the entire rail transit, the communication path of the delayed vehicles is changed and switched, ensuring that the three-dimensional stereoscopic image of the entire transportation management can accurately reflect the current transportation situation, realize efficient management of transportation management, and reduce the delay of the entire rail transportation network.

[0101] See also Figure 4 Another embodiment of the three-dimensional visual operation and maintenance management device applied to rail transit in the embodiment of the present invention includes:

[0102] An acquisition module 301 is used to acquire location data of N vehicles to obtain a location data set, where N is a positive integer greater than 2;

[0103] An analysis module 302 is used to analyze the timestamps corresponding to all the location data in the location data set, and to extract the maximum timestamp and the minimum timestamp;

[0104] The judging module 303 is used to judge whether the difference between the maximum timestamp and the minimum timestamp is greater than a preset time threshold;

[0105] A reset module 304, configured to modify the communication transmission path of the location data in the location data set if it is greater than, and reacquire the location data of the vehicle;

[0106] The construction module 305 is used to obtain the punctuation data of all preset sensors if it is less than , and to perform three-dimensional visualization on all the punctuation data based on the Unity platform system to obtain a three-dimensional visual operation and maintenance graph of rail transit.

[0107] The reset module 304 is specifically used for:

[0108] Sending a test signal to a calibrated vehicle among the N vehicles to obtain a feedback duration;

[0109] Determining whether the feedback duration is less than a preset transmission threshold;

[0110] If it is less than the transmission threshold, the timestamp corresponding to the position data of the calibrated vehicle is determined as the test timestamp, and the test timestamp is compared and changed with the timestamps corresponding to all the position data according to the preset path change algorithm to obtain N new communication transmission paths of the vehicles;

[0111] Re-acquire the location data of the vehicle;

[0112] If it is greater than the transmission threshold, the calibrated vehicle among the N vehicles is removed, and a test signal is sent to another calibrated vehicle among the N-1 vehicles to obtain a new feedback duration.

[0113] The resetting module 304 may also be specifically used for:

[0114] The test timestamp and the timestamps corresponding to all the position data are subjected to absolute difference processing to obtain N-1 time differences;

[0115] Determine in sequence whether the time difference is less than a preset qualified threshold;

[0116] If it is less than the qualified threshold, the position data corresponding to the time difference is determined as not needing to be changed;

[0117] If it is greater than the qualified threshold, the position data corresponding to the time difference is determined to be to be changed;

[0118] The communication transmission paths corresponding to all the position data to be modified are modified to obtain new communication transmission paths corresponding to the vehicle for all the position data to be modified.

[0119] Wherein, the construction module 305 includes:

[0120] The acquisition unit 3051 is used to acquire the punctuation data of all preset sensors and generate a punctuation matrix according to all the punctuation data;

[0121] The communication unit 3052 is used to establish a communication connection with the Unity platform system and send the punctuation matrix to the Unity platform system;

[0122] The simulation unit 3053 is used to receive the feedback data from the Unity platform system, and based on the plantSimulation platform, simulate the feedback data to obtain a three-dimensional visual operation and maintenance graph of the rail transit.

[0123] The communication unit 3052 is specifically used for:

[0124] Realize two-way communication connection with the Unity platform system through Socket communication.

[0125] The analysis module 302 is specifically used for:

[0126] According to a preset coding algorithm, converting the timestamps corresponding to all the position data in the position data set into binary numbers;

[0127] Compare and sort all the binary numbers to obtain a time sort;

[0128] The binary data at both ends of the time sorting are captured, the sizes of the two binary data are determined, the larger binary data is determined as the maximum timestamp, and the smaller binary data is determined as the minimum timestamp.

[0129] The three-dimensional visual operation and maintenance management device for rail transit further includes a plane construction module 306, and the plane construction module 306 is specifically used for:

[0130] Construct a plan map of rail transit to facilitate the selection and viewing of N types of transportation tools in three-dimensional visualization.

[0131] In the embodiment of the present invention, by comparing the signal times of the transportation vehicles in the entire rail transit, the communication path of the delayed vehicles is changed and switched, ensuring that the three-dimensional stereoscopic image of the entire transportation management can accurately reflect the current transportation situation, realize efficient management of transportation management, and reduce the delay of the entire rail transportation network.

[0132] above Figure 3 and Figure 4 The three-dimensional visual operation and maintenance management device applied to rail transit in the embodiment of the present invention is described in detail from the perspective of modular functional entities. The three-dimensional visual operation and maintenance management device applied to rail transit in the embodiment of the present invention is described in detail from the perspective of hardware processing.

[0133] Figure 5 : is a structural schematic diagram of a three-dimensional visual operation and maintenance management device for rail transit provided by an embodiment of the present invention. The three-dimensional visual operation and maintenance management device 500 for rail transit may have relatively large differences due to different configurations or performances, and may include one or more processors (central processing units, CPU) 510 (for example, one or more processors) and a memory 520, and one or more storage media 530 (for example, one or more mass storage devices) storing application programs 533 or data 532. Among them, the memory 520 and the storage medium 530 can be short-term storage or permanent storage. The program stored in the storage medium 530 may include one or more modules (not shown in the figure), and each module may include a series of instruction operations corresponding to the three-dimensional visual operation and maintenance management device 500 for rail transit. Furthermore, the processor 510 can be configured to communicate with the storage medium 530, and execute a series of instruction operations in the storage medium 530 on the three-dimensional visual operation and maintenance management device 500 for rail transit.

[0134] The three-dimensional visual operation and maintenance management device 500 applied to rail transit may also include one or more power supplies 540, one or more wired or wireless network interfaces 550, one or more input and output interfaces 560, and / or one or more operating systems 531, such as Windows Serve, Mac OS X, Unix, Linux, FreeBSD, etc. Those skilled in the art will appreciate that Figure 5 The structure of the three-dimensional visual operation and maintenance management equipment applied to rail transit shown does not constitute a limitation on the three-dimensional visual operation and maintenance management equipment applied to rail transit, and may include more or fewer components than shown in the figure, or a combination of certain components, or a different arrangement of components.

[0135] The present invention also provides a computer-readable storage medium, which may be a non-volatile computer-readable storage medium or a volatile computer-readable storage medium. Instructions are stored in the computer-readable storage medium. When the instructions are executed on a computer, the computer executes the steps of the three-dimensional visual operation and maintenance management method applied to rail transit.

[0136] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working process of the above-described system, device, or unit can refer to the corresponding process in the aforementioned method embodiment and will not be repeated here.

[0137] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention is essentially or the part that contributes to the prior art or all or part of the technical solution can be embodied in the form of a software product. The computer software product is stored in a storage medium, including a number of instructions to enable a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM), random access memory (RAM), disk or optical disk and other media that can store program codes.

[0138] As described above, the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features thereof may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A three-dimensional visual operation and maintenance management method applied to rail transit, characterized in that: Includes steps: Acquire location data of N vehicles to obtain a location data set, where N is a positive integer greater than 2; Analyze the timestamps corresponding to all the location data in the location data set, and extract the maximum timestamp and the minimum timestamp; Determine whether the difference between the maximum timestamp and the minimum timestamp is greater than a preset time threshold; If the time is greater than the threshold, modifying the communication transmission path of the location data in the location data set, and reacquiring the location data of the vehicle; If it is less than the time threshold, the punctuation data of all preset sensors are obtained, and all the punctuation data are three-dimensionally visualized based on the Unity platform system to obtain a three-dimensional visual operation and maintenance graph of rail transit; Modifying the communication transmission path of the position data in the position data set to reacquire the position data of the vehicle comprises: Sending a test signal to a calibrated vehicle among the N vehicles to obtain a feedback duration; Determining whether the feedback duration is less than a preset transmission threshold; If it is less than the transmission threshold, the timestamp corresponding to the position data of the calibrated vehicle is determined as the test timestamp, and the test timestamp is compared and changed with the timestamps corresponding to all the position data according to the preset path change algorithm to obtain N new communication transmission paths of the vehicles; Re-acquire the location data of the vehicle; If it is greater than the transmission threshold, the calibrated vehicle among the N vehicles is removed, and a test signal is sent to another calibrated vehicle among the N-1 vehicles to obtain a new feedback duration.

2. The three-dimensional visual operation and maintenance management method applied to rail transit according to claim 1 is characterized in that: The comparing and changing processing of the test timestamp with the timestamps corresponding to all the position data according to the preset path change algorithm to obtain N new communication transmission paths of the transportation means includes: The test timestamp and the timestamps corresponding to all the position data are subjected to absolute difference processing to obtain N-1 time differences; Determine in sequence whether the time difference is less than a preset qualified threshold; If it is less than the qualified threshold, the position data corresponding to the time difference is determined as not needing to be changed; If it is greater than the qualified threshold, the position data corresponding to the time difference is determined to be to be changed; The communication transmission paths corresponding to all the position data to be modified are modified to obtain new communication transmission paths corresponding to the vehicle for all the position data to be modified.

3. The three-dimensional visual operation and maintenance management method applied to rail transit according to claim 1 is characterized in that: The acquisition of the punctuation data of all preset sensors and the three-dimensional visualization of all the punctuation data based on the Unity platform system to obtain the three-dimensional visual operation and maintenance graphics of rail transit include: Acquire punctuation data of all preset sensors, and generate a punctuation matrix according to all the punctuation data; Establishing a communication connection with the Unity platform system, and sending the punctuation matrix to the Unity platform system; The feedback data from the Unity platform system is received, and based on the plant simulation platform, the feedback data is simulated and processed to obtain a three-dimensional visual operation and maintenance graph of rail transit.

4. The three-dimensional visual operation and maintenance management method applied to rail transit according to claim 3 is characterized in that: The establishing of a communication connection with the Unity platform system includes: Realize two-way communication connection with the Unity platform system through Socket communication.

5. The three-dimensional visual operation and maintenance management method applied to rail transit according to claim 1, characterized in that: The analyzing the timestamps corresponding to all the location data in the location data set and capturing the maximum timestamp and the minimum timestamp comprises: According to a preset coding algorithm, converting the timestamps corresponding to all the position data in the position data set into binary numbers; Compare and sort all the binary numbers to obtain a time sort; The binary data at both ends of the time sorting are captured, the sizes of the two binary data are determined, the larger binary data is determined as the maximum timestamp, and the smaller binary data is determined as the minimum timestamp.

6. The three-dimensional visual operation and maintenance management method applied to rail transit according to claim 1, characterized in that: Before obtaining the position data of N vehicles, the method further includes: Construct a plan map of rail transit to facilitate the selection and viewing of N types of transportation tools in three-dimensional visualization.

7. A three-dimensional visual operation and maintenance management device applied to rail transit, characterized in that: The three-dimensional visual operation and maintenance management device applied to rail transit includes: An acquisition module is used to acquire the location data of N vehicles to obtain a location data set, where N is a positive integer greater than 2; An analysis module, used to analyze the timestamps corresponding to all the location data in the location data set, and to capture the maximum timestamp and the minimum timestamp; A judging module, used to judge whether the difference between the maximum timestamp and the minimum timestamp is greater than a preset time threshold; A reset module, configured to modify the communication transmission path of the location data in the location data set and reacquire the location data of the vehicle if the time is greater than the time threshold; A construction module is used to obtain the punctuation data of all preset sensors if the time is less than the time threshold, and to perform three-dimensional visualization of all the punctuation data based on the Unity platform system to obtain a three-dimensional visual operation and maintenance graph of rail transit; The reset module is specifically used for: Sending a test signal to a calibrated vehicle among the N vehicles to obtain a feedback duration; Determining whether the feedback duration is less than a preset transmission threshold; If it is less than the transmission threshold, the timestamp corresponding to the position data of the calibrated vehicle is determined as the test timestamp, and the test timestamp is compared and changed with the timestamps corresponding to all the position data according to the preset path change algorithm to obtain N new communication transmission paths of the vehicles; Re-acquire the location data of the vehicle; If it is greater than the transmission threshold, the calibrated vehicle among the N vehicles is removed, and a test signal is sent to another calibrated vehicle among the N-1 vehicles to obtain a new feedback duration.

8. A three-dimensional visual operation and maintenance management device applied to rail transit, characterized in that: The three-dimensional visual operation and maintenance management device applied to rail transit includes: a memory and at least one processor, the memory stores instructions, and the memory and the at least one processor are interconnected through a line; The at least one processor calls the instructions in the memory so that the three-dimensional visual operation and maintenance management device applied to rail transit executes the three-dimensional visual operation and maintenance management method applied to rail transit as described in any one of claims 1-6.

9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, a three-dimensional visual operation and maintenance management method for rail transit as described in any one of claims 1 to 6 is implemented.

Citation Information

Patent Citations

  • Three-dimensional intelligent-station scene simulation system based on dynamic generation of Unity and realization method

    CN107679281A

  • Sensor data loss analysis method and system

    CN111078466A